UNIVERSITAS MUHAMMADIYAH SURAKARTA

Jl A Yani Pabelan Kartasura Tromol Pos 1 Surakarta 57162


Telp. 0271-717417 Fax: 0271-715448 Email: ums@ums.ac.id

UJIAN AKHIR SEMESTER GENAP 2019/2020


FINAL EXAM OF SECOND SEMESTER 2019/2020
FAKULTAS (Faculty): TEKNIK (Engineering)
JURUSAN (Department) : TEKNIK SIPIL (Civil Engineering)
Mata Uji - Course Construction Technique Hari/Tanggal - Day/Date Monday/06 July 2020
Smt/Kelas - Class 6/A Jam ke - Session 3
Penguji - Examiner Mochamad Solikin, Ph.D. Waktu – Duration 90 Minutes
Petunjuk – Guidance:
1. Answer shet should use folio paper line on it and this is open book exam. Soal dikerjakan di lembar
jawaban, kertas folio bergaris dan Soal bersifat buku terbuka
2. Start upload your answer sheet at least 15 minutes before the end of exam schedule. Mahasiswa harus
upload lembar jawaban minimal 15 menit sebelum waktu habis agar tidak tertinggal mengupload
lembar jawaban.
3. After time is finished some exams uploading system will be locked so you can’t upload your answer
sheet. Setelah waktu ujian habis beberapa Mata Kuliah UAS di-lock otomatis sehingga mahasiswa
tidak dapat upload jawaban.
4. You should have reliable internet connection during the exam, to avoid the problem of answer sheet
upload process. Mahasiswa harus memastikan memiliki koneksi internet yang reliabel sehingga tidak
menyampaikan alasan terlambat upload lembar jawaban karena kendala koneksi internet.
Capaian Pembelajaran Mata Kuliah – Course Learning Outcomes (CPMK - CLO):
1. Ability to make project schedule
2. Ability to analysis of S curve
3. Ability to prepare manpower to finish a job

Nilai CPMK
No
Soal – Questions - - CLO
.
Score
1 A project sequence is shown in the following table 35 1
Event Duration ES EF LS LF TF
(weeks) (Early Start) (Early Finish) (Late Start) (Late Finish) (Total Float)
1–2 6
1–3 4
1–4 9
2–6 4
3–5 8
4–6 5
4–7 1z
5–7 4
6–7 8
z = is your last student ID
Based on the table,
a) Make a network diagram of the project! (15%)
b) Complete the table to Find the critical path of the network! (20%)

2 A weekly schedule of pipeline construction is shown in the following table:

z = is your last student ID

Halaman 1 dari 2
UNIVERSITAS MUHAMMADIYAH SURAKARTA
Jl A Yani Pabelan Kartasura Tromol Pos 1 Surakarta 57162
Telp. 0271-717417 Fax: 0271-715448 Email: ums@ums.ac.id

Based on the schedule: 45 2


a) Complete the percentage weight of the schedule! (15%)
b) Draw the S curve for the schedule! (20%)
c) If at 7th weeks the progress of the job is 70%, what is your comment
to the schedule? (10%)

3 Based on SNI, resources to finish excavation job is shown in the following 20 3


data:
3.a. 6.2 Menggali 1 m3 tanah biasa sedalam 2 meter (soil excavation per m3 up to 2 m depth

Kebutuhan Tenaga kerja Indeks


Pekerja (O/H) (worker Man/Daily) 0,9

If total volume of excavation job is 1z0 m3 (z = is your last student ID), how
many workers are needed per day to finish the pipeline job?