Professional Documents
Culture Documents
This project has been approved and accepted in partial fulfilment of the requirements
for the award of a Bachelor of technology (B.TECH) Degree in Civil Engineering.
THIS PIECE OF
WORK IS
DEDICATED TO
MY LOVELY ONES
this report with thanks, to those who taught us a lot and even to those who were kind
enough to make this professional experience a profitable moment. This report is the
result and the effort of several persons, which with their absence could not be
possible.
In addition, we thank:
This work will not be a success without the commitment of Mrs. ESSIMI
To my parents Mr. FOSSOUO KAMGA and WETE Adeline for their moral
To all those who gave us precious support throughout our training and have not
been mentioned here, we would like to send them our sincere thanks.
RESUMEABSTRACT
The research aim expresses the intention or an aspiration of the research study, it
summarizes in a single sentence what you hope to achieve at the end of a research
project. Any student who is completing B-TECH (Bachelor of technology) is expected
to produce and submit an end of year report in order to deepen their knowledge and
better understand the professional world. Roads play a very important part in any
nation’s infrastructure. Their construction and maintenance, and the vehicles that
travel over them, consume large amounts of energy. Concrete roads are durable and
safe. They are considerably less prone to wear and tear defects like rutting, cracking,
stripping and potholes that can occur with flexible pavement surfaces. To make our
project feasible, we first did site investigation
ACKNOWLEDGMENTS...................................................................................................................3
ABSTRACT.........................................................................................................................................4
RESUMEABSTRACT........................................................................................................................4
RESUME..............................................................................................................................................5
INTRODUCTION...............................................................................................................................8
MOTIVATIONS OF THE TOPIC.................................................................................................9
PROBLEM STATEMENT...........................................................................................................10
OBJECTIVES OF THE PROJECT.............................................................................................11
CHAPTER I : LITERATURE REVIEW........................................................................................12
SECTION 1: HISTORY OF PAVEMENT..................................................................................12
A. ROMAN ROADS...............................................................................................................12
B. TELFORD..........................................................................................................................14
C. MACADAM.......................................................................................................................14
PAVEMENT DEFINITION:................................................................................................15
TYPES OF PAVEMENT STRUCTURES...........................................................................16
SECTION 2: HISTORY OF CONCRETE ROAD.....................................................................20
CHAPTER II : MATERIALS AND METHODS............................................................................20
SECTION 3: HISTORY OF BITUMINOUS ROAD..................................................................22
Patented roadways.....................................................................................................................22
Changing techniques in the production and construction......................................................23
ROAD PAVEMENT STRUCTURES..................................................................................24
CHAPTER II: DESIGN OF PAVEMENT STRUCTURES...........................................................26
I. DESIGN OF PAVEMENT STRUCTURES:.......................................................................26
II. DESIGN PARAMETERS.................................................................................................28
III. DESIGN METHODS.........................................................................................................30
IV. DESIGN OF PAVEMENT THICKNESSES...................................................................37
CHAPTER III : MATERIALS AND METHODS..........................................................................38
1. MAIN OBJECTIVE:
Our main objective is to do a comparative analysis between concrete road and
bituminous road.
2. SPECIFIC OBJECTIVES:
A brief view of how pavement design, construction and performance has evolved
should help provide perspective on present and possible, future practice. This short
view into the past will start with the Romans, and then moved on to the Macadam and
Telford era, then into the first 150 years of asphalt and Portland cement concrete
pavement. The evolution of pavement design will emphasize the U.S.A and U.K and a
bit more than for other parts of the world.
A. ROMAN ROADS
In fairness, the Carthaginians are generally credited with being the first to construct
and maintain a road system. The romans eventually decided that their neighbors
across the Mediterranean were a bit of a threat to the empire destroying Carthage (the
Carthage ruins are located in Tunisia (Northern Africa) next door to Algeria (on the
left) and Libya (on the right- so to speak).) It is suggested that the Romans took up the
practice of a military road system from the Carthaginians. It is estimated that the
Romans built about 87,000 km of roads within their empire (about equal to the length
of the U.S.Interstate system).
Apparently, there is no record of “traditional” roads in the U.K. prior to the Romans.
For the most part, the main Roman roads in the U.K. (total of about 4100 km) were for
military purposes in that they connected camps which were about 30 km apart (or
about one day’s march). Since the primary purpose of these roads was for foot
soldiers, the roads were straight, but virtually without regard to grade. They generated
high noise levels, were rough and labor intensive (slave and “statue” labor often used).
The Roman design for their primary U.K. roads generally consisted of four layers (top
to bottom) as follows:
Summa Crusta (surfacing): Smooth, polygonal blocks bedded in underlying layer.
Nucleus: A kind of base layer composed of gravel and sand with lime cement.
Fig 1: cross sectional of ancient Roman road Fig 2: ancient Roman road
Roman road construction was not expensive. Updated construction estimates of the
Appian Way in Italy are about Rs.124, 000,000 per km. the oldest known road in the
U.K is near the River Brue in southwestern England. Actually, the “road” is a 6,000-
year-old walkway, which was discovered in 1970 in a peat bog. The construction of
the road coincides with the arrival of the first farmers in the U.K. about 4,000 B.C.
B. TELFORD
Thomas Telford served his apprenticeship as a building mason. Because of his, he
extended his masonry knowledge to bridge building. During lean times, he carved
gravestones and other ornamental work (about 1780). Eventually Telford became the
“Surveyor of Public Works” for the county of Salop, thus turning his attention more to
roads. Telford attempted, where possible, to build roads on relatively flat grades (no
more than 1 in 30) in order to reduce the number of horses needed to haul cargo.
PRESENTED BY MAKUATE FOSSOUO CARELLE FRANKLYN 13
Further, the pavement section was about 350 to 450 mm in depth and generally
specified in three layers. The bottom layer was comprised of large stones (100 mm)
wide and 75 to 180 mm in depth). Figure 3 shows cross section of Telford.
It is this specific layer, which makes the Telford design unique (Baker, 1903). On top
of this were placed two layers of stones of 65 mm maximum size (about 150 to 250
mm total thickness) followed by a wearing course of gravel about 40 mm thick (refer
to figure 2). It was estimated that this system would support a load corresponding to
88 N/mm (500 Ib per in.of width).
C. MACADAM
John Macadam (born 1756) observed that most of the “paved” U.K. roads in early
1800s were composed of rounded gravel (Smiles, 1904). He knew that angular
aggregate over a well-compacted subgrade would perform substantially better. He
used a sloped subgrade surface to improve drainage (unlike Telford who used a flat
subgrade surface) on which he placed angular aggregate (hand-broken, maximum size
75 mm) in two layers for a total depth of about200 mm (Gillette, 1906). On top of this,
the wearing course was placed (about 50mm thick with aggregate size of 25 mm)
(Collins, 1936). Macadam’s reason for the 25 mm maximum aggregate size was to
provide a “smooth” ride for wagon wheels. Thus, the total depth of a typical Macadam
pavement was about 250 mm (refer to figure 3). An interesting quote attributed to
Macadam about allowable maximum aggregate sizes was that “no stone larger than
will enter a man’s mouth should go into a road” (Gillette, 1906). The largest
PAVEMENT DEFINITION:
Pavement is the actual travel surface especially made durable and serviceable to
withstand the traffic load commuting upon it. Pavement grants friction for the vehicles
thus providing comfort to the driver and transfers the traffic load from the upper
surface to the natural soil. In earlier times before the vehicular traffic became most
regular, cobblestone paths were much familiar for animal carts and on foot traffic
load.
There are three types of pavements based on design considerations that is flexible
pavement and rigid pavement. It is important to know about them, details of these two
are presented below:
a) Flexible pavements:
Flexible pavement can be defined as the one consisting of a mixture of asphaltic or
bituminous material and aggregates placed on the bed of compacted granular material
of appropriate quality in layers over the subgrade, the bituminous material is more of
the asphalt whose viscous nature allows significant plastic deformation. Most asphalt
surface are built on gravel base although some full depth asphalt surface are built
directly on the subgrade. Water bound macadam roads and stabilized soil roads with
or without asphaltic toppings are examples of flexible pavements. Depending on the
temperature at which it is applied asphalt is categorized as hot mix asphalt HMA
warm mix asphalt or cold mix asphalt. Flexible pavement is so named as the pavement
surface reflects the total deflection of all subsequent layers due to the traffic load
acting upon it.
The design of flexible pavement is based on the principle that for a load of any
magnitude, the intensity of a load diminishes as the load is transmitted downwards
from the surface by virtue of spreading over an increasingly larger area, by carrying it
deep enough into the ground through successive layers of granular material. Types of
flexible pavements are conventional flexible pavement and full-depth asphalt
pavements.
Minor variations in subgrade strength have little influence on the structural capacity of
a rigid pavement. In the design of a rigid pavement, the flexural strength of concrete is
the major factor and not the strength of subgrade. Due to this property of pavement,
when the subgrade deflects beneath the rigid pavement, the concrete slab is able to
bridge over the localized failure and areas of inadequate support from subgrade
because of slab action.
Concrete pavement design in the United States started with the first concrete street
built in 1892. An older Portland Cement Concrete street. This is actually the Sunset
Highway in Washington, paved in 1919.
In turn of this century (1900), cements were categorized as “organic” or “artificial”.
Natural cements were created directly from specific rock. Artificial cement was
created from proportioned ingredients and became famous as “Portland” (named after
the pure limestone found on Portland Bill, which is a little projection of property into
the English Channel near Weymouth in the southern U.K. shore). The first authentic
Portland cement has been produced in the U.K. roughly 1824 (really, Joseph Aspdin, a
bricklayer in Leeds patented Portland cement in 1824, U.K) and in the U.S. roughly
1865 (in Tillson, 1900).
Interestingly, Portland cement concrete (PCC) was not utilized as a sidewalk-wearing
course considerably until later about 1910 (Agg, 1940); nonetheless, it had been
frequently employed as a “stiff” foundation to encourage other wearing courses like
wooden blocks, bricks, cobble stones, etc.. One likely reason for this is the absence of
a consistent specification for its early cements. Tillson in 1900 summarized over 109
distinct specifications on Portland cement fineness. Add to this confusion the fact that
organic cements were widely utilized too (roughly 60 percent of total cement
consumption in 1898). Further, the PCC hand mixing was still typical in 1900, which
definitely restricted productivity and precise proportioning. From 1900 (as mentioned
by Tillson), it had been standard to volumetrically proportion PCC as a 1:2:4 or 1:2:5
(cement: sand: coarse aggregate).
A quotation from Baker (1903) is of interest:
“This kind of street surface is not likely to come in overall usage owing to its price
and slipperiness when laid as are sidewalks, and its price and lack of durability when
laid like the foundation of a sidewalk.”
Hubbard (1910) sheds additional light on using PCC as a surfacing layer:
“If motor traffic alone were to be considered, a street built entirely of cement concrete
might prove the most satisfactory and most economical form for your future. For
mixed traffic (horses and motor vehicles), nevertheless, such a street is by no means
ideal as well as in spite of the increase in motor vehicles, the amount of horse drawn
vehicles will not appear to be decreasing…”
A 1916 report from Agg and McCullough to the lowa State Highway Commission
further illustrates a number of those issues, which held back the use of PCC as a
wearing course. These include: A quotation in the Agg and McCullough report is
useful: “Expansion and contraction might cause longitudinal fractures but normally,
The first bituminous mixtures produced in the United States were used for sidewalks,
crosswalks, and even roads starting in late 1860s. In 1870, a Belgian chemist named
Edmund J. DeSmedt laid the first true asphalt pavement in this country, a sand mix in
front of the City Hall in Newark, New Jersey. DeSmedt’s design was patented after a
natural asphalt pavement placed on a French highway in 1852.
DeSmedt went on to pave Pennsylvania Avenue in Washington, DC, a project that
included 54,000 sq. yds. Paved with sheet asphalt from Trinidad Lake Asphalt. The
durability of this pavement proved that the quality of the asphalt found in the
Americas was as good as that imported from Europe.
Patented roadways
Builders, quick to see the advantages of asphalt, tried to stake out claims to the
material. “Looking back from today’s marketplace, where Hot Mix Asphalt (HMA) is
compared and classified only by its technical qualifications, it is difficult to
comprehend that until 70 years ago, competing proprietary brands of HMA were
peddled, touted, and huckstered with all the enthusiasm that now is used to advertise
soft drinks,” writes Gillespie.
Nathan B. Abbott of Brooklyn, New York filed the first such patent in 1871. In 1900,
Frederick J. Warren filed a patent for “Bitulithic” pavement, a mixture of bitumen and
aggregate; despite vigorous efforts by the Warren Brothers Company to defend its
patent (and the name of the material), “bitulithic” was often used to describe any
asphalt pavement. Other trade names for asphalt mixes included Wilite, Romanite,
National Pavement, Imperial, Indurite, and Macasphalt. Many of these patented mixes
were successful and technically innovative.
The fierce competition among asphalt producers, however, allowed cities to require
more stringent requirements for their asphalt roadways. In 1896, for example, New
York City adopted asphalt paving in place of brick, granite, and wood block.
However, it also required 15-year warranties, which did not recognize pavement
failures caused by factors beyond the asphalt contractor’s control, bankrupted many
builders. The result was fewer and higher bids for asphalt pavements.
The patents for “bitulithic” pavement expired in 1920, and subsequent improvements
in pavements by Federal and state engineers forced most of the remaining patented
pavements from the market.
Until about 1900, almost all asphalt used in the U.S came from the natural sources of
Lake Trinidad and Bermudez Lake in Venezuela. Refined petroleum asphalt, used
initially as an additive to soften the natural asphalt for handling and placing, made an
appearance in the mid-1870s and slowly gained acceptance. By 1907, production of
refined asphalt had outstripped the use of natural asphalt.
Meanwhile, as the automobile grew in popularity, local and state governments were
besieged by requests for more and better roads. This demand led to innovations in
both the production and laying of asphalt. Roadway testing gradually became an
accepted practice thanks to the efforts of Logan Waller Page, who had studied the
procedures in France.
The earliest HMA production units consisted of shallow iron trays heated over open
coal fires. The operator dried the aggregate on the tray, poured hot asphalt on top, and
stirred the mixture by hand. The quality of the mix usually depended on the skill and
experience of the operator. The first mechanical mixers were used in Paris in 1854,
but they were crude and required four hours to produce just one batch of asphalt.
The Cummer Company opened the first central asphalt pavement production facilities
in the U.S in 1870; by the end of the century, builders on both sides of the Atlantic
were producing mixers and dryers in a variety of forms. While some asphalt producers
tried to develop portable machines, others turned to units mounted on railroad cars,
most production facilities were costly and cumbersome, limiting the areas in which
asphalt pavement was readily available.
3. Level of earthworks: surface of the upper part of the earthworks supporting the
subgrade (if present).
4. Form layer: layer located between the upper part of the earthworks and the
pavement layers, making it possible to homogenize the characteristics of the
support soil, to achieve and sustain the geometric, mechanical, hydraulic and
thermal performances taken as assumptions in the design and the sizing
calculation of the roadway. The sub-layer can be made of materials in place or
added, treated or untreated.
11. Cement concrete structures: structures with a cement concrete base layer of
more than 0.12m.
13. Interface: contact surface between two layers of pavement, of the same or
different nature. In the dimensioning method, the mechanical operation of the
interfaces can be glued, sliding or semi-glued type depending on the materials
in contact. The interfaces are also assumed to be closed, the interfaces are also
assumed to be closed, the consideration of other physical situations being
ensured by means of adjustment coefficients.
15. Slippery interface: horizontal shear stresses are assumed to be zero. The
deformations in the plane of the interface are then discontinuous.
The pavement structure is a stack of more or less thick materials, arranged in one or
more well-individualized layers each having a determined role. Its function is to resist
the mechanical actions of vehicles as long as possible, to attenuate the loads reaching
the adjacent layers, to protect the platform soil which is of low bearing capacity and
sometimes very sensitive to water. Depending on the mode of transmission of the
loads, they can be classified in an arbitrary way into three main categories:
Flexible structures: they have a certain deformation under load but a sufficient
thickness.
Rigid structures: Generally, thin, they are covered with a concrete slab giving
them a high modulus of elasticity.
There are also some which acquire their rigidity in the balance between the
improved cohesion of different layers and the importance of the thickness
overall body of the roadway. These are semi-rigid structures.
1. Flexible structures:
They are capable of deforming to a greater or lesser extent when passing rolling loads,
thus making it possible to locate the pressures induced in a small radius. To reduce the
maximum stresses reaching the ground support, it is therefore necessary to increase
the thickness of the roadway. Thus, flexible pavements are of great thickness arranged
in several layers of improved geotechnical quality from bottom to top.
Platform floor: The setting up constitutes the execution of the earthworks in
the soil. It is either the ground in place when the road is in cut, or the ground
brought up when it is in backfill. In general, we consider the layer to be 30cm
thick; it is improved when it is very compressible or weakly wearing.
The top layer: it is the filler material to be put in place to compensate for the
insufficiency of the natural soil. It also makes it possible to improve the
bearing capacity of the soil, to be considered in the design. It protects it against
The foundation layer: its main role is to reduce the loads that are transmitted to
the platform. It only supports vertical constraints; its implementation work is
less neat than the upper layers. However, it must be less deformable and more
resistant than the underlying layers. A common practice consists in making its
lower part not very permeable in order to evacuate water, which could have
infiltrated the base layer; this zone also prevents the capillary rise of water
from the platform.
Base coat: at its level, the forces due to the traffic are still very important, even
the effects of the environment are not entirely amortized; also, the materials
used must be of good geotechnical qualities i.e. a suitable grain size to avoid
segregation during the various manipulations. Good resistance to forces by
internal friction, for this, it must be formed of aggregates that are harder and
more resistant the greater the loads. The main role of this layer is to increase
the load bearing capacity of the structure because of the importance of its
thickness and the quality of the material sometimes improved. It contributes to
the flexural rigidity and overall resistance to fatigue, it helps to drain water and
resist erosion of all kinds.
2. Rigid structures:
Thanks to their great cohesion, these structures by their slab effect: they transmit loads
with a relatively large pressure surface. Thus the forces reaching the underlying layers
are weaker than the slab thickness which is high. They consist of a slab resting, either
directly on the natural soil or through a subgrade.
Natural soil: the platform floor, when called upon to support the slab, must be
protected from shrinkage or swelling movements. Likewise, embankments
3. Semi-rigid structures: these are hybrid structures: there are very low-dose
concrete pavements, covered with hydrocarbon pavements or even flexible
pavements, some layers of which are stabilized with bitumen or cement. They
are more flexible than conventional concrete but less resistant. On the other
hand, they are based on sufficiently thick foundations.
The design load is that of the most stressed wheel which would tackle the
structure during its lifetime. It is obtained after a statistical analysis of the
traffic, integrating the economic factor. It is then increased to take into account
the dynamic effects.
2. The design life: the life span of the pavement is the number of years between
the base year and the year during which the structure reaches its limit state
(complete failure). A structure, which have exceeded its life span chosen for
any project, is directly related to the investment strategies of the building
owners.
4. The environment: it is an important factor, the hydric state of the subsoil and
climatic data have an influence on the resistance, durability, deformability of
pavements and their support. The sizing must undergo a freeze/thaw check
according to the geotechnical location of the project and its exposure to winter
rigors.
e=
100+150 √ p (75+50 log ( 10N ))
CBR+5
N = Average daily number of vehicles of greater than 1500 Kg
P = Weight of the wheel in tons
The disadvantage of an empirical method is that it can be applied only to a given set
of environmental, material, and loading conditions. If these conditions are changed,
the design is no longer valid, and a new method must be developed through trial and
error to be conformant to the new conditions.
Table 1: traffic classes as defined by the CEBTP for French African countries
(CEBTP 1984)
The AASHTO method : The American method of roadway design AASHTO
(American Association of State Highways and transport Officials) is based on
an empirical analysis of the AASHO Road test realized at the end of the 1950s
on more 500 test section of the roadway [M Diak 2007]. They are usually
expressed with the formula:
log [ ∆ pSI ]
4,2−1,5
log W 18=Z R × S o +9,36 log ( SN + 1 )−0,2+
1094
0,4+ ¿
¿¿
The role of the equation is to establish a relation between structural characteristics and
the evolution with time of the level of quality of the roadway; PSI (Present
serviceability Index). It expresses the lifespan of the application of a reference axle
W 18 with the lost in quality defined by ( ∆ pSI ). The input parameters of the equation
are :
The structural number (SN) which represent structural thickness of the roadway
The resilient modulus M R of the subgrade
Due to the complexity in the behavior of roadways, a dispersion corresponding to the
error So on the real lifespan is considered. To take into account this error, the equation
is calculated according to the probabilistic mode and utilizes a multiple of this error,
which depends on the degree of the risk, which the user is ready to accept.
The CEBTP Guide: based on the African experience, the Experimental Center
for Research and Studies of Building and Public Works (CEBTP) in France,
proposes a table giving the thickness of pavements and the type of coating
according to traffic and CBR. This experiment considered of a general study of
the behavior and reinforcement of 7000 km of asphalt pavements in Tropical
Africa, since 1969. The input parameters are:
- Traffic
- The nature of the soil of the structure
- CBR
Traffic is defined according to the degree of precision of the available data by:
- Daily traffic, all vehicle categories combined.
- Cumulative heavy vehicle traffic (vehicle with a payload equal to 3T).
- The cumulative traffic according to the axle equivalents, taken from AASHTO
tests
SECTION 1: METHODOLOGY
This section will represent the set of step that we will implement to carry out the study
of this project. The simplest comparison is the quantified one. Therefore, we tried to
back up our remarks by the economic study of certain particular sections. In practice,
new road construction cannot be done without an economic analysis of the placed to
be served to define its level of service. We assumed this phase had already been
completed, and considered the traffic. After having defined what we mean by rigid
structure and flexible structure, we studied their different constituent elements, and
then analyzed their behavior under traffic. However, as the construction of a road is
very often guided by the availability and the nature of the materials, as well as the
environment, one cannot be omitted from these. In addition, we have estimated a
simple analogy certain factors relating to the climatic context within the framework of
the dimensioning. In this part, we have reviewed various methods to retain only those,
which seem to us better adapted to the environmental conditions, an economic
analysis allowed us to compare the construction costs, having no information about
the maintenance costs in Cameroon, they are not included. Throughout this study, we
have tried to be realistic as much as possible.
III.2.1.3 Principle:
The preparation can be done in two different ways:
By quartering or manual splitting of a quantity of material. This method is to be
used when there are large quantities of material.
By means of “sampler” dividers, devices, which separate a determined quantity
of material into, equal parts.
III.2.1.4 Equipment:
Balance whose limit capacity is compatible with the masses to be weighed and
which perform all weighing with a relative accuracy of 0.1%
Shovels and trowels.
A bag, which is used for the laying of the material.
III.2.2.1. Definition:
Set of operations resulting in the separation according to their size of the elements
constituting a sample, using a square mesh sieves in order to obtain a representation of
the distribution of the mass of particles in the dry state according to their size.
III.2.2.3. Principle:
The test consists of dividing, by means of a series of sieves, a material into several
granular classes of decreasing size. The masses of the various refusals and sieves are
related to the initial mass of the material. The percentages thus obtained are used in
graphical form.
III.2.2.4. Equipment:
An 80µm mesh sieve for washing the sample.
Tubs and water for washing.
The oven for drying.
A set of interlocking sieves with square opening meshes in accordance with the
standard NF ISO 565.
Lid and sieve bottom of the same diameter as the sieves.
Containers made of non-alterable material, brush, and paintbrush.
Electronic balance.
III.2.2.5. Procedure:
The material is pre-washed in the 80µm sieve to remove any impurity.
It is dried in an oven at 105⁰ for 24 hours.
Then put the material in the larger sieve.
You can either place the sieves on the vibrio-sieve or activate the device or you
can vibrate the sieves manually.
III.2.3.1. Definition:
Determine the remarkable water contents located at the borders between different
states of a soil, which are the “Atterberg limits”: Liquid limit, WL (border between
plastic and liquid state): Plastic limit, WP (border between solid state and plastic).
III.2.3.3. Principle:
The test is carried out in two phases:
Research of the water content for which a groove made in a soil placed in a
cup of imposed characteristics closes when the cup and its contents are
subjected to repeated shocks.
Research of the water content for which a roll of soil, of fixed dimension and
made manually, cracks.
III.2.3.5. Procedure:
Preparation of the sample
In a container, soak at least 250g of the sample and leave for 24 hours. Then sift
through a 400µm sieve in a tank and collect the sieve. Leave to settle for 24 hours.
Dry in an oven for 24 hours. The material is ready for testing.
Plastic limit
The sample is mixed with varying amounts of water; a roll 6 mm diameter is shaped
with the dough for about a hundred mm in length. Then we reach 3mm in diameter by
rolling it (often with the fingers), after 5 to 10 back and forth trips maximum. The
plastic limit is the percentage water content of the roll, which cracks and breaks when
it reaches a diameter of 3mm. Then take, place in a petri dish of known mass, weigh
and place in an oven set at 105⁰c.
Liquid limit
The soil is mixed with a quantity of water. The paste obtained is placed in a cup
approximately 100mm in diameter. A standardized groove is drawn on the smoothed
dough with a special tool. Using a cam, the cup is subjected to a series of shocks. At
the end of the experiment, the contact of the two lips of the groove is observed. The
PRESENTED BY MAKUATE FOSSOUO CARELLE FRANKLYN 42
liquid limit is the water content in percentage, which corresponds to a closure in 25
shocks.
Then take, place in a petri dish of known mass, weigh and place in an oven set at
105⁰c.
III.2.4.1. Definition:
The density of solid soil particles ( ρ s) is the quotient of the mass of these solid
particles (ms) by their volume ( v s).
ρ s=ms /v s
III.2.4.3. Principle:
The mass of the particles is obtained by weighing. The volume is measured with a
pycnometer.
III.2.4.4. Equipment:
Oven
Electronic balance
2mm square mesh sieve with opening
Cups for drying the soil
Mortar and pestle
Pycnometers
Reserve of distilled water
A vacuum effecting the vacuum
A thermometer
III.2.5.1. Definition:
It is a geotechnical test, which allows determining the water content necessary to
obtain the maximum dry density of a granular soil (or not) by compaction at a fixed
energy (ram’s weight, number of strokes and standardized dimensions).
III.2.5.4. Equipment:
A CBR mold
Dame proctor modified
A ruler to level
Homogenization tanks
A 20mm sieve
A trowel
A graduated cylinder
Tares
An electronic balance
An oven set at 105⁰ C
III.2.5.4. Procedure:
All the material sampled is, if necessary, dried in air or in an oven set at 50 ⁰ C
maximum until a water state considered sufficiently dry to start the test
After drying, the material is sieved at 20 mm and only the sieve is kept for
carrying out the test
The material is homogenized and divided by visual assessment into least five
equal parts
The parts are humidified to a water content such that the water contents of at
least three parts and at most four are distributed between 0.8 W OPM and 1.2 W OPM
Join together: mold , base and extension
Lubricate the walls of the mold, if necessary
Place the spacer disc at the bottom of the CBR mold
Place a filter paper or plastic film on the spacer disc the CBR mold to facilitate
demolding
Then introduce the quantity of material so that the height of the first layer after
compaction is slightly greater than a fifth of the height of the mold
PRESENTED BY MAKUATE FOSSOUO CARELLE FRANKLYN 45
Compact this layer with the corresponding dame by applying respectively 56
strokes per layer (eight series of six strokes on the perimeter and one in the
center), and repeat the operation for the five layers. Weigh it all
Carry out a new compaction at a slightly higher water content
The test ends when the mass of the mold is less than the previous one.
III.2.6.1. Definition:
The CBR (California Bearing Ratio) test allows us to perform the mechanical
characterization of natural soils and compacted soils in embankments and subgrade
layers, foundations and sub-foundations of roads and airports. It measures the shear
resistance of a soil and the swelling of the soil when submerged in water for 4 days. It
allows us to calculate the bearing capacity of the ground, by estimating its resistance
to punching.
III.2.6.3. Principle:
The principle consists in measuring the forces to be applied to a cylindrical punch to
make it penetrate at a constant speed into a test piece of tamped material. Three test
pieces groomed at 10, 25 and 55 strokes are produced.
III.2.6.4. Equipment:
Punch press
CBR molds
Proctor dame
Electronic balance
Oven at 105⁰ C
Bins
Swelling discs and overloads
III.2.6.4. Procedure:
The material is dried in the open air or in an oven
Weigh the molds empty
Then introduce the quantity of material so that the height of the first layer after
compaction is slightly greater than a fifth of the height of the mold
Compact this layer with the corresponding dame by applying 10 strokes, 25
strokes or 55 strokes on each of the molds per layer for the layers
The mold containing the test piece is then separated from its base plate turned
upside down so that the upper plate of the test piece comes into contact with
the base and the latter is again secured
Weigh the mold with the material
Position the swelling disc on the test tube before placing the overload
Set up and initialize the swelling measuring device
Immerse the whole so that the test tube is covered by a height of water at least
20mm
After 4 days, note the swelling value reached
Remove the mold from the immersion tank and after draining, proceed with
punching
Bring the upper surface of the specimen into contact with the piston
Initialize the force and sag measurement devices
Execute the punching while keeping the penetration speed constant at
1.27±0.1mm / min
Establish the force / deformation curve corresponding at least to the 0mm
depressions, 0.625mm, 1.25mm, 2mm, 2.5mm, 5mm, 7.5mm and 10mm.
SECTION 2: ECONOMIC ANALYSIS
1. COST STUDY:
Estimating the overall cost of a road project is one of the most difficult design steps,
due to the many factors involved that are usually not under control. The investment
cost is divided into two main headings.
The initial investment cost:
It is very determining, and generally the most considered by our states. It depends on
market conditions, especially on the availability of the various materials involved in
the construction. It also depends on the lifespan of the structure.
Maintenance cost:
The maintenance cost includes the cost of the various maintenance operations
scheduled during commissioning until the reinforcement carried out at the end of the
commissioning. It includes routine maintenance consisting of seasonal brush cleaning;
cleaning of ditches and culverts, as well as repairs of cracks etc.
The planned general maintenance consists of reinforcement works of longer
periodicity than usual. Its cost is a function of the lifespan; the structure index and the
quality of materials are so meticulous that maintenance becomes very low.
The overall cost of our road project is therefore the amount that we must have
available at the time of construction to carry out the work and maintain this
road during the period of planned service. The total cost of a road investment
must take into account both the initial cost and the discounted maintenance
cost. Moreover, the choice of the design year should be dictated by the
optimum of these two costs.
This part highlights all the materials we will use for the completion of this project.
Indeed, the resolutions of each step enunciated in the previous section requires the use
of very specific materials. We have among others the following materials.
I. Work Tools
We can have:
a) Documentation
Neufert:
It is a book, whose main title is les elements des projets de construction, Dunod,
Paris, 1996, for the 7th French edition. ISBN 2-10-002716-6, translation and
adaptation under the direction of P-F.C. Walbaurn, translated into French by C
Bacheré, M. Bart and U.Benderitter. Indeed, Ernst Neufert is a book that provides
information on the essential technics, projects and science of building. We used it for
the architectural design of this project, because depending on the type of building it
b) The computer:
The use of computer for the writing of a summary concerning the study of this
project.
For the application of sizing software, drawing, planning and table.
c) Internet:
We have used it as part of the manual research, documentation, methods and useful
execution process to carry out the study of this project.
MS PROJECT
Software used for planning of works in any project, we used it for the elaboration of
the estimates.
Microsoft Excel
Software used for programming tables and charts. We use it for the preparation of
estimates.
Microsoft Word
Software used for the execution of report writing, invitation ticket, vita curriculum,
business card. We used it to write a summary of the study of the said project.
Microsoft PowerPoint
Software used for developing project presentation as slides.
The results of the various cumulative weighing are recorded on a test sheet. The
masses of the various cumulative rejections Ri, are compared to the calculated total
mass of the sample for dry test Ms and the cumulative rejections percentages thus
obtained:
Ri
×100
Ms
The percentages of cumulative sieve or those of the rejects are presented either in the
form of a table and in the form of a curve.
To plot the curve, it suffices to record the various percentages of the sieves or of the
various cumulative rejects on the sheet of semi-logarithmic paper.
- On the abscissa: the mesh dimensions, on a logarithmic scale.
- On the ordinate: the percentages on an arithmetic scale.
The results thus obtained for each sample are summarized in the following table:
I P =W L −W P