You are on page 1of 22

AL FATEH UNIVERSITY ODAC

Division 14 Conveying system section 14200

Division 14 - Conveying Systems


Section 14200 – General

Part 1: General

1 01 Work Included
A. Comply with Division 1 and with all referenced documents in this and other
Sections of Division 14.
B. Provide all labour, material, equipment and services to complete vertical
transportation lift systems:
1. Passengers Elevators, per Section 14210:
a. Elevators No: (1), No: (2), No: (3), No: (4), No: (5), and No: (6):
- Drive: Variable Voltage Variable Frequency (VVVF) (for each lift)
- Operation Control: Microprocessor, simplex selective collective
- Designated: Arch. Drawings

C. Provide vertical transportation maintenance services in full accord with Section


14600.

1 02 Works by Other Divisions


A. legal hoistway for each lift (with divider beams separating elevator units sharing
a common hoistway), including pit and motor room with self-closing self-
locking access doors. Finished walls around landing entrances.
B. Installed pit steel to support impact loads related to car and counterweight rail
stacks, car and counterweight buffers, compensation up-pull and for motor
section loads (as applicable). Pit waterproofing and drainage.
C. Overhead structural systems to support reaction loads imposed by lift
equipment. Pockets to fasten rail brackets to building structure filled after
brackets have been installed. Support for sill brackets.
D. Finish masonry and grout, including at entrance frames where masonry walls
about and otherwise as needed.
E. Motor room mechanical ventilation to maintain temperature as 10-30°C. based
on contractor’s heat generation schedules.
F. Electric power sources:
1. Provide a ”stiffened” power supply network (high short-circuit capacity) to
produce lower voltage distortion of harmonic currents, considering use of the
converter-type drives provided for herein. Ensure that capacitor-bank phase
correction systems can minimize the distortion levels resulting from harmonic
resonance.
2. Main power feeders for each lift, to a 3-phase disconnect adjacent to the motor
room access door. Secondary disconnect(s), as needed to suit room layout.
3. Temporary power for illumination, hand-tool operation and rail hoisting.
Temporary power of ”permanent characteristics” for initial running,
testing and adjusting of lifts.
4. Signal and common panel feeders for each functional lift group, to
disconnect or circuit breaker adjacent to the motor room access door.

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

5. Two 1-phase circuit breakers per lift, connected to Normal/Standby power


sources and located adjacent to motor room access door, for use in car
lighting, car exhaust blower and duplex utility receptacles on each lift car.
6. Normal-power/Standby-power sensing circuits to each motor room, having two
pairs of contact wire terminating at a junction box: under Normal power one
pair presents a closed circuit, and on Standby power the same pair presents
an open circuit. The second pair shall present an open circuit about 20
seconds prior to switching from the Standby-power source to a Normal-
power source.
7. Fire and smoke detectors in each hoistway and motor room.
8. Fire Alarm signals to initiate Emergency Recall of elevators (to a fire access
landing). Provide two signals: one for a designated level; another for all other
levels, terminated at a motor-room junction box. In each case, two contact
wires present a closed circuit for Normal conditions and an open circuit for
Alarm conditions.
9. Fluorescent lighting in front and behind each lift control cabinet, via a switch
next to the motor room access door, connected to the Standby-power supply.
Illuminate to at least 200 lux at floor level.
10. Duplex receptacles on walls of motor room and pit, spaced at 350-cm
intervals and clear of elevator equipment, with at least one motor room
receptacle being connected to the Standby power supply.
11. A 1-phase power source connected to a duplex power receptacle and lighting
switch in each pit, adjacent to the access door.

G. Conduit of suitable size to run wire from hoistways to a remote security


monitor panel.
H. Security system hardware related to the elevator system operation.
I. Advise the Consultant, with necessary detail, of additional work items. If no
exception is noted at the time of Bid Submission pay the cost of modifications
to suit proposed lift system designs.

1 03 Regulatory Requirement
A. Supply equipment and do the work in accordance with building codes, by-
laws, regulations and requirements of all local authorities, in effect at the time
of executing the work.
B. Provide installations complying with European Standard EN-81 (or with the
American Code ANSI A17.1 - if so instructed by the Engineer “consultant”
and to any other code that governs the work. Provide the Engineer
“consultant” with prompt written notification of any regulation or requirement
known to be in process that might affect acceptability of the installation work.
C. Extra cost resulting from changes to applicable codes or regulations,
subsequent to the time of Bid Submission, shall be treated as an extra to the
Contract Price.
D. Obtain and pay for all testing, inspections and permits. Carry out tests called
for by all Inspecting Authorities and as specified herein.

1 04 Definition of Terms
A. The terms lift and elevator, as used herein, are interchangeable.
B. The term Inspecting Authorities, as used herein, refers to those authorized
agents of governments and insurance providers who are responsible for
carrying out inspections and tests an vertical transportation equipment.
C. The term Consultant or “Engineer”, as used herein, refers to an agent of the
Owner empowered to interpret drawings and specifications for vertical

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

transportation equipment systems, and to confirm that related inspections


and tests have been carried out and meet all specified requirements.
D. Terms not otherwise defined herein shall have meanings listed in the EN-81
Standard.

1 05 Coordination

A. Provide shop drawings, detailing dimensions and the methods of joining lift
work to the work of other trades. Include all required information and
templates.
B. Specific approvals are required for all work items needing co-ordination
between the contractor and other construction trades.

1 06 Materials, Systems & Workmanship

A. Provide equipment systems in a neat, accurate and workmanlike manner.


Executing the work shall include verifying all dimensions with the actual site
conditions. Provide only system designs thoroughly field-tested for the
intended application, with ample capacity to meet specified performance
criteria with long term reliable operation.
B. Install lift equipment to run smoothly and quietly, free from vibration or side-
sway. The only approved method for structurally fastening lift equipment is by
bolts, lock- washers, flat-washers and nuts. Field welding of any part of a lift
system is not permitted without prior written approval by the Consultant.
C. When welding is specifically permitted, each welder shall identify his work by a
unique code mark. Procedures and weld quality will be determined by testing
a welder’s ability, under standard working conditions, with equipment as
intended to be used on the project, in accordance with applicable regulations.
Submit certified copies of each welder’s qualifications, along with each name
and identifying mark
D. Install equipment so that access for maintenance is both safe and readily
available, and all major components are removable using conventional
means.
E. Remove debris as fast as it accumulates and keep the pit, hoistway and motor
room free from dirt, oil and grease.

1 07 Samples

A. Submit samples of all materials and finishes exposed to the general public,
including push-buttons, operating switches, plastic laminates, glass, stone or
metal to be used for cab interiors, landing entrances and signal fixtures.
Sample finishes shall be the actual finishes on base materials to be installed.

1 08 Submittals

A. Submit layout and shop drawings in ample time for considered review,
showing all lift work including cab enclosure and landing entrance co-
ordination details. Show the top clearance above crosshead and
counterweight frames and locations of equipment on top the car. Show motor
room layout (power needs, heat release), pit steel, machine beams and their
elevations, reaction loads and their locations. Show hoistway sections with
vertical and horizontal bracket spacing, signal fixtures and all other items.
3

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

B. Show all connections, attachments, reinforcements, anchorage and the


locations of all exposed fastenings.
C. Submit descriptive brochures and drawings with detailed data for all landing
fixtures, position indicators, car operating panels, lighting and ventilation
means, cab interior finish materials, door panels and entrance jambs.
D. When submittals differ from Contract Document requirements, make specific
mention of differences in a transmittal along with a written request detailing
reasons for each. Such submittal shall not relieve contractor of responsibility
to execute the work in full accord with the Contract Documents and his
responsibility for any delay, whether or not the substitution is approved.
E. Approval of submitted data or shop drawings shall not relieve the equipment
supplier’s responsibility to furnish equipment of proper dimension, weight,
capacity, speed, size, quantity, quality and installation detail, meeting the
intent of Contract Documents.

1 09 Preliminary Information

A. Ensure complete interface and co-ordination with other sub-trades. Submit


within thirty (30) working days of contract award complete data regarding
needed work by other Divisions, including:
1. Verification of hoistway plumb, and hoistway and motor room dimensions.
2. Structural supports, along with associated reaction loads and locations.
3. Voltage confirmation, power ratings, starting, running and stopping
currents.
4. Motor room heat generation.
5. Wire-count (types and sizes) for each remote-monitor panel, along with
connection diagrams from each source to each device on a panel.
6. Pulley-room (only when architecturally available overrun is adequate), pit,
motor room and service hatch access means and lighting requirements.
7. Interface between lift equipment and building structure, both for reaction
loads and for finish materials.
8. Suitability of architectural or structural elements adjacent to lift equipment,
to comply fully with governing regulations for clearances, and to meet the
rules for workplace safety.
9. Information needed to complete the work of other trades and permit
completing the lift systems work in accordance with project schedules,
including major delivery of system materials and hoisting requirements.

1 010 Technical Personnel

1 Do installation work with competent licensed mechanics directly supervised by


contractor. Provide senior field personnel (adjuster or field engineer) to assist
the Consultant with Acceptance Inspections and Testing and with subsequent
re-testing, if needed, due to a failure to deliver specified performance.

1 011 Completion program

A. Submit a detailed program for lift systems installations, co-ordinated with the
project construction schedule, containing data needed for close monitoring of
work progress, including: lift system engineering, design approval,
manufacturing, equipment delivery, as well as individual installation events
and related activities by other trades. Include material lists with delivery dates

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

and lead times for all major components. Update the schedules as required,
and submit each update for review,
B. Show anticipated building progress, including the time for work by other trades,
as well as to test, correct deficiencies, re-test, as well as for required run-in
periods. For each scheduled activity, provide the elapsed time (days),
expended time (team-hours or man-hours), actual number of men used to
perform the activity and accumulated event-days (total number and associated
calendar dates).

1 012 Organisation & Manpower

A. Submit an organization chart, showing relationships of off-site management


(directly involved with this project) to the on-site personnel who supervise
foremen, scheduling, adjusting, etc.
B. Submit a manpower chart, fully co-ordinated with the program schedule, listing
overall staff 1oading and a week-to-week basis throughout the construction
period Update the chart whenever scheduling changes are made.

1 013 Specification Corection


A. Review all Division 14 Sections and associated drawings and charts, and
report any ambiguity or discrepancy to the Consultant, as to not alter or delay
work progress. Do not proceed with affected work until all discrepancies are
clarified and corrected.

1 014 Trade Mark

A. Display no trade mark or manufacturer’s nameplate, visibly to the general


public.

1 015 Graphics
A. All that are visible to the general public shall be of custom design, with each
item and its location subject to the Consultant’s specific approval.

1 016 Equipments Warranty

A. A Final Acceptance Date for all lift systems certified by the Consultant shall
initiate the Warranty Period Guarantee all system materials, workmanship
and performance for twelve (12) months following the Final Acceptance Date.
B. Replace defective parts, not due to improper use, that develops within the 12-
months period. The Warranty period shall be stopped when remedial work is
underway, and recommenced upon completion of remedial work.
C. Final payment shall not relieve the contractor of responsibility for negligence,
poor workmanship or faulty material, within the extent and period provided for
by law.
D. Upon written notice, remedy any defect and pay all expenses for damage to
other work resulting from an elevator system defect.

1 017 Project Change Orders

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

A. In anticipation of possible future Change Orders, submit billing rates for lift
system construction mechanics, helpers and work teams, for normal working
hours and for overtime hours.

1 018 New Installation Service

A. Maintain lift systems for twelve (12) months after the Final Acceptance Date.
Include the cost in the Base Price but identify the amount to permit separating
operating costs from capital costs.
B. Maintenance service shall include systematic examination, adjustment and
lubrication of lift equipment. Repair or replace electrical and mechanical
components as needed, using only parts produced by the original
manufacturer. Replace wire rope as often as needed to maintain safety. Keep
an adequate stock of parts on site.
C. Use technically qualified maintenance personnel (different from the
construction force), directly employed and supervised by Lift Installer, in
sufficient number and skill levels to do all maintenance inspection and repair
without unreasonable delay.
D. Do routine examination and repair during regular working hours, without
expense to the Owner. Provide emergency call-back services (24 hours/day,
7 days/week) during the 12-months without cost to the Owner, except for
malfunctions due to misuse or abuse of lift equipment.

1 019 Interim Maintenace

A. Provide interim maintenance of completed lifts, taken over by the General


Contractor or Owner for construction use or for tenant fit-out.
B. Submit separate prices (per unit, per month) for the use of one car of each lift
group.

1 020 Full Mainntenance Service Contract


A. At the time of Bid Submission, propose a full-maintenance program meeting
schedules and procedures of Section 14600, for 5-years and for 10-years
following completion of the New Installation Service included with the
Contract Price.
B. Base the proposal on labour rates and material indices in effect at Bid
Submission, but subject to annual escalation. State the labour rates and
material indices used, as well as percentages to be escalated by each
Escalation shall not exceed three (3) percent per year, throughout the term of
the maintenance contract.
C. Include preventive maintenance procedures at least twice monthly for tower
elevators, and at least monthly for all other low-rise elevators:
1. Give the Property Manager a service receipt each time maintenance is
carried out, identifying the work done.
2. Do inspection and repair work in normal working hours, excluding
holidays.
3. Provide emergency call-back services (7 days/week, 24 hours/day) to
correct any shutdown or malfunction due to equipment maladjustment or
part failure.

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

4. Check Standby Power and Fire Emergency operations every two (2)
months and deliver written certification of successful operation to
Property Manager.
5. Warrant that lifts are operational no less than ninety-seven percent (97%)
of the normal business hours, in each functional area, as determined by
formula:
[(Total Available Time) - (Down Time)] x 100

Total Available Time

a. Available Time: Normal business hours, all cars.


b. Down Time: Duration the lifts are out of service (due to equipment
failure or maintainer’s shut down) during normal business hours.
Equipment taken out of service for normal maintenance or scheduled
repair shall not be counted as Down Time.
D. The Owner shall have the right to terminate the Maintenance Agreement on
thirty (30) days written notice, for any of the following reasons:
1. Sale of property.
2. Failure to maintain equipment operation as original installation, due to
Maintainer’s inability to correct problems.
3. Lift equipment being removed from service for excessive periods, over an
extended time span, due to Maintainer’s inability to correct problems.
4. Lift system not performing as specified herein, for an extended time
period, due to the Maintainer’s inability to correct problems.
E. At the time of Bid Submission, state the current hourly billing rates for a
maintenance mechanic and for a service team, for normal working hours and
for overtime hours.
F. The Owner may, at his discretion, exercise the option of accepting the
maintenance proposal at any time within the New Installation Service period.

1 021 Alternative Prices

A. Alternative prices include all labour, materials, respective overhead,


disbursements and profit, to be added to or deducted from the Bid Price, for
any item selected by Owner.
1. REMOTE MONITORING: Provide all devices (other than leased data lines)
to permit monitoring all lift system operations, at a location remote from
the project site.
a. Automatically record equipment shutdowns and other operational
problems. Provide means to create hard copy reports of such events
(date, time, nature of problem, action taken, by which mechanic, etc.).
2. FIRE EMERGENCY IN-CAR OPERATION; Provide, in the main operating
panel of each passenger lift, a key-switch (ON/OFF) with jewel and a
car-call cancel button (or switch position).
a. Allow for the In-car Operation to be activated after a fire emergency
condition is detected by the building fire alarm system and the in-car
key-switch is set to its ”ON” position after having been recalled to the
”designated level”.
3. TENANT SECURITY CARD SYSTEM: Install a card-reader, provided by
Security Sub-contractor, on an elevator car. Provide a locked cabinet in
the motor room for security interface wiring and terminals, sized to hold
devices for all cars of a group.

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

Part 2: Product

2 01 EQUIPMENT LOCATION
A. Locate motor rooms as indicated on architectural drawings, with motors and
all related equipment at the same level.
1. Provide machine beams to interface the hoisting machine and sheaves
with building structure, having shelf-angles at each side, tie-down bolts,
ancillary bed-plates, metal flooring and overhead support stands, as
needed. Provide bearing plates and anchors, as required to secure
machine beams to the structural supports.
2. Where structural drawings do not show a floor slab immediately on top of
the hoistway, provide suitable solid-metal flooring to meet requirements
of all governing authorities, having a non-slip steel checker-plate surface
or resilient vinyl over a metal floor.
B. Ground all non-conducting metal parts, including controller cabinets.
C. Provide metal and angle iron guards at all floor openings to protect against
accidental contact with moving rope.

2 02 CONTROLLER
A. Provide a sheet metal cabinet with removable hinged doors (key-locked) and
with filtered ventilation sufficient to maintain interior temperature at a
reasonable level. Position the controller cabinets securely on self-supporting
steel frames, so the lowest operating part is more than 150 mm above the
floor.
B. Use relays only for safety, dispatcher backup and power circuits. Design
relays for electrical and mechanical life equivalent to 30-years of operation.
Design the contacts with a wiping action to ensure maximal conductivity.
C. Use microprocessors for all logic functions (motion control, dispatch, car
control, etc.). Use crystal-regulated frequencies. Provide dispatch programs
in EPROM with at least 25-percent spare capacity. Power each processor by
a separate power supply. Isolate inputs and outputs with optical devices or
relays.
D. Use easily removable printed circuit boards for all solid-state devices other
than high power SCR’s and rectifiers. Protect circuits from oxidation. Design
solid-state circuits to operate in the anticipated environment, with
consideration to typical humidity.
E. Make wire connections through properly dimensioned pads (no patched
connections). Incorporate noise suppression devices in power supplies,
inputs and outputs.
F. To ease testing and troubleshooting, ground one side of control power supply
used for external circuits (outside microprocessor or solid-state devices, as:
relays, lights, limits, locks, buttons, etc.). Arrange safety circuits to not be
compromised by accidental grounding of control circuits.
8

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

G. Install wiring runs neatly. Terminate wire at studs or terminal strips, with
connections to ensure substantial electrical and mechanical integrity. Identify
all major components exactly as indicated on wiring diagrams by engravings,
lamicoid or metal tags mounted immediately adjacent to the component.

2 03 POSITION ENCODER

A. Simulate lift motion and position through electrical coupling. Generate primary
data for all functions related to car position (position and direction, slowdown
and leveling, call cancellation, etc.). Design the unit so parts are easily
accessible for adjustment.
B. Accomplish electrical stepping using solid-state devices, pulse-generators or
magnetic switches (do not use electromechanical stepper switches).
C. Automatically reset the simulated position at terminal landings when it is out
of step relative to actual position.

2 04 GUIDE RAIL
A. Provide standard T-section rail (hot-rolled structural steel) with guide surfaces
accurately planed or ground, and sufficiently precise tolerance for Class A
rating. Overall length of each pair of rail stacks (car or counterweight) shall be
equal. Total thickness variation of each running surface shall be less than
0.25 mm, measured from the base.
B. Fix rail brackets to building structure so no movement can occur. Through-bolt
the rail bracket. Pin adjustable brackets after final alignment, with bolts and
nuts.
C. Securely fasten the guide rail with suitable slip-clips and brackets. Rail slip-
clips shall contain brass inserts and be properly secured (remain in position
even if fastening bolts become loose). Place and support the guide rail to
prevent distortion due to eccentric loading of the lift car, or application of a
safety device.
D. Review structural drawings to verify the locations of rail supports through the
hoistway. Size the guide rail for indicated spacing between successive
supports, using suitable rail size (or rail-backing) to prevent deflection
affecting ride quality. Advise the Consultant of any structural support
deficiency, or install intermediate support as needed to provide the specified
ride quality.
E. Align and plumb the guide rail with metallic shim (5-20 mm) between rail
bracket and rail back. Shims to secure alignment and maintain orientation
even if fastening bolts loosen.
F. Use steel splice plates at least 20 mm thick. Machine rail contact surface of
splice plates and back of the guide rail to match joints at the rail face with
riding surfaces in the same plane and all joints are closed. Provide at least
four through-bolts per rail end (eight per fish-plate) Locate rail joints to not
interfere with support brackets or divider beams. Do not cut, grind or
otherwise modify divider beams (or structural beams).
G. Verify structural tolerance and hoistway plumb as within ± 25 mm at all
formed walls. Use jack bolts so rail rests on and is attached to steel structure
in the pit, spanning the car rails and the counterweight rails. Align car and
counterweight rails so:

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

1. Distance between rail faces does not vary by more than 0.75 mm at any
point, with cumulative variation less than 1.5 mm over any 30-meter length.
2. Align guide rail faces so arrows on alignment gauge indicate zero tolerance at
brackets, and no more than 1.5 mm at any intermediate location.
3. Plumb the guide rail so the measured distance (using a thumb gauge)
between any rail face and its respective work line, varies no more than 0.75
mm at any point in the X or Z planes, and cumulative variation does not
exceed 1.5 mm over any 30 m.
4. Protect machined surface with factory-applied coat of suitable corrosion
protection (readily removable after rail installation). Protect non-machined
surface with factory applied paint coat. Protect the guide rail against adverse
weather throughout the construction period. Remove corrosion and re-paint
non-machined areas prior to Final Acceptance testing. Corroded or damaged
rail will not be accepted.
5. Arrange rail stack length to compensate for building compression (6 mm per
4 m) with from 150 to 300 mm top and bottom clearances. Use jack bolts at
the bottom, and provide anti-snag guards to prevent fouling the rope or
snagging traveling cable.

2 05 TERMINAL STOPPING DEVICES


A. Provide normal terminal stopping devices (NTSD) to automatically and
exponentially slow and stop an elevator at top and bottom terminal landings,
under any load other than overload, and from any speed attainable in normal
operation. Design NTSD to function independently of normal stopping means,
and independently of final terminal stopping devices (FTSD). Design NTSD to
operate until the FTSD is actuated. NTSD designs that allow an elevator to
enter the FTSD shall not be accepted, nor shall high-speed stops be
considered equivalent to exponential slowdown.
B. Install slowdown and normal stopping devices on top of each elevator wholly
enclosed in dust-proof steel casing. Arrange that, as an elevator approaches
a terminal landing, the device causes a roller (noiseless tread mounted on a
moveable arm) to contact a cam in the shaft and operate a stop mechanism
that (automatically) brings the car to a smooth stop at the terminal landing.
Arrange the entire width of roller tread to engage the cam.
B. Provide FTSD to automatically stop an elevator (car and counterweight)
within top and bottom over-travel spaces, independently of buffers and
NTSD. Through-bolt or dowel the final limit switch brackets, after adjusting
an elevator but prior to doing safety tests for the Inspecting Authorities.

2 06 FURRING
A Review architectural and structural drawings to determine where hoistway
furring is provided. If required for code clearance, provide sheet steel fascia,
reinforced and supported.

2 07 GOVERNOR ROPE
A. Provide rope with manila or sisal core meeting governor manufacturer’s
specification. Fasten both ends together at the safety actuator and pass the
rope over a governor sheave at top and through an adjustable tensioning
device in the pit.

10

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

B. Restrain rope sway to prevent contact with a moving elevator at any point of
travel. Design retainers for minimal friction or noise and to preserve rope life.
Space retainers at appropriate intervals.

2 08 CAR SAFETY & GOVERNOR


A. Use a speed governor to operate the safety and stop a car running at
excessive speed. Include means to cut electric power from a motor and apply
the brake prior to safety application. Include means to slow the car when
speed exceeds 55 percent of the difference between rated speed and
governor tripping speed.
B. Design the safety to release by moving the car in the UP-direction. Provide a
switch to cut motor power and apply the brake, if a safety is applied without a
governor tripping.
C. Arrange the governor system (governor, rope & tension sheave) so the carrier
will not release due to system dynamics when a car is subjected to an
emergency stop in either travel direction. Provide rope guards on governor
tension sheave.
D. Provide means to prevent uncontrolled motion of the elevator car within
landing zones, caused by control system failure and/or brake failure and/or
drive system failure.

2 09 LOAD WEIGHING
A. Provide separate devices for each lift car, able to give multiple output signals
in the range of 30-80 percent of rated capacity, with long-term accuracy ± 5
percent.

2010 CAR FRAME & PLATFORM


A. Construct the frame of steel channel, plate or angle, all securely bolted or
riveted. Do not use iron castings, but rolled or formed steel members are
allowed. Reinforce and brace the frame to relieve a cab enclosure of any
strain under non-uniform loading.
B. Ensure that no permanent set occurs when a safety device is applied. Use at
least four brace rods to support the platform, fastened to vertical side-stiles,
secured by steel bolts (welding not permitted). Where brace rods are
attached through slotted holes, they shall be pinned with bolts of ample size.
C. Construct the platform with a structural steel frame, filled with two layers of
structural grade plywood with a depression to receive a finished floor (per
architectural drawings). Mount the platform on isolating pads to prevent
transmitting noise or vibration from the frame to car enclosure. Provide
sufficient float to allow load- weighing devices to monitor eccentric loads.
D. Design for no direct metal-to-metal contact between a car enclosure and
frame, except for occasional use of metallic flex (mounted and run to provide
vibration isolation).

20 11 CAR POSITION INDICATOR


A. Provide a digital display at top of each car-operating panel, using current
technology for vacuum fluorescence, 16-segment LED or high-resolution
11

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

electro-luminescence, having a life expectancy over 20,000 hours.


Continually display both position and direction, corresponding to the landing
at which a car is stopped or is passing. Provide alpha-numeric symbols at
least 35 mm high.
B. Sound a soft tone as the car stops at or passes a landing (distinguish the tone
from any sound used to denote push-button actuation). Provide volume and
pitch controls in the service cabinet.

20 12 CAR EMERGENCY LIGHTING


A. Provide a battery powered lighting system designed to operate immediately in
the event of electric mains power failure. Use at least two lamps to illuminate
operating panels with at least 10 lux, for up to four hours.
B. Use a sealed rechargeable battery (3-years maintenance-free) with trickle
charge circuit to maintain battery readiness at all times. Charge the battery
only during Normal Power supply. Do not illuminate during Normal Power
other than for testing.
C. Provide a charger pilot-light (charging) and a switch in the service cabinet
(manual test of battery and lamps). Install the unit on top of the cab, not
easily removable.
D. Obtain Consultant’s approval of the design and location of all in-car
components.

20 13 WORK LIGHT AND PLUG


A. Provide 10-A, 240-Vac receptacles, on top and under each elevator.
B. Provide a pendant mounted work light with wire lamp-guard and switch, at the
top and a guarded fixed lamp with switch underneath.

20 14 UTILITY RECEPTACLE
A. Provide a 10-A, 240-Vac duplex receptacle in each cab supplied from a
separate power source than that used for lighting and ventilation. Obtain
Consultant’s approval of design and location.

20 15 CAB VENTILATION
A. Provide cabs with 2-speed centrifugal exhaust fans, able to move at least
0.165 m³/s and 0.280 m³/s, developing at least 2.5-mm static pressures.
B. Design to bring air into the cab through ventilation slots near the base of walls,
and to exhaust through a ceiling mounted fan. Provide a screen grille over the
intake. Protect the fan from damage.

20 16 DOOR REVERSAL SYSTEM


A. Protect door openings with a solid-state infrared-web safety system using
electronically operated devices on the leading edge of car door panels,
specifically designed for elevator door applications and enclosed in an
insulated chassis. Arrange the device to:
1. Give totally silent operation (no moving parts) and present a clean
appearance.
2. Be capable of giving long-term, reliable operation.
3. Be equipped with visible diagnostics (on the device).
4. Provide the specified clear opening and protect the entire entrance width,
by:
a. Triggering protection when any object is in the entrance.
12

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

b. Causing the doors to reopen, without engaging the object.


c. Protecting the entrance for the full travel distance of its door panels.
d. Arranging that, after the elapse of normal door open dwell time, it can
provide limited door reversal (retract sufficiently to permit a person
passing through; continue closing when the detection zone is clear).
B. Upon a failure of the door protection system, move the lift slowly to the next
served landing and shut it down. Provide a signal at Security panel to indicate
the failure.

20 17 DOOR EQUIPMENT
A. Provide all devices for door operation: hanger, track, electric contact, closer,
relating mechanism, linkage, gibs and all related devices needed for correct
door operation. Use uniform mounting hardware. Design for a minimum of
noise.
B. Design the track and sheave for no metal-to-metal contact so that regular
lubrication is not required for smooth operation. Provide 2-point suspension
hangers and 70 mm (or larger) diameter sheaves with sealed ball-bearings
mounted on stands directly fastened to sliding door panels. Equip hangers
with ball-bearing eccentrics, adjustable to take the door up-thrust.
C. Use approved interlocks (with necessary unlocking device), separate interlock
circuits for every 10 landings served all controlled by a single fuse (so circuit
grounding will blow the fuse and stop the car from running).
D. Equip each landing door with a counterbalanced self-closing device (close a
door from any point of normal travel). Cushion door closing with continuous
interlocking flexible astragal and limit the gap between closed door panels to
less than 12 mm.

20 18 ENTRANCES
A. Provide 1.5 hours fire rating by a recognized testing authority. Provide a
metallic label on the hoistway side of landing door panels and frames,
attached by rivets.
B. Provide complete entrances with: frame, jambs, transom (as applicable), door
panels, sill and support angle, struts, full length header (5 mm thick) bolted to
each strut and arranged to receive an applied solid-bar or extruded track, full
length 3-part dust cover (with tear-drop fasteners - remove cover without
removing screws), fascia, sight guards, toe guard and all necessary items.
Provide grouting at the landing sill.
C. Mount adjustable rubber bumpers on each strut to prevent landing doors
opening past the entrance frame. Bumper is a 12-mm diameter bolt with 25-
mm diameter rubber.
D. Construct frames as one continuous piece for each side jamb, extending from
sill to header jamb. Provide an internal structural system for each side jamb
to rigidly define and maintain its profile. Mitre and grind smooth all joints.
E. Construct door panels of sheet steel, internally braced to ensure flat surfaces
and with substantial support for mounting hardware. Incorporate two
removable gibs per panel.
F. Provide landing sills (strut to strut) to support 4.5 KN point loads, anywhere
on its length. Design the support to securely clamp the sill, eliminate gaps
between sill bottom and adjacent supports and prevent rotation on major axis
when 4.5 KN point load is applied at any sill location.
G. Provide fascia plate (properly reinforced and supported) extending from top
of header to sill above, and from top header (highest entrance) upwards.
Provide a toe guard (properly reinforced and supported) at the lowest landing,
13

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

gradually beveled to the wall with straight portion to equal the distance from
the landing to top of a fully compressed car buffer.
H. Provide 3 mm raised tactile designations (alphanumeric) of the same colour
and finish as the entrance jamb, with at least 50 mm high characters centered
horizontally on each jamb width, 1500 mm above the finished floor.
I. Provide sight guards for each leading door panel; of the same finish as the
panel face. All visible metal surfaces shall be continuous, without blemish or
distortion.

20 19 KEYS, SWITCHES & LOCKS


A Except for hoistway access, switches for: Fire Recall, Standby power,
Independent Service, etc., as well as all other keyed switches and locks in
areas accessible to the general public shall be made to suit the Project’s
master key system.
B. Switches shall be keyed-cylinder type, designed to accept replaceable
cylinders suiting the master key system.
C. Provide necessary boxes for Fire Emergency Recall keys, as located by
Consultant.

20 20 FIXTURES
A. Obtain Consultant’s specific approval for each fixture type, style, finish and
fastening.

20 21 SPARE PARTS
A. Provide a complete parts catalogue, including original source and designation
of all purchased components. Provide a listing of current prices.
B. Provide spare parts on request for at least fifteen (15) years subsequent to the
Final Acceptance of equipment system.

20 22 CONTAINERS, CABINETS & DRAWINGS


A. Provide a metal container for clean wipers, in each motor room. Provide a
parts cabinet in each motor room (sheet steel, baked enamel finish) with at
least 0.15 m³ capacity. Provide a second similar cabinet, containing:
1. Lockable, impact resistant area at the top, with slots and shelves for
replacement PC-boards and diagnostic modules. Mark each slot with
board or module name.
2. Storage area to hang a full complement of as-built drawings including: field
record controller, schematic and wiring diagrams; logic flow diagrams; layout
plans and sections, cab drawings and installation mechanic’s notes. Use
Masonite hang-up boards (smooth both sides) with retainer clips at the top.
B. Maintain all drawings, schematics and listings up to date, with legible
changes reflecting the actual installation condition. Drawings, spare parts and
cabinets shall be the Owner’s property and remain on-site even if a service
contract is terminated.

20 23 HARMONIC DISTORTION REDUCTION


A. Arrange the electrical feed to the drive system with isolation transformers so
arranged as to minimize the level of harmonics-related current and voltage
distortion, resulting from the operation of the power converters used for the
VVVF elevator drives.

14

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

B. Provide the engineer with all necessary data to facilitate his design of the
power supply network, as to result with minimal current and voltage distortion.

20 24 WIRING MATERIALS
A. Provide all wiring, conduit and associated devices to interconnect all parts of
the lift equipment systems. Comply with prevailing codes.
B. Use stranded copper field wire (except multi-conductor cable other than
traveling cable may be stranded or solid), with at least 10 percent spare wire
throughout signal runs (including wire between hoistways and remote
panels).
C. Use insulated wire with a moisture-resisting, flame-retarding
sheath. Use aluminum flexible conduit (where use is
permitted). Use colour coded wire in all multi-conductor
cable.
D. Provide separate junction boxes to connect non-lift devices (telephone,
intercom, video, etc.) on a side of a controller cabinet. Use waterproof
terminal labels.
E. In addition to 10 percent spares, provide each elevator with:
1. At least 6-pair of twisted-shielded, stranded-copper (18-AWG) for the
Owner’s future use.
2. At least 6-pair of twisted-shielded, stranded-copper (18-AWG) for the
Security
3. One RG-11 coaxial cable with stranded-copper core (Belden 9212-18 or
equal) for the Owner’s future use.
F. Provide flexible traveling cable connecting devices on the car to a junction
box (no direct connections to controller devices). Use alphanumeric
designations to facilitate service. Supply traveling cable specifically designed
for elevator use, containing:

1. Stranded-copper conductor with flame-retarding moisture-resisting cover.


2. Shielded wire sufficient in number for all signal communications between
the car and motor room.
3. Two pair (14-AWG) for duplex utility receptacle. Isolate security wiring and
Owner’s wiring from high energy AC-circuits.
4. 10 percent spares in each cable (in addition to wire designated for the
Owner and Security).
5. 12-pair of twisted-shielded stranded-copper (18 AWG) and one RG-11
coaxial cable (Belden 9389-18 or equal) for the Owner and Security
needs. Provide at least 2000 mm extra lengths (at the car and at the motor
room cabinet) neatly coiled, tied and labeled.
6. A steel-supporting strand when suspended weight exceeds 35 kg.
7. In each hoistway, traveling cable of near equal diameter, flexibility and
numbers of conductors.
G. Run wiring from the car to a car-top junction box, and onwards to an
intermediate junction box, thence to a machine room controller (traveling
cable wired directly to controller devices shall not be accepted). Run all wire
for remote panels and for the Owner’s uses onward to the base of hoistways,
to a terminal strip.

20 25 ELECTRICAL DIAGRAMS
A. Submit six (6) sets of complete wiring diagrams, schematic field record
diagrams and connection diagrams. Show electrical connections, functions
and operation sequences.
B. Provide the Consultant with four (4) sets of bound, reduced-scale prints.
Provide one full-sized set of Mylar reproducible prints and a full-sized set of
15

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

blue-line prints protected with plastic laminate (10 mil) for mounting in a
machine room cabinet.
C. As part of schematic diagrams, provide an index listing the locations of
electric components and wire interconnections for all: relay coils, relay
contacts, integrated circuits, etc., so that the position of any device shown on
the drawings can be readily determined. Include a copy of the connection
diagram provided under Preliminary Information.
D. If changes are subsequently made to the installation, provide an additional
three (3) prints and one (1) reproducible, of each affected drawing showing
the changes made.

20 26 TEST DATA FORM


A. After installation is complete and prior to Initial Acceptance Tests, submit a
Test Data Form certifying that the group is complete and ready for inspection
and testing by Consultant. The technical person responsible for doing the
installation work shall sign Test Data Form.
B. Include a check list for all specified items and pertinent performance data, as:
1. Brake-to-brake time, operating time, rated speed and measured speed.
2. Door open, close and dwell times.
3. Starting, running and stopping currents. Running full load voltages.
4. Slowdown and limit settings. Governor settings. Settings of adjustable
devices.
C. List all safety device settings and state whether they have been checked and
adjusted.
D. Provide a checklist for the dispatch system, listing all features and test
procedures to be used for each.

20 27 MANUALS
A. Four (4) weeks prior to completing all installation work, provide:
1. A complete parts catalogue, including original source and designation of
purchased components.
2. Operations manuals with manufacturer’s detailed operating instructions; a set
of reduced-scale drawings; step-by-step description of special operations
(Standby Power, Fire Emergency, Independent Service, Security, etc.).
Include diagrams for all operating panels, with functional descriptions of all
indicators and switches.
3. Maintenance manuals, describing all procedures needed to keep equipment
in proper operating condition; a Troubleshooting Quick Reference for easy
categorization of problems; copy of Section 14600 – “Maintenance”. Indicate
all adjustments needed to obtain required operations and performance
parameters specified herein. Include a copy of completed Test Data Forms
for each group.
4. Provide manuals for all monitoring systems, including: hardware, system and
application software, hardware arrangement (to chip, bus and timing levels),
hardwired connection points (signal characteristic and information taken
therefrom), maintenance trouble-shooting procedures and reference material
required to ensure complete documentation of the overall monitor system.
5. Provide operating instructions in such detail that relationships between the lift
systems and monitor displays can be readily inferred. Include sufficient data
to allow predicting lift system response patterns, based on instantaneous
data for car and landing calls, car positions, running status, group operation
mode, etc.

16

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

B. For each manual, provide a title page with project name and unit designations.
Number the pages consecutively, divide information into logical sub-sections
and provide a table of contents.
C. When presenting manuals to Consultant, provide a complete demonstration
for the Owner’s staff, of all items dealt with in the manuals.

20 28 COMMUNICATIONS SYSTEM
A. Install a complete 2-way hands-free intercommunications system with speaker
behind perforations in a car operating station, or above the car ceiling.
B. Provide master stations at Security and Fire Control panels, with slave
stations in each elevator car and motor room. Arrange for Security staff to
initiate communications in response to an Alarm signal from a lift car. Provide
2-way communications between:
1. Security and any one car or motor room.
2. Security and all cars of a group at the same time.
3. Security and all slave-stations (cars and motor rooms).
4. Fire Control panel and any one car or motor room.
5. Fire Control panel and all cars of a group.
6. Fire Control panel and all slave-stations (cars and motor rooms)
simultaneously.
7. Fire Control panel and Security.

20 29 MONITORING PANEL
A. Provide a security panel with performance monitor, consisting of; computer(s),
keyboard, monitor(s), fixed and floppy disc drives and a printer. Work from
data taken at discreet hardware elements, rather than from elevator system
software.
B. Bring all data points to connectors (or terminal strip) at a common location in
the motor room, then to the base of hoistways in preparation for running to
Security Desk or Fire Control panels. Wire from terminal blocks at the base of
hoistways, to terminal blocks on remote panels.
C. Provide Security Desk with a colour monitor, full-function keyboards with key-
switched lock-on and lock-off.
1. Provide easy selection of screen displays using interactive software, and
ensure that alarm conditions are printed immediately, regardless of monitor
display.
2. Provide a range of formatted display screens showing all relationships
needed to observe unit and group response to traffic demand. Arrange
information screens to display in real-time (for normal monitoring) and at
selected rates (for playback), with screen selection and rate selection made
by simple keyboard entries.
3. Display alarms (emergency stop, car alarm, premature door opening,
malfunctioning door protective device, speed beyond specified limits,
improper leveling, etc.). Cause a buzzer to sound and display the affected lift
(provide separate means to reset the buzzer and display). Store alarm data
sequentially for at least 10-days operation. Provide keyboard means to print
alarms and to reset the accumulation process.
4. Provide a 2-colour printer with tractor drive, to print alarm conditions in red
colour and everything else in black (alternately, use a separate printer for
alarms). Arrange all print options to be implemented by keyboard entry.
D. Provide Fire Control panel with display of car position and door status, group
and unit operating modes, and operating status for all elevators
simultaneously. Provide control devices, using miniature LED indicators and
switches for:
17

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

1. 3-position (On-Auto-off) fire-recall key-switch.


2. Indicators for each car, when running on In-car Emergency mode.
3. Standby Power selector-switch (each group).
4. 1ntercommunication master station.
5. Items defined elsewhere as being located at the CACF panel.

Part 3: Execution

30 1 SITE CONDITION INSPECTION


A. During construction of building structure and prior to installing any elevator
equipment, examine hoistways and machinery spaces to verify that no
irregularities exist that can affect the work quality specified. Note particularly:
1. Hoistway plumb (+ 25 mm), hoistway, pit and overrun dimensions.
2. Support areas for beams, brackets, etc., both in pit and machinery
spaces.
3. Divider beams between adjacent elevators in a common hoistway.
4. Pit dimensions and drainage.
5. Access means to pits, hoistways and machine rooms.
6. Adequacy of power sources, illumination and ventilation.
B. Report defects in writing to Consultant.

30 2 CRATING
A. Crate components to prevent damage and allow proper storage. Use a rigid
crate with internal membrane to protect from moisture, and rigid internal
supports designed to suit component shape. Use a numeric designation for
each crate (in plastic folder, securely attached) and cross-reference the list of
materials, to help examination of contents.
1. Car slings (safety planks, safety blocks, crossroads, styles) and
platforms. Crate each separately.
2. Buffers, pit steel, cams and switches.
3. Door frames, door panels and associated entrance systems. Crate door
panels for storage on their leading or trailing edges, to prevent
distortions.
4. Car cab enclosure and interior finish systems.
5. Switches, signal and operating devices, wire systems.
6. Controller and drive systems. Machine and bed-plate systems.
7. Supports and fastenings (guide rail, cam and switch brackets).
8. Hoisting, compensating and governor rope.

30 3 DELIVERY AND STORAGE


A. Supply material in ample time to meet construction schedules, particularly:
inserts, anchors, bearing plates, brackets, supports and bracing. Ensure that
templates and diagrams (co-coordinating work by other trades) are received
on time.

18

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

B. Store material to prevent damage, deterioration or loss of essential properties.


Store in original protective packaging, taking precautions to protect finish.

30 4 CAB INSTALLATION
A. Set the cab plumb on its platform, in alignment with landing entrances, with
sound and vibration isolation between the cab and its structural frame.
Assemble the cab and associated components so the noise level from
operating all lift equipment does not exceed maximum noise limits specified
herein.
B. Install only undamaged architectural material; any material damaged in transit
or handling shall not be set. Prior to Final Acceptance tests, remove
protective covering from finished or ornamental surfaces; clean and polish
with due regard to material type.

30 5 CAR & COUNTERWEIGHT BALANCE

A. Set the empty car (doors closed) at mid-point of travel, hanging centered
between its rails with top roller guides removed, and balance the car so that,
with its roller guides adjusted, there is no pressure on any roller.
B. Arrange equipment so that at any point of travel, the force on guides does not
exceed 110 N for cab loading between no load and full rated load.

30 6 ENTRANCE INSTALLATION
A. Set frames and sills in perfect alignment with guide rail, prior to finishing lobby
walls. Secure the sill to building structure by support angles or substantial
brackets. Secure frames at sill and header. Secure frame and header to
building structure.
B. Install struts, fascia, toe-guard, sight guards and associated devices that
complete the entrance. Plumb frames to within 1.5 mm, and set sills to within
1.5 mm of level, across the entire entrance.
C. Install door panels and related hardware for smooth and quiet sliding. Adjust
the doors so that 110 N force applied horizontally (pushing doors apart) does
not produce a visible gap between panels of center-opening entrances.
D. Adjust the entrance so that, with the closing device disconnected, doors can
be moved from any initial position by a force of less than 27 N per panel
applied horizontally at the mid-point of the door in line with the direction of
normal door motion.
E. Install fascia plate (including support and reinforcement) from top of header to
the sill above, above the topmost header and over any steel beam at front of
the hoistway. Install a toe guard below the bottom sill.
F. Install only undamaged architectural material; do not set material damaged in
transit or handling. Prior to Final Acceptance tests, remove protective
covering from finished or ornamental surfaces, clean and polish with due
regard to material type.

30 7 WIRING INSTALLAT LON


19

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

A. Run fixed wiring in conduit or duct (painted steel, galvanized steel or


aluminum). Do not use flexible conduit longer than 900 mm (except type SO
power-cord used between fixed car wiring and car door switches. Use steel
compression fittings for metallic tubing; set screws are accepted only when a
separate ground conductor is included.
B. Interconnect all hoistway conduit and wiring, traveling cable, car wiring and all
remote alarms, indicators and controls, etc., from the device to terminal
blocks mounted in the appropriate controller cabinet or selector device.
C. Traveling cable shall have an intermediate junction box, so that electrical
connections to controller devices first occur at a convenient terminal strip,
properly identified.
D. Use a separate junction box for each elevator, mounted outside its control
cabinet, for wiring related to Security and Intercommunication systems as
well as for all spare wire and those designated for Owner’s use. Connect all
wire to identified terminals using permanent waterproof labels. Run wire for
security and Intercommunications to an interface terminal box, common to all
cars of a group.
E. Run electric wiring (including spares and shielded wire) between terminal
blocks. Make no splice (provide field wiring and component wiring sufficiently
long). Connect coaxial cable with approved connectors (ensure at least 97%
continuous shield).
F. Check all wire (including spares) for continuity and ground. Ensure that
terminal strips and connectors for shielded wire maintain proper ground
continuity (minimize potential for signal deterioration).
G. Use colour coded wire in multi-conductor cable. Identify each wire and mark
each group as to destination, with waterproof marker. Identify connections at
intermediate terminal blocks with waterproof label. Mark individual wire, multi-
wire cable and terminals with waterproof markers.
H. Provide legible waterproof lists of colour and number codes for all field-wiring
runs, attached to the side of a controller cabinet.
I. Maintain the availability of 10% spares throughout signal runs, without
restricting wire for Security and Owner’s use. Ensure that wire for
Intercommunications, Owner’s use and Security are all isolated from high
voltage AC circuits.

30 8 PAINTING
A. Apply a rust inhibiting paint, either in the field or at the factory, to all exposed
ferrous metal surfaces of control cabinets, machines, struts, headers, dust
covers, rail brackets, car frames, buffers, ladders, working platforms and
other ferrous metal products supplied under this Section. After installation
and final cleaning re-paint non- machined surfaces as required.
B. Ferrous metal surfaces that are concealed in the completed work shall have a
factory applied primer and finish coat of rust inhibiting paint. After installing,
but before work is done to conceal, clean and re-paint damaged areas.
C. Field paint (or factory plate) wire duct and enclosures, switch boxes, signal
boxes, junction boxes, terminal boxes, push-button boxes, rigid conduit,
trough, toe guards, fascia and all brackets that support the fixtures. Paint
sheaves and other moving parts in bright yellow.

30 9 CLEANING
A. Prior to the start of Acceptance Inspections and Tests, ensure that all
installation work has been completed, including:
1. Clean top of car, machine room, pit and hoistway. Blow out the controllers.
2. Ensure that all wiring runs are neat; and all spares are connected to
terminals.
20

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

3. Remove all non-permanent equipment from machine spaces.

30 10 RECALL TO LOBBY
A. Actuating a parking command (switch or keyboard entry at Security Desk)
shall remove a car from group operation and run it directly to the main lobby,
after answering all registered car-calls but bypassing hall-calls.
B. When at the main lobby, open the doors for a pre-determined time and then
close the doors. Park the car with lights and fans turned off.

30 11 IN-SERVICE INDICATOR
A. Provide a signal at Security Desk to indicate that safety circuits of a car are all
closed, and the unit is ready to run.

30 12 DISTRESS LIGHT & BUZZER


A. Provide a distress indicator for each unit at a Security Desk panel. Provide a
reset button and buzzer, common to all elevators of a group. Cause the
appropriate indicator to illuminate and buzzer to sound when:
1. Alarm button is pressed, or.
2. Dispatched car sits at a landing longer than 30 seconds, or.
3. An electrical safety circuit is open.
B. Provide a distress signal (via intercom system) when an Alarm button is
pressed or an electrical safety circuit is open.

30 13 LEVELLING
A. Stop a lift car automatically, without noticeable hunting, within 5 mm of a
landing sill under normal load conditions and in both travel directions.
B. Correct for over-travel or under-travel from any cause, by imperceptibly
returning the car to the landing. Initiate re-leveling to limit creep to less than 5
mm.

30 14 INDEPENDENT SERVICE
A. Initiate Independent Service by key-switch in the car, after clearing out all
passengers. When on Independent Service:
1. Keep the elevator dissociated from hall-calls and any group control.
2. Render the door protective devices, lanterns and chimes inoperative.
3. Respond to a car-call only when the floor button is pushed until doors are
closed and interlocks made up. Re-open the door immediately if the button is
released at any time before the elevator starts to move.
4. Cause the car to travel to the car-call floor and park with its doors open.
Cancel all car-calls when one is answered, when direction is reversed, or by
momentary actuation of the Independent Service key-switch.
B. Restore an elevator to normal operation when the Independent Service key-
switch is reset to the OFF-position.

30 15 POWER INTERRUPTION RESTART

21

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV
AL FATEH UNIVERSITY ODAC
Division 14 Conveying system section 14200

A. Design the system so that, in the event of stoppage due to a power failure, all
cars can re-start efficiently and operate entirely normally, and as specified
herein.
B. Where data needed for continued operation is stored in volatile memory,
provide means to preserve such data on power loss or voltage diminution.

3.16 BRAKE STOP


A. Arrange the brake to stop a lift carrying 100 percent of rated load, from full
speed in the down direction, within the normal stopping distance and without
shock or jarring. Test braking characteristics by removing electric power at
the machine room disconnect and measuring the resulting stop distance.
B. Adjust the brake to hold more than 125 percent of rated load. Design and
adjust the brake to operate without discernible noise.

3.17 BRAKE SPRING

A. Prior to safety tests by Inspecting Authorities, adjust the brake and insert a
cotter-pin or lead seal to positively define brake spring length.

3.18 SAFETY TESTS


A. Arrange the safety to stop a car, under both no load and 100 percent of rated
load, without excessive acceleration and without damage to the equipment.

END OF SECTION (14200)

22

Al LABINA / AL MANAR
in partnership with Hamza/ ECH/ LCE JV

You might also like