You are on page 1of 2

Quotation for Inatsllation Penstock

Thalasouk Engineering Co.,LTD 18/6/2022


Title : Penstok

Cost
Item Description Quality Unit Remark
USD$

Porject 1 : Nam Boak Hydropower project


1 Machinery and Equipment
­ Equipment LS 6,000
­ Backhole 2 101,563
Total 107,563
2 Inastall . Penstok Work
­ Penstok ID 1700 mm wall thickness 10 mm. Length 259.00 m. 109,223.24 kg. 42,665
­ Penstok ID 1700 mm wall thickness 12 mm. Length 103.73 m. 52,554.34 kg. 20,529
­ Penstok ID 1700 mm wall thickness 14 mm. Length 163.34 m. 96,660.84 kg. 37,758
­ Penstok ID 1700 mm wall thickness 16 mm. Length 48.80 m. 33,042.76 kg. 12,907
­ Penstok ID 1700 mm wall thickness 20 mm. Length 28.27 m. 23,982.99 kg. 9,368
­ Penstok ID 1300 mm wall thickness 20 mm. Length 19.50 m. 12,695.73 kg. 4,959
­ Penstok ID 800 mm wall thickness 20 mm. Length 19.50 m. 7,886.74 kg. 3,081
Total 336.05 Tons. 131,268
Nam Boak Hydropower project GRAND TOTAL 238,831 USD

Cost
Item Description Quality Unit Remark
USD$

Porject 2 : Nam Yaim Hydropower project


1 Machinery and Equipment
­ Equipment LS 6,000
­ Backhole 2 142,188
Total 148,188
2 Inastall . Penstok Work
­ Penstok ID 1250 mm wall thickness 10 mm. Length 606.61 m. 188,086 kg. 73,471
­ Penstok ID 1250 mm wall thickness 12 mm. Length 184.99 m. 52,620 kg. 20,555
­ Penstok ID 1250 mm wall thickness 14 mm. Length 262.78 m. 114,471 kg. 44,715
­ Penstok ID 1250 mm wall thickness 15 mm. Length 105.54 m. 49,296 kg. 19,256
­ Penstok ID 1250 mm wall thickness 20 mm. Length 293.35 m. 183,422 kg. 71,649
­ Penstok ID 1250 mm wall thickness 22 mm. Length 207.04 m. 142,620 kg. 55,711
­ Penstok ID 800 mm wall thickness 22 mm. Length 78.02 m. 34,696 kg. 13,553
­ Reduce ID 1250/800 mm wall thickness 22 mm. Length 2 m. 2,282 kg. 891
Total 767.49 Tons. 299,802
Nam Yaim Hydropower project GRAND TOTAL 447,990 USD

Page 1 of 4
Quotation for Inatsllation Penstock
Thalasouk Engineering Co.,LTD 18/6/2022
Title : Penstok
Cost
Item Description Quality Unit Remark
USD$

Porject 3 : Nam Sak Hydropower project


1 Machinery and Equipment
­ Equipment LS 6,000
­ Backhole 2 170,000
Total 176,000
1 Inastall . Penstok Work
­ Penstok ID 900 mm wall thickness 8 mm. Length 345.3 m. 61,857.39 kg. 28,029
­ Penstok ID 900 mm wall thickness 9 mm. Length 178.5 m. 36,013.37 kg. 16,319
­ Penstok ID 900 mm wall thickness 10 mm. Length 286.6 m. 64,318.62 kg. 29,144
­ Penstok ID 900 mm wall thickness 12 mm. Length 305.4 m. 82,426.01 kg. 37,349
­ Penstok ID 900 mm wall thickness 14 mm. Length 363.6 m. 114,740.64 kg. 51,992
­ Penstok ID 900 mm wall thickness 15 mm. Length 344.4 m. 116,572.11 kg. 52,822
­ Penstok ID 900 mm wall thickness 16 mm. Length 109.5 m. 39,577.53 kg. 17,934
­ Penstok ID 900 mm wall thickness 18 mm. Length 280.7 m. 114,387.02 kg. 51,832
­ Penstok ID 900 mm wall thickness 19 mm. Length 385.1 m. 165,829.50 kg. 75,141
­ Penstok ID 900 mm wall thickness 20 mm. Length 170 m. 77,141.11 kg. 34,955
­ Penstok ID 900 mm wall thickness 22 mm. Length 102 m. 51,023.82 kg. 23,120
­ Penstok ID 900 mm wall thickness 24 mm. Length 104 m. 56,876.87 kg. 25,772
­ Penstok ID 900 mm wall thickness 25 mm. Length 335.9 m. 191,562.68 kg. 86,802
­ Penstok ID 900 mm wall thickness 26 mm. Length 111 m. 65,906.23 kg. 29,864
­ Penstok ID 900 mm wall thickness 28 mm. Length 77.4 m. 49,598.22 kg. 22,474
­ Penstok ID 600 mm wall thickness 18 mm. Length 61.816 m. 16,958.25 kg. 7,684
Total 1,304.79 Tons. 591,233
Nam Sak Hydropower project GRAND TOTAL 767,233 USD
Scope of Work
Employer Contractor
1. Engineering Detail Design for Construction Drawing 1. Manpower for Installation and Erection Weilding (Labor,Supervisor)
2. Steel Penstock : Suppile and Delivery on site 2. Equipment and Tool for Welding Erection only
3. All of Accessories and Tool
4. Erection and Installation and Test Commissioning
(Engineer,Survey )
5. Welding Inspector and Commissioning test on site
6. Access road
7. Security
8. Camp ­
9 Water and Power Supply (Cable Wiring)
10. Schedule and Step Method for Constrction
11. Unloading and Lifting at site
(Blackhole , Cran , Truck , Lifing and Hoist )
12. Work Permit in Lao
13. Custom Clearance in Laos'side
14. Foundation Construction
- Excavation
- Structure Concrete

Page 2 of 4

You might also like