UREA MELT-AI-DU-STEEL DRAWING-HOLD REMOVAL

DESCRIPTION (DRAWING TITLE) DRAWING NUMBER Revision

UREA MELT STRUCTURE 2201-BL016I-LOT-1


PLAN AT EL. 100.500(BOB) AND BASE PLATE DETAILS 4124-AI-DU-22201I016S01

3
UREA MELT STRUCTURE 2201-BL016I-LOT-1
4124-AI-DU-22201I016S02
BASE PLATE DETAILS AND SECTIONS 2

UREA MELT STRUCTURE 2201-BL016I-LOT-1 4124-AI-DU-22201I016S03


PLAN AT EL. EL.108.900(TOS), EL.109.900(TOS). EL.110.500(TOS) & SECTIONS

2
LD REMOVAL
MAJOR HOLD- DESCRIPTION- REFER
Input status/ Remark
DWG FOR SPECIFIC HOLD

1. lift data is not available


1. Lift data awaited 2. & 3. Hold for approval of 60% MR tag, PIPING to remove
2. Platform EL 104.00 Hold HOLD as per resolution provided to owner. If there will be
more changes due owner comment then to be evaluated
3. Stair access for platform EL 103.73 accordingly
NO HOLD

1. Hold to be removed by piping by 2 Aug 21 as PSV 22016,


22015 dimensions has been increased & platform layout study
to be done accordinlgy. For 60% tags related to maintenance of
p-501, PIPING to remove HOLD as per resolution provided to
owner. If there will be more changes due owner comment then
1. Monorail Hold to be evaluated accordingly. Loads may be increased.
2. Platform at EL 109.900 Hold 2. Hold to be removed by piping by 2 Aug 21
ACTION BY HOLD QUANTITY

PIPING/MACH/PRENG

PIPING