Mobility, Barricades, and Facility
Mobility, Barricades, and Facility
2. Propose to have small barricade (blue dot line) to ensure everyone using dedicated pedestrian
pathway. The routing to of entrance to follow green arrow.
3. To have small barricade for all dedicated pedestrian path way where applicable.
6. Understand this shelter can be utilize for workers to have a rest, Coulomb to calculate number of
manpower and to ensure have adequate rest shelter. If required to build temporary shelter,
Hitachi Energy will communicate with SNAP according to propose location from Coulomb.
7. Propose this location as Toolbox Meeting location every morning before start the work.
9. Coulomb to clearly indicate the waste bin, the waste bin should be segregated as per minimum
requirement.
10. wind shock need to install near lifting activities will perform since site located on hills and wind
will consider during mechanical lifting