1 A project sequence is shown in the following table 35 1
Event Duration ES EF LS LF TF
(weeks) (Early Start) (Early Finish) (Late Start) (Late Finish) (Total Float)
1–2 6
1–3 4
1–4 9
2–6 4
3–5 8
4–6 5
4–7 1z
5–7 4
6–7 8
z = is your last student ID
Based on the table,
a) Make a network diagram of the project! (15%)
b) Complete the table to Find the critical path of the network! (20%)
Halaman 1 dari 2
UNIVERSITAS MUHAMMADIYAH SURAKARTA
Jl A Yani Pabelan Kartasura Tromol Pos 1 Surakarta 57162
Telp. 0271-717417 Fax: 0271-715448 Email: ums@ums.ac.id
If total volume of excavation job is 1z0 m3 (z = is your last student ID), how
many workers are needed per day to finish the pipeline job?