Reporting requirements for Company Man working onsite.

According to DLD wellsite supervisor management, all wellsite


supervisors should keep close monitoring on drilling operations and
report any abnormal situation to project manager at the first time,
including safety issue and downhole problems.

A----Daily Report:
1、 QQ Report:
 Time: 6:00-6:30 of every day
Operation Summary in Operation Management Group.
The brief operation 0:00~24:00 + brief operation 00:00~06:00 + next plan.
Notice: Filling the ahead/behind of design days. Mud density and viscosity.
 Time: 6:00-6:30 of every day
Diesel Report in Operation Notice Group.
Daily diesel report, including received, daily consumption, Available (pumpable),
Dead Volume.
 The quantity of diesel received should be sent each time in Operation Notice Group.
 Time: 11:20-11:30 and 16:20-16:30 every day.
Operation Summary from 6:00 till report time in Operation Management Group.
Operation Summary from 11:30 till report time in Operation Management Group.
2、 DDR Reports by email:
 Time: 6:00-7:15 of every day .(The main important report: DDR)
 This Report attachments:
1) 24Hrs Operation: PDF file of Well View.
2) 6Hrs Operation: PDF file of Well View.
3) Well time Distribution: Excel Sheet: Update S1, S2, S3 every day, don’t do
anything on sheet# 4& 5 (Those sheets are formulated) .
4) Rig DDR report.
5) Mud Engineer DMR.
6) Directional Driller Report (Slide & Rotary report+ survey data sheet) if any.
7) Updated Well View Export file
3、 Daily Evening Report (EDR Excel Sheet) by email. Time 18:00-18:20 every
day.
4、 Monthly Reports by email.
 Monthly CNOOC Material Report : End of each month submit (Send to both
operation and design section).
 Monthly Diesel Report: End of each month submit (Send to operation section).
Notice: The Monthly material and diesel Report should be signed and scanned.
5、 Section Report by email.
 After each section finished, section technical report should be prepared and
normally first sent to Project Manager and after checking with him, then submit the
PDF file to all related person.
6、 Diesel and Company material received report by email.
 After receiving diesel or company material and signature by Rig manager and
Company man (Signature should be full English name), the scanned files should be
sent to all related person in time.
 Check the diesel amount of consumed, received and remained. Make sure the
number you fill in DDR is same with actual one.
7、 Demanding Request Report by email.
 Should be sent in the proper time after signature and scanned.

B----Requirement for casing tally and casing accessories:


1、Inspect the casing and liners accessories once they are sent to the well site to see if
they meet the requirement of the program.
2、Photos of casing accessories and liner hanger should be taken by yourself to show
the specifications.
3、Certificates of all casing accessories and liner hangers should be supplied by the
manufacturer.
5、Please check the casing tally carefully to make sure it meets the design, including
the steel type for all the casing and accessories, pup joint, crossover, and also the
length should meet the planed requirement, isotope, short liner depth…etc.). Report at
the first time if you are not sure or not same as the design.
6、The draft casing & liner tally should be sent to all related person before running with
cementing program & cement slurry lab test report.
7、The final casing & liner tally should be sent to all related person after running
finished and checking with the draft tally(mention the casing damaged and not used).
The cementing operation report is also sent.
The casing tally, photos and certificates of the casing accessories and liner hangers
send to the following address:
Send to: Wang Xiaoyong(王小勇) <wangxiaoyong@cnoociraq.com>;Lin Feng(林枫)
<linfeng@cnoociraq.com>; 'Alla Makki Ibraheem' <AllaMakkiIbraheem@cmitfod.com>;
Liu Haihan(刘海涵) <liuhh@cnoociraq.com>; Yang Jianzheng(杨建政)
<yangjzh@cnoociraq.com>; Yu Dawei(于大维) <yudw@cnoociraq.com>; Li Xin(李鑫)
<lixin4@cnoociraq.com>; Zhang Fan(张帆) <zhangfan2@cnoociraq.com>; 'Murtadha
Abdul Zahara Issa' MurtadhaAbdulZahara@cmitfod.com; Riyadh Bidda Shanoon
<RiyadhBiddaShanoon@cmitfod.com>; Drilling Assistant
<Drillingassistant@cnoociraq.com>
CC to: 'Ahmed Abdul Hameed' <AhmedAbdulhameed@cmitfod.com>; Wang
Shengxiang(王胜翔) <wangshx@cnoociraq.com>; 'Ahmed Ismail Kareem'
<AhmedIsmailKareem@cmitfod.com>; Wan ShengLiang(万圣良)
<wanshl@cnoociraq.com>; 'yasirjabbar' <yasirjabbar@cmitfod.com>; Zhu GuoNing(朱
国宁) <zhugn@cnoociraq.com>; wangjia2@cnoociraq.com;Drilling material
<Drillingmaterial@cnoociraq.com>; 'Almahdi@cmitfod.com';
'HaiderNoori@cmitfod.com'; Shouqahmed@cmitfod.com;

C----Some detail requirement for DDR report:


Before filling CODE for DDR, please check the wellview rules carefully:
 Please Set email headers to a consistent format as “well name +DDR+#number
+Date”, Such as “FQCN-59D DDR#35 20211216”.
 Fill the wellhead specifications (manufacturer and S/N) in remarks each time you
N/U the wellhead. Fill the specifications (Grade and Weight) of casing accessory
and liner hanger in remarks when the operation is running casing or liner.
 The wiper trip before running casing is to prepare for cement job so the CODE
should be D-P-C-01. The casing pressure test is done for cement quality check so
the CODE should be D-P-C-08.
 For directional and vertical hole, the time of finishing drilling operation is right after
P/T liner if completion operation is performed by same drilling rig. Otherwise the
time is after N/U blind flange.
D----Final well report:
 When close to finish drilling operation, Collect and review the 18 items for DOD
design section. Prepare the hand over file between DLD and DOD if completion
operation performed by drilling rig.
 Keep update bit record, drilling duration statistics and URS report timely and send
them to OPMA right after the well finished.
 Check the wellview carefully and export the CNOOC Final Drilling Report. Sign your
name in tittle page and send to DrillingAssistant.
 After the well completed prepare the well technical summary and Acceptance
Criteria for well & Drilling Contractor Performance reports. Collect well data for
drilling supervisor working file.

E----Other reporting requirements:


 Sign with full English name in any paper on well site and also require the rig
managers to do so.
 The wireline logging data should be sent to all related person after completion of
logging operation.
 Fill the cement evaluation in cement\cement evaluation results in wellview.
 Fill all NPT in interval problems.
 Check and confirm with the levelness, orientation and P/T of casing & tubing head
each time and fill the result in DDR.

2022.6.7