You are on page 1of 117

I.

BASEMENT
A. Parking A
a. Earthwork = Rp. 992,500,000.00
b. Structure Work = Rp. 34,514,001,060.00
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
B Mall B
a. Earthwork = Rp. 50,400,000.00
b. Structure Work = Rp. 12,017,407,660.00
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
C. Parking B
a. Earthwork = Rp. 1,107,050,000.00
b. Structure Work = Rp. 54,770,359,000.00
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
D Mall B
a. Earthwork = Rp. 64,420,000.00
b. Structure Work = Rp. 15,143,220,240.00
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
E. Office Tower
a. Earthwork = Rp. -
b. Structure Work = Rp. -
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
F. Apartement Tower
a. Earthwork = Rp.
b. Structure Work = Rp.
c. Architectural Work = Rp.
d. Mechanical = Rp.
e. Electrical = Rp.
LUAS LANTAI GRAND INDONESIA
ZONE VOID OFFICE TOWER
NO LANTAI SAT
A B TOWER LANTAI

1 BASEMENT 1 m2 25,985.50 28,719.00 - -

2 SEMI BASEMENT m2 21,325.00 28,719.00 - -

3 GROUND m2 14,992.00 14,510.50 - -

4 MEZZANINE m2 14,992.00 12,977.00 - -

5 1st m2 14,992.00 14,984.63 - -

6 2nd m2 14,992.00 13,648.50 - -

7 3rd m2 14,992.00 13,596.00 - -

8 4th m2 14,992.00 13,596.00 - -

9 5th m2 14,992.00 13,722.63 - -

10 6th m2 11,309.50 13,857.50 - -

11 7th m2 11,309.50 13,857.50 - -

12 8th m2 14,189.50 10,979.00 - -

13 9th m2 11,309.50 10,629.00 - -

14 10th m2 11,309.50 10,979.00 - -

15 11st m2 14,399.50 8,723.75 - Tower 1

16 12nd m2 - - - Tower 2

17 13rd - 20th m2 - - 6,430.72 Tower 3 - 10

18 21st m2 - - 803.84 Tower 11

19 22nd m2 - - 803.84 Tower 12

20 23rd - 38th m2 - - 12,861.44 Tower 13 - 28

21 39th m2 - - 803.84 Tower 29

22 40th m2 - - 803.84 Tower 30

23 41st m2 - - 803.84 Tower 31

24 42nd - 50th m2 - - 7,234.56 Tower 32 - 40

25 51st m2 - - 803.84 ROOF

26 52nd m2 - - 803.84 -
27 53rd m2 - - 803.84 -
28 54th m2 - - 803.84 -
TOTAL m2 226,081.50 223,499.00 33,761.28
OFFICE TOWER RESIDENTAL TOWER VOL BETON
BRIDGE TOTAL
LUAS (m2) LANTAI LUAS (m2) TEBAL = 12 cm

- - - 1,596.00 56,300.50 6,756.06

- - - 1,196.00 51,240.00 6,148.80

- - - - 29,502.50 3,540.30

- - - - 27,969.00 3,356.28

- - - 3,520.00 33,496.63 4,019.60

- - - 3,292.00 31,932.50 3,831.90

- - - 3,292.00 31,880.00 3,825.60

- - - 3,292.00 31,880.00 3,825.60

- - - 3,292.00 32,006.63 3,840.80

- - - 3,313.00 28,480.00 3,417.60

- - - 3,313.00 28,480.00 3,417.60

- - - 3,313.00 28,481.50 3,417.78

- - - 3,313.00 25,251.50 3,030.18

- - - 3,313.00 25,601.50 3,072.18

1,888.75 Amenites 1,232.50 - 26,244.50 3,149.34

1,888.75 Tower 2 1,523.34 - 3,412.09 409.45

15,110.00 Tower 3 - 10 9,860.00 - 24,970.00 2,996.40

1,888.75 Tower 11 1,232.50 - 3,121.25 374.55

1,888.75 Tower 12 1,232.50 - 3,121.25 374.55

30,220.00 Tower 13 - 28 19,720.00 - 49,940.00 5,992.80

1,888.75 Tower 29 1,232.50 - 3,121.25 374.55

1,888.75 Tower 30 1,232.50 - 3,121.25 374.55

1,888.75 Tower 31 1,232.50 - 3,121.25 374.55

16,998.75 Tower 32 - 40 11,092.50 - 28,091.25 3,370.95

1,888.75 Tower 41 1,232.50 3,121.25 374.55

- Tower 42 1,232.50 1,232.50 147.90


- Tower 43 1,232.50 1,232.50 147.90
- Tower 44 1,232.50 1,232.50 147.90
77,438.75 54,520.84 36,045.00 617,585.09 74,110.21
547,396.36 110,661.75 436,734.61

128,838.34 3,121.25 131,959.59


VOLUME DOMINAN

HARGA SATUAN
NO ITEM VOLUME RATA2 TOTAL

1 REINFORCING STEEL 40,545,450 5,028 203,848,853,000

249,546 353,080 88,109,788,400


2 CONCRETE

3 FORM WORK 791,610 54,988 43,529,200,000

4 SUPPLY & INSTALLASION OF METAL DECKING 508,850 80,050 40,733,442,500

5 METAL DECKING & STEEL MESH 554,750 25,957 14,399,827,576

6
BLOCK AND BRICK WORK 143,850 77,613 11,164,600,000

7 FLOOR & WALL FINISHING WORK 887,950 15,953 14,165,120,000

8 EXTRA OVER CONCRETE FOR WATER TIGHT CONCRETE (Incl. Integral WP) 15,750 403,000 6,347,250,000

9 WATER PROOFING MEMBRANE 94,140 61,500 5,789,610,000

10 EARTH WORK 143,175 16,049 2,297,770,000

11 MISCELLANEOUS STEEL WORK 15,650 248,673 3,891,730,000

12 INSERTED / EMBEDED MATERIAL 1 1,543,643,000 1,543,643,000


GRAVEL 100 MM AND LEAN CONCRETE 50 MM
121,100 12,478 1,511,085,800
13 ( BASEMENT TO UP STRUCTURE )

14 SEISMIC JOINT 4,360 318,458 1,388,475,000

15 WATER PROOFING COATING 1 56,090 44,600 2,501,614,000

16 DOOR WORK 4,082 264,397 1,079,270,000

17 STEEL STRUCTURE WORK 348,580 3,024 1,054,105,700

18 TERMITE CONTROL 100,000 8,500 850,000,000

19 CUTTING OF PILEHEADS (INC DISPOSAL OF DEBRIS) 3,096 461,224 1,427,950,000

20 WATER STOP 9,100 68,856 626,590,000

21 WATER PROOFING COATING 2 9,540 44,600 425,484,000

22 CHEMICAL ANCHOR FOR STARTED BAR 3,820 26,110 99,739,700

23 WATER PROOFING ANY (Not Mentioned) 100 44,600 4,460,000


REKAPITULASI VOLUME
GRAND INDONESIA PROJECT

NO URAIAN SAT TOTAL VOLUME

1 EARTH WORK 143,175.00


- Excavation for substructure, foundations , pile caps, ground m3 70,500.00
beams, etc including grading and compaction of the bottom
surface
- Load and cart away off site surplus soil to be dumped at the m3 24,000.00
Contractor's disposal area
- Backfill and compaction with selected excavated material m3 10,150.00
- Sand - fill including compaction m3 425.00
- Excavation for road, planter, canopy, guard houses, etc m3 550.00
including grading and compaction
- Load and cart away off site surplus soil to be dumped at the m3 34,850.00
Contractor's disposal area
- Backfill and compaction with selected off - site imported material m3 2,150.00
including compaction
- Sand Gravel - fill including compaction m3 550.00

2 TERMITE CONTROL 100,000.00


- Termite control as per Specifications m2 100,000.00

3 CUTTING OF PILEHEADS (INC DISPOSAL OF DEBRIS) 3,096.00


- Dia. 1200 mm nos 1.00
- Dia. 1000 mm nos 1,380.00
- Dia. 800 mm nos 1,715.00

4 SEISMIC JOINT
- Wall, 100 mm width m' 470.00
- Wall, 150 mm width m' 50.00
- Floor, 100 mm width m' 3,740.00
- Floor, 150 mm width m' 100.00
4,360.00
5 BASEMENT TO UP STRUCTURE
- 100 mm thick gravel filling spread, leveled and compacted m2 60,550.00
under blind / lean concrete for pile caps, ground beams, slabs
and other foundations
- 50 mm thk blind / lean concrete K 100, under pile caps, ground m2 60,550.00
beams, slabs and other foundations
121,100.00
6 CONCRETE
- K 600 m3 16,930.00
- K 500 m3 54,610.00
- K 400 m3 178,006.00
249,546.00
7 REINFORCING STEEL
- U 50, 16 - 25 mm kg 21,814,450.00
- U 50, 29 - 32 mm kg 5,735,200.00
- U 50, 36 mm kg 4,346,200.00
- U 40, 10 - 13 mm kg 8,138,200.00
- U 24, <10 mm kg 511,400.00
40,545,450.00
8 FORM WORK
- FF, exposed surfaced m2 267,800.00
- NF, non-exposed surfaced m2 507,100.00
- FF Curved, exposed surfaced m2 16,210.00
- NF Curved, non-exposed surfaced m2 500.00
791,610.00
NO URAIAN SAT TOTAL VOLUME

9 METAL DECKING & STEEL MESH


- M5 dia. 5 mm x 150 mm m2 27,620.50
- M6 dia. 6 mm x 150 mm m2 165,723.00
- M7 dia. 7 mm x 150 mm m2 165,723.00
- M8 dia. 8 mm x 150 mm m2 165,723.00
- M9 dia. 9 mm x 150 mm m2 29,960.50
554,750.00
10 CHEMICAL ANCHOR FOR STARTED BAR
- Re bar 22 mm, 9.123 ton nos 900.00
- Re bar 16 mm, 4.825 ton nos 1,640.00
- Re bar 13 mm, 3.185 ton nos 1,280.00
3,820.00
11 WATER STOP
- 100 mm m' 2,700.00
- 150 mm m' 5,100.00
- 200 mm m' 1,300.00
9,100.00
12 WATER PROOFING
- For Ground Slab Membrane m2 58,090.00
- For Diaphragm Wall Integral m2 13,910.00
- For Outside STP, Resservoir & Ret Wall Coating 1 m2 750.00
- For Inside of STP, Reservoir Wall & Floor Coating 1 m2 5,300.00
- For Roof Deck Membrane m2 35,150.00
- For Toilet & mech. Room wet areas Coating 2 m2 8,590.00
- For others, if any Membrane m2 100.00
- For Upper Ground Floor below landscape and road area Coating 1 m2 31,000.00
- For Planter Coating 1 m2 5,130.00
- For Mech. Room - wet area Coating 2 m2 950.00
- For Swimming pool & Lagoon Coating 1 m2 900.00
159,870.00
13 SUPPLY & INSTALLASION OF METAL DECKING m2 508,850.00

14 EXTRA OVER CONCRETE FOR WATER TIGHT CONCRETE (Incl. Integra m3 15,750.00

15 STEEL STRUCTURE WORK


- Column 300 x 300 - 94 kg 10,900.00
- Beams WF 800 x 300 - 267.4 kg 141,000.00
- Truss beams ###
- Top Chord WF 200 x 200 - 65.7 kg 26,200.00
- Bottom chord, Tees 400 x 200 - 84 kg 12,300.00
- Bottom Chord, Tees 200 x 300 - 47.1 kg 11,900.00
- L 40x 40, 50x50, 60x60, 70x70, 80x80, 90x90 kg 21,600.00
- Embeded plate & Connection plate kg 24,800.00
- Anchor bolt ø 19 mm nos 530.00
- Stud bolt ø 16 mm nos 2,200.00
- High tensile bolt ø 19 mm nos 350.00
- Primary (Zincromate) paint kg 248,700.00
348,580.00
16 BLOCK AND BRICK WORK
- Celcon block wall 100 mm thk, including bedding, jointing m2 139,700.00
in mortar and necessary concrete studs and lintels, etc.
- Celcon block wall 150 mm thk, including bedding, jointing m2 1,800.00
in mortar and necessary concrete studs and lintels, etc.
- Brick wall 120 mm thk, including bedding, jointing in mortar m2 1,100.00
and necessary concrete studs and lintels, etc.
- Hollow block wall 100 mm thk, including bedding, jointing in m2 1,250.00
mortar and necessary concrete studs and lintels, etc.
143,850.00
NO URAIAN SAT TOTAL VOLUME

17 FLOOR & WALL FINISHING WORK


- Concrete trowel finish m² 172,550.00
- Concrete broom finish m² 20,800.00
- Concrete floor hardener m² 124,700.00
318,050.00
- Plastering 20 mm thk, even and troweled enough to receive m² 433,700.00
painting finish or wall paper finish
- Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)
- Painting to steel doors and frames m² 4,960.00
- Painting to plastering wall, column, etc. m² 125,640.00
130,600.00
- Supply, fabricate and install precast concrete wheel stops, nos 5,600.00
including all fixing accessories
887,950.00
18 DOOR WORK
- Installation of steel doors (including fire doors) with frame
including hardwares :
- Type single leaf 800 x 2100 mm unit 214.00
- Type single leaf 900 x 2100 mm unit 11.00
- Type single leaf 1000 x 2100 mm unit 749.00
- Type double leaf 1600 x 2100 mm unit 125.00
- Type double leaf 2400 x 2400 mm unit 3.00
- Installation of wooden doors with frame including hardwares :
- Type single leaf 750 x 2100 mm unit 8.00
- Type double leaf 800 x 2100 mm unit 94.00
- Type double leaf 1000 x 2100 mm unit 8.00
Swing type
- Type single leaf 750 x 2100 mm unit -
- Type single leaf 800 x 2100 mm unit 2,240.00
- Type single leaf 1000 x 2100 mm unit -
- Type single leaf 1600 x 2100 mm unit 200.00
Sliding type
- Type single leaf 900 x 2100 mm unit 50.00
- Type single leaf 1800 x 2100 mm unit 380.00
4,082.00
19 MISCELLANEOUS STEEL WORK
- Supply, fabricate and install stairway railings, including m 3,550.00
all necessary fixtures, accessories and painting, etc.
- Ditto, but wall railing at stair m 3,440.00
- Supply, fabricate and install galvanized steel grating cover m² 490.00
complete with frame, anchors and all accessories, etc.
- Steel plate heavy duty manhole cover, including steel frames,
and resin paint finish, etc.
- Dia. 600 mm nos 31.00
- Dia. 800 mm nos 39.00
- Supply, fabricate and install L 65 x 65 x 6 mm mild steel column nos 8,100.00
guard including painting stripe with resin paint (black & yellow)
complete with anchors, bracket & any other fixtures/accessories.
15,650.00
20 INSERTED / EMBEDED MATERIAL

1 Anchors for curtain walling system Ls 1


2 Anchors for lift doors, jambs and heads Ls 1
3 Davit socket for gondola system Ls 1
4 Any other matrials to be inserted, embedded or casted into Ls 1
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1
NO URAIAN SAT TOTAL VOLUME

Other Contractors and Employer's Own Forces 1


THE SUMMARY OF BILL OF QUANTITIES
Grand Indonesia Project

No. Description Amount

1 Bill No. 1 - Preliminaries Rp 50,951,332,743.13

2 Bill No. 2 - Parking A Rp 101,783,248,340.00


2.1 EARTH WORK Rp 992,500,000.00
2.2 TERMITE CONTROL Rp 340,000,000.00
2.3 CUTTING OF PILE HEADS Rp 616,300,000.00
2.4 SEISMIC JOINT Rp 718,875,000.00
2.5 STRUCTURAL WORK Rp 90,661,949,340.00
2.6 WATERPROOFING WORK Rp 3,042,400,000.00
2.7 BLOCK AND BRICK WORK Rp 976,300,000.00
2.8 FLOOR & WALL FINISHING WORK Rp 2,311,150,000.00
2.9 MISCELLANEOUS STEEL WORK Rp 1,829,550,000.00
2.10 Insert, embed or cast into concrete, following materials supplied Rp 201,524,000.00
2.11 DOOR WORK Rp 92,700,000.00
Rp 101,783,248,340.00

3 Bill No. 3 - Mall A Rp 56,760,167,520.00


3.1 EXTERNAL EARTH WORK Rp 50,400,000.00
3.2 DRIVEWAY, SIDEWALK, EXTERNAL ROAD, AND ECT. to be issued letter
3.3 SITE DRAINAGE to be issued letter
3.4 SEISMIC JOINT CONSTRUCTION Rp 165,600,000.00
3.5 STRUCTURAL WORK Rp 52,073,392,520.00
3.6 WATERPROOFING WORK Rp 660,080,000.00
3.7 BLOCK AND BRICK WORK Rp 1,435,025,000.00
3.8 FLOOR & WALL FINISHING WORK Rp 1,795,000,000.00
3.9 MISCELLANEOUS STEEL WORK Rp 198,785,000.00
3.10 Insert, embed or cast into concrete, following materials supplied Rp 282,135,000.00
3.11 DOOR WORK Rp 99,750,000.00
Rp 56,760,167,520.00

4 Bill No. 4 - Parking B Rp 112,970,948,896.00


4.1 EARTH WORK Rp 1,107,050,000.00
4.2 TERMITE CONTROL Rp 510,000,000.00
4.3 CUTTING OF PILE HEADS Rp 811,350,000.00
4.4 SEISMIC JOINT CONSTRUCTION Rp 344,250,000.00
4.5 STRUCTURAL WORK Rp 98,980,269,896.00
4.6 WATERPROOFING WORK Rp 3,628,933,000.00
4.7 BLOCK AND BRICK WORK Rp 2,541,400,000.00
4.8 FLOOR & WALL FINISHING WORK Rp 3,839,760,000.00
4.9 MISCELLANEOUS STEEL WORK Rp 1,041,710,000.00
4.10 Insert, embed or cast into concrete, following materials supplied Rp 105,206,000.00
4.11 DOOR WORK Rp 61,020,000.00
Rp 112,970,948,896.00

5 Bill No. 5 - Mall B Rp 91,159,583,540.00


5.1 EXTERNAL EARTH WORK Rp 64,420,000.00
5.2 DRIVEWAY, SIDEWALK, EXTERNAL ROAD, AND ECT. to be issued letter
5.3 SITE DRAINAGE to be issued letter
5.4 SEISMIC JOINT CONSTRUCTION Rp 159,750,000.00
5.5 STRUCTURAL WORK Rp 82,481,702,540.00
5.6 WATERPROOFING WORK Rp 918,501,000.00
5.7 BLOCK AND BRICK WORK Rp 2,493,675,000.00
5.8 FLOOR & WALL FINISHING WORK Rp 4,331,740,000.00
5.9 MISCELLANEOUS STEEL WORK Rp 402,745,000.00
5.10 Insert, embed or cast into concrete, following materials supplied Rp 147,290,000.00
5.11 DOOR WORK Rp 159,760,000.00
Rp 91,159,583,540.00

6 Bill No. 6 - Office Tower Rp 47,402,265,800.00


6.1 STRUCTURAL WORK Rp 42,563,134,800.00
6.2 WATERPROOFING WORK Rp 173,304,000.00
6.3 BLOCK AND BRICK WORK Rp 1,611,100,000.00
6.4 FLOOR & WALL FINISHING WORK Rp 2,202,860,000.00
6.5 MISCELLANEOUS STEEL WORK Rp 626,927,000.00
6.7 DOOR WORK Rp 224,940,000.00
Rp 47,402,265,800.00

7 Bill No. 7 - Apartment Tower Rp 42,261,468,380.00


7.1 STRUCTURAL WORK Rp 35,195,845,380.00
7.2 WATERPROOFING WORK Rp 297,950,000.00
7.3 BLOCK AND BRICK WORK Rp 2,107,100,000.00
7.4 FLOOR & WALL FINISHING WORK Rp 3,635,800,000.00
7.5 MISCELLANEOUS STEEL WORK Rp 202,500,000.00
7.6 Insert, embed or cast into concrete, following materials supplied Rp 381,173,000.00
7.7 DOOR WORK Rp 441,100,000.00
Rp 42,261,468,380.00

Sub-Total C & F Works Rp 503,289,015,219.14


Overhead & Profit _____ % Rp 50,328,901,521.91

8 Bill No. 8 - Daywork Rp 1,250,361,000.00

Total (excl. PPn) Rp 554,868,277,741.05


PPn Rp 55,486,827,774.10

Grand-Total (incl. PPn) Rp 610,355,105,515.15


452,337,682,476
THE SUMMARY OF BILL OF QUANTITIES
Grand Indonesia Project

No. Description Amount

1 Bill No. 1 - Preliminaries Rp -

2 Bill No. 2 - Parking A Rp 101,783,248,340.00

3 Bill No. 3 - Mall A Rp 56,760,167,520.00

4 Bill No. 4 - Parking B Rp 112,970,948,896.00

5 Bill No. 5 - Mall B Rp 91,159,583,540.00

6 Bill No. 6 - Office Tower Rp 47,402,265,800.00

7 Bill No. 7 Apartment Tower Rp 42,261,468,380.00

Sub-Total C & F Works Rp 452,337,682,476.00


Overhead & Profit _____ % Rp 45,233,768,247.60

8 Bill No. 8 - Daywork Rp 1,250,361,000.00

Total (excl. PPn) Rp 498,821,811,723.60


PPn Rp 49,882,181,172.36

Grand-Total (incl. PPn) Rp 548,703,992,895.96


Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

1.1 GENERAL

a) This Section is for pricing the Fixed Elements of the Contract including Contractor's duties, obligations,
responsibilities, liabilities, temporary works, supervisions and etc, which do not vary with the quantities.

b) The descriptions in this Section include only a brief indication of the duties, obligation, responsibilities and
liabilities of the Contractor; the full descriptions will be elsewhere in the Tender/Contract document.

c) The prices in this Section are all-inclusive, firm and fixed for the duration of the whole Contract Period
and shall be inclusive of all ancillary and other works and expenditure, whether specifically stated or not
so long as the same is within the Contract and/or reasonably inferable therefrom.

d) Items against which no rate/price is entered by the Contractor shall be considered as included by other
fixed rates/prices. The Contractor shall also include in the Bill of Quantities any other items if the
Contractor is of the view that the same have not been included. Any failure of the Contractor to include
further items shall be deemed to be acceptance by Contractor that Bill of Quantities have included all
items for the Works.

1.2 EMPLOYER'S OTHER CONTRACTORS & EMPLOYER'S OWN FORCES

a) The Contractor will be working along side with the Employer's Other Contractors and Employer's Own
Forces and the Contractor is expected to coordinate his works with them to maximise the use of facilities
for the Project.

b) It has been scheduled that the Contractor shall commence the Works after diaphragm wall, general
excavation and piling works, but may also be paralleled with the said works.

c) The Contractor shall comply with all duties, obligations, responsibilities, liabilities required of him under
the Contract in respect of Employer's Other Contractors and Employer's Own Forces including but not
limited to ensuring that the Contractor's works are integrated effectively and a timely manner into the
other works and to ensure completion of the Project as per Employer's schedule. All works required of
the Contractor shall be in accordance with the Contract or inferable therefrom.

d) It is intention of the Employer at present to let the works under the Project in the following categories and
the Contractor shall acknowledge and accept that the Engineer shall be entitled to revise the arrangement.

i) Works to be carried out by the Employer's Other Contractors

Diaphragm Wall Work


Site Clearing and General Excavation
Pilling Work
Curtain Wall & Exterior Cladding
Suspended Glass Work
Shop Front Work
Special Metal Work
Wall Papering Work
Ceiling Work
Soft / Hard Landscape Work
Ventilation & Air Conditioning Work
Electrical Work

Carried to collection

B1 - 14/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

Fire Fighting & Alarm System Work


Plumbing & Drainage Work
Lifts and Escalators Work
Chillers
Fountains & Lagoon Plant
Swimming Pool Filtration Plant
Kitchen Cabinet Work
Sewage Treatment Plant
Water Purification & Treatment Plant
Building Management & Monitoring System
Deep Well Work
Others, if necessary to be notified by the Engineer

ii) Employer's Supplied Materials

A. It is expected that the Contractor shall install and incorporate the following materials into the Works.
Such Employer's Materials shall be supplied by the Employer at no cost to the Contractor, and the
Contractor is required to carry out everything necessary to receive the Employer's Materials, to take
care and custody of the same upon arrival at Site, and to install / incorporate the same into the Works
including all necessary ancillary materials, etc all as stated in the Contract :

All Doors and Frames and associated Hardwares


Others, if necessary to be notified by the Employer

B. It is expected that the Contractor shall install and incorporate the following materials into the Works.
Such Employer's Materials shall be supplied by the Employer at the prices stated elsewhere in the
Bill of Quantities to the Contractor, and the Contractor is required to carry out everything necessary
to receive the Employer's Materials, to take care and custody of the same upon arrival at Site, and
to install / incorporate the same into the Works including all necessary ancillary materials, etc all as
stated in the Contract :

Ready Mixed Concrete and Mortar


Reinforcing Steel Bar and Steel Mesh
Metal Deck
Others, if necessary to be notified by the Employer

1.3 TENDER DOCUMENT

a) The Tender Document are listed in Instructions to Tenderers. All documents are intended to be mutually
applicable. Any discrepancies should be reported immediately to the Engineer who will clarify the
discrepancy.

b) The Contractor shall submit his proposed work program with his Tender. The Contractor will be expected
to revise his program to best coordinate the requirements of Employer's Other Contractors and Employer's
Own Forces involved in the Project.

c) The Contractor shall price all duties, obligations, responsibilities and liabilities which have to be complied
with him under the Contract as specified herein below ;
i) Form of Agreement;
ii) Form of Warranty;
iii) Letter of Intent;

Carried to collection

B1 - 15/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

iv) Notice to Proceed;


v) Conditions of Contract;
vi) Specifications;
vii) Bill of Quantities;
viii) Drawings;
ix) Instructions to Tenderers;
x) Form of Tender;
xi) Addenda issued during the Tender;
xii) Any other documents forming part of the Contract.

1.4 PAYMENT UNDER THE CONTRACT

a) The payment under the Contract shall consist of three (3) parts for the entire design (if any), construction,
completion, maintenance and guarantee of the Works ;

Part I - which consists of Bill No. 1, shall be the Fixed Lump Sum Portions and which shall include the
costs of preliminaries and fixed indirect costs for the Contract.

Part II - which consists of Bill No. 2 through Bill No. 5 inclusive, shall be the Fixed Rates and Prices
Portion and which consist of firm, fixed and all-inclusive rates and prices. Bill No. 2 through Bill No. 5
inclusive shall be used for the valuation of the Works to be re-measured.

Bill No. 2 - Mall A


Bill No. 3 - Parking A
Bill No. 4 - Mall B
Bill No. 5 - Parking B

The Contractor is to add on as indicated in the Bills to cover overheads, profits, and PPn tax separately.

Part III - which consists of Bill No. 6, shall be Daywork Schedule and only be used for the valuation of
variations pursuant to the Contract and only as directed by the Engineer.

b) Final payment shall be subject to re-measurement based on actual as-built quantities as per the approved
Construction Drawings.

1.5 PERFORMANCE BOND

a) Prior to the commencement of any work under the Contract, the Contractor shall provide Performance
(Surety) Bond equivalent to 10% of the Contract Sum, in the acceptable form of Banker's Guarantee from
an acceptable Bank approved by the Employer.

1.6 SUB - LETTING

a) The Contractor shall not sub - let any part of the Works without the written consent of the Engineer.
Such consent if given shall not relieve the Contractor from any liability and obligation under the Contract
and the Contractor shall be responsible for the acts, defaults and negligence of any sub-contractors, his
agents, servants or workmen as fully as if they were the acts, defaults or negligence of the Contractor,
his agents, servants or workmen.

b) The Contractor shall acknowledge and accept that the Employer shall be entitled at any time, to assign the
Contract.

Carried to collection

B1 - 16/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

1.7 INSURANCE

a) The Employer will arrange for Contractor's All Risk (CAR) and Third Party Liability (TLP) Insurance
Policy as stated in the Conditions of Contract.

b) Insurance taken up by the Employer under the Contract shall not prejudice the Contractor's duties,
obligations, responsibilities and liabilities under the Contract.
c) The Contractor shall take up if he deems necessary, any additional insurances.

d) The Contractor shall indemnify the Employer against all losses not claimable under the Employer's
insurance(s)) and any deductible thereto.

e) The Contractor shall also take up (and/or cause his subcontractors to similarly take up) the following
insurances based on the terms and conditions as stipulated in the Contract:
i) plant and equipment insurances;
ii) motor insurances;
iii) workmen's compensation insurances;
iv) transit insurances;
v) any other insurances necessary for the Works

The insurances shall be from an insurer approved by the Engineer and shall include waiver of subrogation
against the Employer, Engineer, Engineer's Representative and their respective agents, etc in the joint name
of the Employer and the Contractor, and any other terms as required by the Engineer.

1.8 GIVING OF NOTICE AND COMPLIANCE WITH LAWS

a) The Contractor shall give all notices and pay all fees required by any laws, etc.

b) The Contractor shall ascertain and conform with all provisions of any laws, etc.

c) The Contractor shall provide copies of codes and standards as required by the Engineer.

d) In case of conflicts between applicable codes, laws, etc the Contractor shall conform to the most
restrictive requirements as instructed by the Engineer.

1.9 INDEMNITY

a) The Contractor shall indemnify the Employer against all claims, losses, damages, suits, penalties and the
like as prescribed in the Contract arising out of the Contractor in carrying out of the Works.

1.10 PATENTS

a) The Contractor shall indemnify the Employer against all claims, losses, damages, suits, penalties and
the like as prescribed in the Contract arising out of any infringement of any patent rights, design, trade
mark or name of protected right so long as the same arise from the Contractor and/or any party(ies)
under his control, direct, indirect or otherwise.

1.11 SITE MANAGEMENT & ORGANIZATION

a) Allow for all On- and Off-Site Management and establishment costs and keep on Site and the Contractor's
Factory all the necessary experienced manufacturing and installation staff for the proper execution of the
Works.
Carried to collection

B1 - 17/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

The Contractor shall maintain an adequate Site organization under the full-time control of a competent
and experienced Project Manager who should assume the full responsibility of the Contract.

b) Allow for arranging, scheduling and the like of all site meetings as required by the Engineer.

c) Allow for the reasonable use of Construction Plant, Temporary Works and other facilities, utilities and
the like by Employer's Other Contractors and Employer's Own Forces.

d) Allow for scheduling, coordinating, liaising, cooperating activities with Employer's Other Contractors
and Employer's Own Forces.

e) Allow for scheduling, coordinating, liaising, cooperating activities for the installation and incorporation
of Employer's Materials into the Works.

f) Allow for all holiday overtime and incentive payments to Staff and Labor on Site and Contractor's
Factory.

g) Unless the Engineer gives written permission, no workmen will be allowed to live on Site apart from the
necessary number of watchmen.

h) All communications and meetings under the Contract will be in the English language. The Contractor
should ensure that his senior staff have an adequate working knowledge of the English language.

i) Provide, maintain and operate all necessary Construction Plant, Temporary Works and vehicles for the
proper execution of the Works including moving the same onto and about the Site as necessary and
demobilize on completion of the Works.

j) Maintain and operate Employer's Construction Plant, if any, and the care and custody thereof and allow
the same for the reasonable use by Employer's Other Contractors and Employer's Own Forces, etc
and assist to remove and demobilize upon completion or upon the Engineer's instructions.

k) The Contractor shall be entirely responsible for all labor employed and shall indemnify the Employer
against all obligations and risks. The Contractor shall meet all labor regulations in force in the area and
provide all necessary facilities during the whole Contract Period.

l) The Engineer reserves the right to reject or remove any On-Site and/or Contractor's Factory staff including
the Contractor's Project Manager if any in his opinion, the said staff misconducts himself or is incompetent.

m) Provide all Construction Plant, Temporary Works, facilities, utilities and the like including but not limited
to tower cranes, material hoists, passenger lifts, vehicles, etc and remove and demobilize upon completion
or upon the Engineer's instructions.

1.12 ILLEGAL WORKER

a) The Contractor shall ensure that no illegal workers or immigrants shall be employed by him or any of his
subcontractors and suppliers. If any illegal immigrant or worker is found to be so employed, the Employer
shall notwithstanding the provisions of the Contract be entitled to withhold any payment due to the
Contractor for a period of two (2) months and the Employer shall not be liable for any loss or damage
suffered by the Contractor as a result of any payment being so withhold.

Carried to collection

B1 - 18/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

b) For the purpose of this clause "illegal immigrant" means any person who has entered into Indonesia in
contravention of the provision of the Indonesian Immigration Act or any statutory modification or
re-enactment thereof.

1.13 OVERTIME

a) The Contractor shall allow here for the cost of any overtime he considers necessary in order to complete
the Works or any section thereof by the Date(s) of Completion. Prices shall include for any additional cost
in connection with Construction Plant, Temporary Works and the like and other expenses.

b) Any work requiring standing supervision by the Engineer and/or his representatives shall be programmed
to be carried out within normal working hours.

c) Should the Contractor refrain from pricing this item, it will be deemed that the Contractor has made
allowance for all necessary overtime expenses elsewhere in these documents.

* Any subsequent claim for overtime expenses will not be considered.

1.14 FEES AND PERMITS

a) The Employer will obtain the following licenses & permits:

i) B.K.P.M Facilities for high-rise buildings, if it is required by the Employer


ii) Piling License
iii) Approval for Architectural, Structural & M/E Works from the City Development Control Board
(I.M.B.)

b) The Contractor shall assist the Employer in the Employer's procurement of licenses and permits under
1.14 (a) herein Bill No. 1.

c) All other permits and licenses will be obtained by the Contractor at his own expenses.

1.15 DRAWINGS

a) Only three (3) sets of Contract Drawings will be issued after the date of commencement. From time to
time subsequent revised Construction Drawings will be issued.

b) Only one set of drawings for other sections of the works with which the Contractor has to coordinate his
works will be issued at the request of the Contractor.

c) Before commencing the Works, the Contractor shall submit shop-drawings to the Engineer for Approval.
No work is to be carried out or materials ordered until this approval has been reached, unless otherwise
instructed by the Engineer.

d) After Completion of the Works the Contractor is to submit 3 (three) sets accurate "as built" drawings
together with 1 (one) set of sepia original and 1 (one) set of CD to the Engineer.

Carried to collection

B1 - 19/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

1.16 MATERIAL, TEST & SAMPLES

a) The Contractor is responsible for the ordering of all his materials. He is to check the Drawings and
Specifications himself to ascertain the quantities of materials required. Any quantities in Bill of Quantities
whether provided by the Employer and/or the Contractor shall be for guidance only and shall not be used
for planning labor, materials, equipment, etc.

b) The Contractor is to submit the samples of all materials to be purchased for the Engineer's approval.
The Contractor is to remove from Site all materials that do not reach the standard of the sample approved.

c) The Contractor is to carry out such tests/retests that are called for in the Specifications and are required by
good engineering practice. Materials failing the tests/retests will be removed and made good at the
Contractor's own expenses. The Contractor is to afford to the Engineer (of any party designated by the
Engineer) present when any test/retest is being carried out.

d) The Contractor shall bear all costs and expenses of all consumables and the like including but not limited
to fuels, spares, etc and all samples (if any) required for testings and any retestings.

e) The Contractor shall be responsible in receiving, unloading, varying and storing Employer's Materials for
his installation as part of the Works.

f) All materials, workmanship, etc for the Works shall be the best of their respective kinds.

g) The Contractor shall carry out all tests/retests requested by the Engineer under the Specifications either at
the Contractor's Factory and/or at the places of fabrication /manufacture of his suppliers. All consumables,
parts, samples, etc shall be at the costs and expenses of the Contractor. The Contractor shall carry out the
tests as required in the Specifications.

h) The Contractor is responsible to ensure that all materials, workmenship, etc furnished and installed are in
conformance with all applicable ordinances, law, rules, regulations, etc.

i) The Contractor shall be responsible for checking, taking care and custody, protecting, storing of
Employer's Materials for the Contractor's installation as part of the Works.

j) The Contractor shall obtain all technical requirements, installation instructions and all of the like to
properly install Employer's Material into the Works.

k) The Contractor shall provide for further Employer's Materials including but not limited to fixing ancillaries,
seals, etc required by the Contractor in consequence of Contractor's damages to the Employer's Materials
and/or usage in excess of what is to be provided by the Employer.

l) The Contractor shall provide and allow for any On-Site making good, cutting, fitting and the like required
to be made to the Employer's Materials.

1.17 SAFETY / SECURITY

a) The Contractor will keep his work areas in Site and in Contractor's Factory in the safe condition both for
his employees, workmen and visitors.

b) The Contractor shall safeguard the Works, materials and plants against damage or theft including all
necessary watching and lighting for the Works and the protection of the public. The Contractor shall
provide accommodation and other facilities for any watchmen/security guards so required.
Carried to collection

B1 - 20/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

c) The Contractor will be solely responsible for the safety and safe custody of all his materials, Construction
Plant, Temporary Works, etc and equipments whether they have been fixed or unfixed.

d) The Contractor is to employ sufficient security personnel to safeguard his entire works, including fixed and
unfixed Materials, Construction Plant, Temporary Works, etc and temporary building from vandalism and
theft. The Contractor shall indemnify the Employer from whatever loss due to damage or theft.

e) The Contractor shall allow for system, approved by the Engineer, to screen and check all persons entering
and leaving the Site, including the issue of identifications cards for all workers and visitors.

f) The Contractor shall employ an experienced full time safety officer for the Works.

g) The Contractor is to allow adequate safety gears and protective clothing for his employees and workmen,
etc and to comply with all the safety requirements of the relevant authorities.

h) The Contractor shall provide all protective screens, guards rails, protections to penetrations, scaffolding,
protective gantries for his works as the Works proceed in accordance with regulations of the Local
Authorities.

i) The Contractor shall provide all necessary protective netting to the buildings / structures for the safety of
the workmen and the protection of the public and occupants/users of neighboring properties from all risks
of injury especially by falling objects from the building throughout all stages of construction to the
satisfaction of the Local Authorities and the Engineer.

j) The Contractor shall carry out all safety requirements to ensure the safety of all occupants of the Project
pursuant to the phased development of the Project.

k) The Contractor is to provide a safety manual and procedures for the Engineer's approval before the
commencement of the Works.

1.18 SUPPLY EVERYTHING NECESSARY

a) The Contractor shall supply everything necessary including all labor and Materials, Construction Plant,
Temporary Works, etc freightage and all tarpaulins and coverings, required to protect all the Works and
Materials from the weather or other sources of injury.

b) The Contractor shall remove all Construction Plant, Employer's Construction Plant, Temporary Works, etc
upon completion as stated in the Contract or upon Engineer's instructions.

c) The Contractor shall not damage or disrupt the works of Employer's Other Contractors and Employer's
Own Forces.

d) The Contractor shall return all excess unused Employer's Materials that he has received at no cost upon
Completion to the Employer and which shall be properly packed and identified to the Engineer's
satisfaction.

1.19 MAINTENANCE AND PROTECTION OF EXISTING ROADS, FOOT PATHS, FENCES, ETC.

a) The Contractor shall be responsible for ensuring that the roads leading to and around the Site are kept
free from obstruction brought about by his works on Site and in no way shall he cause any hindrance
to traffic or ancillary works either by his own vehicles, or by his work people, materials, etc.

Carried to collection

B1 - 21/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

b) The Contractor shall be responsible for repairing damage to any streets and access roads if deteriorations
occurs due to his Works during the Contract Period.

c) The Contractor shall reinstate and repairs any damage to exiting roads, footpaths, fences, etc due to his
works during the Contract Period.

1.20 AUTHORITIES' RESTRICTION AS TO TRANSPORTATION

a) Contractor to allow for compliance with relevant municipal stipulations and restrictions concerning
movement of heavy vehicles and transportation of heavy equipment on public roadway.

b) Contractor to allow for compliance with relevant by-laws and regulations governing transportation of the
Works and/or any part(s) thereof.

c) The Contractor shall indemnify the Employer against all demands, proceedings, damages, costs, charges
and expenses arising in consequence of transportation of the Works or any part(s) thereof.

1.21 PROTECTION OF PUBLIC AND PRIVATE EXISTING SERVICES

a) Protect, uphold, upkeep and maintain all existing services as pipes, ducts, storm water drains, sewers,
electrical and telephone cables and the like encountered during the performance of the Works by the
Contractor. Special precautions shall be taken to prevent undermining of foundations to these service
lines and the Contractor is to make good any damage due to any cause within his diligence and control
at his own costs and expenses and pay all costs and charges in connection therewith.

b) Where services are required to be temporarily terminated or diverted, the Contractor is to give the
necessary notices to the appropriate Authority and arrange for the works to be carried out. The cost of any
approved diversion will be paid by the Employer.

1.22 PROTECTION OF ADJOINING PROPERTY AND PART OF WORKS TAKEN OVER

a) The Contractor shall take every precaution necessary to protect adjoining property and part of works
taken over from damage and shall pay all expenses incurred in remedying damage caused through lack of
care on his part.

b) The Contractor shall take every precaution necessary to ensure that the businesses of adjoining property
and part of works taken over shall not be disrupted and that the occupier/users of such property shall
have the use of the facilities for the same free from encumbrances and/or disturbances.

1.23 SITE PROGRESS PHOTOGRAPHS

a) Allow for providing site progress photographs to show the Works in progress. Photographs shall be taken
at monthly intervals throughout the whole of the construction period. Each time the negatives and 2(two)
post-card sizes prints of each shall be supplied to the Engineer. Each photograph shall be numbered,
dated and unnotated to show the general details of and the positions from which they were taken.

1.24 REMOVAL OF RUBBISH & DEBRIS

a) All Materials, etc when brought onto the Site shall be stored in neat and orderly manner. The Contractor
shall take all necessary measures to prevent breeding of mosquitoes at his work areas.

Carried to collection

B1 - 22/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

b) Burning of rubbish at the Site is strictly prohibited.

c) All rubbish, disused shoring, crates, waste materials, etc are to be removed from the Site by the Contractor.

d) The Contractor shall coordinate, liaise and provide attendance to Employer's Other Contractors and
Employer's Own Forces and the Contractor shall be responsible to remove all rubbish, etc from Site save
except for some rubbish which are more efficiently to be removed by the Employer's Other Contractors
and/or by Employer's Own Forces as decided by the Engineer

1.25 TELEPHONE AND WALKIE TALKIE

a) Telephones required by the Contractor shall be procured and installed at his own expense, and the
Contractor shall pay all cost and expenses in connection therewith including removal charges.

b) The Contractor shall provide and maintain enough numbers of walkie talkies for his carrying out of the
Works, and the Contractor shall arrange and pay for all licences, fees, charges, maintenance and the like
in connections therewith.

1.26 WATER FOR THE WORKS

a) The Contractor shall be responsible to provide general construction water for the Works.

b) The water supply shall be provided by the Contractor from well/wells constructed and maintained by the
Contractor or from any other sources as instructed by the Engineer and all of which shall have sufficient
running water lines and shall have sufficient temporary meters, mains, storage tanks and distribution
networks as may be necessary, and to clear away all of the same upon completion or upon the Engineer's
instructions.

c) The Contractor shall obtain and pay for all licenses, permits, fees and the like for the supply of water.

d) The Contractor shall provide all connections for the supply of water to locations as may be necessary
for the carrying out of all works for the Project and/or at the Engineer's instructions

e) The Employer may provide the construction water from the existing deep well(s) and/or PALYJA if and
when it is available. The Contractor shall determine by himself if the water provided by the Employer
would be enough for the Works, and the Contractor shall provide any additionally required water for the
Works on his own, should the water provided by the Employer not be sufficient. The Contractor shall
pay all the charges including "Biaya Langganan" to the Employer for the water that he has used from the
Employer's sources at the rates of PALYJA.

f) The Contractor shall also provide any other supplies of water other than the general constructions water
which may be required by the Contractor for testing, etc purposes.

1.27 ELECTRICAL POWER AND LIGHTINGS

a) The Electrical Power shall be provided by the Contractor at his own cost.

b) The Contractor shall provide and maintain temporary lighting system for the Works including all
necessary equipment, etc such as floodlights, spotlights, lighting poles, cable & light fittings, etc.
Further the Contractor shall provide and maintain the temporary lighting system for the Employer's
Other Contractors and Employer's Own Forces until the Completion of the whole Project.

Carried to collection

B1 - 23/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

c) The Contractor shall provide lighting and power distribution system as approved by the Engineer.

d) The Contractor is responsible for all power distribution from the main panel or local distribution boards
to his work locations at the Site and any storage areas therein.

e) The Employer may provide the electrical power to the Contractor if and when it is available. The Contractor
shall determine by himself if the electrical power provided by the Employer would be enough for the
Works, and the Contractor shall provide any additionally required electrical power for the Works on his
own, should the electrical power provided by the Employer not be sufficient. The Contractor shall pay all
the charges including "Biaya Beban" to the Employer for the electricity that he has used from the Employer's
sources at PLN's rates.

1.28 GENERAL ATTENDANCE UPON ALL TRADES AND SERVICES

a) The Contractor shall at all times make good, rectify, replace any of his works which may become disturb
or damage by Employer's Other Contractors and/or Employer's Own Forces or due to any other reason.

1.29 FIRE PROTECTION

a) Allow for keeping the Site safe from fire hazard. The Contractor shall take all necessary precautions
including those specified by the Insurance Company insuring the Works. The Contractor shall request
the Engineer to get all information related thereto.

b) The Contractor shall provide all necessary fire fighting equipment and properly trained staff to the
satisfaction of the Engineer. The approval of the Engineer shall not prejudice the Contractor's liability.

c) The Contractor shall take every precaution to prevent the out break of fires. Storing of highly inflammable
material and lighting of open fires in the Site is strictly prohibited.

1.30 CARTAGE OF MATERIALS TO THE SITE AND REMOVAL OF SPOIL AND SURPLUS MATERIALS

a) The Contractor shall comply with the requirements of Local Authorities and the Police in respect of the
use of motor vehicles delivering materials to or removing spoil or surplus materials from the Site. The
Contractor shall allow for all costs in inconnection therewith and no claim in respect of any additional cost
resulting from such requirements will be allowed.

1.31 ACCESS FOR THE EMPLOYER'S OTHER CONTRACTORS AND EMPLOYER'S OWN FORCES

a) See item 1.40 of Bill No. 1.

b) The Contractor shall allow for the presence of Employer's Other Contractors and Employer's Own Forces
on Site and any other party(ies) authorized by the Employer/Engineer who may be carrying out their
works simultaneously, contemporaneously, sequentially or otherwise with the Contractor.

c) The Contractor:
i) shall have no claims against the Employer in respect of any acts or omissions of the said parties on
Site;
ii) shall have harmless and indemnify the Employer against all claims from the said parties on Site,
arising from failure of the Contractor to fulfill its duties;
iii) shall accept that all defaults of the said other parties on Site arising from the Contractor's failure to
fulfill its obligations shall be deemed to be the default of the Contractor.

Carried to collection

B1 - 24/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

d) The Contractor's obligations with respect to the said other parties on Site shall include but may not be
limited to the following:
i) shall liaise, work, coordinate and the like with the said other parties works;
ii) shall not delay, obstruct, etc the said other parties works;
iii) shall afford free use of the Contractor's facilities and the like as instructed by the Engineer;
iv) shall carry out everything possible to ensure that all works are properly integrated and interphased
into the Project.

e) The Contractor shall note that the taking over of any portions of the Works by other parties on Site
permitted by the Engineer shall not be construed as completion of any sections, phases, etc.

f) In the event of any disputes between the Contractor, Employer's Other Contractors, Employer's Own
Forces, etc the Contractor shall agree that the decisions of the Engineer shall be binding, final and
conclusive.

1.32 CONTRACTOR'S SUBMISSIONS


a) The Contractor shall according to any time stipulated in the Contract, but in any case not later than 30 days
after issue of the Certificate of Practical Completion, submit to the Engineer the followings:

i) Project record documents including one set of approved shop drawings and approved project data,
approved samples, field orders and/or other instructions purported as issued by the Engineer,
(excluding formal written variation order), field test records, previous listed project record documents;
ii) Evidence of compliance with requirements of the relevant statutory bodies;
iii) Performance Guarantees, etc;
iv) Spare parts and maintenance materials;
v) Any other documents as may be reasonably requested by the Employer and/or the Engineer.

b) The Contractor shall also submit, from time to time to the Engineer, all catalog data, samples data, etc
as required under the Contract and such shall only be submitted to the Engineer only after the Contractor
has reviewed the same and satisfied that they comply with the Contract.

1.33 TEMPORARY SHEDS & OFFICE

a) Provide, construct and maintain temporary sheds for the storage of materials, tools and equipments for
the Works at location allocated by the Engineer.

b) Pay all costs and charges in connection with these temporary facilities.

c) Sheds used for storage of any perishable materials and/or materials which may be damaged when in direct
contact with ground, shall have raised floors.

1.34 TEMPORARY WORKING PLATFORMS, GANTRIES AND THE LIKE

a) Provide all necessary temporary scaffoldings, staging, platforms, planks, catwalks, gangways, ladders, etc
of whatever height for the proper execution and completion of the Works and pay all costs and charges in
connection therewith. Alter, shift and adapt from time to time as necessary and remove on completion
of the Works.

b) The design and construction of scaffoldings and staging must comply with all requirements of the relevant
authorities.

Carried to collection

B1 - 25/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

c) The Contractor shall ensure that all Temporary Works are no longer required by Employer's Other
Contractors, Employer's Own Forces, etc before proceeding to remove the same; failing which the
Contractor shall re-erect the same at the Contractor's own cost and expenses.

d) The Contractor shall indemnify the Employer against any claim or action arising out of defective or
improperly constructed scaffoldings or stagings.

1.35 CONTRACTOR'S PLANT, EQUIPMENTS ATTACHED TO STRUCTURE

a) In the installation of any Construction Plant, equipment, etc which places any load on the structure of
the Project, the Contractor must furnish full details of such Construction Plant, equipment, etc to the
Engineer for his approval before the works actually commence.

b) In the case of loads imposed on concrete structures of the Project, such loadings on concrete structure
may only be allowed upon achievement of minimal 28 days strength. If deemed necessary by the Engineer
and architecturally acceptable, the structure may be strengthened structurally to carry any additional loads
and all costs and expenses incurred in permitting the same to be carried out shall be to the account of the
Contractor and the Contractor shall also be responsible for any making good to the concrete structure
which may be caused in consequences thereto.

1.36 TEMPORARY HOARDING, GATES AND TEMPORARY ROADS

a) At locations where temporary hoarding is required, provide temporary hoarding and gates to seal off.

b) Alter, shift, re-erect, adapt from time to time as necessary, and pay all costs and charges in connection
with temporary hoarding and gates, and remove on completion of the Works.

c) The Contractor shall provide, maintain and alter as necessary all temporary roads, tracks, hard standings,
pavement crossings, culverts and, temporary works and the like. All ground and all works must be
reinstated before completion of the Works.

1.37 PUBLIC ADDRESS AND ALARM SYSTEMS

a) The Contractor shall provide maintain such a system as shall allow efficient communication at Site.

b) The Contractor shall pay all costs and charges in connection with the said communication system and
its removal on completion of the Works.

1.38 PUMPING, DEWATERING AND TEMPORARY WATER DISPOSAL

a) Dewatering works shall be carried out by Employer's Other Contractor until the completion of the
basement structural works.

b) Thereafter the Contractor shall keep excavations and the Works free from water by pumping, baling,
temporary discharge or any other means to the satisfaction of the Engineer.

c) The Contractor shall provide silt traps, tanks or other means of removing sediments from water before
being discharged into drains. The Contractor shall provide pumps where water not directly discharged
into drains.

Carried to collection

B1 - 26/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

1.39 PROTECTION OF THE WORKS

a) The Contractor shall provide for carefully covering up and protecting of the Works from inclement weather.

b) The Contractor shall provide full and adequate protection for all finished surfaces and all materials which
can be damaged by staging, and the Contractor shall be responsible for making good all damages made to
such finished surfaces and materials until the Works are completely handed over to the Employer.

c) This protection must be applied or provided as soon as surfaces are finished and/or materials arrive on Site
and shall also be maintained in effective condition throughout the course of the Works.

d) Where the material supplied includes a protective covering, coating, etc the Contractor shall repair, replace
and maintain such covering, coating, etc in proper way to the approval of the Engineer. Remove all
protective coverings, coatings, etc on completion of the Works.

1.40 CONTRACTOR'S GENERAL ATTENDANCE UPON EMPLOYER'S OTHER CONTRACTORS AND


EMPLOYER'S OWN FORCES

a) provide access for the said other parties entry into Site and/or through places where the Works are being
carried out at Site.

b) Provide free and reasonable use of the Contractor's Construction Plant, Temporary Works, etc by such
other parties on Site.

c) Share general construction water, power facilities and other facilities and to plan use of such facilities
taking into the needs of such other parties on Site. In case the Contractor provides the water and electricity,
such other parties shall pay the charges for water and electricity that they have used from the Contractor's
sources at the rates of PALYJA or PLN including "Biaya Langganan" and/or "Biaya Beban" respectively.

d) Making reasonable adjustments to the Works including scheduling, sequence of works, etc so as to ensure
that all works including those of other parties on Site can be completed in accordance with the Employer's
schedule for the Project.

e) Provide all other parties on Site on Contractor's key dates to achieve completion of the Works for proper
coordination of all works being carried out on Site.

f) Obtain key dates from the other parties on Site to ensure that the Contractor's works are planned
accordingly.

g) Obtain all necessary details from and provide all the same to other parties on Site so that all requirements
which may effect the Works or all other contractor's requirements which may effect works of other parties
on Site can be accommodated.

h) Share reasonable use of all site facilities with Employer's Other Contractors, Employer's Own Forces, etc.

1.41 FURTHER RESPONSIBILITIES OF THE CONTRACTOR

a) Design (if any), construct, complete and maintain the Works.

b) Delivery, unload, store and handling of all parts of the Works.

Carried to collection

B1 - 27/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

c) Installation of the Works, all adjustment necessary thereto.

d) The provision, erection, maintenance and removal of all site facilities provided by the Contractor.

e) The provision of all their necessary equipment for welding, installation, testing commissioning and making
good.

f) Cutting of openings, holes, chases and the like in coordination with Employer's Other Contractors,
Employer's Own Forces, etc except for those which prior notifications have been given to the Contractor
to be left in the structure before casting.

g) Removal from the Site of all rubbish deposited at the designated rubbish dump at Site.

h) Full responsibility, subject only to the provisions of the Conditions of Contract, for loss or damage to any
of the Works, materials or goods on Site until such Works, materials and goods on Site have been fully,
finally and properly incorporated into the Works and handed over to the Employer. The Contractor shall
liaise with Employer's Other Contractor's and Employer's Own Forces and establish agreement on when to
install the materials and goods into the Contractor's Works or which effects the Contractor's Works.

i) Full responsibility for loss or damage to the Construction Plant, Temporary Works, etc on Site.

j) Full responsibility for loss or damage to the Employer's Construction Plant and/or Facilities if any, arising
out of the Contractor's Works and/or related thereto.

k) Protection and casing up of the Works until such works have been properly completed and incorporated
into the Project and handed over to the Employer.

l) Setting out of the Works and also provide base lines with necessary offsets as instructed by the Engineer
to serve as references for works of Employer's Other Contractors, Employer's Own Forces and etc.

m) Allow for the installation of anchors including reinforcements of sizes sufficient to carry minimal load of
equipment to be installed, all to be as instructed by the Engineer. Position shall be determined during
construction.

1.42 FURTHER REQUIREMENTS TO BE CARRIED OUT BY THE CONTRACTOR

a) The Contractor shall maintain the Works for 12 months after completion and the Works shall be warranted
against defects for 5 years after completion in the format acceptable by the Engineer/Employer.

b) The Contractor shall submit four (4) copies of program of the Works to the Engineer for approval within
two (2) weeks from the date of Notice To Proceed. The program shall be continuously updated by the
Contractor and/or upon the Engineer's instructions. The requirements of the program shall be in
accordance with Specifications and the Conditions of Contract.

c) The Contractor shall carry out all tests during erection and on completion as specified including the
provisions of all consumables including but not limited to samples, etc and all necessary independently
certified instruments, gauges and test equipments.

d) The Contractor shall submit testing program together with proposed full comprehensive procedures of
tests to the Engineer for approval.

Carried to collection

B1 - 28/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

e) The Contractor shall carry out all re-testing as required under the Contract including the provisions of all
consumables including but not limited to samples, etc and all necessary independently certified instruments,
gauges and test equipments.

f) The Contractor shall carry out and complete all adjustments to the Works, etc necessitated in consequence
of test results, etc.

1.43 RESPONSIBILITIES OF EMPLOYER'S OTHER CONTRACTORS AND EMPLOYER'S OWN FORCES

a) Employer's Other Contractors and Employer's Own Forces will include in their respective contract sums
the costs in connection with the followings:

i) unloading, getting in, storing and handling of their materials, plant, tools, etc and the installation and
erection thereto.

ii) provisions of special equipment for installation and/or erection of their own works.

iii) coordinate with the Contractor for all aspects of their works including provisions for cutting openings
in their works and to advise the Contractor for the same to be done on the Contractor's Works by the
Contractor.

iv) depositing all rubbish, etc into designated dumping areas at Site to facilitate removal off site by the
Contractor.

v) avoid damage and/or disruption to the Contractor's Works.

vi) make reasonable use of the Contractor's Construction Plant, Temporary Works and other facilities.

vii) coordinate, cooperate and liaise with the Contractor to ensure the success of the Project for the
Employer.

viii) make known their schedule to the Contractor and to contain the Contractor's schedule for proper
integration and interplaying of their works for the Project.

ix) coordinate and plan with the Contractor in use of utilities on the Project to be provided by the
Employer.

x) protection of their works against possibly foreseeable damages thereto in consequence of their works
being carried out.

1.44 CHECKING VERTICALITY OF BUILDING

a) As the construction of the buildings progresses, the building structure particularly vertical structural
members such as lifts walls, shear walls, columns, etc shall be checked by the Contractor for verticality.
Such checking shall be carried out with appropriate survey equipment by the Contractor's qualified
surveyor for all floors of the building, one floor at a time and as soon as the structural works for each floor
are completed.

b) Two sets of the surveyors reports and field findings complied in an approved format are to be submitted to
the Engineer as and when completed. Such report shall indicate the verticality and deviation if any, of the
building structure.

Carried to collection

B1 - 29/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

c) The checking of the verticality of the building and the submission of such verticality reports to the Engineer
shall not relieve the Contractor of any of his duties, obligations, liabilities and responsibilities under the
Contract.

1.45 CONTRACTOR'S ACCEPTANCE OF PILING WORKS

a) The Contractor shall be responsible for checking out the setting out of the piling works to be carried out
by Employer's Other Contractors. The Contractor shall submit to the Engineer not later than two weeks or
as instructed by the Engineer, a report detailing any discrepancies between the Contract Drawings issued
to and the works executed by the piling contractors.

b) The Contractor shall accept the piling works as found and shall proceed with the Works as required under
the Contract. Should the Contractor's report referred to above contain any matter which the Contractor
considers should be resolved prior to the Works being executed then such matters shall be decided by
the Engineer.

1.46 COMMISSIONS OF ITEMS IN BILL NO. 1

a) The Contractor shall note and accept that the items as described in Bill No. 1 may at the discretion of the
Employer be omitted if the same can be more effectively carried out by other parties on Site. If such items
are omitted by the Employer, prices in Bill No. 1, or analogous or pro-rated thereto may be used in valuing
the value of items omitted at the discretion of the Engineer. There shall be no claims by the Contractor for
any damages, loss of profits, etc.

1.47 ADDITIONAL ITEMS TO BE COMPLETED BY THE CONTRACTOR

a) The Contractor shall include the details of any items which the Contractor is of the view that they are not
covered in Bill No. 1. Any failure of the Contractor to include further items herein below shall be deemed
acceptance by the Contractor that Bill of Quantities fully describe all works, materials, etc required for the
Contract.

i) _____________________________________________________

ii) _____________________________________________________

iii) _____________________________________________________

iv) _____________________________________________________

v) _____________________________________________________

Carried to collection

B1 - 30/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Item
No. Description

B1 - 31/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 32/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 33/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

266,206,984.05

266,206,984.05

B1 - 34/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

240,000,000.00

1,145,592,185.26

175,000,000.00

12,461,571,700.00

14,022,163,885.26

B1 - 35/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

Included

Included

Included

Included

Included

Included

5,517,886,410.00

21,461,785,000.00

26,979,671,410.00

B1 - 36/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

5,000,000.00

5,000,000.00

B1 - 37/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

413,600,000.00

11,000,000.00

424,600,000.00

B1 - 38/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 39/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

7,780,000.00

7,780,000.00

B1 - 40/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

79,200,000.00

3,500,000.00

41,000,000.00

4,873,798,863.83

4,997,498,863.83

B1 - 41/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

795,980,000.00

2,846,873,600.00

3,642,853,600.00

B1 - 42/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

605,558,000.00

605,558,000.00

B1 - 43/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 44/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 45/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 46/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 47/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 48/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

Lump-sum
Price
(Rp)

B1 - 49/117
Bill No. 1
CIVIL AND FINISHING WORKS Preliminaries

COLLECTION Rp

Page B 1/18 -

Page B 2/18 -

Page B 3/18 266,206,984

Page B 4/18 14,022,163,885

Page B 5/18 26,979,671,410

Page B 6/18 5,000,000

Page B 7/18 424,600,000

Page B 8/18 -

Page B 9/18 7,780,000

Page B 10/18 4,997,498,864

Page B 11/18 3,642,853,600

Page B 12/18 605,558,000

Page B 13/18 -

Page B 14/18 -

Page B 15/18 -

Page B 16/18 -

Page B 17/18 -

Page B 18/18

Total carried to Summary of Tender 50,951,332,743

B1 - 18/18
earth work

EARTH WORKS
- PARKING A = 992,500,000.00
- MALL A = 50,400,000.00
- PARKING B = 1,107,050,000.00
- MALL B = 64,420,000.00
- OFFICE TOWER = -
- APARTMENT TOWER = - 2,214,370,000.00

SUB STRUCTURE/BASEMENT WORKS


- PARKING A = 37,260,841,060.00
- MALL A = 12,944,057,660.00
- PARKING B = 55,819,709,000.00
- MALL B = 15,953,156,240.00
- OFFICE TOWER =
- APARTMENT TOWER = 121,977,763,960.00
=
UPPER STRUCTURE WORKS =
- PARKING A = 58,320,183,280.00
- MALL A = 39,955,014,860.00
- PARKING B = 48,455,093,896.00
- MALL B = 67,606,797,300.00
- OFFICE TOWER = 42,736,438,800.00
- APARTMENT TOWER = 35,493,795,380.00 292,567,323,516.00
=
ARCHITECTURAL WORKS =
- PARKING A = 5,411,224,000.00
- MALL A = 3,810,695,000.00
- PARKING B = 7,589,096,000.00
- MALL B = 7,535,210,000.00
- OFFICE TOWER = 4,440,887,000.00
- APARTMENT TOWER = 6,767,673,000.00 35,554,785,000.00

452,314,242,476.00

16 35,000,000.00 560,000,000.00
64 20,000,000.00 1,280,000,000.00
1,840,000,000.00
70,000.00
26,285.71
101,984,748,340.00
56,760,167,520.00
112,970,948,896.00
91,159,583,540.00
47,177,325,800.00
42,261,468,380.00

452,314,242,476.00
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

2.1 EARTH WORK

1 Excavation for substructure, foundations , pile caps, ground m³ 34,000 17,500 595,000,000
beams, etc including grading and compaction of the bottom
surface
2 Load and cart away off site surplus soil to be dumped at the m³ 24,000 12,500 300,000,000
Contractor's disposal area

3 Backfill and compaction with selected excavated material m³ 10,000 8,400 84,000,000

4 Sand - fill including compaction m³ 100 135,000 13,500,000

2.2 TERMITE CONTROL

Termite control as per Specifications m² 40,000 8,500 340,000,000


(Contractor to propose the Manufacturer and Type)
(Basilleum 505 EC Ex Desowag (Germany))
2.3 CUTTING OF PILE HEADS

Cutting of pile heads including disposal of debris


1 Dia. 1000 mm nos 450 500,000 225,000,000
2 Dia. 800 mm nos 910 430,000 391,300,000

2.4 SEISMIC JOINT

Supply & install seismic joint as per Drawings and Specifications


(Contractor to propose the Manufacturer and Type)

1 Wall, 100 mm width m 110 337,500 37,125,000


2 Wall, 150 mm width m 50 360,000 18,000,000
3 Floor, 100 mm width m 2,000 315,000 630,000,000
4 Floor, 150 mm width m 100 337,500 33,750,000

2.5 STRUCTURAL WORK

2.5.1 BASEMENT TO LOWER GROUND (- 6.800 to - 0.400 m)

1 100 mm thick gravel filling spread, leveled and compacted m² 28,800 12,375 356,400,000
under blind / lean concrete for pile caps, ground beams, slabs
and other foundations

2 50 mm thk blind / lean concrete K 100, under pile caps, ground m² 28,800 12,581 362,332,800
beams, slabs and other foundations

Carried to collection 3,386,407,800

B 2 - 1/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3 CONCRETE WORK

a Concrete K 500
- For Column m³ 900 371,200 334,080,000
- For Shear Wall m³ 400 371,200 148,480,000
b Concrete K 400
- For Pile Cap m³ 10,300 340,900 3,511,270,000
- For Tie Beam m³ 3,350 340,900 1,142,015,000
- For Suspended Girder & Beam m³ 365 340,900 124,428,500
- For Ground Slab m³ 9,200 340,900 3,136,280,000
- For Suspended Slab & Ramp m³ 630 340,900 214,767,000
- For Staircase m³ 36 340,900 12,272,400
- For Parapet & Fascia m³ 20 340,900 6,818,000
- For STP Wall m³ 80 340,900 27,272,000
- For Reservoir Wall m³ 85 340,900 28,976,500
- For Sump Pit m³ 50 340,900 17,045,000
- For Others, if any m³ 50 340,900 17,045,000

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

4 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 4,000 57,500 230,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 25,000 53,500 1,337,500,000

c Fair - Face Curved Formwork for exposed concrete surface m² 500 60,000 30,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 100 56,500 5,650,000

5 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 4,750 80,050 380,237,500

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 260 12,976 3,373,760
- Type M6 dia. 6 mm x 150 mm m² 1,560 18,600 29,016,000
- Type M7 dia. 7 mm x 150 mm m² 1,560 25,350 39,546,000
- Type M8 dia. 8 mm x 150 mm m² 1,560 33,195 51,784,200
- Type M9 dia. 9 mm x 150 mm m² 2,600 41,946 109,059,600
Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.
Carried to collection 10,936,916,460

B 2 - 2/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6 CHEMICAL ANCHOR FOR STARTER BAR

a Re bar ø 22 mm, tensile capacity : 9.123 tons no 100 52,077 5,207,700


(HILTI Type HIT HY150 - 38 cm or equivalent)
b Re bar ø 16 mm, tensile capacity : 4.825 tons no 640 22,240 14,233,600
(HILTI Type HIT HY150 - 24 cm or equivalent)
c Re bar ø 13 mm, tensile capacity : 3.185 tons no 0 12,810 -
(HILTI Type HIT HY150 - 17 cm or equivalent)

7 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Pile Cap kg 1,287,500 5,000 6,437,500,000
- For Tie Beam kg 653,300 5,000 3,266,500,000
- For Ground Slab kg 1,147,500 5,000 5,737,500,000
- For Column kg 88,700 5,000 443,500,000
- For Shear Wall kg 35,000 5,000 175,000,000
- For Girder & Beam kg 65,700 5,000 328,500,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 4,700 5,000 23,500,000
- For STP & Reservoir Wall kg 24,800 5,000 124,000,000
- For Sump Pit kg 6,500 5,000 32,500,000
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Pile Cap kg 0 5,055 -
- For Tie Beam kg 0 5,055 -
- For Ground Slab kg 0 5,055 -
- For Column kg 133,100 5,055 672,820,500
- For Shear Wall kg 15,900 5,055 80,374,500
- For Girder & Beam kg 0 5,055 -
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Pile Cap kg 0 5,110 -
- For Tie Beam kg 0 5,110 -
- For Column kg 0 5,110 -
- For Shear Wall kg 12,700 5,110 64,897,000
- For Girder & Beam kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Pile Cap kg 206,000 5,040 1,038,240,000
- For Tie Beam kg 150,800 5,040 760,032,000
- For Ground Slab kg 68,900 5,040 347,256,000
- For Column kg 55,400 5,040 279,216,000
- For Shear Wall kg 15,900 5,040 80,136,000
- For Girder & Beam kg 18,300 5,040 92,232,000
- For Slab & Ramp kg 8,800 5,040 44,352,000
- For Staircase kg 1,800 5,040 9,072,000
Carried to collection 20,056,569,300

B 2 - 3/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

- For STP & Reservoir Wall kg 6,600 5,040 33,264,000


- For Fascia & Parapet kg 2,800 5,040 14,112,000
- For Others, if any kg 0 - -
e Stirup Re bar U 24 ø < 10 mm
- For Slab & Ramp kg 4,700 5,005 23,523,500
- For Staircase kg 400 5,005 2,002,000
- For Fascia & Parapet kg 200 5,005 1,001,000
- For Sump Pit kg 1,000 5,005 5,005,000
- For Others, if any kg 0 5,005 -
Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

8 Extra Over Concrete for Water Tight Concrete m³ 2,000 403,000 806,000,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

9 WATER STOP

Supply & install water stop


(Contractor to propose the Manufacturer and Type)

a 100 mm wide water stop, type……… m 1,000 52,700 52,700,000


manufacturer : ……….

b 150 mm wide water stop, type……… m 2,000 71,000 142,000,000


manufacturer : ……….

c 200 mm wide water stop, type……… m 500 94,000 47,000,000


manufacturer : ……….

2.5.2 LOWER GROUND TO 5th FLOOR (- 0.4 to + 34.800 m )

1 CONCRETE WORK

a Concrete K 500
- For Column 2,200 371,200 816,640,000
- For Shear Wall 200 371,200 74,240,000

b Concrete K 400
- For Girder & Beam 5,600 340,900 1,909,040,000
- For Slab & Ramp 5,450 340,900 1,857,905,000
- For Staircase 110 340,900 37,499,000
- For Parapet & Fascia 80 340,900 27,272,000
- For Others, if any
Carried to collection 5,849,203,500

B 2 - 4/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 40,000 57,500 2,300,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 10,000 53,500 535,000,000
c Fair - Face Curved Formwork for exposed concrete surface m² 5,000 60,000 300,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 100 56,500 5,650,000

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 41,300 80,050 3,306,065,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 2,265 12,976 29,390,640
- Type M6 dia. 6 mm x 150 mm m² 13,590 18,600 252,774,000
- Type M7 dia. 7 mm x 150 mm m² 13,590 25,350 344,506,500
- Type M8 dia. 8 mm x 150 mm m² 13,590 33,195 451,120,050
- Type M9 dia. 9 mm x 150 mm m² 2,265 41,946 95,007,690
Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 212,500 5,000 1,062,500,000
- For Shear Wall kg 17,200 5,000 86,000,000
- For Girder & Beam kg 1,005,500 5,000 5,027,500,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 14,300 5,000 71,500,000
- For Fascia & Parapet kg 0 5,000 -
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 318,700 5,055 1,611,028,500
- For Shear Wall kg 7,800 5,055 39,429,000
- For Girder & Beam kg 0 5,055 -
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
Carried to collection 15,517,471,380

B 2 - 5/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

c Main Re bar U 50 ø 36 mm
- For Column kg 318,700 5,110 1,628,557,000
- For Shear Wall kg 6,300 5,110 32,193,000
- For Girder & Beam kg 0 5,110 -
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm - -
- For Column kg 132,800 5,040 669,312,000
- For Shear Wall kg 7,800 5,040 39,312,000
- For Girder & Beam kg 279,300 5,040 1,407,672,000
- For Slab & Ramp kg 76,200 5,040 384,048,000
- For Staircase kg 5,500 5,040 27,720,000
- For Fascia & Parapet kg 10,800 5,040 54,432,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm - -
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 40,800 5,005 204,204,000
- For Staircase kg 1,100 5,005 5,505,500
- For Fascia & Parapet kg 800 5,005 4,004,000
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 500 403,000 201,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

2.5.3 6th FLOOR UP TO PARKING ROOF (+ 34.800 to + 50.800 m )

1 CONCRETE WORK

a Concrete K 500
- For Column m³ 2,200 371,200 816,640,000
- For Shear Wall m³ 800 371,200 296,960,000

b Concrete K 400
- For Girder & Beam m³ 7,400 340,900 2,522,660,000
- For Slab & Ramp m³ 8,300 340,900 2,829,470,000
- For Staircase m³ 140 340,900 47,726,000
- For Parapet & Fascia m³ 120 340,900 40,908,000
- For Others, if any m³ 50 340,900 17,045,000
Carried to collection 11,229,868,500

B 2 - 6/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 50,000 57,500 2,875,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 15,000 53,500 802,500,000

c Fair - Face Curved Formwork for exposed concrete surface m² 1,000 60,000 60,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 300 56,500 16,950,000

3 METAL DECKING AND STEEL MESH


a Supply & installation of metal decking m² 63,000 80,050 5,043,150,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 3,450 12,976 44,767,200
- Type M6 dia. 6 mm x 150 mm m² 20,700 18,600 385,020,000
- Type M7 dia. 7 mm x 150 mm m² 20,700 25,350 524,745,000
- Type M8 dia. 8 mm x 150 mm m² 20,700 33,195 687,136,500
- Type M9 dia. 9 mm x 150 mm m² 3,450 41,946 144,713,700

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 209,300 5,000 1,046,500,000
- For Shear Wall kg 71,700 5,000 358,500,000
- For Girder & Beam kg 1,333,100 5,000 6,665,500,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 18,100 5,000 90,500,000
- For Fascia & Parapet kg 0 5,000 -
- For Others, if any kg 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 313,900 5,055 1,586,764,500
- For Shear Wall kg 32,600 5,055 164,793,000
- For Girder & Beam kg 0 5,055 -
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
Carried to collection 20,496,539,900

B 2 - 7/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

c Main Re bar U 50 ø 36 mm
- For Column kg 313,900 5,110 1,604,029,000
- For Shear Wall kg 26,100 5,110 133,371,000
- For Girder & Beam kg 0 5,110 -
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 130,800 5,040 659,232,000
- For Shear Wall kg 32,600 5,040 164,304,000
- For Girder & Beam kg 370,300 5,040 1,866,312,000
- For Slab & Ramp kg 115,900 5,040 584,136,000
- For Staircase kg 6,700 5,040 33,768,000
- For Fascia & Parapet kg 16,800 5,040 84,672,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 62,100 5,005 310,810,500
- For Staircase kg 1,400 5,005 7,007,000
- For Fascia & Parapet kg 1,200 5,005 6,006,000
- For Others if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 1,000 403,000 403,000,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

2.6 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)
(
- For Ground Slab m² 26,640 61,500 1,638,360,000
- For Diaphragm Wall m² 5,250 44,600 234,150,000
- For Outside STP, Reservoir & Retaining Wall m² 750 44,600 33,450,000
- For Inside of STP, Reservoir Wall & Floor m² 5,300 44,600 236,380,000
- For Roof Deck m² 14,200 61,500 873,300,000
- For Toilet & Mech. Room wet areas m² 500 44,600 22,300,000
- For Others, if any m² 100 44,600 4,460,000
Carried to collection 8,899,047,500

B 2 - 8/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

2.7 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 12,000 77,500 930,000,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 200 106,000 21,200,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 200 65,500 13,100,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 200 60,000 12,000,000
mortar and necessary concrete studs and lintels, etc.

2.8 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 500 5,000 2,500,000

2 Concrete broom finish m² 1,500 2,500 3,750,000

3 Concrete floor hardener m² 60,000 11,000 660,000,000

4 Plastering 20 mm thk, even and troweled enough to receive m² 35,000 32,000 1,120,000,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 400 19,000 7,600,000


b Painting to plastering wall, column, etc. m² 25,000 12,500 312,500,000

6 Supply, fabricate and install precast concrete wheel stops, nos 4,000 51,200 204,800,000
including all fixing accessories

2.9 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 540 225,000 121,500,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 520 75,000 39,000,000

3 Supply, fabricate and install galvanized steel grating cover m² 150 1,125,000 168,750,000
complete with frame, anchors and all accessories, etc.

Carried to collection 3,616,700,000

B 2 - 9/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4 Steel plate heavy duty manhole cover, including steel frames,


and resin paint finish, ect.
a Dia. 600 mm nos 10 430,000 4,300,000
b Dia. 800 mm nos 10 1,100,000 11,000,000
-
5 Supply, fabricate and install L 65 x 65 x 6 mm mild steel column nos 5,400 275,000 1,485,000,000
guard including painting stripe with resin paint (black & yellow)
complete with anchors, bracket & any other fixtures/accessories.

2.10 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 25,256,000 25,256,000


2 Anchors for lift doors, jambs and heads Ls 1 4,578,000 4,578,000
3 Davit socket for gondola system Ls 1 13,026,000 13,026,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 10,737,000 10,737,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 147,927,000 147,927,000
Other Contractors and Employer's Own Forces

2.11 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 19 600,000 11,400,000


- Type single leaf 900 x 2100 mm unt 0 610,000 -
- Type single leaf 1000 x 2100 mm unt 90 620,000 55,800,000
- Type double leaf 1600 x 2100 mm unt 25 900,000 22,500,000
- Type double leaf 2400 x 2400 mm unt 3 1,000,000 3,000,000

2 Installation of wooden doors with frame including hardwares :

- Type single leaf 750 x 2100 mm unt 0 100,000 -


- Type double leaf 1800 x 2100 mm unt 0 150,000 -
- Type double leaf 1000 x 2100 mm unt 0 160,000 -

Carried to collection 1,794,524,000

B 2 - 10/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 2
CIVIL AND FINISHING WORKS PARKING A

COLLECTION

Page 2 - 1/11 Rp. 3,386,407,800

Page 2 - 2/11 Rp. 10,936,916,460

Page 2 - 3/11 Rp. 20,056,569,300

Page 2 - 4/11 Rp. 5,849,203,500

Page 2 - 5/11 Rp. 15,517,471,380

Page 2 - 6/11 Rp. 11,229,868,500

Page 2 - 7/11 Rp. 20,496,539,900

Page 2 - 8/11 Rp. 8,899,047,500

Page 2 - 9/11 Rp. 3,616,700,000

Page 2 - 10/11 Rp. 1,794,524,000

SUB TOTAL BILL NO. 2 - Carried To Summary Rp. 101,783,248,340

B 2 - 11/11

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3.1 EXTERNAL EARTH WORK

1 Excavation for road, planter, canopy, guard houses, etc m³ 250 17,500 4,375,000
including grading and compaction

2 Load and cart away off site surplus soil to be dumped at the m³ 150 12,500 1,875,000
Contractor's disposal area

3 Backfill and compaction with selected excavated material m³ 50 8,400 420,000

4 Backfill and compaction with selected off - site imported m³ 50 50,100 2,505,000
material including compaction

5 Sand - fill including compaction m³ 75 135,000 10,125,000

6 Sand Gravel - fill including compaction m³ 250 124,400 31,100,000

3.2 DRIVEWAY, SIDEWALK, EXTERNAL ROAD, AND ECT.

"To Be Issued Later"

3.3 SITE DRAINAGE

"To Be Issued Later"

3.4 SEISMIC JOINT CONSTRUCTION

Supply & install seismic joint as per Drawings and Specifications


(Contractor to propose the Manufacturer and Type)

1 Wall, 100 mm width m 80 337,500 27,000,000


2 Wall, 150 mm width m 0 360,000 -
3 Floor, 100 mm width m 440 315,000 138,600,000
4 Floor, 150 mm width m 0 337,500 -

3.5 STRUCTURAL WORK

3.5.1 LOWER GROUND FLOOR ( - 3.800 m)

1 CONCRETE WORK

a Concrete K 500
- For Column m³ 1,750 371,200 649,600,000
- For Shear Wall m³ 380 371,200 141,056,000

Carried to collection 1,006,656,000

B 3 - 1/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

b Concrete K 400
- For Girder & Beam m³ 1,470 340,900 501,123,000
- For Slab & Ramp m³ 2,510 340,900 855,659,000
- For Staircase m³ 30 340,900 10,227,000
- For Parapet & Fascia m³ 20 340,900 6,818,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 6,000 57,500 345,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 11,000 53,500 588,500,000

c Fair - Face Curved Formwork for exposed concrete surface m² 250 60,000 15,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 19,000 80,050 1,520,950,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 1,043 12,976 13,527,480
- Type M6 dia. 6 mm x 150 mm m² 6,255 18,600 116,343,000
- Type M7 dia. 7 mm x 150 mm m² 6,255 25,350 158,564,250
- Type M8 dia. 8 mm x 150 mm m² 6,255 33,195 207,634,725
- Type M9 dia. 9 mm x 150 mm m² 1,043 41,946 43,728,705
Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 CHEMICAL ANCHOR FOR STARTER BAR

a Re bar ø 22 mm, tensile capacity : 9.123 tons no 100 37,077 3,707,700


(HILTI Type HIT HY150 - 38 cm or equivalent)
b Re bar ø 16 mm, tensile capacity : 4.825 tons no 0 11,240 -
(HILTI Type HIT HY150 - 24 cm or equivalent)
c Re bar ø 13 mm, tensile capacity : 3.185 tons no 480 4,810 2,308,800
(HILTI Type HIT HY150 - 17 cm or equivalent)
Carried to collection 4,389,091,660

B 3 - 2/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

5 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 168,200 5,000 841,000,000
- For Shear Wall kg 33,400 5,000 167,000,000
- For Girder & Beam kg 264,600 5,000 1,323,000,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 3,400 5,000 17,000,000
- For Fascia & Parapet kg 0 5,000 -
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 252,300 5,055 1,275,376,500
- For Shear Wall kg 15,200 5,055 76,836,000
- For Girder & Beam kg 0 5,055 -
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 252,300 5,110 1,289,253,000
- For Shear Wall kg 12,200 5,110 62,342,000
- For Girder & Beam kg 0 5,110 -
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 105,100 5,040 529,704,000
- For Shear Wall kg 22,100 5,040 111,384,000
- For Girder & Beam kg 73,500 5,040 370,440,000
- For Slab & Ramp kg 53,100 5,040 267,624,000
- For Staircase kg 1,300 5,040 6,552,000
- For Fascia & Parapet kg 2,800 5,040 14,112,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 18,800 5,005 94,094,000
- For Staircase kg 300 5,005 1,501,500
- For Fascia & Parapet kg 200 5,005 1,001,000
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities
Carried to collection 6,448,220,000

B 3 - 3/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6 Extra Over Concrete for Water Tight Concrete m³ 500 403,000 201,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

7 WATER STOP

Supply & install water stop


(Contractor to propose the Manufacturer and Type)

a 100 mm wide water stop, type……… m 200 52,700 10,540,000


manufacturer : ……….

b 150 mm wide water stop, type……… m 100 71,000 7,100,000


manufacturer : ……….

c 200 mm wide water stop, type……… m 50 94,000 4,700,000


manufacturer : ……….

3.5.2 UPPER GROUND FLOOR TO 5th FLOOR (+ 1.200 to + 34.800 m)

1 CONCRETE WORK

a Concrete K 500
- For Column m³ 4,800 371,200 1,781,760,000
- For Shear Wall m³ 2,550 371,200 946,560,000

b Concrete K 400
- For Girder & Beam m³ 5,980 340,900 2,038,582,000
- For Slab & Ramp m³ 8,110 340,900 2,764,699,000
- For Staircase m³ 180 340,900 61,362,000
- For Parapet & Fascia m³ 140 340,900 47,726,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 17,000 57,500 977,500,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 47,000 53,500 2,514,500,000

c Fair - Face Curved Formwork for exposed concrete surface m² 2,300 60,000 138,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -


Carried to collection 11,494,529,000

B 3 - 4/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 66,300 80,050 5,307,315,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 3,643 12,976 47,265,080
- Type M6 dia. 6 mm x 150 mm m² 21,855 18,600 406,503,000
- Type M7 dia. 7 mm x 150 mm m² 21,855 25,350 554,024,250
- Type M8 dia. 8 mm x 150 mm m² 21,855 33,195 725,476,725
- Type M9 dia. 9 mm x 150 mm m² 3,643 41,946 152,788,305
Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.
4 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 462,700 5,000 2,313,500,000
- For Shear Wall kg 224,800 5,000 1,124,000,000
- For Girder & Beam kg 1,077,000 5,000 5,385,000,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 23,700 5,000 118,500,000
- For Fascia & Parapet kg 0 5,000 -
- For Othes,r if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 694,100 5,055 3,508,675,500
- For Shear Wall kg 102,200 5,055 516,621,000
- For Girder & Beam kg 0 5,055 -
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Othes,r if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 694,100 5,110 3,546,851,000
- For Shear Wall kg 81,700 5,110 417,487,000
- For Girder & Beam kg 0 5,110 -
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Othes,r if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 289,200 5,040 1,457,568,000
- For Shear Wall kg 102,200 5,040 515,088,000
- For Girder & Beam kg 299,200 5,040 1,507,968,000
- For Slab & Ramp kg 113,500 5,040 572,040,000
- For Staircase kg 9,100 5,040 45,864,000
- For Fascia & Parapet kg 19,600 5,040 98,784,000
- For Others,r if any kg 0 5,040 -
Carried to collection 28,321,318,860

B 3 - 5/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

e Stirup Re bar U 24 ø < 10 mm


- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 60,800 5,005 304,304,000
- For Staircase kg 1,800 5,005 9,009,000
- For Fascia & Parapet kg 2,800 5,005 14,014,000
- For Others,r if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 750 403,000 302,250,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

3.6 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)

- For Roof Deck m² 0 61,500 -


- For Upper Ground Floor below landscape and road area m² 13,400 44,600 597,640,000
- For Toilet & Mech. room wet area m² 800 44,600 35,680,000
- For Planter m² 0 44,600 -
- For Mech. Room - wet area m² 600 44,600 26,760,000

3.7 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 18,000 77,500 1,395,000,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 200 106,000 21,200,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 150 65,500 9,825,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 150 60,000 9,000,000
mortar and necessary concrete studs and lintels, etc.

Carried to collection 2,724,682,000

B 3 - 6/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3.8 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 49,800 5,000 249,000,000

2 Concrete broom finish m² 0 2,500 -

3 Concrete floor hardener m² 11,000 -

4 Plastering 20 mm thk, even and troweled enough to receive m² 44,500 32,000 1,424,000,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 500 19,000 9,500,000


b Painting to plastering wall, column, etc. m² 9,000 12,500 112,500,000

3.9 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 420 225,000 94,500,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 410 75,000 30,750,000

3 Supply, fabricate and install galvanized steel grating cover m² 60 1,125,000 67,500,000
complete with frame, anchors and all accessories, etc.

4 Steel plate heavy duty manhole cover, including steel frames,


and resin paint finish, etc.
a Dia. 600 mm nos 5 395,000 1,975,000
b Dia. 800 mm nos 7 580,000 4,060,000

3.10 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 35,359,000 35,359,000


2 Anchors for lift doors, jambs and heads Ls 1 6,409,000 6,409,000
3 Davit socket for gondola system Ls 1 18,236,000 18,236,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 15,033,000 15,033,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 207,098,000 207,098,000
Other Contractors and Employer's Own Forces

Carried to collection 2,275,920,000

B 3 - 7/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3.11 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 66 600,000 39,600,000


- Type single leaf 900 x 2100 mm unt 1 610,000 610,000
- Type single leaf 1000 x 2100 mm unt 53 620,000 32,860,000
- Type double leaf 1600 x 2100 mm unt 26 900,000 23,400,000
- Type double leaf 2400 x 2400 mm unt 0 1,000,000 -

2 Installation of wooden doors with frame including hardwares :

- Type single leaf 750 x 2100 mm unt 8 100,000 800,000


- Type double leaf 1800 x 2100 mm unt 8 150,000 1,200,000
- Type double leaf 1000 x 2100 mm unt 8 160,000 1,280,000

Carried to collection 99,750,000

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

B 3 - 8/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 3
CIVIL AND FINISHING WORKS MALL A

COLLECTION

Page 3 - 1/9 Rp. 1,006,656,000

Page 3 - 2/9 Rp. 4,389,091,660

Page 3 - 3/9 Rp. 6,448,220,000

Page 3 - 4/9 Rp. 11,494,529,000

Page 3 - 5/9 Rp. 28,321,318,860

Page 3 - 6/9 Rp. 2,724,682,000

Page 3 - 7/9 Rp. 2,275,920,000

Page 3 - 8/9 Rp. 99,750,000

SUB TOTAL BILL NO. 3 - Carried To Summary Rp. 56,760,167,520

597088034.xls 06/19/2022
B 3 - 9/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4.1 EARTH WORK

1 Excavation for substructure, foundations , pile caps, ground m³ 36,500 17,500 638,750,000
beams, etc including grading and compaction of the bottom
surface
2 Load and cart away off site surplus soil to be dumped at the m³ 34,500 12,500 431,250,000
Contractor's disposal area

3 Backfill and compaction with selected excavated material m³ 2,000 8,400 16,800,000

4 Sand - fill including compaction m³ 150 135,000 20,250,000

4.2 TERMITE CONTROL

Termite control as per Specifications m² 60,000 8,500 510,000,000


(Contractor to propose the Manufacturer and Type)

4.3 CUTTING OF PILE HEADS

Cutting of pile heads including disposal of debris


1 Dia. 1200 mm nos 1 200,000 200,000
2 Dia. 1000 mm nos 930 500,000 465,000,000
3 Dia. 800 mm nos 805 430,000 346,150,000

4.4 SEISMIC JOINT CONSTRUCTION

Supply & install seismic joint as per Drawings and Specifications


(Contractor to propose the Manufacturer and Type)

1 Wall, 100 mm width m 180 337,500 60,750,000


2 Wall, 150 mm width m 0 360,000 -
3 Floor, 100 mm width m 900 315,000 283,500,000
4 Floor, 150 mm width m 0 337,500 -

4.5 STRUCTURAL WORK

4.5.1 BASEMENT (- 7.000 m) Including BRIDGE location

1 100 mm thick gravel filling spread, leveled and compacted m² 31,750 12,375 392,906,250
under blind / lean concrete for pile caps, ground beams, slabs
and other foundations

2 50 mm thk blind / lean concrete K 100, under pile caps, ground m² 31,750 12,581 399,446,750
beams, slabs and other foundations

Carried to collection 3,565,003,000

B 4 - 1/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3 CONCRETE WORK

a Concrete K 600
- For Column m³ 350 422,700 147,945,000
- For Shear Wall m³ 380 422,700 160,626,000
b Concrete K 500
- For Column m³ 790 371,200 293,248,000
- For Shear Wall m³ 190 371,200 70,528,000
- For Tie Beam m³ 0 371,200 -
- For Ground Slab m³ 770 371,200 285,824,000
c Concrete K 400
- For Pile Cap m³ 23,080 340,900 7,867,972,000
- For Tie Beam m³ 6,890 340,900 2,348,801,000
- For Girder & Beam m³ 0 340,900 -
- For Ground Slab m³ 9,920 340,900 3,381,728,000
- For Suspended Slab m³ 0 340,900 -
- For Staircase m³ 40 340,900 13,636,000
- For Sump Pit m³ 50 340,900 17,045,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

4 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 6,000 57,500 345,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 27,000 53,500 1,444,500,000

c Fair - Face Curved Formwork for exposed concrete surface m² 600 60,000 36,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -

5 CHEMICAL ANCHOR FOR STARTER BAR

a Re bar ø 22 mm, tensile capacity : 9.123 tons no 500 52,077 26,038,500


(HILTI Type HIT HY150 - 38 cm or equivalent)
b Re bar ø 16 mm, tensile capacity : 4.825 tons no 1,000 22,240 22,240,000
(HILTI Type HIT HY150 - 24 cm or equivalent)
c Re bar ø 13 mm, tensile capacity : 3.185 tons no 0 12,810 -
(HILTI Type HIT HY150 - 17 cm or equivalent)

Carried to collection 16,461,131,500

B 4 - 2/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Pile Cap kg 2,884,900 5,000 14,424,500,000
- For Tie Beam kg 1,342,600 5,000 6,713,000,000
- For Ground Slab kg 1,336,600 5,000 6,683,000,000
- For Column kg 108,900 5,000 544,500,000
- For Shear Wall kg 41,100 5,000 205,500,000
- For Staircase kg 5,300 5,000 26,500,000
- For Sump Pit kg 6,500 5,000 32,500,000
- For Othesr if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Pile Cap kg 0 5,055 -
- For Tie Beam kg 0 5,055 -
- For Ground Slab kg 0 5,055 -
- For Column kg 95,300 5,055 481,741,500
- For Shear Wall kg 22,800 5,055 115,254,000
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Pile Cap kg 0 5,110 -
- For Tie Beam kg 0 5,110 -
- For Column kg 68,100 5,110 347,991,000
- For Shear Wall kg 27,400 5,110 140,014,000
- For Girder & Beam kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Pile Cap kg 461,600 5,040 2,326,464,000
- For Tie Beam kg 309,800 5,040 1,561,392,000
- For Ground Slab kg 80,200 5,040 404,208,000
- For Column kg 68,000 5,040 342,720,000
- For Shear Wall kg 22,800 5,040 114,912,000
- For Staircase kg 2,100 5,040 10,584,000
- For Sump Pit kg 1,000 5,040 5,040,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Ground Slab kg 80,200 5,005 401,401,000
- For Staircase kg 400 5,005 2,002,000
- For Fascia & Parapet kg 200 5,005 1,001,000
- For Others, if any kg 0 5,005 -
Note )
All steel bar shall be supplied by the Employer at cost to
the Contractor as per the attached in the Bill of Quantities
7 Extra Over Concrete for Water Tight Concrete m³ 1,500 403,000 604,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacture and Type
Carried to collection 35,488,724,500

B 4 - 3/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

8 WATER STOP
Supply & install water stop
(Contractor to propose the Manufacturer and Type)
a 100 mm wide water stop, type……… m 1,500 52,700 79,050,000
manufacturer : ……….

b 150 mm wide water stop, type……… m 3,000 71,000 213,000,000


manufacturer : ……….

c 200 mm wide water stop, type……… m 750 94,000 70,500,000


manufacturer : ……….

4.5.2 6th FLOOR TO PARKING ROOF (+ 34.800 to + 50.800 m )


Including BRIDGE location

1 CONCRETE WORK

a Concrete K 600
- For Column m³ 660 422,700 278,982,000
- For Shear Wall m³ 1,450 422,700 612,915,000

b Concrete K 500
- For Column m³ 2,260 371,200 838,912,000
- For Shear Wall m³ 430 371,200 159,616,000
- For Tie Beam m³ 1,130 371,200 419,456,000
- For Ground Slab m³ 1,280 371,200 475,136,000

c Concrete K 400
- For Girder & Beam m³ 8,940 340,900 3,047,646,000
- For Slab & Ramp m³ 10,420 340,900 3,552,178,000
- For Staircase m³ 150 340,900 51,135,000
- For Parapet & Fascia m³ 150 340,900 51,135,000
- For Planter m³ 860 340,900 293,174,000
- For Others, if any m³ 100 340,900 34,090,000

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 85,000 57,500 4,887,500,000
instructed by the Engineer
b Normal Formwork for non exposed concrete surface m² 17,500 53,500 936,250,000

c Fair - Face Curved Formwork for exposed concrete surface m² 2,200 60,000 132,000,000
as instructed by the Engineer
d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -
Carried to collection 16,132,675,000

B 4 - 4/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 86,500 80,050 6,924,325,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 4,751 12,976 61,642,488
- Type M6 dia. 6 mm x 150 mm m² 28,503 18,600 530,155,800
- Type M7 dia. 7 mm x 150 mm m² 28,503 25,350 722,551,050
- Type M8 dia. 8 mm x 150 mm m² 28,503 33,195 946,157,085
- Type M9 dia. 9 mm x 150 mm m² 4,751 41,946 199,264,473

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 280,700 5,000 1,403,500,000
- For Shear Wall kg 134,600 5,000 673,000,000
- For Girder & Beam kg 1,268,300 5,000 6,341,500,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 19,500 5,000 97,500,000
- For Fascia & Parapet kg 0 5,000 -
- For Planter kg 0 5,000 -
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 245,600 5,055 1,241,508,000
- For Shear Wall kg 74,800 5,055 378,114,000
- For Girder & Beam kg 362,400 5,055 1,831,932,000
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 175,400 5,110 896,294,000
- For Shear Wall kg 89,800 5,110 458,878,000
- For Girder & Beam kg 181,200 5,110 925,932,000
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others, if any kg 0 5,110 -

Carried to collection 23,632,253,896

B 4 - 5/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 175,400 5,040 884,016,000
- For Shear Wall kg 74,800 5,040 376,992,000
- For Girder & Beam kg 503,300 5,040 2,536,632,000
- For Slab & Ramp kg 163,800 5,040 825,552,000
- For Staircase kg 7,500 5,040 37,800,000
- For Fascia & Parapet kg 21,000 5,040 105,840,000
- For Planter kg 120,100 5,040 605,304,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 87,600 5,005 438,438,000
- For Staircase kg 1,500 5,005 7,507,500
- For Fascia & Parapet kg 1,500 5,005 7,507,500
- For Others, if any kg 8,600 5,005 43,043,000

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 1,500 403,000 604,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

4.6 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)

- For Ground Slab m² 31,450 61,500 1,934,175,000


- For Diaphragm Wall m² 8,660 44,600 386,236,000
- For Roof Deck m² 16,700 61,500 1,027,050,000
- For Toilet & Mech. Room wet area m² 500 44,600 22,300,000
- For Planter m² 4,570 44,600 203,822,000
- For Swimming pool & Lagoon m² 900 61,500 55,350,000

Carried to collection 10,102,065,000

B 4 - 6/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4.7 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 31,700 77,500 2,456,750,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 500 106,000 53,000,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 300 65,500 19,650,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 200 60,000 12,000,000
mortar and necessary concrete studs and lintels, etc.

4.8 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 250 5,000 1,250,000

2 Concrete broom finish m² 19,300 2,500 48,250,000

3 Concrete floor hardener m² 64,700 11,000 711,700,000

4 Plastering 20 mm thk, even and troweled enough to receive m² 79,700 32,000 2,550,400,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 460 19,000 8,740,000


b Painting to plastering wall, column, etc. m² 35,000 12,500 437,500,000

6 Supply, fabricate and install precast concrete wheel stops, nos 1,600 51,200 81,920,000
including all fixing accessories

4.9 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 370 225,000 83,250,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 360 75,000 27,000,000

3 Supply, fabricate and install galvanized steel grating cover m² 160 1,125,000 180,000,000
complete with frame, anchors and all accessories, etc.

Carried to collection 6,671,410,000

B 4 - 7/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4 Steel plate heavy duty manhole cover, including steel frames,


and resin paint finish, etc.
a Dia. 600 mm nos 8 395,000 3,160,000
b Dia. 800 mm nos 10 580,000 5,800,000

5 Supply, fabricate and install L 65 x 65 x 6 mm mild steel column nos 2,700 275,000 742,500,000
guard including painting stripe with resin paint (black & yellow)
complete with anchors, bracket & any other fixtures/accessories.

4.10 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 13,185,000 13,185,000


2 Anchors for lift doors, jambs and heads Ls 1 2,390,000 2,390,000
3 Davit socket for gondola system Ls 1 6,800,000 6,800,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 5,605,000 5,605,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 77,226,000 77,226,000
Other Contractors and Employer's Own Forces

4.11 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 21 600,000 12,600,000


- Type single leaf 900 x 2100 mm unt 2 610,000 1,220,000
- Type single leaf 1000 x 2100 mm unt 50 620,000 31,000,000
- Type double leaf 1600 x 2100 mm unt 18 900,000 16,200,000
- Type double leaf 2400 x 2400 mm unt 0 1,000,000 -

2 Installation of wooden doors with frame including hardwares :

- Type single leaf 750 x 2100 mm unt 0 100,000 -


- Type double leaf 1800 x 2100 mm unt 0 150,000 -
- Type double leaf 1000 x 2100 mm unt 0 160,000 -

Carried to collection 917,686,000

B 5 - 8/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 4
CIVIL AND FINISHING WORKS PARKING B

COLLECTION

Page 4 - 1/9 Rp. 3,565,003,000

Page 4 - 2/9 Rp. 16,461,131,500

Page 4 - 3/9 Rp. 35,488,724,500

Page 4 - 4/9 Rp. 16,132,675,000

Page 4 - 5/9 Rp. 23,632,253,896

Page 4 - 6/9 Rp. 10,102,065,000

Page 4 - 7/9 Rp. 6,671,410,000

Page 4 - 8/9 Rp. 917,686,000

SUB TOTAL BILL NO. 4 - Carried To Summary Rp. 112,970,948,896

B 4 - 9/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

5.1 EXTERNAL EARTH WORK

1 Excavation for road, planter, canopy, guard houses, etc m³ 300 17,500 5,250,000
including grading and compaction

2 Load and cart away off site surplus soil to be dumped at the m³ 200 12,500 2,500,000
Contractor's disposal area

3 Backfill and compaction with selected excavated material m³ 100 8,400 840,000

4 Backfill and compaction with selected off - site imported m³ 100 50,100 5,010,000
material including compaction

5 Sand - fill including compaction m³ 100 135,000 13,500,000

6 Sand Gravel - fill including compaction m³ 300 124,400 37,320,000

5.2 DRIVEWAY, SIDEWALK, EXTERNAL ROAD, AND ECT.

"To Be Issued Later"

5.3 SITE DRAINAGE

"To Be Issued Later"

5.4 SEISMIC JOINT CONSTRUCTION

Supply & install seismic joint as per Drawings and Specifications


(Contractor to propose the Manufacturer and Type)

1 Wall, 100 mm width m 100 337,500 33,750,000


2 Wall, 150 mm width m 0 360,000 -
3 Floor, 100 mm width m 400 315,000 126,000,000
4 Floor, 150 mm width m 0 337,500 -

5.5 STRUCTURAL WORK

5.5.1 LOWER GROUND FLOOR (- 3.800 m), Including BRIDGE location

1 CONCRETE WORK

a Concrete K 600
- For Column m³ 540 422,700 228,258,000
- For Shear Wall m³ 610 422,700 257,847,000

Carried to collection 710,275,000

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

B 5 - 1/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

b Concrete K 500
- For Column m³ 1,140 371,200 423,168,000
- For Shear Wall m³ 300 371,200 111,360,000
- For Tie Beam m³ 300 371,200 111,360,000
- For Ground Slab m³ 370 371,200 137,344,000

c Concrete K 400
- For Girder & Beam m³ 2,430 340,900 828,387,000
- For Slab & Ramp m³ 2,980 340,900 1,015,882,000
- For Staircase m³ 40 340,900 13,636,000
- For Parapet & Fascia m³ 20 340,900 6,818,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 4,000 57,500 230,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 22,000 53,500 1,177,000,000

c Fair - Face Curved Formwork for exposed concrete surface m² 560 60,000 33,600,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 25,400 80,050 2,033,270,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 1,395 12,976 18,101,520
- Type M6 dia. 6 mm x 150 mm m² 8,370 18,600 155,682,000
- Type M7 dia. 7 mm x 150 mm m² 8,370 25,350 212,179,500
- Type M8 dia. 8 mm x 150 mm m² 8,370 33,195 277,842,150
- Type M9 dia. 9 mm x 150 mm m² 1,395 41,946 58,514,670

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

Carried to collection 6,844,144,840

B 5 - 2/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4 CHEMICAL ANCHOR FOR STARTER BAR

a Re bar ø 22 mm, tensile capacity : 9.123 tons no 200 52,077 10,415,400


(HILTI Type HIT HY150 - 38 cm or equivalent)
b Re bar ø 16 mm, tensile capacity : 4.825 tons no 0 22,240 -
(HILTI Type HIT HY150 - 24 cm or equivalent)
c Re bar ø 13 mm, tensile capacity : 3.185 tons no 800 12,810 10,248,000
(HILTI Type HIT HY150 - 17 cm or equivalent)

5 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 161,300 5,000 806,500,000
- For Shear Wall kg 65,000 5,000 325,000,000
- For Girder & Beam kg 344,500 5,000 1,722,500,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 5,200 5,000 26,000,000
- For Fascia & Parapet kg 0 5,000 -
- For Others, if any kg 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 141,100 5,055 713,260,500
- For Shear Wall kg 36,100 5,055 182,485,500
- For Girder & Beam kg 98,400 5,055 497,412,000
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 100,800 5,110 515,088,000
- For Shear Wall kg 43,300 5,110 221,263,000
- For Girder & Beam kg 49,200 5,110 251,412,000
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 100,800 5,040 508,032,000
- For Shear Wall kg 36,100 5,040 181,944,000
- For Girder & Beam kg 136,700 5,040 688,968,000
- For Slab & Ramp kg 46,800 5,040 235,872,000
- For Staircase kg 2,000 5,040 10,080,000
- For Fascia & Parapet kg 2,800 5,040 14,112,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
Carried to collection 6,920,592,400

B 5 - 3/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

- For Slab & Ramp kg 25,100 5,005 125,625,500


- For Staircase kg 300 5,005 1,501,500
- For Fascia & Parapet kg 200 5,005 1,001,000
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

6 Extra Over Concrete for Water Tight Concrete m³ 1,500 403,000 604,500,000
` - Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

5.5.2 UPPER GROUND TO 5th FLOOR (+ 1.200 to + 30.000 )


Including BRIDGE location

1 CONCRETE WORK

a Concrete K 600
- For Column m³ 3,500 422,700 1,479,450,000
- For Shear Wall m³ 3,700 422,700 1,563,990,000
b Concrete K 500
- For Column m³ 4,600 371,200 1,707,520,000
- For Shear Wall m³ 1,300 371,200 482,560,000
- For Tie Beam m³ 2,200 371,200 816,640,000
- For Ground Slab m³ 2,600 371,200 965,120,000
c Concrete K 400
- For Girder & Beam m³ 8,600 340,900 2,931,740,000
- For Slab & Ramp m³ 10,400 340,900 3,545,360,000
- For Staircase m³ 300 340,900 102,270,000
- For Parapet & Fascia m³ 140 340,900 47,726,000
- For others, if any m³ 0 340,900 -
Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 1,800 57,500 103,500,000
instructed by the Engineer
b Normal Formwork for non exposed concrete surface m² 124,000 53,500 6,634,000,000

c Fair - Face Curved Formwork for exposed concrete surface m² 3,800 60,000 228,000,000
as instructed by the Engineer

d Normal Curved Formwork for non exposed concrete surface m² 0 56,500 -


Carried to collection 21,340,504,000

B 5 - 4/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 98,000 80,050 7,844,900,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 5,400 12,976 70,070,400
- Type M6 dia. 6 mm x 150 mm m² 32,400 18,600 602,640,000
- Type M7 dia. 7 mm x 150 mm m² 32,400 25,350 821,340,000
- Type M8 dia. 8 mm x 150 mm m² 32,400 33,195 1,075,518,000
- Type M9 dia. 9 mm x 150 mm m² 5,400 41,946 226,508,400

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 REINFORCING STEEL BAR

a Main Re bar U 50 ø 16 - 25 mm
- For Column kg 785,400 5,000 3,927,000,000
- For Shear Wall kg 356,400 5,000 1,782,000,000
- For Girder & Beam kg 1,364,800 5,000 6,824,000,000
- For Slab & Ramp kg 0 5,000 -
- For Staircase kg 280,100 5,000 1,400,500,000
- For Fascia & Parapet kg 0 5,000 -
- For Others, if any kg 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 687,200 5,055 3,473,796,000
- For Shear Wall kg 198,000 5,055 1,000,890,000
- For Girder & Beam kg 389,600 5,055 1,969,428,000
- For Slab & Ramp kg 0 5,055 -
- For Staircase kg 0 5,055 -
- For Fascia & Parapet kg 0 5,055 -
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 490,900 5,110 2,508,499,000
- For Shear Wall kg 237,600 5,110 1,214,136,000
- For Girder & Beam kg 195,000 5,110 996,450,000
- For Slab & Ramp kg 0 5,110 -
- For Staircase kg 0 5,110 -
- For Fascia & Parapet kg 0 5,110 -
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 490,900 5,040 2,474,136,000
- For Shear Wall kg 198,000 5,040 997,920,000
- For Girder & Beam kg 541,600 5,040 2,729,664,000
- For Slab & Ramp kg 181,300 5,040 913,752,000
Carried to collection 42,853,147,800

B 5 - 5/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

- For Staircase kg 14,000 5,040 70,560,000


- For Fascia & Parapet kg 19,600 5,040 98,784,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Column kg 0 5,005 -
- For Shear Wall kg 0 5,005 -
- For Girder & Beam kg 0 5,005 -
- For Slab & Ramp kg 97,200 5,005 486,486,000
- For Staircase kg 2,800 5,005 14,014,000
- For Fascia & Parapet kg 1,400 5,005 7,007,000
- For Others, if any kg 0 5,005 -
Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 1,500 403,000 604,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

6 Steel Structure work


Supply, fabrication and installation, etc of the steel structure
as follows :
a Column 300 x 300 - 94 kg 10,900 8,682 94,633,800
b Beams WF 800 x 300 - 267.4 kg 141,000 11,398 1,607,118,000
c Truss beams
- Top Chord WF 200 x 200 - 65.7 kg 26,200 8,682 227,468,400
- Bottom chord, Tees 400 x 200 - 84 kg 12,300 8,682 106,788,600
- Bottom Chord, Tees 200 x 300 - 47.1 kg 11,900 8,682 103,315,800
- L 40x 40, 50x50, 60x60, 70x70, 80x80, 90x90 kg 21,600 8,682 187,531,200
d Embeded plate & Connection plate kg 24,800 8,682 215,313,600
e Anchor bolt ø 19 mm nos 530 36,375 19,278,750
f Stud bolt ø 16 mm nos 2,200 15,763 34,678,600
g High tensile bolt ø 19 mm nos 350 8,003 2,801,050
h Primary (Zincromate) paint kg 248,700 631 156,929,700

5.6 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)

- For Roof Deck m² 750 61,500 46,125,000


- For Upper Ground Floor below Landscape & Road area m² 17,600 44,600 784,960,000
- For Toilet area m² 1,050 44,600 46,830,000
- For Planter m² 560 44,600 24,976,000
- For Mech. Room - wet area m² 350 44,600 15,610,000
Carried to collection 4,955,709,500

B 5 - 6/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

5.7 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 31,400 77,500 2,433,500,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 300 106,000 31,800,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 250 65,500 16,375,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 200 60,000 12,000,000
mortar and necessary concrete studs and lintels, etc.

5.8 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 61,000 5,000 305,000,000

2 Concrete broom finish m² 0 2,500 -

3 Concrete floor hardener m² 0 11,000 -

4 Plastering 20 mm thk, even and troweled enough to receive m² 115,500 32,000 3,696,000,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 960 19,000 18,240,000


b Painting to plastering wall, column, etc. m² 25,000 12,500 312,500,000

5.9 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 865 225,000 194,625,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 840 75,000 63,000,000

3 Supply, fabricate and install galvanized steel grating cover m² 120 1,125,000 135,000,000
complete with frame, anchors and all accessories, etc.

4 Steel plate heavy duty manhole cover, including steel frames,


and resin paint finish, etc.
a Dia. 600 mm nos 8 395,000 3,160,000
b Dia. 800 mm nos 12 580,000 6,960,000

Carried to collection 7,228,160,000

B 5 - 7/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

5.10 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 18,459,000 18,459,000


2 Anchors for lift doors, jambs and heads Ls 1 3,346,000 3,346,000
3 Davit socket for gondola system Ls 1 9,520,000 9,520,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 7,848,000 7,848,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 108,117,000 108,117,000
Other Contractors and Employer's Own Forces

5.11 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 108 600,000 64,800,000


- Type single leaf 900 x 2100 mm unt 8 610,000 4,880,000
- Type single leaf 1000 x 2100 mm unt 64 620,000 39,680,000
- Type double leaf 1600 x 2100 mm unt 56 900,000 50,400,000
- Type double leaf 2400 x 2400 mm unt 0 1,000,000 -

2 Installation of wooden doors with frame including hardwares :

- Type single leaf 750 x 2100 mm unt 0 100,000 -


- Type double leaf 1800 x 2100 mm unt 0 150,000 -
- Type double leaf 1000 x 2100 mm unt 0 160,000 -

Carried to collection 307,050,000

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

B 5 - 8/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 5
CIVIL AND FINISHING WORKS MALL B

COLLECTION

Page 5 - 1/9 Rp. 710,275,000

Page 5 - 2/9 Rp. 6,844,144,840

Page 5 - 3/9 Rp. 6,920,592,400

Page 5 - 4/9 Rp. 21,340,504,000

Page 5 - 5/9 Rp. 42,853,147,800

Page 5 - 6/9 Rp. 4,955,709,500

Page 5 - 7/9 Rp. 7,228,160,000

Page 5 - 8/9 Rp. 307,050,000

SUB TOTAL BILL NO. 5 - Carried To Summary Rp. 91,159,583,540

B 5 - 9/9

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6.1 STRUCTURAL WORK

6.1.1 11st FLOOR TO 20th FLOOR

1 CONCRETE WORK

a Concrete K 600
- For Column m³ 1,510 422,700 638,277,000
- For Shear Wall m³ 1,400 422,700 591,780,000
b Concrete K 500
- For Girder & Beam m³ 1,560 371,200 579,072,000
- For Slab m³ 1,940 371,200 720,128,000
c Concrete K 400
- For Staircase m³ 70 340,900 23,863,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 0 57,500 -


instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 64,000 53,500 3,424,000,000

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 15,900 80,050 1,272,795,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 810 12,976 10,510,560
- Type M6 dia. 6 mm x 150 mm m² 4,860 18,600 90,396,000
- Type M7 dia. 7 mm x 150 mm m² 4,860 25,350 123,201,000
- Type M8 dia. 8 mm x 150 mm m² 4,860 33,195 161,327,700
- Type M9 dia. 9 mm x 150 mm m² 810 41,946 33,976,260

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

Carried to collection 7,669,326,520

B 6 - 1/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Column kg 145,300 5,000 726,500,000
- For Shear Wall kg 100,900 5,000 504,500,000
- For Girder and Beam kg 70,900 5,000 354,500,000
- For Staircase kg 8,500 5,000 42,500,000
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 127,100 5,055 642,490,500
- For Shear Wall kg 56,000 5,055 283,080,000
- For Girder and Beam kg 30,400 5,055 153,672,000
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 90,800 5,110 463,988,000
- For Shear Wall kg 67,300 5,110 343,903,000
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 90,800 5,040 457,632,000
- For Shear Wall kg 56,000 5,040 282,240,000
- For Girder and Beam kg 28,200 5,040 142,128,000
- For Slab kg 96,950 5,040 488,628,000
- For Staircase kg 3,250 5,040 16,380,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Staircase kg 700 5,005 3,503,500
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 500 403,000 201,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

6.1.2 21st FLOOR To TOP OF PARAPET

1 CONCRETE WORK

a Concrete K 500
- For Column m³ 3,290 371,200 1,221,248,000
- For Shear Wall m³ 3,290 371,200 1,221,248,000

Carried to collection 7,549,641,000

B 6 - 2/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

b Concrete K 400
- For Girder and Beam m³ 2,060 340,900 702,254,000
- For Slab m³ 7,110 340,900 2,423,799,000
- For Staircase m³ 230 340,900 78,407,000
- For Parapet and Fascia m³ 110 340,900 37,499,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 54,000 57,500 3,105,000,000
instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 56,000 53,500 2,996,000,000

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 58,500 80,050 4,682,925,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 2,965 12,976 38,473,840
- Type M6 dia. 6 mm x 150 mm m² 17,790 18,600 330,894,000
- Type M7 dia. 7 mm x 150 mm m² 17,790 25,350 450,976,500
- Type M8 dia. 8 mm x 150 mm m² 17,790 33,195 590,539,050
- Type M9 dia. 9 mm x 150 mm m² 2,965 41,946 124,369,890

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

4 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Column kg 315,900 5,000 1,579,500,000
- For Shear Wall kg 236,500 5,000 1,182,500,000
- For Girder and Beam kg 259,400 5,000 1,297,000,000
- For Staircase kg 29,900 5,000 149,500,000
- For Others if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 276,500 5,055 1,397,707,500
- For Shear Wall kg 131,400 5,055 664,227,000
- For Girder and Beam kg 111,200 5,055 562,116,000
- For Others if any kg 0 5,055 -
Carried to collection 22,393,687,780

B 6 - 3/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

c Main Re bar U 50 ø 36 mm
- For Column kg 197,500 5,110 1,009,225,000
- For Shear Wall kg 157,700 5,110 805,847,000
- For Others if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 197,500 5,040 995,400,000
- For Shear Wall kg 131,400 5,040 662,256,000
- For Girder and Beam kg 103,000 5,040 519,120,000
- For staircase kg 11,500 5,040 57,960,000
- For Parapet and Fascia kg 16,500 5,040 83,160,000
- For Others if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For staircase kg 2,300 5,005 11,511,500
- For Others if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 2,000 403,000 806,000,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

6.2 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)

- For Roof Deck m² 2,100 61,500 129,150,000


- For Toilet & Mechanical room wet area m² 990 44,600 44,154,000
- For Planter m² 0 44,600 -
- For Others, if any m² 0 44,600 -

6.3 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 20,100 77,500 1,557,750,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 300 106,000 31,800,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 100 65,500 6,550,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 250 60,000 15,000,000
mortar and necessary concrete studs and lintels, etc.
Carried to collection 6,734,883,500

B 6 - 4/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6.4 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 61,000 5,000 305,000,000

2 Concrete broom finish m² 0 2,500 -

3 Concrete floor hardener m² 0 11,000 -

4 Plastering 20 mm thk, even and troweled enough to receive m² 54,000 32,000 1,728,000,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 1,940 19,000 36,860,000


b Painting to plastering wall, column, etc. m² 10,640 12,500 133,000,000

6.5 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 675 225,000 151,875,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 650 75,000 48,750,000

6.6 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 53,427,000 53,427,000


2 Anchors for lift doors, jambs and heads Ls 1 9,684,000 9,684,000
3 Davit socket for gondola system Ls 1 27,555,000 27,555,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 22,714,000 22,714,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 312,922,000 312,922,000
Other Contractors and Employer's Own Forces

Carried to collection 2,829,787,000

B 6 - 5/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

6.7 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 0 600,000 -


- Type single leaf 900 x 2100 mm unt 0 610,000 -
- Type single leaf 1000 x 2100 mm unt 342 620,000 212,040,000
- Type double leaf 1600 x 2100 mm unt 0 900,000 -
- Type double leaf 2400 x 2400 mm unt 0 1,000,000 -

2 Installation of wooden doors with frame including hardwares :

- Type single leaf 750 x 2100 mm unt 0 100,000 -


- Type double leaf 1800 x 2100 mm unt 86 150,000 12,900,000
- Type double leaf 1000 x 2100 mm unt 0 160,000 -

Carried to collection 224,940,000

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

B 6 - 6/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 6
CIVIL AND FINISHING WORKS OFFICE TOWER

COLLECTION

Page 6 - 1/7 Rp. 7,669,326,520

Page 6 - 2/7 Rp. 7,549,641,000

Page 6 - 3/7 Rp. 22,393,687,780

Page 6 - 4/7 Rp. 6,734,883,500

Page 6 - 5/7 Rp. 2,829,787,000

Page 6 - 6/7 Rp. 224,940,000

SUB TOTAL BILL NO. 6 - Carried To Summary Rp. 47,402,265,800

597088034.xls 06/19/2022
B 6 - 7/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

7.1 STRUCTURAL WORK

7.1.1 11st FLOOR TO 20th FLOOR

1 CONCRETE WORK

a Concrete K 600
- For Column m³ 1,220 422,700 515,694,000
- For Shear Wall m³ 1,610 422,700 680,547,000
b Concrete K 500
- For Girder & Beam m³ 1,100 371,200 408,320,000
- For Slab m³ 2,080 371,200 772,096,000
c Concrete K 400
- For Staircase m³ 60 340,900 20,454,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 0 57,500 -


instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 19,000 53,500 1,016,500,000

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 10,000 80,050 800,500,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 580 12,976 7,526,080
- Type M6 dia. 6 mm x 150 mm m² 3,480 18,600 64,728,000
- Type M7 dia. 7 mm x 150 mm m² 3,480 25,350 88,218,000
- Type M8 dia. 8 mm x 150 mm m² 3,480 33,195 115,518,600
- Type M9 dia. 9 mm x 150 mm m² 580 41,946 24,328,680

Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.

Carried to collection 4,514,430,360

B 7 - 1/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

4 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Column kg 117,400 5,000 587,000,000
- For Shear Wall kg 116,300 5,000 581,500,000
- For Girder & Beam kg 138,000 5,000 690,000,000
- For Staircase kg 8,450 5,000 42,250,000
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 127,100 5,055 642,490,500
- For Shear Wall kg 64,600 5,055 326,553,000
- For Girder & Beam kg 39,400 5,055 199,167,000
- For Others, if any kg 0 5,055 -
c Main Re bar U 50 ø 36 mm
- For Column kg 73,400 5,110 375,074,000
- For Shear Wall kg 77,500 5,110 396,025,000
- For Others, if any kg 19,700 5,110 100,667,000
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 73,400 5,040 369,936,000
- For Shear Wall kg 64,600 5,040 325,584,000
- For Girder & Beam kg 28,200 5,040 142,128,000
- For Slab kg 145,500 5,040 733,320,000
- For Staircase kg 3,000 5,040 15,120,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Staircase kg 600 5,005 3,003,000
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 500 403,000 201,500,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

7.1.2 21st FLOOR To TOP OF PARAPET

1 CONCRETE WORK

a Concrete K 500
- For Column m³ 1,760 371,200 653,312,000
- For Shear Wall m³ 3,750 371,200 1,392,000,000

Carried to collection 7,776,629,500

B 7 - 2/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

b Concrete K 400
- For Girder & Beam m³ 4,380 340,900 1,493,142,000
- For Slab m³ 8,320 340,900 2,836,288,000
- For Staircase m³ 240 340,900 81,816,000
- For Parapet and Fascia m³ 60 340,900 20,454,000
- For Others, if any m³ 0 340,900 -

Note )
All ready mixed concrete shall be supplied by the Employer
at cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities.

2 FORM WORK

a Fair - Face Formwork for exposed concrete surface as m² 0 57,500 -


instructed by the Engineer

b Normal Formwork for non exposed concrete surface m² 69,600 53,500 3,723,600,000

3 METAL DECKING AND STEEL MESH

a Supply & installation of metal decking m² 20,200 80,050 1,617,010,000

b Steel Mesh
- Type M5 dia. 5 mm x 150 mm m² 1,060 12,976 13,754,560
- Type M6 dia. 6 mm x 150 mm m² 6,360 18,600 118,296,000
- Type M7 dia. 7 mm x 150 mm m² 6,360 25,350 161,226,000
- Type M8 dia. 8 mm x 150 mm m² 6,360 33,195 211,120,200
- Type M9 dia. 9 mm x 150 mm m² 1,060 41,946 44,462,760
Note )
All metal decking & steel mesh shall be supplied by the
Employer at cost to the Contractor as per the Price List of
Employer's Materials attached in the Bill of Quantities.
4 REINFORCING STEEL BAR

a Main Re bar U 50, ø 16 - 25 mm


- For Column kg 169,300 5,000 846,500,000
- For Shear Wall kg 269,700 5,000 1,348,500,000
- For Girder & Beam kg 551,900 5,000 2,759,500,000
- For Staircase kg 31,200 5,000 156,000,000
- For Others, if any kg 0 5,000 -
b Main Re bar U 50 ø 29 - 32 mm
- For Column kg 148,100 5,055 748,645,500
- For Shear Wall kg 149,800 5,055 757,239,000
- For Girder & Beam kg 236,500 5,055 1,195,507,500
- For Others, if any kg 0 5,055 -
Carried to collection 18,133,061,520

B 7 - 3/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

c Main Re bar U 50 ø 36 mm
- For Column kg 105,800 5,110 540,638,000
- For Shear Wall kg 179,800 5,110 918,778,000
- For Others, if any kg 0 5,110 -
d Stirup Re bar U 40 ø 10 - 13 mm
- For Column kg 105,800 5,040 533,232,000
- For Shear Wall kg 149,800 5,040 754,992,000
- For Girder & Beam kg 219,000 5,040 1,103,760,000
- For Staircase kg 12,000 5,040 60,480,000
- For Parapet and Fascia kg 8,300 5,040 41,832,000
- For Others, if any kg 0 5,040 -
e Stirup Re bar U 24 ø < 10 mm
- For Staircase kg 2,400 5,005 12,012,000
- For Others, if any kg 0 5,005 -

Note )
All reinforcing steel bar shall be supplied by the Employer at
cost to the Contractor as per the Price List of Employer's
Materials attached in the Bill of Quantities

5 Extra Over Concrete for Water Tight Concrete m³ 2,000 403,000 806,000,000
- Contractor shall seek Engineer's Instruction & Approval
before using the Water Tight Concrete
- Contractor to propose the Manufacturer and Type

7.2 WATERPROOFING WORK

Supply and installation of Waterproofing & Protection System,


including all necessary ancillary works
(Contractor to propose the Manufacturer , Type and System)

- For Roof Deck m² 1,400 61,500 86,100,000


- For Toilet & Mechanical room wet area m² 4,750 44,600 211,850,000
- For Planter m² 0 44,600 -
- For Others, if any m² 0 44,600 -

7.3 BLOCK AND BRICK WORK

1 Celcon block wall 100 mm thk, including bedding, jointing m² 26,500 77,500 2,053,750,000
in mortar and necessary concrete studs and lintels, etc.

2 Celcon block wall 150 mm thk, including bedding, jointing m² 300 106,000 31,800,000
in mortar and necessary concrete studs and lintels, etc.

3 Brick wall 120 mm thk, including bedding, jointing in mortar m² 100 65,500 6,550,000
and necessary concrete studs and lintels, etc.

4 Hollow block wall 100 mm thk, including bedding, jointing in m² 250 60,000 15,000,000
mortar and necessary concrete studs and lintels, etc.
Carried to collection 7,176,774,000

B 7 - 5/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

7.4 FLOOR & WALL FINISHING WORK

1 Concrete trowel finish m² 0 5,000 -

2 Concrete broom finish m² 0 2,500 -

3 Concrete floor hardener m² 0 11,000 -

4 Plastering 20 mm thk, even and troweled enough to receive m² 105,000 32,000 3,360,000,000
painting finish or wall paper finish

5 Painting Work
Supply and installation of painting work
(Contractor to propose the Manufacturer, Type and System)

a Painting to steel doors and frames m² 700 19,000 13,300,000


b Painting to plastering wall, column, etc. m² 21,000 12,500 262,500,000

7.5 MISCELLANEOUS STEEL WORK

1 Supply, fabricate and install stairway railings, including m 680 225,000 153,000,000
all necessary fixtures, accessories and painting, etc.

2 Ditto, but wall railing at stair m 660 75,000 49,500,000

7.6 Insert, embed or cast into concrete, following materials supplied


by Employer's Other Contractors or Employer's Own Forces

1 Anchors for curtain walling system Ls 1 47,771,000 47,771,000


2 Anchors for lift doors, jambs and heads Ls 1 8,659,000 8,659,000
3 Davit socket for gondola system Ls 1 24,638,000 24,638,000
4 Any other matrials to be inserted, embedded or casted into Ls 1 20,310,000 20,310,000
concrete works
5 Make openings for the works to be carried out by Employer's Ls 1 279,795,000 279,795,000
Other Contractors and Employer's Own Forces

Carried to collection 4,219,473,000

B 7 - 5/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

7.7 DOOR WORK

Installation of doors and frames including all necessary accessories,


hardwares, door sill, etc. (Door, door frame and all hardware such
as hinges, locksets, stoppers, door closers, panic bars, etc shall be
supplied by the Employer at no cost to the Contractor)

1 Installation of steel doors (including fire doors) with frame


including hardwares :

- Type single leaf 800 x 2100 mm unt 0 600,000 -


- Type single leaf 900 x 2100 mm unt 0 610,000 -
- Type single leaf 1000 x 2100 mm unt 150 620,000 93,000,000
- Type double leaf 1600 x 2100 mm unt 0 900,000 -
- Type double leaf 2400 x 2400 mm unt 0 1,000,000 -

2 Installation of wooden doors with frame including hardwares :


- Swing type
- Type single leaf 750 x 2100 mm unt 0 110,000 -
- Type single leaf 800 x 2100 mm unt 2,240 115,000 257,600,000
- Type single leaf 1000 x 2100 mm unt 0 120,000 -
- Type double leaf 1600 x 2100 mm unt 200 140,000 28,000,000
- Sliding type
- Type single leaf 900 x 2100 mm unt 50 110,000 5,500,000
- Type double leaf 1800 x 2100 mm unt 380 150,000 57,000,000

Carried to collection 441,100,000

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER
RATE AMOUNT
NO. DESCRIPTION UNIT QT'Y (Rp.) (Rp.)

B 7 - 6/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 7
CIVIL AND FINISHING WORKS APARTMENT TOWER

COLLECTION

Page 7 - 1/7 Rp. 4,514,430,360

Page 7 - 2/7 Rp. 7,776,629,500

Page 7 - 3/7 Rp. 18,133,061,520

Page 7 - 4/7 Rp. 7,176,774,000

Page 7 - 5/7 Rp. 4,219,473,000

Page 7 - 6/7 Rp. 441,100,000

SUB TOTAL BILL NO. 7 - Carried To Summary Rp. 42,261,468,380

597088034.xls 06/19/2022
B 7 - 7/7

597088034.xls 06/19/2022
GRAND INDONESIA PROJECT BILL No. 8
CIVIL AND FINISHING WORKS DAYWORK RATES

Item Description Unit Q'ty Unit Rate Amount

Where works cannot be properly measured and valued, such work shall be paid
as daywork at the rates hereinafter listed.

Daywork rates will not be applicable to the following:


- Jobbing or any other work carried out as a main or separate contracts, or
- Works of which rates and prices are itemized in the Bill of Quantities, or
- Works which are included in the scope of works or deemed to be the
Contractor'sresponsibility.

A. LABOR

The rates for labor are to include the followings:


a. The amount of wages actually paid to the Contractor's employees / workers
when carrying out dayworks.
b. The amount of bonuses, incentive payments and other emoluments actually
paid to the Contractor's employees / workers when carrying out dayworks.
c. The additional amount payable for overtime and etc.
d. Food, lodging and transportation, etc.
e. Supervision cost.
f. Overheads and profit as defined below.

B. PLANT

The rates for plant are to include the followings:


a. Use of mechanically operated plant for the time engaged upon the carrying
out of dayworks.
b. Hire charges where applicable.
c. Fuel, grease, lubricating oil, etc.
d. Maintenance and repair.
e. Consumables.
f. Spare parts.
g. Insurance and road taxes where applicable.
h. Supervision cost.
i. Overheads and profit as defined below.

The rates for plant are to exclude the cost of wages in respect of drivers and
operators, and such cost are to be included in labor rates.

Payment will be made only for such time as the plant is actually engaged upon
daywork operations and shall exclude all standing-by times.

C. MATERIALS

Tenderers shall enter the basic prices of the materials listed. Fluctuation in the
market prices of these materials shall be allowed by the Contractor in the rates.
Overheads and profit shall be included in the rates.

Carried to collection -

B 8 - 1/5

Bill No. 8 Daywork Rates 06/19/2022


GRAND INDONESIA PROJECT BILL No. 8
CIVIL AND FINISHING WORKS DAYWORK RATES

Item Description Unit Q'ty Unit Rate Amount

D. OVERHEADS AND PROFIT

Overheads and profit are to be included in the daywork rates in respect of Labor,
Plant and Materials.

"Overheads" shall include:

a. Head office charges


b. Site supervision and site staffs
c. All government and statutory taxes and levies
d. Overtime other than that allowed for in Bill no.1
e. Time losses due to inclement
f. Traveling time and expenses.
g. Subsistence allowances.
h. Safety, health and welfare facilities and measures
i. Any insurances to be covered by the Contractor.
j. Holiday and sick pay
k. Tools allowances
l. Use, repair and sharpening of small tools
m. Bonus, annual wage supplements and incentive payments for all site and
head-office staffs.
n. All non-mechanically operated plant, erected scaffolding, staging and trestles,
artificial lighting, protective clothing, storage facilities and the like that may
be in general use on the Site of works.
o. All other liabilities and obligations whatsoever.

LABOR

1) Laborer, Common or unskilled Hr 200 7,200 1,440,000

2) Laborer, Skilled Hr 200 9,000 1,800,000

3) Formwork Carpenter Hr 200 9,000 1,800,000

4) Finish Carpenter Hr 200 10,800 2,160,000

5) Mason, Bricklayer Hr 200 10,800 2,160,000

6) Mason, Plasterer Hr 200 10,800 2,160,000

7) Mason, Tile Setter Hr 200 10,800 2,160,000

8) Mason, Stone Setter Hr 200 10,800 2,160,000

9) Concrete Layer / Finisher Hr 200 10,800 2,160,000

10) Concrete Vibrator Operator Hr 200 7,200 1,440,000

11) Steel Bar Bender Hr 200 8,100 1,620,000

12) Steel Worker Hr 200 7,200 1,440,000

Carried to collection 22,500,000

B 8 - 2/5

Bill No. 8 Daywork Rates 06/19/2022


GRAND INDONESIA PROJECT BILL No. 8
CIVIL AND FINISHING WORKS DAYWORK RATES

Item Description Unit Q'ty Unit Rate Amount

13) Welder Hr 200 10,800 2,160,000

14) Painter Hr 200 7,200 1,440,000

15) Driver, for jeep, sedan, etc Hr 200 7,200 1,440,000

16) Driver, Heavy Vehicles Hr 200 9,000 1,800,000

17) Operator, Heavy Equipment Hr 200 10,800 2,160,000

18) Mechanic Hr 200 10,800 2,160,000

19) Electrician Hr 200 10,800 2,160,000

20) Any other tradesman not included above Hr 200 10,800 2,160,000

PLANT

Contractor is to enter the size or capacity of plant that he propose to have or


utilize on Site, where not stated.

1) Crane - Mobile 35 Ton Hr 200 280,188 56,037,600


- Ditto 45 Ton Hr 200 379,260 75,852,000

2) Generating sets, 175 KVA Hr 200 104,184 20,836,800

Ditto, 250 KVA Hr 200 150,912 30,182,400

3) Air compressor including concrete breakers and all other necessary Hr 200 74,592 14,918,400
accessories, 175 CFM

Ditto, but air compressor only, 370 CFM Hr 200 93,384 18,676,800

4) Welding set including all accessories as well as required power Hr 200 29,232 5,846,400

5) Cutting set including all accessories as well as oxygen and acetylene Hr 200 21,600 4,320,000

6) Tower Crane, 60 M, 10 Ton Hr 200 1,008,000 201,600,000

Ditto, 55 M, 10 Ton Hr 200 986,400 197,280,000

7) Material hoist, 1 ton Hr 200 48,672 9,734,400

8) Passenger Hoist, 1 ton Hr 200 396,000 79,200,000

9) Dump Truck, 20 Ton Hr 200 141,552 28,310,400

10) Road Roller, 10 Ton Hr 200 274,032 54,806,400

11) Payloader, 1.7 M3 bucket Hr 200 261,792 52,358,400

12) Excavator, 0.7 M3 bucket Hr 200 268,272 53,654,400

Carried to collection 919,094,400

B 8 - 3/5

Bill No. 8 Daywork Rates 06/19/2022


GRAND INDONESIA PROJECT BILL No. 8
CIVIL AND FINISHING WORKS DAYWORK RATES

Item Description Unit Q'ty Unit Rate Amount

MATERIAL

1) Portland Cement, Type 1 Ton 10 720,000 7,200,000

2) Aggregate for concrete M3 50 150,000 7,500,000

3) Sand for concrete and mortar M3 50 120,000 6,000,000

4) Timber for Formwork M3 50 1,800,000 90,000,000

5) Plywood for Formwork

- 10 mm thick M2 200 50,000 10,000,000


- 13 mm thick M2 200 58,333 11,666,600
- 16 mm thick M2 200 66,667 13,333,400
- 19 mm thick M2 200 75,000 15,000,000
- 22 mm thick M2 200 83,333 16,666,600

7) Timber for carpentry work M3 50 2,400,000 120,000,000

8) Sand for Sandtill work M3 50 108,000 5,400,000

9) Emulsion paint Ltr 1,000 6,000 6,000,000

In the event there are any items of the works, labors, plants and/or materials
described in the Bill Of Quantities and/or daywork rates, the Contractor
not shall quote hereinafter in percentage of his supervision cost, overheads
and profit, and all othercost to cover his works to the actual work cost,
labor cost, plant cost, and materialcost.

1) Work cost Add ……%

2) Labor cost Add ……%

3) Plant cost Add ……%

4) Material cost Add ……%

Carried to collection 308,766,600

B 8 - 4/5

Bill No. 8 Daywork Rates 06/19/2022


GRAND INDONESIA PROJECT BILL No. 8
CIVIL AND FINISHING WORKS DAYWORK RATES

COLLECTION

Page 8 - 1/5 Rp. -

Page 8 - 2/5 Rp. 22,500,000

Page 8 - 3/5 Rp. 919,094,400

Page 8 - 4/5 Rp. 308,766,600

SUB TOTAL BILL NO. 8 - Carried To Summary Rp. 1,250,361,000

B 8 - 5/5

597088034.xls 06/19/2022

You might also like