Professional Documents
Culture Documents
Only the above copies and the computer display are considered as “CONTROLLED
DOCUMENTS”. Any copies taken from the computer will be deemed to be
“UNCONTROLLED”.
AMENDMENTS
All amendments to this manual must be approved by the ABB Project Manager who
will modify the computer record and re-issue the amended sections as necessary.
CONTENTS
1.0. INTRODUCTION
This Project Emergency Response – Plan (ERP) describes the process for responding to a crisis
that may arise during the construction and commissioning of Project -Supply and Installation,
Sem-Calaca Power Corporation (SCPC) Rehabilitation Works: Electrical System Upgrade.
The ERP is based on the organizational and management principles of the ABB Way Emergency
Preparedness and Response Plan SA-M-10. This system provides a globally accepted standard
management structure for incident and emergency management. This system further
establishes consistent principles, terminology, and procedures to be used by both ABB and ABB
Contractor in the management of emergency incidents during the construction and
commissioning stage of the SCPC-Electrical System Upgrade project.
1.1. PURPOSE
The purpose of this document is to outline the emergencies that are the responsibility of the
Contractor (ABB) and to detail the necessary emergency response measures, equipment and
facilities that need to be planned, implemented and maintained during the construction and
commissioning of the “SCPC-Electrical System Upgrade”. This document also addresses the
recovery stage to enable recovery from an emergency incident. In detail, the objectives of this
Emergency Response Plan are to:
(1) Identify the nature and type(s) of emergencies that may arise during the
construction and commissioning phase of the project that ABB will be responsible
to manage.
(2) Identify the required equipment and facility, personnel and training at project site
necessary to manage the potential emergencies and incidents that have been
identified, analysed and assessed as per SA-M-02 “Hazard identification and
assessment of risks and opportunities”.
(3) Establish the roles and responsibilities of Contractor and Subcontractor staff on
site during an incident or emergency;
(4) Ensure that each emergency is managed in accordance with a detailed set of
procedures during the construction stage, up to mechanical completion, of the
project; and
(5) Ensure that all Emergency Response activities are undertaken in accordance with
Customer Emergency Response Procedure for construction and commissioning.
1.2. SCOPE
This ERP is a contractual requirement and is intended to be binding on all members of the ABB
Project Management Team as well as all ABB staff and Sub-contractors. This ERP enables ABB to
take actions necessary to protect project personnel and the public, the environment, and
assets.
During construction and commissioning of the SCPC-Electrical System Upgrade Project this ERP
will be used by Supervisors and Subcontractor’s personnel who have a duty of care in the event
of any emergency, to protect and assist all members of the workforce and to minimize any
adverse impacts of any emergency incident on workers, the general public and the environment.
This ERP covers all construction sites, including access roads and worker camp(s).
1
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
2.0. REFERENCES
2.1. DEFINITION
2.1.1. Incident
An incident is any event that causes or has the potential to cause (Near Miss) personal injury,
damage/loss of assets, environmental damage or harm to the health and/or safety of any
individual.
Incidents do not include operations, maintenance, quality or reliability issues which had no HSE
consequence or potential. Incidents do not include degradation or failure of plant or equipment
resulting solely from normal wear and tear unless this results in injury to persons, damage to the
environment, asset loss or reputation damage.
2.1.2. Crisis
A crisis is an incident (either a situation or an event) that has the potential to impact the wider
organization in terms of safety of life, continuity of business or damage to reputation; where
there is a degree of complexity so that it is unclear what action should be taken; and where
extraordinary resources are required to bring the incident under control and manage it to a
satisfactory outcome.
2.1.3. Emergency
2. Medevac emergencies;
5. Facility Emergencies (fire, explosion, toxic gas leakage, hazardous material spillage etc.);
2
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
2.2. ABBREVIATION
Throughout the project construction and commissioning stage the HSE Supervisor will develop
Emergency Response Team(s) (ERTs) that consist of experienced, trained personnel, able to deal
with emergencies that may arise at the workplace and camp.
All emergency responders will be fully responsible for controlling the emergency scenarios and
notify the senior management and customer ERT team for immediate response. The Emergency
Response Team(s) shall be involved in training programs and drills (to be established by the
customer ERT or HSE) which shall include, but not be limited to the following:
Each ERT team will be led by a team leader responsible for the co-ordination of the team’s
activities.
The On Scene Commander (OSC) is the person designated to coordinate the rescue efforts at
the rescue site and control the emergency responders. He will be supported by the ERTs along
with ABB’s HSE and Senior Site management personnel. He will also be supported as required by
SCPC’s ERT team.
SCPC HSE Department/Incident Command Centre is the focal point in all major emergencies at
3
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
project
4
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
The On-Scene Commander shall have the following emergency response responsibilities:
1) The team(s) shall be responsible for recovering any casualties and properly transporting
them to the Medical Center.
2) The team shall also assist the nurse and first aider on duty in rendering medical aid to
injured parties. If nursing staff and first aider are not available, the leader of the team
shall take charge by administering first aid and sending injured or sick person(s) for
further treatment to the medical center or local accident and emergency hospital.
5
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
• If required for more help summon them by means of the easiest communication
way.
6
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Training shall be conducted on a regular basis for the team involved in the emergency
procedure.
A comprehensive emergency response training schedule will be prepared and updated twice
yearly.
7
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
7) Do not enter the building or work area under any circumstances until the all clear signal is
given.
All new staff, as part of their induction, shall be given instructions on the evacuation procedures
for the site.
All visitors and Subcontractors are to be advised of the Site's Evacuation Procedure and the
location of Muster Point when they are admitted to the site.
Appendix A:
PERSONNEL
INJURY Provide the Board victim injured to
necessary ambulance/
resources and Vehicle and send to
notify the nearest accredited
Alert ERT MEDEVAC authorized hospital with the Escort
(MEDEVAC) required? personnel
Team Leader -
ABB
No Yes
9
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Appendix B
FIRE INCIDENT
Extinguish
Evacuate the area completely
Head count /
Attendance Investigate and
recommend
Salvage
Proceed to Muster station and
Missing ? No wait for further instruction
Final Report
Yes
No
Yes MEDEVAC
Yes
Appendix C
10
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
TYPHOON EMERGENCY
Signal No.
1 2 3
Head Count
Yes Missing
Person?
No
Mobilize Search and
rescue
Wait for
Standby vehicle further
ininstructions
Yes Recovered / No
Retrieve? Report as per
NOI
No MEDEVAC? Yes
Board Standby
Vehicle and
proceed to Safe
Areas
Appendix D
EARTHQUAKE
Proceed to designated
muster point
Head count
Star of crisis
situation
No Structure Yes
collapse?
Person
missing?
No
Yes
Wait for further
instruction Mobilize Search and
Rescue Team
Yes
Proceed to
assembly area
MEDEVAC
No Yes
12
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Appendix E
EMERGENCY HOTLINE NUMBERS EMERGENCY RESPONSE MANAGER ABB PROJECT MANAGER (SG)
BENHUR S.N. (SM) PANKAJ KUMAR
SCPC HOTLINE NUMBER – (043) 773-6444 +63 945-210-5272 +65 9654-2958
ABB HSE MANAGER (SG)
SCPC SAFETY - +63 929-698-7171 PRADEEP BHALLA
+63 956-396-7051 +65 9651-6249
EMERGENCY PLANNER
SCPC FIRE RESPONSE TEAM SCPC ENVIRONMENTAL SCPC SEARCH & RESCUE SCPC MEDEVAC TEAM SITE EVACUATION
EMERGENCY RESPONSE TEAM
(043) 773-6444 (043) 773-6469 (043) 773-6444 (043) 773-6452 (043) 773-6444
MUSTERING TEAM
ABB / Subcontractor
(PDI)
13
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Appendix F
EMERGENCY CONTACT NUMBERS – SCPC PROJECT
ABB
Singapore Contact
Site Contact
Position Contact Number Contact Position Number
Personnel
Personnel
Benhur S.N. Site Manager +63 945-210-5272 Pankaj Kumar Project Manager +65 9654-2958
HSE Hub
Regin Rex Mercado HSE Site Supervisor +63 998-470-1592 Pradeep Bhalla +65 9651-6249
Manager
+63 917-585-3989
ABB Philippines
Edgardo Patajo +632 821-777 (Land
HSE Manager Line)
14
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
15
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Appendix G
MUSTER POINT
16
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
Appendix H
17
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
18
ABB Pte. Ltd., Singapore Emergency Response Plan, Rev 3
____________________________________________________________________
19
ABB Pte. Ltd., Singapore Project HSE Plan, Rev 0
______________________________________________________________________