Project: 70MW CAPA WIND POWER PROJECT PHASE II

Location: Pagudpud, Ilocos Norte

Method Statement for


Dressing of Steel Poles
Revision History
Revision Date Description
0 14/April/2023 Initial Issue

Prepared By:

Noted By:

Eugenio Manarpaac Jr.

Project Manager
Project: 70MW CAPA WIND POWER PROJECT PHASE II
Location: Pagudpud, Ilocos Norte

STEPS:

A. Procedures Before Pole Dressing


1. Review the engineering plan and determine the construction point for pole dressing.
2. Check completeness of materials withdrawn at stores for the assigned pole dressing
job.
3. Check logistics requirements.
4. To avoid any inconvenience to the public, clearance shall be secured from concerned
traffic authorities or local barangay officials prior to actual work, if necessary.
5. Check existing overhead distribution/sub-transmission facilities if there is a need to
interrupt affected lines. Submit a request for pre-arranged job interruption to
operations planning unit if needed.

B. Procedures during Pole Dressing


1. The supervisor shall conduct tailgate conference before stating work, in order to
instruct linemen on the work to be done and the safety precautions to be observed.
2. Position line trucks and mechanized equipment so as not to obstruct or interfere with
vehicular traffic or driveways.
3. Post early warning devices or caution signs at the job site for safety.
4. For night work, set up the floodlights energized through a portable generator,
installed an appropriate location for optimum visibility.
5. Electrically ground all mechanized equipment using equipment supplied grounding
cable or with additional grounding clusters, if necessary.
6. Request for appropriate clearance tag when working near energized distribution
lines.
7. For work with pre-arranged job interruption, coordinate with system operation for
thew clearance to work on the interrupted line. Perform line testing on the
interrupted line then enclose the work area with grounding clusters prior to
commence with the assigned activity.
8. Install conductor covers or other insulated protective cover when working near
overhead distribution facilities.
9. For work without gondola, linemen will climb the sub-transmission pole bringing with
him a hand line which will be used for raising tools and line materials needed for
pole dressing.
Notes:
Project: 70MW CAPA WIND POWER PROJECT PHASE II
Location: Pagudpud, Ilocos Norte

1. Before and while working on the pole, the involved personnel shall
observe all the safety rules and regulations as stated in the latest
edition of the Company Safety Code to ensure their safety.
2. If there are parked vehicles under the pole, request the owner or
driver to relocate the vehicle in a safe place.

C. Installation of Pole Dressing


1. Assemble the insulators and other line hardware at the ground prior
to Installation.
2. Damaged insulators should be removed and replace. The insulators
should be clean and free contamination.
3. Insulators and hardware, when properly aligned, should fit together
without using undue force.
4. Raise the insulators and other line hardware.
5. Care should be taken in raising the insulators to avoid damage or
breakage.
6. Attach the insulators and other line hardware into the pole using
bolts specified in the engineering plan. Ensure that all machine bolt
nuts were properly tightened.
7. After the Installation of pole dressing, remove all installed pole steps
and hand line.

D. Procedures before leaving the Work Area


1. Check that all personnel are all accounted for and have climbed down
the pole.
2. Remove any installed grounding, conductor covers or other insulated
protective covers.
3. Properly dispose all water materials and clean the surroundings.
4. Remove the early warning device or caution signs posted at the job
site.