Professional Documents
Culture Documents
Kuliah Ke 4 - Cement Industry
Kuliah Ke 4 - Cement Industry
Definition:
• Defined as a product material obtained by calcination of
calcareous (a material containing lime) and argillaceous
(a material which contain silica) materials.
• According to (specification stand as) ASTM (American
standard testing material)
“Cement is defined as a product obtained by
pulverizing (crushing followed by grinding) clinkers to
which no addition has been made except H2O.”
Composition
• Chemically cement is a mixture of Silicates, Aluminates
like aluminoferrites with some amount of MgO and
gypsum.
• Various complexes which are contained in cement are
• (2CaO.SiO2) Di Calcium Silicate (C2S) 22-24%
• (3CaO.SiO2) Tri Calcium Silicate (C3S) 50-58%
• (3CaO.Al2O3) Tri Calcium Aluminate (C3A) 10-11%
• (4CaO.Al2O3.Fe2O3) Tetra Calcium Aluminoferrite (C4AF) 8-9%
• (6CaO.Al2O3.Fe2O3) Hexa Calcium Aluminoferrite (C6AF) traces
• MgO <5%
• Gypsum (CaSO4.2H2O) 4-5%
Various oxides
• Cement contains various oxides as follows
1) CaO 60-66%
2) Total silica 20-15%
a) Combined silica/active silica
b) Uncombined or inert silica
3) Alumina (Al2O3) 3-8%
4) Fe2O3 1-5%
5) MgO <5%
6)Alkalies <5%
Color
• The gray color in cement is due to presence of complexes
of Ferric ions in O.P.C (ordinary Portland cement).
• White cement is produced from those raw materials which
contain extremely low conc. of Iron & even like low conc.
of Iron is converted from Fe+3 to Fe+2 (which can be done
by reducing or maintaining atmosphere in the kiln) &
eventually the product appears to be white.
Raw materials used in the production of
O.P.C:
1) Lime stone
2) Clay
3) Gypsum
Lime stone:
9. The loss of raw material in the 9. The loss of the raw material in the
form of dust contained in the flue form of dust is much higher and
gas coming out of the kiln is less. about 15% raw material is lost
It amounts to about 1.5% of the with the flue gas coming out of
clinker produced. the kiln.
10. The dust particles leaving with 10. Dust contained in the flue gas is
the flue gas are recovered by recovered in the same way as in
installing scrubbers, cyclone wet process.
separators and by installing
high density electrical
precipitators.
11. The heat recovery in dry process
11. The recovery of heat from the is 20% more in this process.
flue gases is less.
Crushing & grinding of clay and lime
stone
• The limestone and the clay needed for the production of
cement as excavated from the quarries are crushed to
approximately a particle size of 100mm using crushers
which are called as the primary crushers.
• The secondary crusher installed in the same area crushes
the limestone and the clay to obtain a particle size of about
10mm.
• In the wet process, the crushed lime and clay is fed into a
rotary grinding ball mill in the presence of water. The
grinding is carried out using the technique of close circuit.
Mixing of ground raw material to
obtain an almost homogeneous mass
• The lime and clay obtained from the classifier is received in
a correcting tank where the composition w.r.t. limestone
and clay is adjusted. The slurry should contain 65-70%
limestone and 30-35% clay in it. In case any of the two is
less in quantity, the difficulty is made up by adding required
quantity of deficient material.
• Then slurry containing corrected limestone and clay is
pumped to a dark thickener where excess of water of any is
removed which in turn is reused for grinding in the ball mill.
The slurry obtained from the dark thickener should contain
30-40% water and 60-70% of the solids. This slurry is then
introduced into the kiln for pyro processing (heat treatment).
Transportation of ground raw materials to
rotary kilns & burning of raw materials to
clinkers
Construction and working of the rotary kiln:
• The pyro-processing of slurry obtained in the wet method
and the dry ground raw materials in the dry process is
carried out in a rotary kiln. It is made from sheets of plain
carbon steel riveted together to obtain a shell.
• In the old versions the rotary kiln tapered towards the top.
Now a days large no. of cement industry is using rotary
kiln of uniform internal diameter.
• In the old versions the rotary kiln was placed in a way that
it made an angle of 15 degrees with the horizontal which
facilitates the movement of material from the feed end to
the discharge end.
Construction and working of the rotary
kiln:
• Now a days the inclination of shell with the horizontal has
been reduced to about 5-6 degrees. To facilitate the
movement of the material from feed end to the discharge
end, chains are installed inside the rotary kiln.
• The kiln rotates in the clockwise direction by standing at
the discharge end. The revolutions of the kiln about its axis
ranges between half to one rpm in some cases, while in the
others it may be 1-3 rpm.
• This depends upon the size of the kiln which may be 300-
400 ft in case of wet process and up to 150 ft in dry
process. From the feed end to the discharge end the total
time taken for the movement of material is between 2-3
hours.
Cont..
• The temperature maintained inside the rotary kiln ranges
between 300-1400 degree Celsius in dry process and
100-1400 degree Celsius in wet process.
• At elevated temperature, calcium oxide behaves as a very
strong base and it can attach the material of construction of
the shell of rotary kiln. It is therefore necessary to take
appropriate measure to increase the working life of rotary
kiln. For this purpose, lining is provided on the interior of
the shell of rotary kiln.
Merits of Lining in rotary kiln
dumper
loader
Quarry face
1. BLASTING 2. TRANSPORT
crushing storage at
the plant
conveyor
1. BLASTING : The raw materials that are used to manufacture cement (mainly limestone and clay) are blasted
from the quarry.
2. TRANSPORT : The raw materials are loaded into a dumper.
3. CRUSHING AND TRANSPORTATION : The raw materials, after crushing, are
transported to the plant by conveyor. The plant stores the materials before they are Next
homogenized.
THE CEMENT MANUFACTURING PROCESS
Raw grinding and burning
1. RAW GRINDING
preheating
kiln
cooling
clinker
2. BURNING
1. RAW GRINDING : The raw materials are very finely ground in order to produce the raw mix.
2. BURNING : The raw mix is preheated before it goes into the kiln, which is heated by a flame that can
be as hot as 2000 °C. The raw mix burns at 1500 °C producing clinker which, when it leaves the kiln, is
rapidly cooled with air fans. So, the raw mix is burnt to produce clinker : the basic material needed to
make cement.
Back Next
THE CEMENT MANUFACTURING PROCESS
Grinding, storage, packing, dispatch
1. GRINDING
silos
dispatch
bags
1.GRINDING : The clinker and the gypsum are very finely ground giving a “pure cement”. Other secondary
additives and cementitious materials can also be added to make a blended cement.
2. STORAGE, PACKING, DISPATCH :The cement is stored in silos before being dispatched either in
bulk or in bags to its final destination.
Back Home page