Professional Documents
Culture Documents
R E I N F O R C E D CONCRETE BEAM-COLUMN
J O I N T S FOR S E I S M I C L O A D I N G
P a r t II - E x p e r i m e n t a l Results
R. C. Fenwick and H. M . I r v i n e *
ABSTRACT
The theory relating to the earthquake The concrete for the tests was supplied
resistant design of beam column joints was by a local ready mix company. The specified
reviewed and extended in an earlier p a p e r ^ cylinder strength was 35 MPa with a 75 mm
and need not be repeated here. slump and a maximum aggregate size of 10 mm.
The concrete strengths listed in Table 1
The four tests reported herein were are the averages of three 300 mm x 150 mm
designed to compare the performance of cylinder crushing tests for each mix.
joints proportioned in accordance with
existing practice with a special unit in 1.1 Bond Plate Design Details (Units 2 and 4)
which yield in the joint zone was controlled
and bond slip was prevented by the use of The units with bond plates were designed
bond plates welded to the flexural steel. to transmit all the joint shear by diagonal
strut action (see Figures 3 and 2 (b) and
In designing the tests a careful watch (d)). No bond transfer was assumed for the
had to be kept on the costs involved. For main flexural steel in the joint zone and,
this reason the units' dimensions were kept consequently, the complete change in force
small. This economic constraint, together in the bar, from yield in compression on
with the size of the existing testing frame, one side to yield in tension on the other,
resulted in a unit with a rather long column was taken out on the bond plate which
which gave a relatively flexible structure supported the diagonal compression force
requiring a high section to displacement on the concrete.
ductility ratio.
The plates were proportioned so that
The column axial load was taken as the bearing stress on the concrete was
zero to simplify the tests and to create a approximately at the cylinder crushing
severe loading condition for the joint. strength. There was no evidence of local
With no axial load, small joint dimensions crushing adjacent to the plate so that it
(thereby accentuating the bond problem) is likely that the procedure is conservative,
and the high ratio of section to displacement possibly overly so bearing in mind the con-
ductility, the test conditions were severe finement of the diagonal strut.
compared with previous tests reported in the
literature (see References 3-8 in Reference To reduce the possibility of a local
2 and References 13-37 , 39-44 in Reference 3 ) . brittle failure in the bar due to high welding
shrinkage stresses, the bond plates were
The test set-up is illustrated in Figure cut in two and each half was then butt
1. The units were tested in a horizontal welded to the bar. The junctions between
position in a frame that was bolted down on the two halves of the plate were then
to the test floor. The joint zone reinforce- lightly welded together.
ment for the four units is shown in Figure 2.
If the bar between the bond plates
Unit 1 was designed to comply with the yields (in this region of the bar only
ACI 318-71 code. Unit 2 was the first of yield in tension is p o s s i b l e ) , then, on
two units in which bond plates were detailed load reversal, the bar would slip back
to prevent slip. Unit 3 was designed by Mr. through the concrete to allow the second
I. C. Armstrong (District Structural Engineer, bond plate to bear against the concrete.
M.W.D., Auckland) to comply with the draft Clearly, to prevent this slippage and the
revision PW 81/10/1 - May 1976. Finally, consequent degradation of stiffness, it
Unit 4 was an improved version of Unit 2. is necessary to prevent, or at any rate
The main features of these are listed in limit, the inelastic extension of the
Table 1. In all cases the columns had an flexural reinforcement in the joint zone.
appreciably greater theoretical ultimate
In Unit 2 an attempt was made to limit
* Senior Lecturers in Civil Engineering,
the yield extension between the bond plates
University of Auckland.
by the addition of extra flexural reinforce- units. However, extensive yielding of the
ment in the beam. This took the form of four reinforcement in the joint zones of Units
12 mm bars which were placed on the inside 1, 2 and 3 rapidly caused the strains to
of the main flexural reinforcement cage. exceed the gauge capacities. By comparison,
These bars extended between the bond plates, the cracks in the joint zone of -Unit 4 were
but away from this location they were bent well controlled and this allowed readings
into the centre of the beam (see Figure to be taken to the end of the ductility
2(b)). The test results showed that this six displacements.
was only partially successful. At the higher
ductility levels these bars appear to have In Units 3 and 4 measurements were
become debonded allowing extensive yielding taken of the expansion of the central 1.6 m
of the main steel in the joint and, therefore, of the beam under cyclic loading. At low
slip of the bars through the joint. ductility levels these values were found,
using demec gauge readings, but at higher
Yielding of the main beam steel in the levels the expansion was measured directly
joint of Unit 4 was prevented by the addition with a tape.
of two 10 mm bars fillet welded onto each
24 mm bar between the bond plates (see 2. EXPERIMENTAL RESULTS
Figure 2(d)). This arrangement worked
extremely well and no slippage was apparent. The main experimental results are
recorded in Figures 5-14.
With diagonal strut action as the
principal method of load transfer in the 2.1 Units 1 and 3
joints of Units 2 and 4, joint shear rein-
forcement was not required. However, some Unit 1 was designed to comply with
joint steel is needed to control the diagonal the current ACI code (318-71), and Unit 3
splitting which occurs in the joint, as was proportioned to meet the draft provisions
indicated in the previous p a p e r . The of PW 81/10/1 of May 1976, with the exception
areas of joint reinforcement actually used that as the gap between the flexural steel
to control this cracking (1584mm and 999mm
2
in the column was small no intermediate
for units 2 and 4 respectively) were markedly column bars were used. The effect this may
less than those required for joint shear have had on the joint is unknown. (See
resistance in units 1 and 3 (see Table 1 ) . Table 1 in Reference 1.) The flexural
In the case of Unit 4 only half the steel tension steel percentage in the beam in
specified by equation (7) and Reference (1) Unit 3 was considerably less than in the
was used (i.e. y hi see equation (8)).
s
other units (1.3% as against 1 . 8 % ) , as it
It was felt that once diagonal cracks form was limited by the calculated shear
the tension stiffness across the diagonal strength of the joint zone corresponding
decreases and the forces required to be to the maximum quantity of stirrup reinforce-
transmitted across the crack are substantially ment that could be fitted into this region.
reduced. The experimental results bear out
this conclusion. The behaviour of both joints was
similar in that both suffered severe load
1.2 Load Sequence and Experimental Measure- and stiffness degradation. The considerable
Men ts increase in the ratio of shear reinforcement
to flexural steel increased the toughness
The loading sequence was the same for of Unit 3, but the gain appears to be
all units, being similar to that used in small (Figures 5, 6, 9, and 10) .
recent MWD tests(4). In the first two
complete cycles of the test on Unit 1, the Both joints cracked diagonally at a
load was increased in each direction to load of 18 kN in the jacks. These cracks
three-quarters of the level calculated to opened up when the units were taken into
give first yield of the reinforcement. The the inelastic region. The inelastic
resulting load-deflection relationship was extension of the steel was concentrated in
plotted and a straight line was fitted to the joint and in the beam close to the
the points and extended to the calculated joint.
first yield level. The displacement corres-
ponding to this was then used as a reference For load cycles involving ductilities
value of "ductility one". From this stage greater than two slippage of the beam rein-
on displacements were imposed on the beams forcement through the joint zone was
as indicated in Figure 4 ( a ) . All subsequent apparent. Inspection of the joint of Unit
units were subjected to the same displacements 1 showed clear evidence of bar slip, with
as Unit 1. the deformations on the steel moving relative
to the indentations in the concrete by as
Readings of the beam deflections were much as 3 - 5 mm. Such slippage gives
taken at the two points shown in Figure 4 ( b ) . rise to beam displacements as is apparent
In addition, the deflected shapes of the from the flat portions of the load deflection
complete units were picked out using a curves at higher ductilities (see Figure 5 ) .
theodolite to measure the movement of In the joint of Unit 3 the concrete contained
targets attached to the unit. These measure- around and between the six bars in each
ments were taken at only a few representative face of the beam was extensively broken up.
load increments. It was apparent in this case that the bond
was destroyed not so much at the steel-
Electrical resistance strain gauges concrete interface as by disruption of the
were attached to the main flexural steel concrete surrounding the bars in the joint
in Unit 1. In all, eighteen gauges were region. For this type of bond failure the
used, their positions being as shown in reduction in bar diameter from 20 mm in
Figure 7. Unit 1 to 12 mm in Unit 3 did not appear
to help because it was the concrete inter-
Demec gauge readings were taken on all face right round the group that failed.
1, w
2.4 Crack Widths in the Joint Zone Mr. B. W. Buchanan, M.W.D., Wellington,
has suggested that sliding shear failures
The opening of cracks in the joint zone could possibly be prevented by providing
was indirectly measured from displacement an element with a high dowel shear capacity
readings made across this region by mechanical in the centre of the beam.
strain gauges. A few of the results are
shown plotted in Figure 14. It can be seen A scaffolding tube filled with concrete
that the crack widths in the joint zones of and placed in a debonded state in the middle
Units 1, 2 and 3 increased rapidly once of the beam in the plastic hinge zones might
they were taken into the inelastic region. satisfy this requirement. Alternatively,
By contrast, the crack widths in the joint the authors believe it may be possible to
of Unit 4 remained small and well controlled control sliding shear by the use of some
until the second cycle of ductility six. unstressed prestressing strands which are
added to the normal flexural mild steel in
3. CONCLUSIONS the beam. This, it is thought, may change
the character of the plastic hinge and
The test results from Unit 4 clearly increase the sliding shear capacity of the
indicate that beam-column joints may be hinging region.
designed to resist joint shear by diagonal
strut action. Such joints require that: With the bond plate detail difficulties
would arise with site placing of reinforcement,
(i) Extra beam flexural steel be placed and it would be important to avoid this
through the joint to control the amount problem by having the steel cages prefabricated
of yielding in the joint zone and to in a workshop. From discussions with contractors
keep the plastic behaviour mainly in the it appears that just this approach has been
beams. This additional reinforcement used to considerable advantage on several
must be adequately anchored in the beams recent structures with conventional joints.
178
C o n s e q u e n t l y it i s d i f f i c u l t t o
determine joint stirrup requirements by a
l o g i c a l a n a l y s i s o f j o i n t f o r c e s in c o l u m n s
with low axial loads. The expected mode
of a c t i o n is n o t c l e a r , a n d t h e p o o r p e r f o r m -
ance of Units 1 and 3 under these conditions
is not s u r p r i s i n g . F i n a l l y , it should b e
noted that the c o n d i t i o n s for these tests
w e r e s e v e r e in t h a t t h e r e w a s n o a x i a l l o a d
(a c o n d i t i o n w h i c h l e a d s t o a h i g h v e r t i c a l
s t i r r u p requirement), and t h e r a t i o o f s e c t i o n
to d i s p l a c e m e n t d u c t i l i t y w a s h i g h .
4. ACKNOWLEDGEMENTS
T h e a u t h o r s a r e g r a t e f u l t o M r . I. C .
Armstrong, M . W . D . Auckland, and M r . B. W.
B u c h a n a n , M . W . D . W e l l i n g t o n , for their h e l p
with this project. In a d d i t i o n , M r . W .
S t r i n g e r a n d Mr. K. C u r r y o f the M . W . D .
Auckland provided valuable assistance.
Downer and C o . Ltd. provided material
assistance.
5. REFERENCES
(1) F e n w i c k , R. C . a n d I r v i n e , H . M . ,
"Reinforced Concrete Beam-Column Joints
for S e i s m i c L o a d i n g , Part I - T h e o r y " ,
B u l l e t i n o f t h e N . Z. N a t i o n a l S o c i e t y
for E a r t h q u a k e E n g i n e e r i n g , S e p t . 1 9 7 7 .
V o l . 1 0 , N o . 3.
(2) ACI-ASCE Committee 352, "Recommendations
for D e s i g n of B e a m - C o l u m n J o i n t s in
Monolithic R e i n f o r c e d C o n c r e t e S t r u c t u r e s " ,
P r o c . A C I , V o l . 7 3 , N o . 7, J u l y , 1 9 7 6 .
(3) P a r k , R. a n d P a u l a y , T . , " R e i n f o r c e d
C o n c r e t e S t r u c t u r e s " , J. W i l e y a n d
Sons , 1976 .
(4) Priestley, M.J.N., "Testing of Two
Reinforced Concrete Beam-Column
Assemblies Under Simulated Seismic
Loading", Report N o . 5-75/1, MWD Central
L a b o r a t o r i e s , W e l l i n g t o n , 1 9 7 5 . (See,
also, Bulletin of the N . Z . National
Society for Earthquake Engineering,
V o l . 8, N o . 1, M a r c h , 1 9 7 5 , p p . 3 8 - 7 0 . )
(5) A C I C o m m i t t e e 408 - "Bond Stress - T h e
State of the A r t " , A C I Proceedings,
Vol. 63, No. 11, 1966.
Paper received 26 S e p t e m b e r , 1 9 7 7 .
179
TABLE 1
Cylinder
42.9 MPa 35.6 MPa 39.3 MPa 40.4 MPa
strength f^
Beam flexural
3 - D20 mm 3 - D20 mm 6 - D12 mm 2 - D24 mm
steel (T & B)
280 MPa 317 MPa 318 MPa 291 MPa
f
y
2 2
A . = A * 942 mm 2
942 mm 2
905 mm
st sb 678 mm
width 200 200 200 200
effective depth 260 260 254 252
Beam steel % p 1.81 1.81 1.34 1.80
Joint vertical
2 - D16 mm 2 - D16 mm ' Nil 2 - D16 mm
steel
2
in jt. zone (ZA ) v 402 mm 2
402 mm 402 m m 2
2463 mm 2463 mm 2
1810 mm 2
2614 mm 2
columns
width 250 250 250 250
effective depth 260 260 254 252
Steel ratios
2.03 1.25 3.32 0.66
Z
V st A
(EA h + ZA )/A
v s t 2.46 1.68 3.32 1.10
* L - A C I - 7 1 cj) = 1.0
u 50.1 kN 55.5 kN 40.8 kN 52.4 kN
* Notes
L u - calculated ultimate flexural load on each beam (ACI-318-71 <f> = 1.0)
L x - calculated load on each beam at 1st yield of beam steel
L 2 - measured load on each beam at ductility two 1st cycle clockwise direction
A - flexural steel bottom of beam, A . - flexural steel top of beam
sb st
180
SUPPORT BEARINGS
RACKING ON PACKNG
30 TON JACK
BEAM ri BEAM
L J L J
It - ^
1
' Mr
30 TON JACK
r i
I. J H—PACKING
COLUMN
PACKING
30 TON LOAD
CELL - ROLLER BEARING
1 4?5 J1X
-6-SETS R6 5 -200I
DOUBLE T I E S - 1 0 0
3Qj JO
f ^ O
6-D20-
1&I
R6-5 TIES
-BEAM
6-R6-5 TIES-150 - ^3-020. T& B
- 55- -S5E T S TRIPLE
" ^ j T I E S IN JOINT R = plain round.
D = deformed. A-A ¥
- 6 - SETS R 6 - 5 016 = deformed 16mm
DOUBLE T I E S - 1 0 0 nominal bar.
Oi
CO
CD R12 TIE 2-016 ,R6-5 TIES
N R10 TIE R6 5 TIE 2-016
-2-016
4-020 4-020 4-020 4-020
- 4 - 0 2 0 E. F.
-9-R6 5 TIES-150
4 -COLUMN
^Fillet weld R12" "-Fillet weld
& R10 ties. R6-5 tie
300
STRUCTURE IS
ETRICAL ABOUT £ ' s C-C
FIGURE 2 ( a ) : R E I N F O R C E M E N T DETAILS FOR T H E FOUR S P E C I M E N S (?) U N I T 1
1 - D16 E.F.
i 2T 2J
52
2-012E.F.
W] WW BEAM
6 - R 6 - 5 TIES-150
3 - 0 2 0 T. & B.
60 x 60 x 2 0 * .
D20 OR 016
BAR
5 - SETS TRIPLE
TIES IN JOINT BOND PLATE DETAIL
- - 6 - SETS R6-5
DOUBLE T I E S - 1 0 0
2 - D16
^ ^ _^ ^ 0 016 016- -R6-5 TIES
o
CO 2-016-v
iD"\ r- 6 - 0o-
20 R6-5 TIE — n | R6 5 TIES 012 012
2-020* - ^ , 012 -i
2 -D16 E.F. •—012 o
4
9 -R6 5 -
TIES-150 o
o
CO' f]-016-
020 •^
5$
i ^ If
r^ 5
c-c
F I G U R E 2 ( b ) : R E I N F O R C E M E N T D E T A I L S FOR T H E F O U R S P E C I M E N S (b) U n i t 2
182
1*8
ffl
"XTEAM
7-SETS R6-5 - -3-D12 T. & B.
TRIPLE TIES -100
^ - 5 - S E T S TRIPLE B-B
TIES IN JOINT
— 6 - SETS R6 5
TRIPLE T I E S - 60 200
-4-D12E.F. 300
NOTE STRUCTURE IS
:
Fillet weld-
of R6-5 tie I
R 6 5 TIE
J
L
fcJB 45. j_ il
N 0 T E STRUCTURE IS
;
U 30J ^
SYMMETRICAL ABOUT ^'s C-C
FIGURE 2 ( d ) : R E I N F O R C E M E N T D E T A I L S FOR THE FOUR S P E C I M E N S (d) U n i t 4
CYCLE
1-250J
DIAL o |JACKS
GAUGES^
,J-250.j
3 200
FIGURE 4
F I G U R E 5: L O A D D E F L E C T I O N C U R V E S FOR U N I T 1 F I G U R E 6: L O A D D E F L E C T I O N C U R V E S FOR U N I T 3
184
-—-D4i
-D4i
7 04i
YIELD STRAIN i 1 4 Q 0 j L l Q f L _
F I G U R E 8: S T R A I N R E A D I N G S ON C O L U M N
F I G U R E 7: S T R A I N R E A D I N G S ON BEAM B A R S BARS U N I T 1 UP TO D U C T I L I T Y 4
U N I T 1 UP T O D U C T I L I T Y 2 (SEE F I G U R E 7 FOR S T R A I N G A U G E L O C A T I O N S )
Load
ri, Displacement
^ ACI Ultimate
(0=1) — 7
^oad /
±
Displacemeni
0-8
UNIT 4
eJasto-plastic
0-6
0-4
DUCTILITY
UNIT 1
0-2
UNIT 4
2i 4i 6i 8i
DISPLACEMENT DUCTILITY - 1st CYCLE
0-6 H
F I G U R E 9: L O A D S U S T A I N E D A T D I F F E R E N T
D U C T I L I T I E S (i= first cycle, ii=second cycle)
0-4
Unit 4
: 0-2 ^ Unit 3
-_\Unit 2
~Unit 1
2ii
4ii 6ii 8ii
DISPLACEMENT D U C T I L I T Y - 2 n d CYCLE
F I G U R E 10: E N E R G Y D I S S I P A T I O N
VERSUS D U C T I L I T Y
JOINT ZONE
SPALLS 4
.•i -i +ii - h . .+i -i +it - i i • i+» -i +ii - i i . ,+i -i +ii - i i . i+i -i +ii - i i , DUCTILITY
J
/^D 2D 4D 6D 8D