You are on page 1of 2

0260-9576/05/$17.63 + 0.

00
 Institution of Chemical Engineers 2005

Fire on an electrostatic paint line

Process description No staff were injured, and damage was limited to the
spray line.
In order to improve the performance of the metal However this was a one-off facility. No other
anodes used in an electrochemical process, they were facilities were known to be available anywhere else in
given a thin surface coating of a mixture of precious the world for refurbishing the anodes, which were used
metals (platinum and rhodium). This was achieved by in a number of other plants with a turnover well in
mixing metal salts with a flammable hydrocarbon excess of £ 100 million per annum. Following a great
solvent to produce a ‘paint’, which was applied to the deal of effort the line was rebuilt and back on line before
anodes by spray painting. In order to minimise losses the stock of refurbished anodes was exhausted.
of the very expensive ‘paint’, an electrostatic painting
process was used. In this the spray nozzle was given a
high voltage electrostatic charge, which was transferred
to the spray particles. In order to attract the paint
particles, the anode to be painted was given the opposite Investigation
charge to the spray head. The gap between the spray It quickly became clear that the paint at the spray heads
head and the anodes was designed to be sufficient to had initially ignited. This small fire had then melted the
prevent an electrostatic discharge. plastic pipes used to convey the paint from the supply
The anodes were mounted onto jigs fixed to a tank to the spray heads and resulted in the whole paint
conveyer, which transferred them past the spray inventory becoming involved in the fire. Although the
heads at a preset speed. dry powder had subdued the fire, the hot metal surfaces
During design the whole process was subjected to a had re-ignited it.
Hazard Study. During the study it was concluded that Why had the spray ignited? More detailed
the fire risk was low, since: investigation showed that parts of the conveyer were
• the hydrocarbon solvent was being used below its worn and some of the jigs used to hold the anodes were
flash point; distorted. This had allowed the anodes to become too
• only a limited amount of ‘paint’, less than five litres, close to the spray head, leading to sparking.
was present in the rig at any one time. The assumption that handling the solvent above its
On this basis, no fixed fire protection equipment flash point made the process safe was incorrect. The fine
was provided although a number of dry powder spray produced in the process was capable of ignition,
extinguishers were provided in the building. even by the very low energy of the electrostatic
charge device.

The incident
Shortly after starting the spray line the operator noticed
Corrective action
a fire. The line was stopped, the site fire and security • During restatement of the process, detailed checks
staff were called and attempts were made to extinguish were made on the alignment of the conveyer and
the fire with a portable dry powder extinguisher. of the jigs.
Although this subdued the fire it re-ignited immediately. • The Hazard Study was reconvened which
On arrival at the scene the fire/security staff isolated the recommended:
electrical supplies and extinguished the fire with a hand- 䊊 more frequent checks on conveyer wear and
held foam extinguisher. alignment;

LOSS PREVENTION BULLETIN 181

29
䊊 fitting of fire detectors, both smoke and IR to the • The whole process was reviewed to assess business
spray rig coupled to a shutdown system to stop interruption risks.
the paint spray; • An inherently safe approach involving changing
䊊 automatic fire extinguishers, Halon, fitted in the the process to use a non-flammable solvent was
spray booth (since replaced with a non CFC considered. However such a change would have
extinguisher); required extensive product development and
䊊 although plastic components had to be retained to retesting over several years and was deemed
provide electrical isolation, an isolation valve, impracticable.
linked to the shutdown system, was installed
below the paint supply.

LOSS PREVENTION BULLETIN 181

30

You might also like