PT SAMUDRA MARINE INDONESIA

CONTROL ITEM
Date of Issue : 15-Jan-2022 REV : 0
Project code : C-1406
Ship's Name : MT. PETROSTAR Update : 27/Jun/2022
Plan/
Request Day Request Day Expected %
NO
Original Additional
PIC/ DEPT. PAGE NO. Description actual
Finish Progress
Update Progress Owner Comment
start
14 CARGO TANK & COMPRESSOR ROOM MACHINERY
118 PAGE 174 LPG CARGO PUMP 16 Set (Overhaul By Specialist) , Provide assistance/
manpower & workshop 100% ALREADY DONE

119 PAGE 176 CARGO CONDENSOR 14 pcs, Removed & repair end cover 75% PROG. PAINTING
ORIGINAL
120 MECHANICAL PAGE 185 BRAINE COOLER 2 Pcs, Removed & repair end cover 75% MODIF. PIPING
JOB SCOPE
121 PAGE 187 PREASSURE RELIEF VALVE 71 Pcs, overhaul & preassure test 95% SUBC. SARI MANDA
~ Relief Valve in Compressor romm 28 Pcs 100% ALREADY DONE
~ LPG liquid and condensate and Vapour relief valves 43 Pcs 90% REMAINING SERVICES 9 PCS
15 ENGINE ROOM MACHINERY
122 PAGE 48 SEA VALVE 84 pcs, Overhaul 73% Subc. SMS
Seachest valve 27 Pcs, Renew 11 Pcs (9 ready) 80% WAITING PIPE AND NEW VALVE
ORIGINAL Overboard 26 Pcs, Renew 7 Pcs (Ready 5 Pcs)
MECHANICAL 80% WAITING PIPE AND NEW VALVE
JOB SCOPE
Intermaddiate 31 Pcs, Renew 2 Pcs (Ready 2 Pcs) 60% WAITING PIPING
124 PAGE178 AUX ENGINE NO. 1 & NO.2, provide assistance for removed & renew Unit 90% STUD BOLT, ETA 13/04/22
PAGE178 AC CONDENSER 1 UNIT, CHEMICAL CLEANED, HYDROTEST 100% DONE
REF. CONDENSER 1 UNIT, CHEMICAL CLEANED, HYDROTEST 90% MODIF PIPE
SAFETY VALVE REF. CONDENSER 1 UNIT, OVERHAUL AND TEST 100% DONE
REMOVED & INSTALL NEW PUMP IN ENGINE ROOM 5 UNIT 100% DONE
23/Mar/2022 REMOVED PUMP IN ENGINE ROOM 2 UNIT 100% DONE
16 DECK MACHINERY
130 PAGE 89 PV valve/ Cargo Tank MARVS 19 unit, Overhaul & calibration 90% PROG. INSTALL
132 PAGE 107 CARGO TANK DOME STUB, Remove & renew blank (7 SET ) 100% PROG. INSTALL BLANK
134 MECHANICAL PAGE 255 GANGWAY (STBD) Renew hydraulic hose 12 PCS 80% READY TO INSTALL
TELESCOPIC GANG WAY (RENEW BUSH AND PIN) 90% MODIF GREASE PIPE BY. PIPING
ANCHOR (FREE UP PIN) PORT AND STBD SIDE 100% DONE
TOTAL PROGRESS #REF!
#REF! TOTAL % PROGRESS
NUMBER OF ITEMS 114
DOCKING WORK SUBCONT PIC REVIEW, CHECK AND ACKNOWLODGE SIGN
UNDOCKING SUBCONT PLANT START PLANT FINISH DONE OPNAME
PROJECT SUPT
FINAL DATE
FLOATING DATE
OWNER REP
SAIL OUT DATE SMI

Page 1 of 1 SMI-SR-PRO-01