Professional Documents
Culture Documents
Technical Specification
Title:
Document No.:
Revision: 01
Date: 26/01/2016
Prepared by:
Reviewed by:
Approved by:
This document is property of Abeinsa EPC Khi. Its total or partial reproduction is strictly forbidden by any means, as well as its distribution to
third parties without the express written consent of Abeinsa EPC Khi.
If for exceptional reasons, due to specific aspects of the project (eg: project confidential information, legal requirements or local regulations
and/or contractual requirements of the client), there was a need to modify the requirements included in this procedure, these changes must
be properly documented in the quality, environment and health and safety plan of the project, prior approval from the company
headquarters management system department.
The original copy of this document is electronically signed and filed in the document management system of Abeinsa EPC Khi.
Document: 0331-ESP-UDS-00-00-046
Page: 2 of 17
Page: 3 of 17
Table of Contents
1. General ................................................................................................................... 4
1.1. Purpose ............................................................................................................... 4
1.1. Reference Documents .......................................................................................... 4
1.2. Exceptions to this Specification ............................................................................ 5
1.3. Measurement units .............................................................................................. 5
1.4. Contractor ........................................................................................................... 5
1.5. Safety .................................................................................................................. 5
2. Description of the activities .................................................................................. 6
2.1. Preoperational Activities ....................................................................................... 6
2.2. Scope of Work..................................................................................................... 6
2.2.1. 2.2.1. Preoperational Chemical Treatment ....................................................................................6
2.2.2. Steam Blowing .............................................................................................................................7
Page: 4 of 17
1. General
1.1. Purpose
The purpose of this technical specification aims to define the requirements for the Contractor
for the Chemical Cleaning procedure of Dead Sea Works Project. The conditions and
standards to be applied in the development of works are listed below in the documentation
for reference. This document shall include all final agreements issued by both parties during
the contract awarding process, and particularly this requisition and the Contractor's bid
The Contractor shall deliver all documents prescribed hereunder, as well as the information
required by third parties for the performance of the rest of the work which may be related
with the assembly of equipment and/or the mentioned systems
Nothing stated herein shall exempt the Contractor from carrying out, in addition to what is
contained herein, those analysis and tests or activities which may be considered necessary by
UTE Dead Sea for guaranteeing that the materials, assembly and workforce are satisfactory
for the desired purpose or are required by good practice.
This document shall include all final agreements issued by both parties during the contract
awarding process, and particularly this requisition and the Contractor’s bid. Therefore, this
Technical Specification shall be from now on the only document which shall govern the
administration of the contract.
ASME “Guidelines for watertube boilers with restritive steam purity needs” Table
2.13.1
VGB 513 Guideline “Internal Cleaning of Water-Tube Steam Generating Plants and
Associated Pipework”
EPRI Guideline for Chemical Cleaning
Discharge Manifold - 10-TPS1_Discharge_Manifold_Sht_1
Suction Manifold 14-TPS1_Suction_Manifold_Sht_1
Temporary Pump System 2 Suction - 8-TPS3-SUC
Temporary Pump System 2 Discharge - 6-TPS3-DIS2
Temporary Pump System 2 Discharge - 8-TPS3-DIS1
Temporary connection to filter housing unit 10-TEMP_STRAINER_OUTLET
Temporary connection to filter housing unit 10-WTP-Bypass
Piping technical specification
0331-CAL-AEE-017-062-0010_Chemical Cleaning process hydraulic calculation report-
Annex I.II
0331-PLN-USD-000-061-0001 - General Drawing
Document: 0331-ESP-UDS-00-00-046
Page: 5 of 17
Any additional costs which may arise as a consequence of any exceptions that have not been
indicated shall be paid by the Supplier.
Likewise, if the Supplier considers it necessary to add any part or equipment which has not
been included in the Specification, it shall include a justification.
1.4. Contractor
The contractor shall have the right to execute part or its whole work through a third party but
ultimately the contractor will be the only one responsible for it.
The contractor cannot be made without previously reporting the UTE Dead Sea and getting its
approval. In that sense, the contractor will indicate in its offer all the particular tasks that will
be subcontracted and the information about the subcontractor.
The contractor will coordinate the works of all the subcontractors and will solve the problems
between them. It will also guarantee the satisfactory design and operation of the system and
all the auxiliary equipment. The contractor will be the solely responsible for them as well.
The contractor will be responsible for approaching the subcontractor to the appropriate
documentation and information.
1.5. Safety
The contractor shall submit material datasheet for each chemical proposed to be used on site.
In addition the contractor shall provide a spill prevention action plan for our review and
approval. As part of the prevention plant the contractor shall provide with the equipment
layout (including barriers, warnings panels, portable showers, etc as per rule regulations) to
define the work and storage area.
Document: 0331-ESP-UDS-00-00-046
Page: 6 of 17
Stage 1
Preoperational Inspection
Stage 2
Water Reverse Flushing
Alkaline stage
Acid cleaning
Passivation stage
Draining with N2
Rinsing Cascade Flushing
Preservation of the system with N2 (if applicable)
Stage 3
Magnetite Layer Formation
Steam blowing
Final inspections
Page: 7 of 17
The activity shall be conducted in four (4) different circuits running simultaneously:
Temporary System: The temporary system is composed of a discharge header and a suction
header.
Circuit 1
From Condenser tank D-88-37-M_00757/01 through temporary piping TPS1, across
temporary WTP bypass, thru gland seal condenser up to TP38 and TP39 and down to
the feedwater system via TP31, TP32 and TP33.
From feedwater system to IP feedwater admission line up to HRSG IPSystem Temporary
bypass TP28-TP37 and from HP feedwater admission line up to HRSG HP system
temporary bypass TP29-TP30.
Return from TP37 will connect to HP system via TP20-TP40. And HP flow shall split into
two different ways simultaneously. One part of the flow shall go to steam blow
temporary piping at Steam Turbine TP18 and return via IP steam piping TP17; and the
other part of the solution shall circulate towards DSW and return to IP piping from TP23
to TP22. Both IP streams will mix at TP21and return to the suction header of the
condensate pumps.
Cirtuit 2
From Condenser tank D-88-37-M_00757/01 through temporary piping TPS1. The
temporary pump system has been designed with a temporary connection to
30”D88STL90BR001 (TP16).
From temporary TP16 thru 30”D88STL90BR001 to Dump Condensers D-88-37-
M_00753 01 and 02
From Dump Condensers D-88-37-M_00753 01/ 02 the chemical water will return to a
temporary pump system - TPS3 and then it shall split into two branches:
Thru the pipe D88CO_98BR002 to return to Condenser tank D-88-37-
M_00757/01
Thru temporary piping connect to TP06 at D88CWD51BR001 all the way to
the Existing Condensate Tank D849-3 where it will be bypassed with a
temporary jumper from TP01-TP02
For further information please refer to 0331-PLN-USD-000-061-0001 - General Drawing
The blowing activity intended to be executed for this proyect is a low pressure & high velocity
continuous steam blowing. The purpose of this activity is to remove leftovers, welding slags,
debris and other foreign materials from steam lines and it will necessarily be performed after the
chemical cleaning of the entire system.
The contractor shall be required to assist AEPC with equipment and supervision.
The blowing sequences to successfully accomplish this goal are listed below. Each of them may
have subsequences:
Document: 0331-ESP-UDS-00-00-046
Page: 8 of 17
Sequence 1 - HP Main steam line to Steam Turbine: from steam generator thru HP steam line,
connecting to main steam header from steam generator to the turbine HP stop valve thru
temporary piping to finally exit to atmosphere thru silencer D-88-30-M-00100/06
Sequence 2 – HP Main steam line to Existing Facilities (TP06): from steam generator
thru HP steam line, connecting to main steam header to the existing facilities (TP06)
thru temporary piping to finally exit to atmosphere thru silencers /D-88-30-M-
00100/01-02-03. After primary criteria is achieved steam can be sent to
dumpcondenser and start bypass mode.
Sequence 3A– IP Main steam line up to Steam Turbine: from steam generator thru IP
steam line to both permanent TP06 and ST silencer D-88-30-M-00100/06. The drag
factor shall only be considered up to temporary TP20.
Sequence 3B – IP Main steam line to Existing Facilities (TP07): from steam generator
thru IP steam line, connecting to main steam header to the existing facilities (TP06) thru
temporary piping to finally exit to atmosphere thru silencers D-88-30-M-00100/01-02-
03. After primary criteria is achieved steam can be sent to dumpcondenser and start
bypass mode.
Sequence 4 – IP Main steam line to ST: from steam generator thru IP steam line,
connecting to main steam header from steam generator to the turbine IP stop valve
thru temporary piping to finally exit to atmosphere thru silencer D-88-30-M-
00100/06.After primary criteria is achieved steam can be sent to dumpcondenser and
start bypass mode.
Sequence 5 – LP Main Steam Line: No target steam blow. Service steam through the
system
Sequence 6 – LP Extraction to Dump Cond: No target steam blow. Service steam
through the system.
Page: 9 of 17
Shall be responsible for the correct installation and tear down of the temporary
system.
Shall be responsible for the operation, lineup the system for sequences, tempering
water, temperature and pressure indicators. Purge and drain the system, check for
leaks, control of venting points, control levels, diesel consumption within the
temporary system.
Shall be responsible for the management of the water pump.
Shall be responsible chemical injection stage and monitor the evolution of SiO2, pH,
solids in suspension, [Fe], conductivity, temperature, pressure.
Shall be responsible for the coordination of loading the equipment to the plant.
The contractor shall be responsible for the supply of all items included in this chapter but shall
not be limited to them:
Document: 0331-ESP-UDS-00-00-046
Page: 10 of 17
Page: 11 of 17
Gloves in rubber
Antiacid gloves
Safety suit
Antiacid suit
Emergency shower
Emergency safety box
Analysis box
Safety signs
Stainless Steel hoses (1”, 2”, 4”, 6”, 8”)
Set of carbon steel spools for additional assemblies
Carbon steel elbows, tees, reducers, flanges, blind plates for additional assemblies
Flow meters
Filter hosing for 900m3/h flow process
Filter elements (10um, 40um, 80um, 200um)
Additional equipment such as fire extinguishers, pressure gauges, temperature
indicators, water spargers, joints, etc
Rubber gaskets, and paper gaskets
Required equipment and tools to clean death and/or inaccessible places where
mechanical cleaning is necessary
Atmospheric tank for the preparation of the solutions
Electric panels for pumps
Cables 150CV, 50CV, 25CV
All equipment and chemical dosing area shall be preserved by mean of spill berms.
Target inserters for steam blows (pneumatic inserter)
Targets bar material and dimensions according to VGB513 (including folder protection
for each)
The contractor shall provide a list of the above items, but not limited to them, along with the
quantities estimated for the execution of the job. This estimation shall be based upon a site
visit when a walkdown of the plant will be carried out.
Temperature 204.31ºC
Enthalpy 2,794.53 kJ/kg
Maximum Pressure17.00 bar
Saturated steam flow 3.50 kg/s
Estimation frame time 8 hours
The heating stage does not involve any heat exchanger as it is a direct injection of steam into
the water. That would result in an increment of water in the system of roughly 100m3 during
this stage. So avoid any loss of water the heating stage shall be performed once the LP and
HP systems are completely full and balanced.
Document: 0331-ESP-UDS-00-00-046
Page: 12 of 17
The auxiliary boiler shall be equipped with a water and diesel tank along with shutoff valve
and relief system.
5. Design Basis
The preoperational chemical treatment has been designed according to the following design
conditions:
Pumps
According to hydraulic calculations 0331-CAL-AEE-017-062-0010_Chemical Cleaning process
hydraulic calculation report-Annex I.II (Q750) and the final report 0331-CAL-AEE-017-062-
0010_Chemical Cleaning process hydraulic calculation report follow the pump specifications
for the correct hydraulic of the system:
Temporary Pumps 1:
Flow:375 m3/h
TDH: 118.7 m
NPHSa: 3.813 m
Temporary Pumps 2:
Flow: 125 m3/h
TDH: 19.8 m
NPHSa: 3.2 m
The contractor shall present by the end of the job a report with all data collected during the
activities with the following points (but shall not be limited to them)
Document: 0331-ESP-UDS-00-00-046
Page: 13 of 17
PH regression line
TDS concentration regression line
Sulphite concentration regression line
OH and alkalinity concentration regression line
Phosphate concentration regression line (if applicable)
Temperature regression line
Pressure regression line
Fe2+, Fe3+ regression line
Acid concentration regression line
Conductivity
Document: 0331-ESP-UDS-00-00-046
Page: 14 of 17
Technical procedures
Instructions and planification of work before activities
Chemical Cleaning Sequences - Supporting documentation should include each circuit
clearly defined. Ensure back-up equipment and spares are listed in procedure and
available to supports.
Water needs - Quality, Quantity and Flow
Nitrogen supply and pressure reducer
Hydraulic Calculations
Manpower for construction, assembly, rearming the system and installation of
temporary elements, valve manipulations, chemical inyection assistance.
Preparations to be perform by UTE Dead Sea, lineup and checking the circuit prior
activities.
Utilities including water, oil free compressed air, electricity and fuel for boiler and
pumps
Unloading of trucks transporting the equipment on the site. Unloading on the
equipment base, including alignment and fixation thereof to the bases or previous
unloading in the field storage area and subsequent transfer to their final location.
The electric supply required for the execution of work shall be supplied by the UTE
Dead Sea at his expense including the rental of the generators, combustible, cables,
connections, protections, distribution panels, signposting, etc… as optional.
P&ID´s for temporary system and for the preoperational chemical treatment.
Isometrics of temporary system.
3D model (if applicable)
Connection points and main (suction-discharge) manifolds.
Execution of activities with manpower and supervisor from UTE Dead Sea.
1. The temporary pump system 1 (TPS1) is the main pump system and it shall be prepared with
chemical inyection system, filtration hosing unit, atmospheric mixer tank, etc.
UDS shall provide the suction manifold and the discharge manifold for the contractor to attach
their equipment and assemble the system.
The drawings 10-TPS1_DISCHARGE_COL_Sht_1and 14-TPS1_SUCTION_COL_Sht_1 show all
available connections for this purpose.
2. The temporary pump system 2 (TPS2) is a secondary pump system that shall be composed by a
pump system and fittings to connect to the tie-in points shown in the drawings Temporary
Pump System 2 Suction - 8-TPS3-SUC_Sht_1, Temporary Pump System 2 Discharge - 8-TPS3-
DISCH1_Sht_1 and Temporary Pump System 2 Discharge - 8-TPS3-DISCH2_Sht_1
Document: 0331-ESP-UDS-00-00-046
Page: 15 of 17
3. The system is also composed by a filtration housing unit and the following drawnigs show the
details of the connections available for the contractor to attach their temporary system
Temporary connection to filter housing unit 10-TEMP_STRAINER_OUTLET_Sht_1 and
Temporary connection to filter housing unit 10-WTP-Bypass_Sht_1
The contractor shall include in the offer the following services as an optional:
The equipment shall be delivered to site 2 weeks before the start of the activities. Both
supervisors shall be on site to assist and supervise the unloading of the equipment. They will
be working on day shift to manage the installation of the temporary system.
Once the assembly and installation of the temporary system is completed, the operation will
start and last for a total of 10 days.
With the completion of the activities, teardown of the temporary system will follow during an
estimated period of 6 days.
Document: 0331-ESP-UDS-00-00-046
Page: 16 of 17
Contractor shall recieve a letter note to proceed three (3) weeks in advance to start
mobilization, delivery of equipment and supervisors.
Contractor shall submit all required documentation for UDS to issue access and permits.
10.Table of responsibilities
Page: 17 of 17
Pipes
Flanges
Note 4: Use A105 FF ASME B16.5 150# flanges for butterfly valves.
Note 5: Class B up to pressure 5.93 bar, class D up to 10.34 bar, class E up to 18.96 bar
Note 6: WN flanges shall be designed with the same schedule as the pipe attached.
Note 7: Flanges connected to the equipments will be the same type as the equipment flanges.
Fittings
Note 8: When so specified in design drawings, ≤ 2" threaded fittings could be used with 3000#.
Note 9: Fittings shall be designed with the same schedule as the pipe attached
Gaskets
Size Material Description
(T≤ 100ºC) C 4430-TYPE ASBESTOS FREE FIBER, ICP 9400 OR SIMILAR ASME B16.21 THK 1,5 mm 150# / 300#
1/2" - 24" (100ºC<T<230ºC) 800 SERIES MULTI-DIRECT EXPANDED PTFE OR SIMILAR ASME B16.21 THK 1,5 mm 150# / 300#
(STEAM, GAS AT T>180ºC, LIQUID AT T>230ºC) 316L SS WITH CS OUTER RING SPIRAL WOUND ASME B16.20 150# / 300#
(T≤ 100ºC) C 4430-TYPE ASBESTOS FREE FIBER, ICP 9400 OR SIMILAR ASME B16.47 THK 3 mm 150#
28" - 48" (100ºC<T<230ºC) 800 SERIES MULTI-DIRECT EXPANDED PTFE OR SIMILAR ASME B16.47 THK 3 mm 150#
(STEAM, GAS AT T>180ºC, LIQUID AT T>230ºC) 316L SS WITH CS OUTER RING SPIRAL WOUND ASME B16.47 150#
Valves
V-1000; V-1001; V-1002; V-1003; V-1200; V-1201; V-1400; V-1401; V-1800; V-2000; V-2200; V-2201; V-2800; V-2900; V-3300; V-3301; V-3302; V-3600; V-3900; V-3901; V-3902;
V-4200; V-4500; V-5010; V-5060
Appendix II: Valve catalogue
Branches
Title:
Prepared by:
Reviewed by:
Approved by:
This document is property of Abeinsa EPC Xina. Its total or partial reproduction is strictly forbidden by any means, as well as its distribution to
third parties without the express written consent of Abeinsa EPC Xina.
If for exceptional reasons, due to specific aspects of the project (eg: project confidential information, legal requirements or local regulations
and/or contractual requirements of the client), there was a need to modify the requirements included in this procedure, these changes must
be properly documented in the quality, environment and health and safety plan of the project, prior approval from the company
headquarters management system department.
Document: 0331-CAL-AEE-017-062-0010
UTE Dead Sea
Revision: 0 Date: 01/04/2016
DSWPP-GT1
Page: 2 of 7
Table of Contents
This document is intended to cover the minimum requirements for the description and
justification of the calculations of the Chemical cleaning process for designing Power Plant for
the Dead Sea Works (DSW) at Sedom
The chemical cleaning process will consist of cleaning several circuits connected at their
respective collectors and suction drive from the temporally pumps (TPS1). Each circuit are
described below:
- Circuit 1: This circuit begins at the common suction of the temporally pumps TPS1.
Continues through the condensate system to the bypass in the inlet/outlet of the
deaerator (10-HRSG-FW-Bypass). The chemical cleaning process continues through the
temporal pipes connecting with the feed water pumps aspiration and discharge lines
One discharge line connects to the HP system, bypasses the HRSG and continues
through existent pipe.
The other discharge line connects to the IP system, bypasses the HRSG and then
connects to line from HP circuit.
This final line splits, the first branch bypasses the steam turbine, and the other
bypasses the customer delivery, and goes through TP21 to finish in the condensate
tank.
- Circuit 2: This circuit begins at the common suction of the temporally pumps (TPS1).
Continues through the existent line D88STL90 (diameter 30”) until the DC condensate
return tank. Then the circuit connects to the aspiration and discharge of the dump
condensate return pumps with the temporally pumps TPS2, one discharge line goes to
the condensate tank and the other continues through the existent line D88CWD51
until the aux condensate pumps, and then returns to the condensate tank.
Document: 0331-CAL-AEE-017-062-0010
UTE Dead Sea
Revision: 0 Date: 01/04/2016
DSWPP-GT1
Page: 5 of 7
2. Hypothesis of calculation
- Pumps suction: 1 m
- Pumps discharge: 1 m
-Temporally Pumps 1 flow: Normal flow per pump 500 m3/h. Total flow 1000 m3/h
- Temporally Pumps 1 flow: Minimum flow per pump 375 m3/h. Total flow 750 m3/h
- Temporally Pumps 2 flow: Normal flow per pump 250 m3/h. Total flow 500 m3/h
- Temporally Pumps 2 flow: Minimum flow per pump 125 m3/h. Total flow 250 m3/h
3. Reference documents:
See annexes to this document (Pipe Flo schemes) and chemical cleaning process diagram
Document: 0331-CAL-AEE-017-062-0010
UTE Dead Sea
Revision: 0 Date: 01/04/2016
DSWPP-GT1
Page: 6 of 7
3D model - 2016/03/10
4. Results
Annex I encloses the results provided by Pipe-Flo software. List report, material report,
pipeline report and scheme of the system are shown, for each calculated case:
It has been simulated two cases for the temporality pumps where are described below:
Temporality Pumps 1:
Flow :375 m3/h
TDH: 118.7 m
NPHSa: 3.813 m
Temporality Pumps 2:
Flow : 125 m3/h
TDH: 19.8 m
NPHSa: 3.2 m
Control valves:
Next table show the percentage of opening of the valves used to compensate the different
circuits in the cleaning process. In the scheme of the circuit (see annex) are represented
control valves that are operating in design case and its set position.
The control valves considered are available, except in the impulsion feed water pumps but
there is a flow meter.