1. What is mean by project network?
2. What are the various stages in project networking?
3. Define event numbering.
4. What are the various steps in development of network?
5. What is work break down structures?
6. What is mean by CPM?
7. Define earliest event time.
8. Define float.
9. What are the Grapical guidelines for network?
10. Define start and finish time of activity.
PART B
9 7 15
7 5 9
4 66
UNIT III
PART A
1. What is mean by cost model?
2. What is direct and indirect cost?
3. Define total project cost.
4. What is mean by cost optimization?
5. Define Resource allocation.
6. What is mean by resource leveling?
PART B
1. Explain in detail about cost model.
2. What are the various types of cost model in a project management?
3. Define cost optimization and various steps involved in it.
4. What are the various resource analysis in a construction project management?
UNIT IV
PART A
1. Define PERT
2. Explain probability and statistics.
3. What is mean by probabilistic time?
4. What is mean by critical path?
PART B
1. Explain in detail about PERT
2. Explain in detail about various activities in PERT.
UNIT V
PART A
1. Define computerized project management.
2. What are the various steps in computerized project management?
3. What are the resources available in project management?
4. Define project tracking.
5. How to analyze the financial progress.
PART B
1. Explain in detail about the computerized project management.
2. Explain the various steps involved in computerized project management.
3. What is mean by project tracking? Explain.
4. Explain in detail about reporting on progress.