Professional Documents
Culture Documents
Clearing of Plans
❑ Mechanical
➢ Installation
➢ Fabrication
❑ Electrical
➢ Installation
EVALUATION OF MECHANICAL PLANS
❑ Installation
➢ Pressure Vessel ➢ Crane and Hoist
➢ Boiler ➢ Elevators
➢ Internal Combustion Engine ➢ Power Piping Line
➢ Turbines
❑ Fabrication
➢ Pressure Vessel
➢ Boiler
NUMBER OF PROCESSED APPLICATIONS
4000
3500
3000
No. of plans
2500
2000
1500
1000
500
0
Approved Return
2019 4198 287
2020 2658 1020
COMMON FINDINGS DURING EVALUATION (Fabrication) :
❑ Transmittal Letter
❑ Certificate of Appearance of Professional Engineer
❑ Photocopy of valid PRC and latest PTR of Professional
Engineer
❑ Application Forms (3 sets per unit)
❑ Drawing Plans (3 sets per unit)
All plans should be signed by the owner/manager/authorized representative, and signed and sealed by Professional Engineer
FABRICATION
Clearing of Plans
a. Transmittal Letter
b. PME’s Certificate of
Appearance • DOLE issued CA
c.
d.
Photocopy of PRC ID and PTR
Application Form
• Must be valid
e. Manufacturer’s Data Report
ASPECT OF EVALUATION
a. Transmittal Letter
c. Photocopy of PRC ID
• PRC ID must be valid
and PTR
d. Application Form
• Latest PTR
e. Manufacturer’s Data Report
ASPECT OF EVALUATION
a. Transmittal Letter
• All data must be filled-out
b. PME’s Certificate of Appearance
f. Drawing Plans
i. Equipment detailed
construction drawing
(include welding details)
iii. Equipment
specification
iv. General Notes
ASPECT OF EVALUATION
f. Drawing Plans
i. Equipment detailed
construction drawing
(include welding details)
iii. Equipment
specification
iv. General Notes
INSTALLATION
Clearing of Plans
e. Drawing Plans
a. Transmittal Letter i. Plant Location / Vicinity Map
b. PME’s Certificate of Appearance ii. Plant and/or Room Lay-out
a. Transmittal Letter
b. PME’s Certificate of
Appearance • DOLE issued CA
c.
d.
Photocopy of PRC ID and PTR
Application Form
• Must be valid
e. Drawing Plans
ASPECT OF EVALUATION
a. Transmittal Letter
c. Photocopy of PRC ID
and PTR
• PRC ID must be valid
d. Application Form
• Latest PTR
e. Drawing Plans
ASPECT OF EVALUATION
a. Transmittal Letter
• All data must be filled-out
b. PME’s Certificate of Appearance
e. Drawing Plans
e. Drawing Plans
i. Plant Location / Vicinity Map
• Complete installation drawings of the
equipment subject of TSI;
ii. Plant and/or Room Lay-out
Pressure Vessel
Boiler
Turbine
Elevator/Dumbwaiter
Pressure Vessel
Boiler
Internal Combustion Engine
Turbine
Elevator/Dumbwaiter
Pressure Vessel
Boiler
Internal Combustion
Engine
Turbine
Elevator/Dumbwaiter
Pressure Vessel
Boiler
Turbine
Elevator/Dumbwaiter
Pressure Vessel
Boiler
Turbine
Elevator/Dumbwaiter
Crane & Hoist
Pressure Vessel
Boiler
Turbine
Elevator/Dumbwaiter
Pressure Vessel
Boiler
Turbine
Elevator/Dumbwaiter
e. Drawing Plans
i. Plant Location / Vicinity Map • Dimensions reflected should support the
ii. Plant and/or Room Lay-out
values stated in the foundation design
calculation
iii. Installation drawings of
equipment
iv. Equipment Specifications
v. Detailed foundation
construction
drawings • if the equipment is in elevated structure,
vi. Foundation design calculation
accept structural analysis with added
conditions:
- with a conclusion on the stability of the equipment;
- Certification that the equipment being applied was considered as load in the
computation, this certification must be signed and sealed by a PME
ASPECT OF EVALUATION
e. Drawing Plans
i. Plant Location / Vicinity Map i. Weight of the equipment & accessories
ii.
iii.
Plant and/or Room Lay-out
Installation drawings of
ii. Weight of content based on volumetric
equipment capacity (heaviest condition)
iv. Equipment Specifications
v. Detailed foundation iii. Base Area of the foundation
construction drawings
v. Weight of concrete
Wf’ = = 10,393.92 kgs.