You are on page 1of 5

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/236742385

Risk assessment in project management: a practical tool

Conference Paper · April 2010

CITATIONS READS

2 9,462

4 authors:

Irina Severin Mihai Caramihai


Polytechnic University of Bucharest Polytechnic University of Bucharest
74 PUBLICATIONS   145 CITATIONS    53 PUBLICATIONS   90 CITATIONS   

SEE PROFILE SEE PROFILE

Amza Gheorghe Anamaria Lupu


Polytechnic University of Bucharest École Supérieure d'Electricité
113 PUBLICATIONS   177 CITATIONS    1 PUBLICATION   2 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Conversaciones informales en un programa de salud comunitaria: evaluación del proceso View project

All content following this page was uploaded by Irina Severin on 11 August 2017.

The user has requested enhancement of the downloaded file.


Proceedings of the International Conference on RISK MANAGEMENT, ASSESSMENT and MITIGATION

Risk assessment in project management: a practical tool


IRINA SEVERIN1, MIHAI CARAMIHAI2, GHEORGHE AMZA1, ANAMARIA LUPU2
1
Engineering & Management of Technological Systems Faculty
2
Control Engineering & Computer Science Faculty
University “Politehnica” Bucharest
Spl. Independentei, 313, sector VI
ROMANIA
iseverin@camis.pub.ro; m.caramihai@ieee.org; amza@amza.camis.pub.ro

Abstract: Project success has depended significantly on the ability to predict a particular outcome. Since risks
are the unpredictable part of the project, it is important for project team to be able to control them as much as
possible and make them as predictable as possible. In the case of projects current registered risks have
appeared, as follows: frequent deadline rescheduling and poor financial execution, meaning non-compliance in
time management and administrative / financial management, respectively. The paper has proposed a practical
tool: an application has been developed in order to monitor the project evolution and control the risks in
implementation, so as to mitigate them.

Key-Words: - risk identification, risk assessment, software application tool, project management

1. Introduction In order to manage effectively and


The risk management, as defined in [1], presents the efficiently the risk, an overall approach should be
systematic approach to apply the management adopted meaning that the risk is recommended to be
policies, procedures and practices to the processes associated to each process and each decision action,
related to the risks context, identification, analysis, all along the project life cycle. All staff involved in
assessment, quantification, treatment, monitoring the project implementation should be included in the
and communication so as to allow organizations to risk management processes through an opened
minimize the looses and to maximize effectively the communication, both inside and outside the project
opportunities. and an effective cost related risk management.
Taking into account the similar description Project risk management should start
of project management [2] and the fact that, through the project context drafting; that means
unavoidably, each project involves risk; active involvement of stakeholders, clear
consequently, project risks are related to the project identification of objectives, expected results,
itself and the project product / result, too. management’s limitations and threats for a certain
project, identification of interfaces with other
constrains or organizational / strategically projects
2. Risks in projects: an overview etc. This responsibility belongs to the project
A risk is a combination of event probability
manager level and includes the following items, too:
occurrence and its’ consequences upon project
 Risk identification management
objectives accomplishment, including the product /
 Assessment and analysis of risk
results expected quality level. Briefly, the risk is a
possible unplanned event; it might be positive or  Recommendation, initiation and implementation
negative. In project management the success of the of risk treatment activities up to reaching an
project depends on the ability to predict a particular acceptable (controlled) risk level
outcome. Since risks are the unpredictable part of  Establishment of an executive procedure for
the project, it appears quite important to be able to conflict related risk treatment
control them as much as possible and turn them to as  Follow up of decisions’ effectiveness
predictable as possible. A pure risk or threat is a risk  Effective communication in due time, all along
that has only a negative possibility as an outcome. the project, of risk related information
The known risks are those that one can identify, and  Adoption of urgency contingency plans and
the unknown risks are those that cannot be assurance concerning their operation ability
anticipated at all.

ISSN: 1790-2769 160 ISBN: 978-960-474-182-3


Proceedings of the International Conference on RISK MANAGEMENT, ASSESSMENT and MITIGATION

 Risk management monitoring & implementation the project constraints of cost, schedule, scope, and
of corrective actions, if required quality. Definitions of the levels of probability and
 Drafting a risk related documentation to assure impact, and expert interviewing, can help to correct
the traceability biases that are often present in the data used in this
Of course, risk management should be process. The time criticality of risk-related actions
treated in a coherent manner, but taking into account may magnify the importance of a risk.
the costs related to risk treatment processes. In d) Quantitative Risk Analysis - Quantitative Risk
project management, a quite effective and efficient Analysis is performed on risks that have been
procedure to treat and control risk is linked to prioritized by the Qualitative Risk Analysis process
project meetings, dedicated or not to risks, so as to as potentially and substantially impacting the
register and report risk related discussions and project's competing demands. The Quantitative Risk
decisions. Analysis process analyzes the effect of those risk
A good practice to notify is the risk events and assigns a numerical rating to those risks.
management plan, including project risk related It also presents a quantitative approach to making
context and limitations, risk treatment methodology decisions in the presence of uncertainty.
(processes and interfaces), risk management in- e) Risk Response Planning - Risk Response
charge staff nomination, reporting responsibility and Planning includes the identification and assignment
authority, meeting schedule, relation with other of one or more persons (the 'risk response owner') to
project documentation (or registration) and plans, take responsibility for each agreed-to and funded
relevant organizational procedures, if necessary risk risk response. Risk Response Planning addresses the
management subcontracting. risks by their priority, inserting resources and
Project risk management includes ongoing activities into the budget, schedule, and project
processes that require to be updated throughout the management plan, as needed.
project. The objectives of project risk management f) Risk Monitoring and Control - Planned risk
are to increase the probability and impact of positive responses that are included in the project
events, and decrease the probability and impact of management plan are executed during the life cycle
events adverse to the project. of the project, but the project work should be
The project risk management processes continuously monitored for new and changing risks.
include the following [3…5]: Risk Monitoring and Control is the process
a) Risk Management Planning - this process should of identifying, analyzing, and planning for newly
be completed early during project planning, since it arising risks, keeping track of the identified risks
is crucial to successfully performing the other and those on the watch list, reanalyzing existing
processes. risks, monitoring trigger conditions for contingency
b) Risk Identification - Participants in risk plans, monitoring residual risks, and reviewing the
identification activities can include the following: execution of risk responses while evaluating their
project manager, project team members, risk effectiveness. Risk Monitoring and Control can
management team (if assigned), subject matter involve choosing alternative strategies, executing a
experts from outside the project team, customers, contingency or fallback plan, taking corrective
end users, other project managers, stakeholders, and action, and modifying the project management plan.
risk management experts. Risk Identification is an The risk response owner must report periodically to
iterative process because new risks may become the project manager on the effectiveness of the plan,
known as the project progresses through its life any unanticipated effects, and any mid-course
cycle. The project team should be involved in the correction needed to handle the risk appropriately.
process so that they can develop and maintain a
sense of ownership of, and responsibility for, the 3. A case study: software for risk
risks and associated risk response actions. assessment
c) Qualitative Risk Analysis - Qualitative Risk
“The evaluation of a project’ evolution” was an
Analysis includes methods for prioritizing the
application developed starting from the following
identified risks for further action, such as
objective: to monitor the project evolution (through
Quantitative Risk Analysis or Risk Response
a Web application), starting from the basic phases of
Planning. Qualitative Risk Analysis assesses the
a project implementation (initialization, plan,
priority of identified risks using their probability of
execution, monitoring & control and project
occurring, the corresponding impact on project
closing). The main steps for the project completion
objectives if the risks do occur, as well as other
were [4, 5]:
factors such as the time frame and risk tolerance of

ISSN: 1790-2769 161 ISBN: 978-960-474-182-3


Proceedings of the International Conference on RISK MANAGEMENT, ASSESSMENT and MITIGATION

1. Documentation of project management and risk


factors
2. Identification of risk indicators and formulas
3. Program implementation for risks and distances
between performance indicators
4. Realization of a friendly user interface

Brief description of the application


The project has a time and a budget with units of
measure of hours and Euro. The user will define
these parameters in the program.
During the first phase, the user will insert
the number of parameters between 1 and 20 (in this
case: 2 parameters – time and budget)
Fig. 3. Parameter values during the 2nd prj phase

It can be seen that, whether a perturbation factor –


„Material resource” – is chosen, the values for this
step are different that those were planned at the
previous step.

Fig. 1. Parameters’ definition

It can be seen that the values for the current step are
different that those were planned.

Fig. 4. Parameters values during the 3rd prj phase

Step 3 accomplishes the same as was previously


planned.

Fig. 2. Parameters values during the first project’


phase

Hence, this aspect will affect the (global) project’ Fig. 5. Parameters values during the 2nd prj phase
risk.
The fourth step estimates the risk for each parameter
as soon as the final value was inserted:

ISSN: 1790-2769 162 ISBN: 978-960-474-182-3


Proceedings of the International Conference on RISK MANAGEMENT, ASSESSMENT and MITIGATION

Fig. 9. Budget evolution plot


Fig. 6. Parameters values during the last project’
phase It must be underlined that each chart parameter has
two characteristics: yellow – for planned values and
After the insertion finish of parameters values, by lavender – for real values (the value attained at the
pressing the „Generate” button, the statistics for current step)
each parameter will appear:
4. Conclusion
The paper has proposed an application developed as
a practical tool for project management in order to
assess the risks during project implementation and to
be able to adjust through corrective or preventive
action the project evolution to mitigate the risks. The
software considered only the most important
identified factors: the time constraint and the budget
execution. A comparison between the real situation
and the planned one is followed on-going in the
project implementation.

Acknowledgement:

Fig. 7. Plot generation

and the evolution charts can be displayed:

a) Time evolution:

References
[1] SR CEI 62198: 2002 - Project risk management –
Application guide
[2] SR ISO 10006: 2005 – Quality management systems.
Guidelines for quality management in projects, ASRO.
[3] Gerard M. Hill, The Complete Project Management
Office Handbook, Auerbach Publications © 2004,
Fig. 8. Time evolution plot ISBN:0849321735
[4] M. Caramihai – „Project” Course Notes
[5] M. & A. Schniederjans, J. Hamaker – Information
b) Budget evolution:
Technology Investment. Decision – Making Methodology

ISSN: 1790-2769 163 ISBN: 978-960-474-182-3

View publication stats

You might also like