You are on page 1of 26

S.

N
SECTION A: TOILET/ BATHROOM SUNKAN WATERPROOFING WORK .
1.00

2.00
3.00

SECTION B: BALCONY/ LIFT ROOM WATERPROOFING


3.00

4.00
5.00

SECTION C: CHAJJA WATERPROOFING


6.00

7.00

SECTION D:TERRACE WATERPROOFING


8.00
9.00

10.00

11.00

12.00
SECTION E : WATER TANK WATERPROOFING
13.00

14.00

15.00

SECTION F: BOX TYPE WATERPROOFING OUTSIDE OF UG TANK AND LIFT


PIT
16.00
17.00
Sub:- Quotation for Waterproofing work
Sir
This has Reference to the between discussion with undersigned subject matter we wish to quote for
follows.

DESCRIPTION

SECTION A: TOILET/ BATHROOM SUNKAN WATERPROOFING WORK .


Toilet Sunkan Area Waterproofing
Proper cleaning & scrapping of all loose material / excess concrete & making surface
ready for waterproofing treatment with necessary ponding. Also injection grouting to be
done at joints wherever necessary as per EIC. 3. After laying of plumbing line,
Providing & applying Epoxy coat and sprinkle the sand over coating at PVC pipe and
filling with micro concrete adjoining the pipe and slab, providing applying 2 coats of
protective coating of Dr. Fixit, around the sleeve and on the wall side etc. all complete.
All around the wall and floor joint Haunch to be made of approved polymer modified
mortar with Dr. Fixit.URP 4. Applying of Cement based brush applied liquid membrane
polymer base Cementious layer- Dr.Fixit WP of M/s. Dr. Fixit,Providing and applying
20mm to 25mm thick protective screed on sunkan portion and wall surface up to 1 mtr
height with proper line level, finishing , Portland Cement: 50 kg, Washed sand: 150 kg,
Dr. Fixit Pidicrete WP: 5 kg & Water: 15-20 Lit curring etc complete.

Toilet Bathroom Wall Area


Toilet Walls - W/p + Plaster 1. Applying of Cement based liquid membrane polymer
base Cementious layer-Dr. Fixit WP,mixed with grey cement in ratio of 1:1 on the slab
in three coats on the slab & up to the vertical height of 1 meter above finished floor
level. This application should be monolithic / seamless. The liquid membrane should
have good adhesive quality with all materials. It can be applied in moist conditions. It
should also have good quality puncture resistance. 1.Waterproofing plaster in cement
mortar 1:4 of 12 to 15mm thk mixed with anti shrinkage compound- Dr.Fixit, to be done
on walls using waterproofing compound up to the height of 1 meter above finished floor
level while the second coat of WP is wet in condition in above application. 2.The works
includes All Labour and Material under contractor's scope, such as Bricks, Sand,
Cement, Chemical, etc.
Brit Bat Cobba in Sunken Toilet Waterproofing :- Searching for cracks and opening the
cracks in (1/2"X1/2") "V" groove manner & filling the same with (1:4) sand cement
motor mixed with Dr.Fixt URP surfacing system for protecting concrete & masonry.
Step 3 :- Opening the construction joint in (1/2"xix1/2") "V" groove manner and fixing
nozzles at a spacing of 1.5m c/c and patching with (1:3) sand cement mortar mixed
with Dr.Fixit LW+Surfacing System for protection concrete and masonry, applying two
coat waterproofing chemicals with protection coat. Plaster Work :- laying 20mm thick
(1:4) protective plaster mixed with Gujarat Sand, Cement SWC 'Dr.Fixit LW+ Integral
waterproofing compound, @200 gms/50kg of cement.Brick Bat Coba :- Providing &
laying of brick bat coba upto average thik 200mm with brick, sand, cement including
mortar mix Integral Waterproofing Compound@200 gms/50kg of cement.Patch Work :-
Searching cracks & honeycombs, if any, shall be repaired withDr.fixit URP coat apply
URP+CEMENT (1:1) by volume.Injection Grounting :- Cement pressure grounting
through Nozzles with cementitious milk mixed with Dr.Fixit Non-Shrink polymeric
waterproofing, grounting compound @250 gm/50kg bag cement, Sealing of the nozzle
after injection grounting operation is over with SWC 'STRUCO NO.3'-'Quick Setting
Admixture

TOTAL OF SECTION A

SECTION B: BALCONY/ LIFT ROOM WATERPROOFING


Surface Preparation
Removing ,cleaning of ,unwanted materials, loose particales at slab top slab ,
removing all dust with air blower, filling crack with Dr.Fixit Crack X Cill . Making half
coving vata at junctin at the wall and slab.lowering the debrise etc.all
complete.Providing and applying 2 coats of waterproof chemical coating with Dr.Fixit
Pidicrete WP chemical, (waterproofing coating Mix Dr. Fixit Pidicrete WP: Cement in
the ratio 1:1 by volume).Providing and applying 2 coats of waterproof chemical coating
with Dr.Fixit Pidicrete WP chemical, (waterproofing coating Mix Dr. Fixit Pidicrete WP:
Cement in the ratio 1:1 by volume) Providing and applying 20mm to 25mm thick
protective screed on sunkan portion and wall surface up to 1 mtr height with proper line
level, finishing , Portland Cement: 50 kg, Washed sand: 150 kg, Dr. Fixit Pidicrete WP:
5 kg & Water: 15-20 Lit curring etc complete.

P/L filling Brick bat coba & IPS finish


providing and laying brick bat coba of average 300 mm thick laid over cement sand
mortar 1:4 12 mm thick with addition of waterproofing compound as per manufacturer’s
specifications up to 225 mm on walls & finishing the top with 20 mm thick cement sand
mortar 1:4 laid in proper slope, finishing it with broom including vattas at the junction,
carting away the debris, necessary labour, tools, tackles, materials, scaffolding, curing
with hessian cloth, etc. complete as per the specifications & as directed by the
engineer etc. curring shall be done for 7 days by ponding with water
Injection Grouting to R.C.C. elements
Providing, Drilling & Inserting 12 mm diameter of PVC injection grouting [perforated]
nipples upto 50-100 mm depth in concrete & securing it properly as directed. Injecting
grout slurry of cement and water with addition of non-shrink grout additive as per
manufacturer's specification into the nipples by suitable gun / pump at 2 Kg./Sq.cm.
pressure, wherever directed, cutting the projected socket portion & sealing the same
including necessary labour, tools, tackles, materials, scaffolding, etc. complete as per
the specification & as directed by C.E

TOTAL OF SECTION B

SECTION C: CHAJJA WATERPROOFING


Surface Preparation

Removing ,cleaning of ,unwanted materials, loose particales at slab top slab ,


removing all dust with air blower, filling crack with Dr.Fixit Crack X Cill . Making half
coving vata at junctin at the wall and slab.lowering the debrise etc.all
complete.Providing and applying 2 coats of waterproof chemical coating with Dr.Fixit
Pidicrete WP chemical, (waterproofing coating Mix Dr. Fixit Pidicrete WP: Cement in
the ratio 1:1 by volume).Providing and applying 2 coats of waterproof chemical coating
with Dr.Fixit Pidicrete WP chemical, (waterproofing coating Mix Dr. Fixit Pidicrete WP:
Cement in the ratio 1:1 by volume) Providing and applying 20mm to 25mm thick
protective screed on sunkan portion and wall surface up to 1 mtr height with proper line
level, finishing , Portland Cement: 50 kg, Washed sand: 150 kg, Dr. Fixit Pidicrete WP:
5 kg & Water: 15-20 Lit curring etc complete.

P/L filling Brick bat coba & IPS finish

providing and laying brick bat coba of average 50 mm thick laid over cement sand
mortar 1:4 12 mm thick with addition of waterproofing compound as per manufacturer’s
specifications up to 225 mm on parapet walls & finishing the top with 20 mm thick
cement sand mortar 1:4 laid in proper slope, finishing it with broom including vattas at
the junction, carting away the debris, necessary labour, tools, tackles, materials,
scaffolding, curing with hessian cloth, etc. complete as per the specifications & as
directed by the engineer etc. curring shall be done for 7 days by ponding with water

TOTAL OF SECTION C

SECTION D:TERRACE WATERPROOFING


Surface Preparation
Removing ,cleaning of ,unwanted materials, loose particales at slab top slab ,
removing all dust with air blower, filling crack with Dr.Fixit Crack X Cill . Making half
coving vata at junctin at the wall and slab.lowering the debrise etc.all
complete.Providing and applying 2 coats of waterproof chemical coating with Dr.Fixit
Pidicrete WP chemical, (waterproofing coating Mix Dr. Fixit Pidicrete WP: Cement in
the ratio 1:1 by volume).Providing and applying 20mm to 25mm thick protective screed
on sunkan portion and wall surface up to 1 mtr height with proper line level, finishing ,
Portland Cement: 50 kg, Washed sand: 150 kg, Dr. Fixit Pidicrete WP: 5 kg & Water:
15-20 Lit curring etc complete

P/L filling Brick bat coba & IPS finish


providing and laying brick bat coba of average 110 mm thick laid over cement sand
mortar 1:4 12 mm thick with addition of waterproofing compound as per manufacturer’s
specifications up to 225 mm on parapet walls & finishing the top with 20 mm thick
cement sand mortar 1:4 laid in proper slope, finishing it with broom including vattas at
the junction, carting away the debris, necessary labour, tools, tackles, materials,
scaffolding, curing with hessian cloth, etc. complete as per the specifications & as
directed by the engineer etc. curring shall be done for 7 days by ponding with water.

P/L HEAT-RESISTANT TILES / CHINA MOSAIC TILES ON A BEDDING MORTAR :

HEAT-RESISTANT TILES / CHINA MOSAIC TILES ON A BEDDING MORTAR : The


fifth part consisting of providing and laying avg. heat-resistant tiles / china mosaic tiles
over 25 mm thick bedding mortar admixed with Dr.Fixit LW+ Integral Waterproofing
Compound @ 100 ml / bag of cement.

P/L Waterproof cement sand plaster on parapet wall


Providing & applying of sand faced waterproof sponge finished plaster of average 25
mm thick on all surfaces in two coats at parapet wall in cement mortar 1:4 with
approved waterproofing compound as per manufacturer’s specification including raking
of joints, cleaning the surface with water jet, applying cement slurry on concrete
surfaces keeping the surface of the base coat rough so as to receive sand faced
plaster treatment, finishing of final coat by taking out grains, including necessary
labour, tools, tackles, materials, curing, etc. complete as per the specifications.

Injection Grouting to R.C.C. elements


Providing, Drilling & Inserting 12 mm diameter of PVC injection grouting [perforated]
nipples upto 50-100 mm depth in concrete & securing it properly as directed. Injecting
grout slurry of cement and water with addition of non-shrink grout additive as per
manufacturer's specification into the nipples by suitable gun / pump at 2 Kg./Sq.cm.
pressure, wherever directed, cutting the projected socket portion & sealing the same
including necessary labour, tools, tackles, materials, scaffolding, etc. complete as per
the specification & as directed by C.E

TOTAL OF SECTION D
SECTION E : WATER TANK WATERPROOFING
Over Head Water tank waterproofing Side Wall
Removing the loose mortar, particals of bainding wire, shuttering, from inside bottom
and side walls without damaging the concrete surface up to the original slab / side
walls cleaning the slab surface filling the holes, hony comb with polymer mortar,
applying neat cement slurry with approved waterproofing compound , exposed R.C.C.
surface with necessary labour, tools, tackles, materials, scaffolding, Providing Applying
Two Coats of W.P. chemical coating with (Dr.Fixit Pidifine 2K ) food grade waterproof
chemical coating to the inside wall of the water tank, Providing & applying of
waterproof smooth finish plaster in cement mortar 1:3 20 mm thick with neat cement
float punning including adding waterproofing compound as per the manufacturer’s
specifications, curing,

Bottom
Removing the loose mortar, particals of bainding wire, shuttering, from inside bottom
and side walls without damaging the concrete surface up to the original slab / side
walls cleaning the slab surface filling the holes, hony comb with polymer mortar,
applying neat cement slurry with approved waterproofing compound , exposed R.C.C.
surface with necessary labour, tools, tackles, materials, scaffolding, Providing Applying
Two Coats of W.P. chemical coating with (Dr.Fixit PidiFine 2k )Food grade waterproof
coating to the inside wall of the water tank, Providing & laying of 25mm thick metal
coba [1:2:4] with neat cement float I.P.S. finish on top including adding waterproofing
compound as per manufacturer’s specifications, curing, etc. complete as per the
specifications & as directed by C.E.

Injection Grouting to R.C.C. elements


Providing, Drilling & Inserting 12 mm diameter of PVC injection grouting [perforated]
nipples upto 50-100 mm depth in concrete & securing it properly as directed. Injecting
grout slurry of cement and water with addition of non-shrink grout additive as per
manufacturer's specification into the nipples by suitable gun / pump at 2 Kg./Sq.cm.
pressure, wherever directed, cutting the projected socket portion & sealing the same
including necessary labour, tools, tackles, materials, scaffolding, etc. complete as per
the specification & as directed by C.E

TOTAL OF SECTION E

SECTION F: BOX TYPE WATERPROOFING OUTSIDE OF UG TANK AND LIFT


PIT Box Type Waterproofing
1) Cleaning Entire the basement with brush, broom to make it clear from all loose
particles dust laitance etc. 2)Add one beg of cement to hundred liters of water .Stir
the mixture to get consistent cement slurry .Spread this slurry on floor slab and allow it
to penetrate uniformly over the cleaned surface.
3)Matel coba 25mm provide a cement mix 1:4 base coat . Using
chemical (Dr.Fixit ) 200 grams /50kg of cement. 4 )Fixing of Shahabad tiles in break
joint method on slab as well as vertical. Filling vertical joint by grouting using chemical
admix with Dr.Fixit -Non-shrink polymeric waterproof grouting compound,@250gm /
50 Kg bag of cement 5) Shahabad on slab pointing to be done-joint to be smooth
finish. 6) Seal the joints between the Shahabad tile with the help of C.M. 1:3 , add
some 15mm metal to this mortar for enhance strength and less shrinkage. 7) After
fixing Shahabad 1 coat to all surface with mixture sand and cement in ratio 4:1 with
smooth finish.Using chemical (Dr.Fixit LW) 200 grams /50 kg of cement.8) Curing .

PCC/Raft
Providing & laying 100 mm thick Plain cement concrete. With proper line level and
finishing with adding Dr.Fixit LW+ in mortar .
TOTAL OF SECTION F
atter we wish to quote for our lowest competitive rate as

QTY. UNIT RATE AMOUNT


Palava Phase 1 Commercial STP

STP WP BOQ

ITEM DESCRIPTION

Vendor shall submit waterproofing detail and method statement (vendor MS) for execution of below work items alongwith the pr
BOQ specifications and details attached in A3 sheet should be checked and verified by vendor then method statement needs to
being issued with this BOQ need to be comunicated and typical details that are agreed with vendor will be part of the final work
Before starting any waterproofing work item vendor shall satisfy himself with quantities, line items, as agreed in the contract and
work item.

Crystalline Waterproofing treatment for Wal


Admixture should be added to the concrete in the form of thin slurry by mixing, Admix (1 Kg) with approx. 1.25 litr
water (dosage rate of 1.00% by weight of the cementitious contents of the concrete subject to max. 3.00Kg per Cu
1 per manufacturer's recommendation),Slurry formed to be added to the concrete directly into the RMC transit mixer
site prior to pumping of the concrete.
After adding the Admix slurry into the concrete, the transit mixer to be rotated at a full speed for around 5 minutes
3 ensure the uniform mixing of the CP Admix into the concrete
Thereafter, the concrete should be placed by the Civil Contractor, with necessary compaction, curing etc. complete
4 per good practices
Waterproofing agency should supervise the entire procedure during the concreting process to ensure that the
5 recommended dosage CP Admix is added into batches of concrete.

1.1.1 Raft
1.1.2 Wall
STP - Internal Side
Surface Preparation
1 Loose material, laitance shall be removed and the surface shall be throughly cleaned and free from fine dust partic
2 Tank to be ponded for 4 days with full height water, to identify and mark dampness/shrinkage cracks/any leakages
3 Surface to be treated as per Vendor MS, which may include the procedure for grouting,application of sealant, crack
4 treatment
Angle filletetc.
of 25mm with polymer modified mortar to be applied at all corners.
5 Cut outs/Tie rod holes in slab, walls to be treated at all heights and levels
Waterproofing Treatement
1 Surface to be prepared for primer application, and primer to be applied.
2 Flexible polymer modified cementitious coats in layers as per Vendor MS to be applied.
3 Waterproofing layer needs to be in such a way that it should provide key/adhesion/bonding for the protective scree
4 Protection for Horizontal Surface - Metal screed M20 (average thickness 50mm) mixed with Integral Waterproofing
5 Compound 200ml
Protection Layer forOR 250gm
Vertical per Bag
Surface to be laid in the
- Waterproofing required
plaster slope on
in cement waterproofing
mortar 1:4 of 12 -layer
15mm thick to be done on
using waterproofing compound 200ml OR 250gm per Bag
Lodha Supplied Material : cement, sand, Light weight broken blocks
Materials - As per mentioned (or equivalent) standard.
Sr No Properties
1 % Elongation
2 Tensile Strength N/mm2
3 Crack Bridging mm
4 Adhesion N/mm2
Mode Of Measurement: Plan area and Vertical wall area of application (as per general drawings) to be paid.
2.1.1 STP Internal walls - WP layer + Protection plaster
2.1.2 STP Raft top - WP layer + Protection screed
Epoxy Coating treatment
Providing and carry out chemical resistant epoxy lining work to sound concrete surface after carry out proper surfac
remove any dust, dirt,loose mortar, paint, algae, fungus or any other foreign material and application of 2 coats of
Nitocote EN 901 -High Chemical resistant protective lining work using suitable brush or roller coverage @ 0.5 ltr/m2
500 microns DFT. Nitocote EN 901 shall be having Solid Content: 100 %,Pot life : 20 min at 35 °C,Tack free time :
hrs at 35 °C, Over coating time : < 10 hrs at 35 °C,Full cure : 5 Days at 35 °C, Tensile Strength : 30 Mpa,Elongatio
Approx. 3 %, Flexural Strength : 45 Mpa, Compressive Strength : 95 Mpa, Shore D Hardness : 85+5,Abrasion
Resistance : 0.1 mg/cycle ( 1 kg,H-22 wheels), Service Temperature : < 60 °C ,Wet film thickness : 200-250
microns/coat, Dry film thickness : 200- 250 microns/coat

STP Top Slab


Surface Preparation
Surface to be grinded to achieve required smoothness. Loose material, laitance, dust particles shall be removed an
1 cleaned thoroughly.
Surface to be ponded for 3 days with minimum 50mm water depth, to identify and mark leakages/dampness/ shrink
2 cracks/any leakages in the concrete substrate.
3 Substrate shall be treated as per vendor MS to rectify the identified water leakages/dampness.
Angle fillet (corner rounding) of 50 mm x 50 mm shall be done using polymer modified mortar at all horizontal and
4 vertical junctions along with screed mixed with waterproofing compound.
Cut outs/sleeves around the plumbing fixtures in slab/beams/walls that are located within the waterproofing area sh
5 sealed as per vendor MS.
Ponding test shall be carried out at a depth of 50 mm for 3 Days to determine the water tightness after closing all th
outlets.Further work of waterproofing to be commenced only after approval of no leakage & dampness from site
incharge.
6
Waterproofing Treatement -
1 Surface to be prepared for primer application as per vendor MS and primer to be applied.
Water proofing shall be single component pure polyurethene based elasomeric seamless liquid spray applied
membrane.Waterproofing coats in predetermined number of layers as per vendor MS to match the dry film
thickness(DFT) - minimum 1.5mm on horizontal surface, 1.2mm on vertical surface. Vendor shall submit the
consumption in litres/sq.m and required number of coats to achieve the specified minimum thickness. This consum
need to be verified at site by conducting mock up prior to the commencement of work
2
3 PU Membrane should be terminated into a groove 5mm height and 8 mm depth on vertical wall at 450mm height fr
Terrace slabpolyester
Non woven top level,GeoTextile
after membrane
fabric termination
200 GSM befillplaced
the groove with a polyurethene
with overlap sealant
at joints as per Vendor MS (Minimum 75m
a separation layer between waterproofing and screed. Apply protective screed within 3 days of application of
waterproofing layer, to protect PU material from damage due to UV rays.
4
5 Protection for Horizontal Surface: Cement mortar screed 1:4 (average thickness 30mm) shall have
6 compound
Ponding testquantity
shall beas per vendor
carried out at MS (minimum
a depth 200ml
of 50 mm for or 250g to
3 days per cement bag)
determine the water tightness. Further work sha
7 commnenced only after approval from site engineer incharge.
On vertical surface of WP layer apply Epoxy bond coat with quartz sand spray followed by waterproofing plaster.
Waterproofing plaster on vertical surfaces upto Groove level- 15 to 20mm thick cement mortar 1:4 mixed with the
waterproofing compound quantity as per vendor MS (minimum 200ml or 250g per cement bag).
8
150mm wide band in cement plaster on parapet above Groove edge throughout groove length - 15 to 20mm thick
cement mortar 1:4 mixed with the waterproofing compound quantity as per vendor MS (minimum 200ml or 250g pe
cement bag), edge of groove and bedding mortar to be covered with beak shaped drip mould in plaster.
9
Filling with broken light weight blocks and cement mortar (1:6) with slope in average thickness of 150mm. The fillin
shall be cured for 24 hours and final finish coat 25mm thickness shall be in cement mortar 1:4. Cement mortars (1:
10 1:4) shall have waterproofing compound quantity as per vendor MS (minimum 200ml OR 250gm per cement bag)
11 Area to be cured for 7days with water.
Lodha Supplied Material : cement, sand, Light weight broken blocks
Materials - As per mentioned (or equivalent) standard.
Sr No Properties
1 % Elongation
2 Tensile Strength N/mm2
3 Crack Bridging mm
4 Adhesion N/mm2
Mode Of Measurement - Plan area and Vertical wall area of application (as per general drawings) to be paid.
3.1.1 Horizontal - Application area (WP layer+Geotextile+Protective Screed+Av 150mm Thick LW filling)
3.1.2 Vertical - Application Area upto External wall top and upto Groove level for Mumty Room (WP Layer+Epoxy
coat+Protective Plaster)
3.1.3 150mm wide band above Groove (Only WP Plaster in 15 to 20mm Thickness) 
3.1.4 5x8mm Groove making and treatment as mentioned in specifications
3.1.5 Providing and fixing China Chips

Treatment of Construction Joints


Providing and fixing, hydrophilic swellable Water bar fixed at construction joints in raft slab and
retaining wall etc.
Construction joints shall be sealed with Hydro swelling water stop of size 20x10mm shall be laid along the construc
joint between the two pours.The water bar shall be low pre-mature swelling and shall not be based on super absorb
The water bar shall have low swelling pressure, not exceeding 0.25MPa at full swelling capacity.

Size
Unrestrained Volumetric Expansion
Hydrostatic pressure resistance
Minimum Cover
Treatment of Construction Joints
Making Groove & Sealing with Non Shrink Grout for C
Identify the construction joints in the member andaserten its cause - shrinkage or structural. Provide a V-groove alo
the construction joints using the grinder (20 mm wide and 12 mm depth). The V-groove will be cleaned properly usi
water. Providing Non shrink Cementitious grout for sealing of construction joints.Making Groove & Sealing with No
Shrink Grout

Grouting (If required)


Identify the member and aserten its cause - shrinkage or structural. . Drilling of hole 14mm dia at 200-300 mm cent
center at a 45 degree. Clean the holes with air blower. Fixing of PVC Injection packer of 14mm x 75mm-85mm long
screwed till the rubber swells & it is totally intact in the hole.Providing & Applying quick setting shrink proof multi-pu
concrete repair mortar in wrong drilled holes, area around Packer & also plug the hole grout hole bore after injectio
Providing & injecting Non shrink Cementitious grout for sealing of construction joints. After injecting first round we m
have to again inject the material Through new packers if the dampness continues till the concrete pores are filled w
Grout material.

5.1.1 Grouting of holes provided for Construction Joints


Sleeve closure
Treat the PVC pipe with Epoxy coating by mixing resin and hardener in the ratio of 65:35 and sprinkle sand on it to
receive bond with micro concrete.
Clean the annular space of bore packing and fix the PVC pipe sleeve in position as per drawing by MEP vendor.Se
gap between PVC sleeve and the bore packing from the underside with flexible backer rod/shuttering/gypsum.Fillin
gap around pipe periphery and core cut by high strenght micro concrete non shrink by mixing 14 to 15% by weight,
per manufacturer’s recommendation.Allow micro concrete to set for 24 hours and cure for 2-3 days.Pond the surfac
around the pipe sleeve for minimum 24 hours.Roughen the balance PVC sleeve above the slab or apply twin sided
adhesive tape on the PVC pipe. For areas excluding bathroom with walls, Provide a primer coat of PU PRIMER aro
the pipe sleeve. Extend the PU primer 300mm X300mm square on the slab by soft paint brush.After drying of the p
(say 30 mins) provide the first coat of flexible polyurethane membrane coating over the primer applied surface
encompassing the entire PVC pipe sleeve and extend 300mmx300mm squre on the slab.After the first coat has dr
(say after 24-48 hours), apply second coat of PU over the same area by using 0.5kg material per sqm. While the se
coat has set but is still in plastic condition, sprinkle sand over the surface to provide rough surface and allow to
set.Provide the CM protective mortar as per specifications and finish as per requirement with tiles/ IPS etc.Ponding
slab for 48 hours to check no leakage (Hold point for mandatory inspection from QC team)If leakage found then gro
of identified leakage area and ensure no leakage.After only confirmation of no leakage inspection, permitted for
waterproof coating system.

300 mm Dia
250 mm Dia
100 mm Dia
80 mm Dia
50 mm Dia
TOTAL BASIC AMOUNT OF RS
UNIT Quantity Rate Amount Remarks

tion of below work items alongwith the proposed materials for the approval of client.
y vendor then method statement needs to be submitted.Any changes proposed by Waterproofing vendor to the typical details
with vendor will be part of the final work order issued to the vendor.
line items, as agreed in the contract and if there is any variation he need to raise RFI for approval prior to initiation of each

e Waterproofing treatment for Walls & Raft


mixing, Admix (1 Kg) with approx. 1.25 litre of
e concrete subject to max. 3.00Kg per Cum as
ncrete directly into the RMC transit mixer at

ted at a full speed for around 5 minutes to

essary compaction, curing etc. complete as

ncreting process to ensure that the

Cum Suncrystalmix
Cum Suncrystalmix
STP - Internal Side
-
hly cleaned and free from fine dust particles. -
ampness/shrinkage cracks/any leakages. -
for grouting,application of sealant, crack -
ers. -
-
-
-
o be applied. -
dhesion/bonding for the protective screed. -
0mm) mixed with Integral Waterproofing -
waterproofing
rtar 1:4 of 12 -layer
15mm thick to be done on walls -
-
-
Test Method Value -
ASTM D 412 100 -
ASTM D 412 2 -
ASTM C 836 1.5 -
ASTM D 4541 1 -
per general drawings) to be paid. -
Sq.m Polyalk Wp
Sq.m Polyalk Wp
Epoxy Coating treatment
crete surface after carry out proper surface to
n material and application of 2 coats of
able brush or roller coverage @ 0.5 ltr/m2 @
Pot life : 20 min at 35 °C,Tack free time : 4-6
°C, Tensile Strength : 30 Mpa,Elongation :
Shore D Hardness : 85+5,Abrasion
0 °C ,Wet film thickness : 200-250

Sq.m
STP Top Slab
-
tance, dust particles shall be removed and
-
tify and mark leakages/dampness/ shrinkage/
-
eakages/dampness. -
er modified mortar at all horizontal and
-
located within the waterproofing area shall be
-
ine the water tightness after closing all the
l of no leakage & dampness from site
-
-
r to be applied. -
meric seamless liquid spray applied
vendor MS to match the dry film
l surface. Vendor shall submit the
ecified minimum thickness. This consumption
ent of work
-
depth on vertical wall at 450mm height from -
tlyurethene sealant
joints as per Vendor MS (Minimum 75mm) as
eed within 3 days of application of
-
ickness 30mm) shall have waterproofing -
nt
nebag)
the water tightness. Further work shall be -
pray followed by waterproofing plaster. -
thick cement mortar 1:4 mixed with the
50g per cement bag).
-
ghout groove length - 15 to 20mm thick
vendor MS (minimum 200ml or 250g per
shaped drip mould in plaster.
-
n average thickness of 150mm. The filling
cement mortar 1:4. Cement mortars (1:6 and
mum 200ml OR 250gm per cement bag) -
-
-
-
Test Method Value -
ASTM D 412 / DIN 52455 400 -
ASTM D 412 / DIN 52455 2 -
ASTM C1305 / C1305M 2 -
ASTM D 903 2 -
as per general drawings) to be paid. -
Top of STP Roof
+Av 150mm Thick LW filling)
Sq.m slab
including peripehry
vel for Mumty Room (WP Layer+Epoxy bond Sq.m wall, Mumty room
wall
ckness)  Mtr
Mtr
Above Mumty
Sqm Room
Treatment of Construction Joints
onstruction joints in raft slab and
-
0x10mm shall be laid along the construction
g and shall not be based on super absorbents.
t full swelling capacity.
-
-
-
-
-
RMT Only Horizontal CJ
Considered,Assumi
ealing with Non Shrink Grout for Construction Joint ng wall joint at
age or structural. Provide a V-groove along starter, mid height
he V-groove will be cleaned properly using and Slab Level
joints.Making Groove & Sealing with Non

RMT
Grouting (If required)
ng of hole 14mm dia at 200-300 mm center-to-
tion packer of 14mm x 75mm-85mm long
plying quick setting shrink proof multi-purpose
ug the hole grout hole bore after injection.
tion joints. After injecting first round we may
ntinues till the concrete pores are filled with

Nos
Sleeve closure
e ratio of 65:35 and sprinkle sand on it to -
osition as per drawing by MEP vendor.Seal the
xible backer rod/shuttering/gypsum.Filling the
on shrink by mixing 14 to 15% by weight,all as
urs and cure for 2-3 days.Pond the surface
sleeve above the slab or apply twin sided self
Provide a primer coat of PU PRIMER around
b by soft paint brush.After drying of the primer
ting over the primer applied surface
ure on the slab.After the first coat has dried
sing 0.5kg material per sqm. While the second
o provide rough surface and allow to
r requirement with tiles/ IPS etc.Ponding of
n from QC team)If leakage found then grouting
f no leakage inspection, permitted for

-
Nos
Nos
Nos
Nos
Nos
RS -

You might also like