Professional Documents
Culture Documents
Create Blog
Sign In
Power Engineering
Cable
abstract Home
Abstract
of Installation & ABOUT ME
Maintenance of Cable upto 33KV Bhagwan Prasad
Panipat, Haryana, India
1) Route Indicator Chartered Engineer in
Power
cable route indicators Electrical Engineering having
should be provided at an interval 20 years experience in Power Distribution,
not exceeding 30 M and
also at Electrical Maintenance, Electrical Projects,
turning points of the power cable basic of SAP, Design, estimation and
route wherever practicable. costing of power distribution,EPC for indoor
substation,street lighting, Language with
Cable laying abstract English, Hindi, Bhojpuri Keen interested in
2) Electrolytic corrosion:
Sharing information/experience and help
Where
the possibility of
technical enthusiasts to update themselves
electrolytic corrosion exists, for example, adjacent to dc
traction system, the potential
on various Engineering Topics. CONTACT
gradient along the pipe-line and the cable
sheath should be specified. :amieclub@gmail.com
View my complete profile
3) Neutral
The
neutral point is earthed in such a manner that during a line-to-earth fault the
highest
rms voltage to earth of a sound phase(s) expressed as a percentage of
the highest line-to- BLOG ARCHIVE
line voltage, does not exceed 80 percent, irrespective of
the fault location, ►
2022
(3)
►
2021
(2)
4) Earthing
►
2020
(9)
The
neutral point is not earthed but a device is installed which automatically and
instantly
cuts out any part of the system which becomes accidentally earthed.
In case of ac systems ►
2019
(3)
only, the neutral point is earthed through an arc
suppression coil with arrangement for ►
2018
(9)
isolation within one hour for the
non-radial field cables and within 8 hours for radial field
►
2017
(5)
cables, of
occurrence of the fault provided that the total of such periods in a year does
not
exceed 125 hours. ►
2016
(3)
►
2015
(26)
5) Tensile Strength ►
2014
(5)
Maximum
Permissible Tensile Strength for Cables: PVC and XLPE insulated armoured
▼
2013
(21)
power
cables P = 9 D2,
►
November
(2)
Where,
P=Pulling Strength (N),
D=Outer Diameter of Cable (mm) ▼
October
(4)
Maximum Permissible
Tensile Strength for Cables: PVC and XLPE insulated Busbar size and calculation
unarmoured power cables P = 5 D2 Voltage drop calculation in cable
Maximum
Permissible Tensile Strength for Cables: Paper insulated armoured power
Cable current rating
cables
P = 5 D3
Cable laying abstract
6) Cable Pulling
►
September
(2)
For
Cables Pulled by Pulling Eye:
►
August
(1)
Expected
Pulling Force When Pulling Cables by Winch:
If
the cables are pulled by gripping the conductor directly with pulling eye, the
maximum ►
July
(4)
permissible tensile stress depends on the material of the conductor and
on their cross- ►
June
(3)
section as given below:
►
May
(4)
§ Aluminium
conductors 30 N/mm2
§ Copper
conductors 50 N/mm2″ ►
April
(1)
The
following values of pulling force are expected = (approximately percentage of
cable
►
2012
(54)
weight):
§ In
trenches without large bends 15-20 percent.
§
In trenches with 1 or 2 bends of 90°
each 20-40 percent. FOLLOWERS Report Abuse
§ In
trenches with 3 bends of 90° each (assuming the use of easy-running support and
corner Followers (231)
rollers) 50-60 percent. Next
In
ducts with bends totalling 360° Up to 100 percent”
10) Crossing
Cables laid across
Roads, Railway Tracks and Water Pipe Lines:
Steel,
cast iron, plastics, cement or earthenware ducts, or cable ducting blocks
should be
used-
a) Where
cables cross roads and railway tracks.
b)
Spare ducts for future extensions should
be provided.
c)
Spare duct runs should be sealed off.
d) Buried
ducts or ducting blocks should project into footpath or up to the edge of road,
Where
there is no footpath, to permit smooth entry of cable without undue bending
11) Diameter of
Pipe
The
diameter of the cable conduit or pipe or duct should be at least 1.5 times the
outer
diameter of cable. The ducts/pipes should be mechanically strong to
withstand forces due
to heavy traffic when they are laid across road/railway
tracks.
14) Railway
Crossing
When
the cables are laid under railway tracks the cables should be laid in
reinforced spun
concrete or cast iron or steel pipes at such depths as may be
specified by the railway
authorities but not less than 1 m measured from the
bottom of sleepers to the top of the
pipe.
On
long run ducts, it is desirable to apply lubrication to the lead or
serving/outer sheath as
it enters the duct.
Petroleum
jelly or graphite powder or a combination of both is effective for this purpose
and through lubrication will reduce the pulling tension by about 40 percent.
Identification
strips/tags of metal or plastics should be attached to the cables,
particularly if several are laid in parallel, 8 to 10 m apart. Identification
tags should also
be attached at every entry point into the buildings and at the
cable end termination The
spacing between three cables laid in one plane should
be not less than the cable diameter.
When
the cable run is several kilometres long, the cables should be transposed at
one-
third and at two-thirds of the total lengths.
Improved fire
performance or Category C1 FR
Cables
in constrained areas, does not propagate fire even when installed in groups in
vertical ducts),
Improved fire
performance for Category C2 FR—LSH (Cables in
constrained areas
with limited human activity and/or presence of sophisticated
systems)
Aluminium
conductor= A,
PVC
insulation=Y, Steel round wire armour= W,
Steel
strip armour= F,
Steel
double round wire armour= WW,
Steel
double strip armour =FF,
PVC
outer sheath= Y
With
temperatures below 3°C, the cables should be warmed before the laying out,
since
otherwise the bending would damage the insulation and protective
coverings of cables.
The cable laying must be carried out swiftly, so that the
cable does not cool down too
much
Identification
strips/tags of metal or plastics should be attached to the cables, particularly
if several are laid in parallel, 8 to 10 m apart. Identification tags should
also be attached at
every entry point into the buildings and at the cable end
termination.
The
spacing between three cables laid in one plane should be not less than the
cable
diameter.
When
the cable run is several kilometres long, the cables should be transposed at
one-
third and at two-thirds of the total lengths.
Note:
CCI
has been manufacturing EHV cables from Mid 1980s and introduced 230 kV cables
in India in the year 1993, presently upto 400 kV.
Book reference :
at
October 12, 2013
12 comments:
Unknown 20 December 2017 at 00:14
Power Cables
Reply
Reply
Reply
Reply
Nice blog.Thank you for sharing the valuable information.Keep update with your blogs...
Reply
Cable
Pulling Winch
Reply
Roller Supports
Reply
It is great to see such a piece of helpful information and thanks for sharing it.
Reply
sarah 10 September 2019 at 22:54
Reply
We can overcome this problem with the help of Cable Pusher Machine
Reply
Reply
Enter comment
Subscribe to:
Post Comments (Atom)
Explore alternate method: Whenever possible, hot work should be avoided in hazardous industry
or in chemical factory Analysis of hazard o...
Busbar size and calculation
Busbar Bus bar A bus bar (also spelled busbar, buss bar or busbar), is a str...
winding copper weight and gross weight induction motor, submersible motor
Winding and weight of induction and submersible motor – winding weight and
motor weight Typical motor, 3 Ph, 40 H, 415v Sr. ...