PORTFOLIO (ALL MINING & NON-MINING PROJECTS)project type

BCCL CCL CIL ECL MCL CHP ERP & IT MIXED OPEN CAST RAILWAY

NCL SECL WCL RLS SOLAR UNDERGROUND WASHERY

TOTAL PROJECT PROJECT COST (Crs) CAPITAL EXPENDITURE (Crs) TOTAL CAPACITY (MTY)

16 13,172.67 817.74 51.26


PROJECT STATUS (SUBSIDIARY WISE) PROJECT STATUS PROJECT TYPE

UNDERGROUND
1
1 OPEN CAST
10 MIXED
6 CHP
ECL 6 10
6

DELAYED ON SCHEDULE DELAYED ON SCHEDULE

Excel

PROJECT DETAILS
NAME TYPE CAPACITY(MTY) CAPITAL(Crs) EXPEN.(Crs) FIN. PROG PHY. PROG SCH. START SCH. FINISH ANT. FINISH DELAY(Yrs) STATUS
KHOTTADIH CM PANDAVESWAR 1 MTY UNDERGROUND 0.600 127.170 102.130 80.0 % 0.0 % 15.05.2011 31.03.2016 31.03.2022 6 DELAYED
MOHANPUR EXPN OC (2.5MTY) OPEN CAST 2.500 888.990 5.030 0.0 % 0.0 % 11.11.2020 31.03.2025 06.09.2025 0 DELAYED
NEW KENDA OC,1.2MTY OPEN CAST 1.200 127.720 15.550 12.0 % 0.0 % 21.10.2014 31.03.2018 31.03.2022 4 DELAYED
SIDULI OC+UG (1.63MTY+1.2MTY) MIXED 2.320 535.170 2.300 0.0 % 0.0 % 25.05.2018 31.03.2026 23.06.2028 2 DELAYED
TILABONI UG MINE (1.86 MTY) UNDERGROUND 1.860 941.850 3.340 0.0 % 0.0 % 12.02.2019 31.03.2027 12.02.2027 0 ON SCHEDULE
Bonjemehari Expansion OCP (1 MTPY) OPEN CAST 1.000 570.110 0.000 0.0 % 0.0 % 19.08.2021 31.03.2025 31.03.2025 0 ON SCHEDULE