Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 2
LIST OF FIGURES IX
PROJECT AT A GLANCE XII
ABSTRACT OF ESTIMATE XIV
EXECUTIVE SUMMARY XVIII
CHAPTER 1 ......................................................................................................................... 1
INTRODUCTION ................................................................................................................ 1
1.1 BACKGROUND ............................................................................................................ 1
1.2 SCOPE OF THE REPORT ............................................................................................. 1
1.3 KOZHIKODE SEWERAGE MASTER PLAN ............................................................. 1
1.4 PROJECT AREA ........................................................................................................... 3
1.4.1 KOZHIKODE CORPORATION ............................................................................ 3
1.5 REVISED MASTER PLAN AND ZONING ................................................................ 9
1.6.1 POPULATION PATTERN ................................................................................... 13
1.6.2 SOCIO-ECONOMIC PROFILE............................................................................ 14
1.6.3 GEOGRAPHICAL FEATURES ........................................................................... 14
1.6.4 RAINFALL & TEMPERATURE.......................................................................... 14
1.6.5 LAND USE ............................................................................................................ 14
1.6.7 DRAINAGE AND DRAINAGE PATTERN ........................................................ 15
CHAPTER 2 ....................................................................................................................... 16
PROJECT RATIONALE AND METHODOLOGY ......................................................... 16
2.1 SANITATION – VISION, STATUS AND GOALS ................................................... 16
2.2 NEED FOR SEWERAGE SCHEME ........................................................................... 17
2.3 PRESENT SEWERAGE SYSTEM- OVERVIEW ...................................................... 19
2.3.1 SEWERAGE SYSTEM TO ZONE- B OF KOZHIKODE CORPORATION ...... 20
2.3.2 SEWERAGE SYSTEM TO ZONE- A OF KOZHIKODE CORPORATION ...... 20
2.4 WATER SUPPLY FACILITIES.................................................................................. 21
2.4.1 PRESENT SYSTEM IN KOZHIKODE CITY ..................................................... 21
2.4.2 PRESENT SYSTEM IN PROJECT AREA .......................................................... 22
2.4.3 GROUND WATER SOURCES ............................................................................ 22
2.5 METHODOLOGY FOR PREPARATION OF SEWERAGE SCHEME .................... 23
2.6. FIELD INVESTIGATIONS........................................................................................ 23
2.6.1 SURVEY WORK .................................................................................................. 23
2.6.2 SOCIAL SURVEY ................................................................................................ 24
Ii
CHAPTER 3 …………………………………………………………………………………………….25
Iii
5.1 GENERAL ................................................................................................................... 60
5.2 CHARECTERISTICS OF SEWAGE .......................................................................... 60
5.2.1 INFLUENT CHARACTERISTICS ...................................................................... 60
5.2.2 EFFLUENT CHARACTERISTICS ...................................................................... 60
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 5
vi
LIST OF FIGURES
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 7
vii
5.12 Activated Carbon Filter 87
5.13 Truck for septage 89
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 8
1 Layout
2 Raw sewage
3 Details of Receiving chamber
4 Anoxic tank Layout
5 SBR
6 Filter feed tank
7 Sludge sump
8 Sludge thickner
9 Centrage sump
10 Chlorine contact tank
11 Treated water tank
12 Centrifuge structure
13 Chlorine room
14 Blower room
15 Administrtive building
16 Sludge storage tank
17 PCF and ACF unit
18 DG room
19 Security room
20 Septage tank
21 Pumping station
22 Manhole
23 Generator and control room
viii
APPENDIX
APPENDIX I - Design of STP
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 9
ix
ACKNOWLEDGEMENT
We wish to express our sincere gratitude to the Managing Director Sri. Venkatesapathy S IAS, Sri.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 10
Sreekumar.G , Technical Member, KWA Sri Jayaprakash C , Chief Engineer PPD- WASCON &
sewerage Works, Smt. Indulekhka TP, former Superintending Engineer PPD Regional office
Kozhikode, Sri Mujeeb Rahman, former Assistant Executive Engineer, PPD Regional office
Kozhikode for the valuable guidance and support.
We express our gratitude to the authorities of Kozhikode Corporation for their valuable support,
without which their endeavor would not have been possible. We extend our gratitude to M/S Jai
Group, contractor for timely completing the DGPS survey work.
We also express our gratefulness to all the PPD Regional office Kozhikode/staff for their valuable
support especially Smt. Suchithra RT , Smt. Sherlynas.K , Smt. Sruthi CK Sri Reghunathan P,
Smt.Jincy K.P , Sri.Shameem MP, Smt.Mini V.M, Smt.Saranya O, Smt.Ajitha S, Smt Abina Pradeep
,Smt Ardhra Paul for their dedication and hard work.
We trust that the project will become a reality as per the time line shown, and it would be beneficial
to reduce the pollution load on the Kozhikode corporation zone B and improve people’s living
standards.
PROJECT AT A GLANCE
Sl.
Item Description
No.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 11
8 Number of wells 2
29672360
13 Electricity charge for one year
3. SBR 150118892
CHLORINATION BUILDING
12. 3106182.7
SEWER NETWORK
27 LAYING OF SEWER NETWORK 161112320.50
TOTAL 1237498495
CENTAGE@10% 123749849.5
GST@18% 222749729
SI NO Item Amount
1 Cost of STP 235863079.4
GST@18%(1+2+3+4+5) 222749729
contingencies 2663988
significantly in the drinking water industry, but it has lagged behind in the sewerage industry.
Widespread sewage management issues and uncontrolled urbanization have both contributed to
the pollution of water resources. This has grown into a complicated problem with effects on
the environment and general health. The administration has spent the preceding few years
discussing and implementing measures to address the threat. Additionally, the National Green
Tribunal (NGT) mandated that a sewage infrastructure be put in place all throughout the state.
Local governments lack the resources and expertise to address the situation despite being
mandated by the constitution to protect the environment. Since Kerala Water Authority is a
state-wide organization with qualified and experienced professionals in Public Health
Engineering, the government has opted to assign the task to them. The Kerala Water Supply
and Sewerage Act of 1986 designates KWA as the entity in charge of collecting and disposing
of waste water. KWA may take part in the planning and implementation of sewage systems for
LSGIs in a methodical and scientific way as a knowledge partner, service provider, and central
organization. Sewerage Vertical Wing was built by KWA to meet the rising demand for waste
water management.
This Detailed Engineering Report envisions the establishment of sewerage facilities to the zone
B 1 of Kozhikode corporation to meet the sewerage demand up to the year 2053, using 2023 as
the base year and a design period of 30 years. and other factors...
The scheme covers 5.32 km2 area in Kozhikode Corporation with the design population of
128630. This proposal includes 27 MLD STP with SBR technology at Sarovaram. In the first
phase land for 3 lifting/pumping stations are available ,for a population of 43472 which covers 4
wards (Chalappuram, Moonnalingal, Palayam,Valiyangadi) Manholes at 30 m intervals and at all
densely intersections are proposed to facilitate maintenance operations. The total estimated cost
of the project including ten years Operation and Maintenance cost comes to Rs.161 crores.
CHAPTER 1
INTRODUCTION
1.1 BACKGROUND
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 17
Provision of drinking water and sanitation facilities has always been a key priority in our country
as it is directly related with the health of the community and the responsibility for providing these
services lies with the public domain. With unplanned urbanization the sewage management and
pollution of water resources has become a complex challenge to the environment as well as to the
public health. Even though Kerala State has achieved significant results in terms of improved water
supply coverage through Kerala Water Authority, the sanitation sector could not cope up with the
water supply sector. Immediate removal of sewage from its source of generation followed by proper
treatment and safe disposal into environment in an eco-friendly manner or reuse is highly necessary
to protect the public health and environment.
The purpose of this project is to plan and design a comprehensive sewerage infrastructure for Zone
B of Kozhikode Corporation in Kozhikode district. The project offers a well- planned sewerage
pipe line network for Zone B area of Kozhikode Corporation, pumping stations, and an SBR-
equipped sewerage treatment plant to ensure effluent quality meets KSPCB standards.
A master plan was prepared during 2008-2010 under KSUDP for comprehensive sewerage system
in the old Kozhikode Corporation area (before merging of Elathur, Beypore and Cheruvannur-
Nallalam panchayats). Merging of Elathur, Beypore and Cheruvannur-Nallalam panchayats in 2009
extended the boundaries of the city. The total population in 2011 increased to 6.13 lakh in the118.59-
sq.km area.
This Master Plan prepared for old corporation area divides the city based on topography,
population, density, business activities etc. into five sewer zones. Out of these five zones, Zone A&
B are already being taken up under KSUDP and AMRUT as Phase I. The master plan envisages
establishment of sewerage facilities to the whole Kozhikode city (Old corporation area) in different
phases and is designed for the year 2046 except for Phase I (KSUDP) for which the design year is
2041.
1
Area
No Zone Boundaries
inkm2
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 18
Zone Kallai
1 Sea Railway line Bhatt Road 5.8
A river
Zone Corporation
3 Sea Kallai river Beypore 7.29
C Boundary(old)
Phase I involves the construction of sewerage infrastructure for Zone A & B including a Sewage
Treatment Plant of 27 MLD capacity, to be established in Government land near Karimbanapalam
with Canoli Canal as the receiving water body. Under phase II, in order to save cost on long
pumping, decentralized STPs are proposed at five different locations with total installed capacity
of 46.5 MLD. The highest plant capacity is 15 MLD and the lowest is 2 MLD. The technologies
suggested are MBBR, SBR, and ASP (Improved version). The treated effluent quality will be much
better than that can be discharged to surface water as per SPCB norms & provision for tertiary
treatment, reuse and recycling as also being provided partly. Project envisages a total initial house
connection of 48500 No‘s. The total length of pumping main would be 30020 meter and the working
capacity of the pump sets 897.5 HP (excluding STPs). The total estimated outlay for the Master
Plan was 454.70 crores (Phase II) and 121.26 crores (Phase I). Funds for the capital cost suggested
were Centrally Assisted or Externally Aided Projects. KSUDP Master Plan envisages reclamation
and reuse of waste water at least partially through tertiary treatment as it would help Water
Conservation, reduce load on water resources, reduce pollution of water bodies caused otherwise
and will proportionately pay back the investment. However, all precautionary and
2
environmental safe guards shall be carried out to prevent health hazards through use for potable
and other prohibited uses.
1.4.1.1 LOCATION
Kozhikode is situated on the west coast of Kerala at Latitude 11°-15‘ N and Longitude 75°-47‘E.
The city is situated 434 km north of Thiruvananthapuram, the State capital, and 215 km North of
3
Kochi. The city is well connected by air, rail and road, and is approximately 678 km from the
nearest metropolitan city of Chennai. Kozhikode occupies a nodal position in the Malabar Coast
and has an undisputed economic standing of its own being the trade centre for a large and
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 20
resourceful hinterland. It is the market place of hill products like pepper, cardamom, etc. It also has
large timber yards along the banks of the Kallayi River. The Airport is located at Karipur 35km
from the city.
4
steadily risen from 1866 when it stood at 36,602 to 609224 in 2011. The family size of Kozhikode
MC is calculated as five. Among the just above vulnerable and the upper crust of the poor category,
the family size was 5.82 and 5.87 respectively. For Middle Income Group (MIG) and most
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 21
Kozhikode city alone accounts for 40 percent of the urban population in the district. In the city‘s
central area, the population density is as high as 5,280 persons per sq.km while it is 2,486 persons
per sq.km in the outer fringes of the city. The city is expected to grow at the same rate over the next
three decades.
5
1.4.1.7 LAND USE
The current land use pattern indicates that 52.27 percent of the city land is for residential use, which
comprises houses in individual plots scattered all over the city. Commercial area is comparatively
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 22
less and comprises small establishments. Large concentrations of development are found in the Big
Bazar area, similar to other cities in the State, paddy fields are used for construction purposes to
accommodate buildings. Industrial sector consists mainly of service industries and small-scale
industries; medium scale industries are concentrated in the southwest part of the city –industries
occupy 4.50 percent of the developed area. Area under public and semi- public use occupies 16.96
percent of the total area. The predominance of land use for residential purposes is expected to
continue almost at the same pattern.
1 Residential 52.27
3 Transportation 2.21
5 commercial 4.5
6 Industrial 16.96
The land use pattern indicates that 52.27 percent of the total developed area is under residential use.
With better planning and phased development, a smaller area of land could have accommodated
the existing population / properties. The present high percentage of land use for residential purposes
is due to the local preference for low-rise/low density housing.
6
1.4.1.8 SOIL TYPES
Three distinct soil types are dominant in the area. The western part of the corporation, the coastal
plain, comprises of alluvium, the fluvial plain covered dominantly by riverine, alluvium and the
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 23
uplands comprise of lateritic soil. The coastal plain in the west comprises of older costal alluvium,
recent costal alluvium, together with the present day beach sand along the coast. The recent coastal
alluvium occurs just east of the beach environment, and further east is older coastal alluvium.
The river line alluvium in the fluvial plane consists of sand, clay and silt in different proportions.
The fluvial plane occurs as flat region of paddy fields, water logged mashes, and slightly elevated
land near valley fields and streams. The valleys (paddy fields area) silt loam is observed on the
surface and organic rich clay layer exist in many areas below the top loamy layer. Most valley fill
area, which was formerly paddy fields, has been filled up for habitations in the recent years, having
deposited with lateritic soil excavated from the hillocks in the corporation itself. The fluvial plane
is mostly water logged during monsoon period and the periodical change in water levels either
through streams and rivers or through tidal channels have reflected itself in the characteristics of
the soil like colour nature and composition of the soils. The soils in the fluvial plains have darker
colour. The soils associated with the wet land marshy systems comprise of clay rich organic soils,
with free trunks and other organic rich soils.
The lateritic uplands in the area which occurs mainly to the east are mostly run off zones. Lateritic
soils are mostly gravelly and reddish in colour. The lateritic soils are generally underlain by a hard
lateritic zone and further underlain by a hard rock is encountered. The depth to the rock decreases
from the west to east. Charnokite, a granolithic metamorphic rock, forms the basement rock in the
corporation area.
1.4.1.9 DRAINAGE AND DRAINAGE PATTERN
The river system consists of Chaliyar River, Kallayi River, Korapuzha and Punurpuzha. The Kallayi
River has only a length of 22km and it has a drainage area of 96km2 originating from
Cherukkulathur village at an elevation of +45m above MSL.
The Korapuzha River is formed by the confluence of the Agalapuzha with the Punurpuzha and joins
the sea at Elathur. The Agalapuzha is more or less a backwater while the Punurpuzha originates
from Arikkankkuni at about +610m. The river has a length of 40km with a drainage area of 624km2.
Punurpuzha is a tributary of Korapuzha. It passes through the northern side of the Kozhikode
Corporation and joins the sea. There are lagoons and back waters. The low lying areas are prone to
saline erosion. Another major drainage system is the Canoly canal running along the
7
Heart of the city for a length of 11km with a width varying from 6m to 20m and depth of water in
peak summer varies from 0.5 to 2m.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 24
8
1.5 REVISED MASTER PLAN AND ZONING
Sewerage Master plan for Kozhikode Corporation was prepared about 13 years back, 2008-2009
year. Addition of 3panchayaths namely Beypore, Elathur and Cheruvannur Nallalam in 2009,
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 25
necessitated a revision in master plan and re-zoning the entire Corporation area considering the
geography, demography and availability of suitable land for Sewerage Treatment Plant.
Accordingly, corporation area is divided into 10 zones.
9
Capacit
S Zo STP STP
Zone Area y in Remarks
L nes location land
MLD
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 26
Corporat Taken up by
1 A1 Beach Area Kothi 6
ion Corporation
Former Elathur
Panchayath west area Purambo
7 E Edakkal 5 New
and Butt Road South kku land
Area
Former Cheruvannur
9 G and Beypore
Panchayath area KINFR
Beypore 20 New
A
1
H Payyanakkal Area
0
10
1.6 PROPOSED PROJECT AREA-Zone B1
The proposed area of the project is divided into zones .Zone B1 and zone B2 .Zone B1 is the
continuation of the work done earlier by KSUDP .The boundaries of this zone includes
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 27
Out of these the land of LS-7 and PH-6 have been already acquired and the work has been partially
completed. As the land of LS -8 is a private land, it has been shifted to the land of Mofussil Bus
stand which is near to it. since the land of other 4 Lifting/pumping stations are not confirmed at
present, the network design of 3 available subzones are included in the first phase of DPR.
Zone B 2 includes the following areas
11
It is located about 12 km north of Kozhikode city on the National Highway 66. It is bounded by the Arabian
Sea at the west and Korapuzha River (Elathur River) at the north, Kakkodi, Thalakkulathur panchayath at
east Kozhikode Corporation at south The Elathur River is generally considered to be the boundary between
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 28
the North Malabar and South Malabar in the erstwhile district of Malabar. At the 2011 census, Elathur
panchayath has a population of 45577 with a nearly equal proportion of Hindus and Muslims. The
panchayath covers an area of 13.58 km2, but a major portion of the area has been taken up by National
Highway 66, the State highway, rivers and the Indian Railways. The area is under Kozhikode Parliament
Constituency and Elathur Assembly Constituency.
12
1.6.1 SOCIO-ECONOMIC PROFILE
1. Kozhikode occupies a nodal position in the Malabar Coast and has an undisputed economic standing
of its own being the trade centre for a large and resourceful hinterland. It is the market place of hill
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 29
products like pepper, cardamom, etc. It also has large timber yards along the banks ofthe Kallai
River. The National Highway NH-17 passes through the city. Kozhikode, which wasan important
railhead, has become one of the busy stations with the opening of Konkan route. Thecity is an
attractive destination for considerable number of North Keralites working in Gulf countries.
Kozhikode city alone accounts for 40 percent of the urban population in the district. In the city‘s
central area, the population density is as high as 5,280 persons per sq.km while it is 2,486
persons per sq.km in the outer fringes of the city. The city is expected to grow at the
same rate over the next three decades..
This area has a mean annual temperature 27oc. The mean annual rainfall is 3100mm. The south
west monsoon occurs between May and October. There is an average 160 rainy days in a year.
Excessive rain fall causes frequent floods in rivers and canals causing submerges in low level areas.
1.6.3 LAND USE
The current land use pattern indicates that 58% of the land is for residential use which comprises
houses in individual plot scattered all over the city. Commercial area is comparatively less and
comprises small establishment.
13
Type of Land Use Area in Km2 % of Total Area
Residential 44.26 52.27
Public and Semi Public 1.23 1.45
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 30
The land use pattern indicates that 52.27 percent of the total developed area is under residential use.
With better planning and phased development, a smaller area of land could have accommodated
the existing population / properties. The present high percentage of land use for residential purposes
is due to the local preference for low-rise/low density housing.
14
1.6.4 DRAINAGE AND DRAINAGE PATTERN
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 31
Korapuzha, also known as Elathur River, is a short river of 40 km (25 mi), with a drainage area of
624 km2 (241 sq mi), flowing through the Kozhikode district of Kerala state in India. It is formed
by the confluence of two streams, Akalapuzha and Punoor puzha which originate in the mountains
of Wayanad district. The Korapuzha empties into the Arabian Sea at Elathur. The river and its main
tributaries become tidal as they near the Arabian Sea. There is heavy boat traffic over the last25 km
(16 mi) of its course. It forms part of the West Coast Inland Navigation System.
15
CHAPTER 2
PROJECT RATIONALE AND METHODOLOGY
2.1 SANITATION – VISION, STATUS AND GOALS
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 32
To address the situation of inadequate sanitation facilities to the urban population, the Government
of India has formally approved the National Urban Sanitation Policy in 2008 which envisions the
creation of totally sanitized cities and towns. The policy articulates awareness generation and
behaviour change, open defecation free cities in which all urban dwellers have access to safe
sanitation, integrated city wide sanitation planning and sanitary and safe disposal of urban wastes.
The vision of the policy is that the municipality shall be totally sanitized, healthy and liveable and
ensure and sustain good public health and environmental outcomes for all the citizens with a special
focus on hygienic and affordable sanitation. The policy articulates the following goals-
Wastewater disposal and treatment is a major problem in cities in Kerala. The wastewater from
toilets has been disposed through septic tanks and soak pits and grey form of wastewater from
kitchen and bathrooms is directly discharged into the sludge drains without any treatment. As per
Census 2011, 45.45% of the urban households have ―no drainage‖. There are 14.32% of the households
connected to centralized sewerage system. About 97.43% of the households in the urban areas of
Kerala state have a toilet within their residential premises. Almost 56.69% of them are connected
to septic tanks, 21.87% to pit latrines while households having connection to the centralized sewer
system are about 14.32%. There are both technical and institutional dimensions to the problem of
septic tanks in the state of Kerala. The septic tanks design does not comply with the national
guidelines with reference to planning, design and construction. Local masons are unaware of the
existing design and construction guidelines to construct and design the septic tanks. There are
multiple agencies involved in operation and maintenance of water and sanitation services in
Kerala.Septage management is viewed as private provision with limited role of urban local bodies.
Another set of reasons cited for urgency in taking up septage management is the occupational
hazards for emptying the septic tanks. The Prohibition of Employment as Manual
16
Scavengers and their Rehabilitation Act, 2013 has expanded the definition of workers engaged in
such sanitation works by including the practice of septic tank emptying and manual handling of
such faecal sludge. The revised Manual Scavenging Act will require states to gear up the Municipal
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 33
bodies in discharging their responsibilities effectively. In the absence of efficient waste water
treatment systems and solid waste management systems, untreated domestic and industrial wastes,
and agriculture-runoff flow into the rivers polluting the rivers in Kerala. There has been widespread
bacteriological contamination of faecal origin in ground and surface water which relate to proximity
of increasing numbers of leach pit latrines, leakages from septic tanks, washing, bathingand other
domestic activities. Hence the goals for setting a sewerage strategy for a district will involve multi-
faceted approach to cover every habitation and other institutions and establishments.This will render
adequate results in both short term and long-term development plans. If a plan hasbeen chalked out
which can provide a systematic and flexible implementation mode, stage by stageimplementation
and better control over the system can be achieved. A district level plan documentfor sewerage
prepared by KWA will create a backbone for the subsequent formation of detailed engineering
reports for ULBs.
National Green Tribunal (NGT) while considering various OAs related to pollution of river
trenches, pollution of coastal regions, pollution of ground water and restoration of water bodies in
various States and UTs has ordered that all States and UTs shall ensure that various measures are
taken to prevent the pollution of river stretches, water bodies and coastal areas on priority basis and
within specified time limits. One of the directions is to ensure 100% treatment of sewage at least to
the extent of in-situ remediation. Following this, being the agency for ensuring sewerage servicesin
the State, Kerala Water Authority (KWA) has created a separate Vertical with init exclusively
for preparation of DPR sewerage works across the State. The newly formed SewerageVertical of
KWA has prepared Preliminary Engineering Report for establishing a sewerage network/ septage
management across the State.
As per order no GO(Rt) No.352/2021/P&EA dated 16/8/2021 Administrative Sanction has been
accorded for conducting DGPS leveling survey work for 28 Urban Local Bodies and 5 DPR
preparation of 4 corporations in Kerala and Kozhikode corporation is one among them. PPD and
Sewerage Circle, Kozhikode is assigned with the task of preparation of DPR for sewerage scheme
for Elathur.
17
development. The works cover a number of substantial social needs and aim to improve the quality
of life and to protect public health and the environment. Some of the benefits and advantages of the
sewerage system are as follows:
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 34
The quality of life and the hygienic conditions in the areas where the system operates have already
improved. The operation of the sewerage system has relieved these areas to a great extent from
previous problems that were caused by the continuous emptying of cesspools. In the past, hotels
and blocks of apartments were required to empty and maintain septic tanks and soak ways. The
sewerage system provides a healthier and more appropriate way to manage liquid wastes.
Previously, all sewage waste was discharged in septic tanks and cesspits, resulting in the pollution
of the ground water of the areas where such waste was discharged. Polluted waters then ended in
the sea and caused various risks and other environmental problems. With the operation of the
sewerage system no more pollution of ground water is effected and the discharge of sewage waste
has significantly been reduced moreover, the wastewater treatment plant produces by-products such
as treated biosolids and methane. Treated sludge is used as a soil-improving substance mainly for
tree cultivations whilst methane is being used for electricity generation, covering part of the power,
required to operate the plant.
Water is a substantial natural resource for our country and it should be managed in the best possible
manner. The tertiary treated effluent at the wastewater treatment plant is reused for agricultural and
other purposes. On completion of the project, the amount of water to be saved is expected to exceed
1.45 million cubic metres per year.
The most significant advantage of the system is maintaining sustainable development, the
protection of the environment and improvement of the quality of life in our town, with a further
impact on the development of tourism and the economy in general.
As a result of the above, the sewerage system contributes to further development and increase of
the standard of living of the town of Kozhikode inhabitants. Considering all the above advantages,
18
there is no doubt that if we all cooperate at this time, ourselves and our children will enjoy a better
quality of life in the years to come and that we will secure a better environment.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 35
19
pollution in well water also. Coliform bacteria is detected in 70% of wells in Kerala and
emphasizing the need for a well-planned sewerage system
2.3.1 SEWERAGE SYSTEM TO ZONE- B OF KOZHIKODE CORPORATION
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 36
Kozhikode Corporation has taken up the Zone B sewerage project under KSUDP through the
funding of Asian Development Bank. The KSUDP Sewerage Division was formed to look into the
3 projects/ packages assigned to Kerala Water Authority to execute and operate on behalf of the
Kozhikkode Corporation. The DERs were prepared by the KSUDP with the help of WAPCOS and
tendered by the KSUDP. The work was transferred by the KSUDP to KWA at the agreement stage.
The project entrusted to KWA which consists of three packages:-
ii) laying sewerage network in part B of Zone B, with a tendered PAC of Rs.27,67,13,372/- &
iii) construction of 13.5 MLD STP at the KWA land near at Sarovaram Bio-park with a tendered
PAC of Rs. 29,08,35,000/-
Although, the work was started for the i) & ii) packages much early (ie. in 2011) lot of hindrances
were faced in executing the work. Public protests, legal issues, vigilance enquiry, non-availability
of work fronts/lands, etc. On 26-11-2015, there was a mishap happened that two labourers of M/s
Shriram EPC and one outsider died due to the suffocation by inhaling of foul gas while entering the
manhole without any protection. Thereafter, it seems to have no progress of the work in these
packages.
The agreement was signed during 3/2015, for the iiird package and the work started by August,
2015. But a person filed a petition in the Chennai Bench of the Hon‘ble National Green
Tribunal(NGT), stating that the proposed land for the construction of the 13.5 Mld STP is in the
wetland and the Hon‘ble NGT stayed the work on 18-12-2015. On 09-12-2019, the Hon‘ble NGT
has conditionally revoked the stay over the work with the condition that the matter has to be
analysed by the Kerala State Wetland Authority (SWAK). Accordingly, Kerala State Wetland
Authority granted permission for the construction of STP at Sarovaram conditionally. But due to
paucity of fund the work could not be taken up.
2.3.2 SEWERAGE SYSTEM TO ZONE- A OF KOZHIKODE CORPORATION
The project involves development of a sewerage system for Zone A of Kozhikode Corporation in
Kerala by construction of sewerage networks, wet wells, pumping stations and pumping mains. It
is being implemented under the Atal Mission for Rejuvenation and Urban Transformation
20
(AMRUT) scheme.
The packages under the project are:
- Package A: Providing, laying, testing and commissioning of underground sewerage pipes of
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 37
varying diameters, construction of a sewage pumping station and sewage treatment plant of capacity
7 MLD to treat municipal sewage wastewater including Operation and Maintenance for a period
of five years at an estimated cost of Rs 59.767 Crores
- Package B: Providing, laying, testing and commissioning of underground sewerage pipes of
varying diameters, construction of a SPS and STP of capacity 6 MLD to treat municipal sewage
wastewater including O&M for a period of five years at an estimated cost of Rs 56.379 Crores
The STPs are being constructed at Kothi and Avikkal Thodu. There had been no response to the
tenders floated the first two times. The only company that responded the third time had pointed out
flaws in the DPR and demanded ₹179 crores for the project. Though the Corporation Council
approved it, the project failed to gain government approval. A high-level committee headed by the
Chief Secretary had asked the Corporation to re-tender the project. Four separate tenders were
floated for the STPs this time, separately for the plants and collection network. Zimak Hi-tech
Productions from Maharashtra has won the tender for the two plants, a 7 MLD plant at Thoppayil
and a 6 MLD plant at Kothi, for ₹20.50 crore and ₹17.11 crore respectively. Ahmedabad-based
Nasit Infrastructure has won the tender for the collection for both the plants at ₹51.86 crore and
₹52.97 crore respectively. The total expense for both the plants and the collection network comes
to ₹142.44 crore, much lesser than the amount quoted in the earlier tender.
Due to the public protest at STP sites, the work could not be started yet.
21
Poonoorpuzha River as source. JICA assisted water supply scheme to Kozhikode and adjoining
Panchayaths was partially commissioned during 2015.
The existing major water source is Peruvannamuzhi dam, and Major Water Supply Scheme is JICA
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 38
assisted water supply scheme with intake at Peruvannamuzhi Irrigation Dam on Kuttiyadi River.
At present The Kozhikode WSS has two water treatment plants with a total capacity of 246 MLD.
Capacity of the
Location Source of water Treatment
Plant
Peruvannamuzhi
Peruvannamuzhi 174MLD Pulsator Technology
Dam
The present storage capacity of the service reservoir is 10.80 ML. The present locations of
reservoirs are at Kovoor (GLSR, 2.70 ML), Malaparambu (GLSR, 3.60 ML), Balamandiram
(GLSR, 0.90 ML) and Pottammel (GLSR, 3.6 ML). In addition to the above, new reservoirs
commissioned in the city under JICA scheme are: Balamandiram (3.18ML), Malaparamba
(9.98ML), Pottammal & Eravathukunnu South (11.58ML), Medical College Kovoor (8.09ML),
Easthill (7.49ML) and Eravathukunnu north (5.58ML).
2.4.2 GROUND WATER SOURCES
Most of the people depends ground water source, open wells and shallow tube wells for their
drinking water needs. Studies have revealed that
● Contamination was higher in the vicinity of onsite sanitation structures especially in open
22
wells situated within 10-15 m from latrines
● Social survey
General Field investigations like topographic survey, geotechnical investigation, and sewage
samples analysis to be conducted to ascertain the topography of the area, the soil classifications and
to ascertain its characteristics for designing the type of treatment, which forms the basis for
proceeding further in designing the sewerage system.
2.6.1 SURVEY WORK
Topographical Survey Topographical survey forms a very important component in formulating the
sewerage project. A detailed topographical survey has been performed covering the area using
DGPS and Total Station. Topographical survey of the project area was conducted using DGPS and
Total station. Ground Levels have been taken along the roads at suitable intervals along straight
portions and at all junctions of alignment. Important features and obligatory points like junctions
such as culverts, major drains, and public utilities, cross roads, railway line have been captured.
Using the topographical survey data and detailed base map showing the features like roads, land
marks, public buildings, parks etc. has been developed.
23
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 40
24
CHAPTER 3
DESIGN CRITERIA
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 41
The sewerage system or storm water carriage system can be separate system or combined system
or partially separate system depending on domestic sewage and rain water are drained through two
separate set of pipes or through single set of piping. However, the combined system is not quite
suitable in tropical Indian conditions as;
i) Heavy and concentrated rainfall occurs during the monsoon period and thus there is a large
variation in the quantity of sewage during different months of the year,
ii) Dry weather flow is generally a very small proportion of the total flow and hence sewers are
likely to get silted up due to low velocity of flow in lean periods,
iv) Treatment costs and pumping costs are significantly reduced in separate system due to reduction
in quantity.
v) If the system is overdesigned, external flushing to attain the areas where the self-cleansing
velocity is not attained which will increase the O&M cost. It affects system efficiency.
i) Zonal pattern in which entire city is divided into suitable zones and a separate interceptor is
provided for each zone,
ii) Radial pattern in which sewers are laid radially outwards from the center of the city to dispose
sewage at multiple points,
iii) Interceptor pattern in which sewers are intercepted by large size sewers laid along the natural
watercourses or,
iv) Fan pattern in which the STP is located at a certain point and the entire sewage flow is directed
towards this point.
Separate drainage system is proposed for rain water as such only dry weather flow will pass through
sewers. The connection of roof, backyard and foundation drains to the sanitary sewers should be
25
Avoided and hence shall not be considered for estimation of sanitary sewage. The prevalent
sewerage systems in India do receive rain water even if separate system for rain water exists but
sewers are designed for 30 years and have spare capacity in early phases of implementation and
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 42
considering that by end of 30 years‘ sewerage system will become water tight to rain water, it is
appropriate to design system assuming no rain water penetration in sewers. The quantity of
domestic sewage can be best estimated by quantity of water supply consumption minus evaporation
plus sewage flow from personal water sources which are other than those of community water
supply and this water reaching to sewers. Another important factor in Indian cities is generally less
connectivity of sewage to the sewerage system as many people continue to use on site sanitation
i.e. septic tanks and soak pits etc. particularly in colonies where sewerage system is laid after a long
gap of construction of houses which is a general phenomenon in Indian cities. In actual practice
about 70-80% of the water supplied is reaching to sewers. As such 80% of quantity of water supply
can be taken as sewage generation.
3.2.1 INFILTRATION AND LEAKAGE.
Some quantity of ground water or subsoil water may infiltrate into sewers through defective joints,
broken pipes etc. This is significant when water table is high and head of ground water is more than
the head of sewage in sewers. Some quantity of sewage may leak out from defective joints and
defective pipes when head of sewage is more in sewers than head of ground water outside.
Infiltration and leakage mainly depends on quality of construction and water table levels.
Infiltration can be considered 5000-50000 liters per day per hectare or 500-5000 liters per day per
km length of sewers or 250-500 liters per day per manhole for sewers laid below ground water
level.
3.2.2 ESTIMATION OF INDUSTRIAL SEWAGE
The quantity of industrial sewage will vary with type and size of industry, the manufacturing
processes involved, degree of water reuse and onsite treatment methods that are used, if any.
However, in general the quantity of industrial sewage may be taken 80 to 90 % of quantity of water
supplied through public water supply system. Some industries develop their own source of water
supply and may discharge their liquid waste into sewers. This should be estimated separately for
large industries. It may, however, be stated that industrial sewage should be treated to the standards
prescribed by the Pollution Control Boards before being discharged into sewers.
Sewerage projects are normally designed to meet the requirements over a period of 30 years after
their completion. However, the period of 30 years may be modified in respect of certain
26
Components of the project depending on their useful life or the facility for carrying out extensions
when required and rate of interest, so that expenditure far ahead of its utilization is avoided. As
such design period for various main components has been taken as indicated in Table below.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 43
6 Sewage Treatment Plants 30 cities initially flows are much less due
to connectivity problems
Years
27
3.4 VARIATION IN RATE OF FLOW
1 Up to 20,000 3.00
The rate of flow of sewage varies from season to season (seasonal or monthly variation), from day
to day (daily variation) and from hour to hour (hourly variation). For design of sewers maximum
or peak flow rates are adopted. The value of peak factor (ratio of maximum flow to average flow)
depends on the contributing population and the values recommended in the Manual on Sewerage
and Sewage Treatment prepared by CPHEEO are given in Table above.
The variation between maximum and average rates of flow is large for domestic and lateral sewers
because they receive the flow directly from the source. This variation gradually diminishes as the
flow reaches the branch or sub main sewers and the main sewers. Minimum rate of flow: The
minimum rate of flow may vary from 0.5 to 0.33 of the average flow.
28
3.5 HYDRAULIC DESIGN OF SEWERS
The design for sewage collection system presumes flow to be steady and uniform. The unsteady
and non-uniform sewage flow characteristics are accounted in the design by proper sizing of
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 45
manhole. The sewage is mostly liquid containing about 0.1% of solid matter and hence follows
same laws of flow as water. However the difference in design for water supply network and sewer
network is, i) In order to avoid clogging of sewers due to settlement of heavier particles of solids,
sewers are to be laid at such gradient that self-cleansing velocity is achieved at all values of
discharge and that the inner surface of the sewers should be capable of resisting the wear and tear
due to abrasive action of solid particles and ii) sewage flows under gravity as open channel flow
and as such sewers are laid at continuous downward gradient.
3.5.1 DEPTH OF FLOW
The sewers shall not run full as otherwise the pressure will rise above or fall below the atmospheric
pressure and condition of open channel flow will cease to exist. Moreover, from consideration of
ventilation, sewers should not be designed to run full. In case of circular sewers, the Manning‘s
formula reveals that:
The velocity at 0.8 depth of flow is 1.14 times the velocity at full depth of flow.
The discharge at 0.8 depth of flow is 0.98 times the discharge at full depth of flow.
Accordingly, the maximum depth of flow in design shall be limited to 0.80 of the diameter at
ultimate peak flow.
3.5.2 HYDRAULIC FORMULAE FOR DESIGN OF SEWERS
Manning‘s formula has been used for design of sewers in case of gravity flow. For pressure flow
(Pumping Mains), the Hazen-William‘s formula has been used. Sewer Network design has been
done with the help of Manning‘s Formulae i.e.
29
Velocity V= [(1/n) x (R2/3 .S1/2)] (in
m/s)For Circular Sections
V = (1/n) (3.968 x 10-3D2/3S1/2) Q = (1/n) (3.118 x 10-6D8/3S1/2)
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 46
The rate of water supply has been adopted 150 LPCD at consumer end throughout the whole
design period as water supply schemes are designed with per capita supply of 150lcd in Kerala.
80 percentof the water supply has been considered as sewage flow into the sewerage system
3.5.4 MINIMUM VELOCITY OF FLOW
A minimum velocity of 0.6 m/s for present peak flow and 0.8 m/s at design peak flow is
recommended for sanitary sewers. Thus the sewers are designed on the assumption that
although silting might occur at minimum flow, it would be flushed out during peak flows.
3.5.5 RECOMMENDED SLOPES FOR MINIMUM VELOCITY
For sewers running partially full, for a given flow and slope, velocity is little influenced by
pipe diameter. As such for present peak flows up to 30 lps, the slopes given in Table below
may be adopted which would ensure minimum velocity of 0.6 m/s in the early years.
1 2 6.0
2 3 4.0
3 5 3.1
4 10 2.0
5 15 1.3
6 20 1.2
7 30 1.0
30
3.5.6 EROSION AND MAXIMUM VELOCITY OF FLOW
Erosion of sewers is caused by sand and other gritty material in the sewer and also by excessive
velocity. Non-scouring or limiting velocities in sewers of different materials are given in
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 47
Sewers shall be designed to ensure that the energy gradient is a continuous smooth line, thus
transitions from larger to smaller diameters shall not be made. The crowns of sewers shall be
kept continuous. In no case, the hydraulic flow line in the large sewers shall be higher thanthe
incoming sewer. To avoid backing up, the crown of outgoing sewer shall not be higher than
the crown of incoming sewer
3.5.8 MINIMUM PIPE DIAMETER
Minimum pipe diameter recommended in CPHEEO manual is 150 mm except that in hilly
areas, where extreme slopes are prevalent, 100 mm can be used. Some states and ULBs have
started adopting minimum diameter as 200 mm or even 250 mm. The logic is Maintenance of
sewer system is generally not good and 150 mm dia sewer will block frequently and remain
un-attended for some time, Quality of construction in smaller size RCC main such as 150 mm
is not good ,The sewerage system is not totally closed one and undesired waste such as solid
waste and drains finds way in sewerage, making smaller size sewer lines more prone to
frequent blocking ,The cost of pipe line element is only about 15 percent of total project cost
and increase in pipe size from minimum of 150 mm to minimum of 200 mm size will increase
cost of project by 2 percent whereas flow capacity increases by more than 80 percent.
The minimum diameter may be adopted as 200 mm for cities having present / base year
population of over 1 lakh. However, depending on growth potential in certain areas even 150
mm diameter can also be considered. However, in towns having present / base year population
of less than 1 lakh, the minimum diameter of 200mm shall be adopted.
The house sewer connection pipe to public sewer shall be (a) minimum 100 mm or higher
based on the number of houses / flats connected and (b) subject to the receiving public sewer
being of higher diameter. In this project 200 mm diameter have been suggested as minimum
diameter in design of sewerage network.
31
3.6 MATERIAL OF CONSTRUCTION FOR GRAVITY SEWERS
Brickwork is used for large diameters as sewers can be constructed in any shape. However,
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 48
now it is not common. Concrete pipes are commonly used now as can be manufactured to any
reasonable strength and laying is easy and jointing is leak proof. However, these pipes are
subject to corrosion where acid discharges are carried or where velocities are not sufficient to
prevent septic conditions or where the soil is highly acidic or contains excessive sulphates.
Only high alumina cement concrete should be used when it is exposed to corrosive sewage or
industrial wastes. Salt glazed stoneware pipes are mostly manufactured in sizes 80-1000 mm
but sizes greater than 380 mm are generally not used due to economic considerations. Thelength
of these pipes is 60 cm75 cm and 90 cm. These pipes are good for corrosionresistance and
erosion resistance. However due to less length, more joints, difficulty in jointing,requirement
of special bedding and less compressive strength of pipes manufacturedin India;use of these
pipes is reducing in India.
EVALU
S.N ATION DI PIPES PE PIPES
RCC DWC HDPE
CRITE
PIPES PIPES
RIA
Simple push fit
joints with
Availabl Butt fusion Elastomeric
e in both Tyton joint With
Type of welding sealing Ring for
1 collar rubber gasket
Joint process. online system or
and S&S with extra
joints. couplers.
Very Light in
Comparison of
Heavy Light
2 Weight Lighter than R.C.C. Other Solid Wall
Pipes.
32
To
prevent
corrosion
sulphate
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 49
Corrosio resistant
Protective layers are Highly
n cement Highly corrosion
3 Required to protect corrosion
resistanc concrete resistant
corrosion resistant
e to be
used for
pipe
manufact
ure.
Smaller
diameter Uses minimal
NP2isCh pipes are material for
Remarks eapest Costlier than other cheaper equal strength,
4
on Cost among pipes but cheaper and higher therefore cost
all than HDPE pipes. diameter cheaper from
materials Pipes are other pipes.
costlier.
Infiltration is very
Infiltrati Infiltrati Infiltration is very Infiltration less
5
on on is less less is veryless
due to
heavy
Light They are user
weight
weight for friendly, very fast
6 Workabil handling Good
easy and inexpensivein
ity to be
handling. installation
done
with care
Jointing
is easy in
S&S
Jointing is easy in
pipes Jointing is Joining time is 2-5
7 Jointing S&S pipes with
with expensive minutes per joint
Rubber ring joints.
Rubber
ring
joints.
33
Almost
nil if Pipe Maintenance is
proper ma
Maintena low because of
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 50
GRP pipes are widely used in other countries where corrosion resistant pipes are required at
reasonable rates. When using concrete or reinforced concrete, high density sulphur resistant
cement should be used. These pipes are made of slag cement that contains fewer calcareous
(CaOH2) particles than pipes made of Portland cement. These particles react with the
sulphuric acid (created by bacterial dissipation of hydrogen sulphide) in sewers, causing the
aforementioned crown corrosion. If this particular cement is not used, lifetime of concrete
sewers cannot be expected more than 30 years. A comparative study of characteristics of
various pipe options for gravity sewers is presented in table above.
34
3.6.1 BENEFITS OF HDPE PIPES FOR SEWERS
When compared to other common wastewater piping system materials, such as PVC, ductile
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 51
iron, or concrete, HDPE pipe offers significant benefits. Some of these include:
Leak-free. PE pipe is joined together via heat fusion, creating a welded, leak- free joint
unlike conventional bell and spigot joints. These leak-free joints prevent infiltration and
exfiltration making it a truly sanitary piping system.
Durability.PE pipe is resistant to fatigue from water hammer and surge events in sewer
force mains. PE pipe is also abrasion resistant, ensuring that flowing water and slurries won‘t
damage the pipe throughout its service life.
Lightweight. PE pipes are much lighter in weight compared with ductile iron or
Concrete alternatives, which makes transportation and installation significantly easier and safer.
Cost-effectiveness. PE pipe is cost competitive with other sewer pipe options. HDPE pipe
is faster, easier, and safer to install due to longer cut lengths and more linear footage per truck,
which significantly reduce the overall project costs. With low maintenance costs and long
service life, PE pipe is the ideal solution for wastewater systems.
However, PE pipes are slightly costlier compare to RCC pipe but as of now most of sewer
pipes are laid through Trenchless technology method and because of this, plastic pipes like
PE/ UPVC are most suitable and easy to use for trenchless as well as open cut trench method
for pipe laying. The use of PE pipes are more economical and to be considered for smaller
diameter pipes up to 110mm where they are available on coils thereby avoiding joints. Hence
lesser number of joints thereby reducing leaks and the rates of pipes are reasonable. As a
general pipe policy decision the use of PE pipe shall be preferred up to 200mm & occasionally
upto 350mm (source- KWA pipe policy, page 19).
35
Therefore, considering the above benefits of PE pipe over RCC pipes, PE pipes are
recommended to use for maximum stretch of network. The pipe policy of KWA also favours
adoption of PE pipes. However, RCC pipe (PE lined) has been recommended for higher
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 52
diameter pipe (i.e. above 700 mm) as PE pipes for higher diameter pipes are not easily
available and very costly for large diameter and generally not manufactured.
3.7 MANHOLES
3.7.1 GENERAL
● Change of direction
● Change of slope
● Change of material
1 Up to 2.50m 1.2m
The simplest type of manhole is that built on a straight run of sewer with no side junctions.
Where there is change in the size of sewer, the soffit or crown level of the two sewers should
be the same, except where special conditions require otherwise.
36
3.7.2.2 HDPE MANHOLES
Polyethylene manholes remain leak-free because there is no chemical attack. The toughness
external ground water, reducing the amount of treatment required. There is no exfiltration of sewage
to the environment. HDPE manholes are available with ladders installed. Ladder design has been
A manhole is provided at every junction of two or more sewers, and the curved portions of the
inverts of tributary sewers have been formed within the manhole. The gradient of the smaller
sewer may be steepened from the previous manhole sufficiently to reduce the difference of
invert level at the point of junction to a convenient amount.
As per CPHEEO manual, drop manhole is to be provided when a sewer connects with another
sewer, where the difference in level between water lines (peak flow levels) of main line and
the invert level of branch line is more than 600mm or a drop of more than 600mmis required
to be given in the same line and it is uneconomical or impractical to arrange the connection
within 600mm. The drop pipe may be either outside the manhole shaft and encased in concrete
or supported on brackets inside the shaft. If the drop pipe is outside the shaft, a continuation
of the sewer should be built through the shaft wall to form a rodding and inspection eye,
whichshould be provided with a half blank flange. If the drop pipe inside the shaft, it should
be in cast iron/ductile iron and it would be advantageous to provide adequate means for
rodding and water cushion of 150mm depth should also be provided. The drop pipe should
terminate at its lower end with a plan or duck-foot bend turned so as to discharge its flowat
45 degrees or less to the direction of the flow in the main sewer and the pipe, unless of cast
iron, should be surrounded with 150mm concrete.
Where it is not possible to obtain self-cleansing velocities due to flatness of the gradient
especially at the starting point of branch sewers which receive very little flow, it is essential
that some form
The idea of RCC manholes is essentially to quicken the work of construction in the roads
37
by adopting precast sections assembled at site. Thus, the issues related to their construction
are more of design itself and quality control in casting. In general, plain and reinforced concrete
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 54
workfor manholes shall be carried out in accordance with the specification given in CPHEEO
manual otherwise specified in this specification. Wherever good quality of brick and
workmanship of the construction cannot be ensured, it is advisable to go in for RCC manholes.
The provisions ofIS: 456 and IS3370 Part I, II and IV shall inter alia apply to the design. The
entire structure shallat all times be designed to the condition where the ground water is at
ground level itself and the inside is empty and there is no superimposed load on the manhole
and not considering the skin friction of the manhole side wall with the soil.
Now the newly available precast RCC chambers shall be conveniently used for the manholes
upto6.0m or more depth. This will make the construction very easy and faster. So the same are
proposed for Kozhikode scheme.
38
A package pump station is a complete unit comprising of a chamber, pumps, pipework, valves,
control panel and level control pre-assembled as a complete unit. There are a wide range of pre-
engineered packaged pump stations including pumps, tank, piping and valve system, all installation
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 55
accessories and monitoring and control equipment. The pump stations are available ina number of
designs and sizes, and they all have in common a design optimized for trouble-free and efficient
pumping.
Since sediment build-up is unwanted in a wastewater pump station, due to odor problems, high
maintenance costs and the risk of clogging, preventing sediment and deposits is one of the main design
focuses. The design of the pump sump bottom in pre-engineered pump stations eliminates or minimizes
sediment build-up. The stations also feature a compact and small footprint, reducing civil works and
making the installation quick and easy. Packaged Pumping stations are proposed in case of lesser
sewage flow.
39
CHAPTER 4
PROPOSED SEWERAGE SYSTEM
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 56
Population of the city normally depends on factors such as birth and death rates, migration, industrial
development, general environmental conditions etc. Usually the population forecast of acity is made
on the basis of methods of population forecast as provided for in section 1.5 of the CPHEO manual for
sewerage and sewerage treatment. The latest available census records are that of 2011. As far as Kerala
is concerned it is quite different from other states on education, health, life expectancy etc. The
demographic pattern of the state therefore is quite different and need to take into account all the
developmental parameters so as to avoid undue over designs.
The anticipation of future growth in any community in terms of population or commercial and industrial
expansion forms the basis for preparation of plan for providing the amenities including installation of
sewers in the area to be served. The anticipated population, its density and its waste production is
generally estimated for a specified planning period. The recommended planning period is 30 years.
40
Table 4.1 population details
SI Ward
Ward name Population
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 57
no number (2011)
2 60 Palayam 6752
5 63 Thuruthiyad 6528
6 64 Eranjipalam 5590
7 65 Nadakkavu 6486
9 69 Karapparamba 7620
11 71 Athanikkal 7886
41
Population details
SI Ward
Ward name Population
no number
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 58
(2011)
2 14 Chevarambalam 7984
3 15 Vellimadukunnu 8838
5 26 Parayancheri 6024
6 25 Kottuli 8306
8 21 Chevayur 6024
The system has been designed using EPASWWM software. Design calculations are shown
in Annexure attached. The sewerage system network has been so planned to limit lifting and
pumping stations.
Design & estimates of the sewer collection system has prepared so as to limit the depth of
excavation and to accommodate changes in location of STP. It is proposed to have separate
collection System for each sub-Zone with a common STP
It will have 4 lifting stations and 2 Nos pumping station. Out of these the land of LS-7 and PH-6
have been already acquired and the work has been patially completed. As the land of LS -8 is a
private land, it has been shifted to the land of Mofussil Bus stand which is near to it. since the land
43
of other 3 Lifting/pumping stations are not confirmed at present ,the network design of 3
available subzones (LS7,PH6 and LS8) are included in the first phase of DPR.
Sewage collected in well of LS-7will be pumped to a MH No MH 4598. PH6, also sewage
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 60
the work the manholes should be found and necessary changes in the design should be made using
the invert level. The details of networks and manholes to be laid are given below.
Open Cut
2299.5 651 123 204.5 3278
in meters
HDD in
203 46 378.5 115.5 - 17.5 1357.5
meters
597
45
4.1.6 MANHOLES
Total number of manholes comes to 159
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 62
Up to 1.5 40
1.5 to 2.5 62
2.5 to 3.5 27
3.5 to 4.5
27
4.5 above 8
Total 164
46
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 63
In sub zone LS8 30 No of manholes and 766.5 m of sewer network have already laid. The balance
comes to around 9886m of network and 342number of manholes. Among the already lain 30 No
of manholes around 20 numbers are in underground. Therefore the exact position and invert level
of the underground manholes are not yet be found. Therefore before executing the work the
manholes should be found and necessary changes in the design should be made using the invert
level. .The details of the networks manholes to be laid are given below.
47
3 315 PE PE100, PN8 1023.3
Total 9886.5m
Table 4.6 : Details of the networks manholes to be laid
Up to 3m depth of sewer line open cutting is proposed and above 3 m depth pipe laying through
HDD method is proposed.
Open Cut
6352.3 1127.4 913- 0 0 8392.7
in meters
HDD in
799.7 271.9 110.3 191.5 - 1493.8
meters
120.4
Manhole depth in No of
Meters manholes
Up to 1.5 169
1.5 to 2.5 88
2.5 to 3.5 41
3.5 to 4.5
23
4.5 above 21
Total 342
48
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 65
49
200 250m 315mm 400m 450 500mm 710 Total
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 66
mm m m mm mm
Open - 7259
5135 410.9 611.8 483.2 618 -
Cut in .1
meters
HDD 61.9 1843
539.7 224.6 182.2 92.2 - 515.6
in
227.5
met
eres
Total 5674.7 635.5 794 575.4 845.6 515.6 61.9 9102.2
Up to 1.5 136
1.5 to 2.5 77
2.5 to 3.5 71
3.5 to 4.5
25
4.5 above 31
Total 340
50
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 67
4.2.1 GENERAL
Pumping or force mains deliver wastewater discharged from a pumping station to its destination,
which may be a treatment plant or the final disposal point.
51
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 68
Lift stations are generally used to restrict the depth of cutting and discharging normally to the
manhole in a downstream trunk sewer. No screens and grit wells are provided in lift stations.
Pumping and lifting stations shall use submersible pumps, such stations have a single well, circular
or rectangular, in which pumps are installed. Superstructure requirement is minimum. The pump
stations have been designed considering easy removal and reinstallation of the pumps without
52
disturbing the connecting delivery pipe work.
Hydraulic Criteria:
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 69
According to the existing ground level contour from the topographic survey, the number of pumping stations
has been finalized. Lift stations are generally proposed where depth of cutting exceeds 5.5 m. However, in
a few places (20 pipes) more than 5.5 m depth of cutting provided to avoid additional lifting stations. The
locationof pumping stations is at lower points of the network, but away from public and flood areas. Overflow
is not allowed.
53
Figure. 4.8 Location of Pumping Station 1
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 70
54
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 71
55
Table 4.7: Lifting station details
2 LS7 2 12 Submersible
56
3 PH6 2 65 Submersible
Table 4.14: Details of pump sets
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 73
In the following sections, important matters in connection with the laying of sewer network and
making the system efficiencies illustrated in detail.
1. On all excavation work, safety precautions for the protection of life and property are essential;
and measures to avoid too great in conveniences to the public are desirable. Such measures and
precautions include the erection and maintenance of signs (to forewarn public), barricades, bridges
and detours; placing and maintenance of lights both for illumination and as danger signals;
provision of watchmen to exclude unauthorized persons, particularly children from tress passing
on the work.
2. Computation of the safe load carrying capacity of the pipe when installed and bedded in the
manner to be specified using a suitable factor of safety and making certain the design supporting
strength thus obtained is greater than the maximum load to be applied.
3. Sewers may be laid in trenches or under embankment in areas which may be temporarily or
permanently submerged in water. The fill load in such cases will be reduced and will correspond to
the buoyant weight of the fill material. However, effect of submergence could be ignored which
provides an additional factor of safety, but it may be necessary to check whether a pipe is subject
to flotation. Under submergence, the minimum height of the fill material that will be required to
prevent flotation ignoring the frictional forces in the fill can be determined. Wherever sufficient
height of fill material is not available, anti-flotation blocks should be provided.
4. All rigid pipes may be tested for strength in the laboratory by the three-edge bearing test
(ultimate load).
5. Width of the trench specified for a particular job should be minimum in consonance with the
57
requirements of adequate working space to allow access to all parts and joints of pipe.
6. The Field Engineer should keep in touch with the Design Engineer throughout the duration
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 74
of the Project and any deviation from the design assumptions due to the exigencies of work,
should be immediately investigated and corrective measures taken in time.
7. All pipes used on the work should be tested as per the IS specifications and test certificates
of the manufacturers should be furnished for every consignment brought to the site.
8. Whenever shoring is used, the pulling out of planks on completion of work, should be carried
out in stages and this should be properly supervised to ensure that the space occupied by the
planks is properly backfilled.
10. In quicksand conditions, it is necessary to anchor the sewer to the ground and hold it at the
grade as laid in the face of soil sinkage.
11. The type of bedding (granular, concrete cradle, full concrete encasement etc.) would depend
on the soil strata and depth at which sewer is laid.
12. It is understood that the line (horizontal alignment) and grade layout of a sewer line as per
design must be carried out meticulously. The horizontal layout determines the location as well
as direction of the sewer line, while slope (grade) of the line provides the necessary hydraulic
carrying capacity of the sewerage system.
13. The location of the trench is generally laid out first as an offset line running parallel to the
proposed sewer centre line. This offset line is demarcated by wooden stakes driven into the
ground surface at intervals of, say, 15 m. The offset line, as is clear, is quite away from the sewer
centre line with a view not to allow it being disturbed during construction; however, it must be
proximate enough so that the transfer of measurements to the actual trench can readily be done.
4.2.7 GANTRY
Gantry of adequate capacity having floor control pendant will be provided for handling heavy parts
of equipment‘s, valves etc. during erection and maintenance of pumping stations. Proper opening
to lift the heavy equipment will be provided at motor floor slab in pumping station.
58
4.3 ARRANGEMENTS FOR POWER SUPPLY
KSEB will supply power at 11/22KV HT supply or 440 V LT supply for the operation of pumps
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 75
in the pumping stations and for operation of equipment in the STP. In respect of HT supply, suitable
transformers would be provided to step down the voltages to 440V. In case the Horse Power of
pump set is less than 75HP, 440V LT supply will be availed. Each pumping station shall have Motor
control centre for start-stop and other controls for protection and safety of motors and otherauxiliary
equipment. Capacitors of suitable capacity would be provided to improve the power factorto so that
power consumption can be brought down.
59
CHAPTER 5
5.1 GENERAL
The constituents of concern found in wastewater are removed by physical, chemical, and biological
methods. The individual methods usually are classified as physical unit operations, chemical unit
processes, and biological unit processes. Treatment methods in which the application of physical
forces predominate are known as physical unit operations. Examples of physical unit operations
include screening, mixing, sedimentation, gas transfer, filtration and adsorption. Treatment
methods in which the removal or conversion of constituents is brought about by the addition of
chemicals or other chemical reactions are known as chemical unit processes. Examples of chemical
unit processes include disinfection, oxidation and precipitation. Treatment methods in which the
removal of constituents is brought about by biological activity are known as biological unit
processes. Biological treatment is used primarily to remove the biodegradable organic constituents
and nutrients in waste water. From practical observations, the rates at which physical, chemical and
biological reactions and conversions occur are important, as they will affect the size of the treatment
facilities that must be provided. The rate at which reactions and conversions occur, and the degree
of their completion, is generally a function of the constituents involved, the temperature, and the
type of reactor. The fundamental basis for the analysis of the physical, chemical and biological unit
operations and processes used for wastewater treatment is the material mass balance principlein
which an accounting of the mass is made before and after reactions and conversions have taken
place.
pH Units 6.00-7.00
60
Table 5.1: Influent Characteristics
pH Units 5.5– 9
61
5.4 UNIT OPERATIONS IN TREATMENT OF SEWAGE
No.
62
5.5 SEQUENCING BATCH REACTOR (SBR)
A sequencing Batch Reactor (SBR) is the same as the activated sludge process. The only
difference is in the activated sludge process, the sewage flows through a primaryclarifier, an
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 79
aeration tank and then through a secondary clarifier continuously whereas in the SBR, the
aeration and settling are carried out in batch mode one after the other in the same tank. All the
four steps shown above take place in the same tank one following the other on a time interval
basis separately.
SBRs are typically configured and operated as multiple parallel basins. It aims to provide
process and equipment performance, and variously include an instrumental control system that
regulates timed sequences for filling, reaction, settling and effluent decanting. All these are
referred to as one cycle of process control operation. It is the time duration between successive
decanting sequences during which the liquid level moves from a lower water depth (bottom
water level) to its fill depth (top water level) and back to its lower water depth (bottom water
level). This volume progression takes place in repetitive sequences that permit reactive filling
to be followed by solids liquid separation. The operational and process controls are governed
as flows
a. A batch reactor consisting of a single tank equipped with an inlet for raw sewage, air
diffusers, with associated compressors and piping for aeration; a sludge draw-off mechanism
for waste sludge; a decant mechanism to remove the supernatant after settling; and a control
mechanism to time and sequence the processes.
b. Decanting of the settled supernatant is carried out by equipment called as decanters. These
consist of sharp edged weir plates over which the settled supernatant overflows similar to
conventional clarifier weirs.
. c. Wasting of surplus sludge typically occurs during the non mixed (aerated) stage. The
sequence to take advantage of the higher concentrations of settled mixed liquor; wasting can
equally take place in an aerated mixed condition.
d. SBR plants consist of a minimum of two reactors in a plant. When one reactor is in the fill
and aeration mode, the other reactor can be in settling and decanting mode of the cycle.
e. In the reaction stage, the oxygen is supplied to the system within the time frame of the
reaction cycle.
63
f. Each single SBR basin has the same floor area for all sequences in each cycle of operation.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 80
The raw sewage is first collected in a raw sewage sump & then for further treatment, into three
distinct parts:
1. Pre-treatment, which comprises of screening and grit removal, (similar unit as explained in
Para 8.4)
3. Tertiary treatment comprising of addition of chlorine to remove the E- coli (similar units as
explained in Para 8.4).
4. Sludge Handling comprising of Sludge sump, Sludge thickener and Centrifuge. (similar units
as explained in (Para 8.4)
The SBR is operated in a batch reactor mode this eliminates all the inefficiencies of the
continuous processes. The complete process takes place in a single reactor, within which all
64
biological treatment steps take place sequentially. No additional settling unit, secondary clarifier
is required. The complete biological operation is divided into cycles.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 81
Normally, the process follows basic steps of Fill, React, Settle and Decant. The ability to create
aerobic or anoxic conditions within the reactor results in flexible operation, better treatment of
waste, and optimum effluent quality.
Sequential operation:
A basic cycle comprises (Schematic representation given below)
Prior to the start of the Mix Fill phase, the reactor contents exist in a stratified condition. The
bottom portion of the reactor consists of settled sludge, and the top portion consists of a clear
supernatant. Typically, the settled sludge zone will contain the majority of the microbial life. This
microbial life continues a certain level of respiration and effectively depletes this settled sludge zone
of any dissolved oxygen (D.O.). The supernatant layer above the settled sludge zone represents a
significant fraction (typically 50 % to 70 %) of the reactor volume. Since the majority of the microbial
life has settled to the bottom of the reactor, the relative effect of microbial respiration in the
supernatant layer (compared to the sludge mass layer) is generally reduced. Therefore, the D.O.
concentration in the supernatant layer typically ranges from 0.50 to 1.5 mg/l
65
prior to the start of the Mix Fill phase. The water in the supernatant layer is generally of reasonably
good quality with respect to the concentration of specific wastewater parameters. Residual soluble
levels of organic material (as determined by BOD5 measurement) are present in concentrations at
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 82
or below the anticipated effluent value. Total suspended solids (TSS), total nitrogen (Tot-N) and total
phosphorus (Total P) are also present in concentrations at or below the anticipated effluent
concentrations
1. Mix Fill
Influent enters the SBR tank. Complete mix of the reactor contents is achieved without the use of
aeration. This phase assists in control of filamentous organisms, and is essential for those systems which
require phosphorus removal.
As the Mix Fill phase of operation begins, wastewater flow is initiated to the reactor and
the mixer is turned on. At this point, the mixer begins mixing the reactor while the air
supply system remains off and is not providing oxygen to the reactor. The stratified
condition of the reactor that existed in the preceding phases is now converted to a
completely mixed condition. The settled biomass is now resuspended and combined with
the previously isolated supernatant layer and the raw wastewater entering the reactor. As
raw wastewater continues to flow into the reactor, the completely mixed condition results
in the dispersal of the microbial life and incoming wastewater throughout the reactor. The
residual level of D.O. that existed in the supernatant layer is rapidly depleted as a result
of microbial respiration being effective throughout the entire reactor volume. As raw
wastewater enters the reactor, the amount of organic material (as measured by the soluble
BOD5 concentration) present in the reactor increases. Since an aerobic phase has not yet
been initiated in this cycle, biological degradation of the organic material in the influent
wastewater is limited.
66
environment in the reactor. The reactor contains a uniform blend of raw influent
wastewater, previously settled biomass, and supernatant from the previous cycle. The
environment is classified as anoxic with D.O. concentrations at or near zero. Effluent
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 83
quality parameters will provide the system operator with a basis for determining the
necessity of adjusting the specific duration of this phase of operation. In essence, this phase
is utilized for denitrification, biological phosphorus release, and anoxic conditioning of the
sludge mass.
The introduction of oxygen converts the reactor from an anoxic environment to anaerobic
environment. Since the SBR was designed to achieve nitrification and denitrification, the
aeration system is cycled on and off during the React Fill phase. This alternately creates
aerobic and anoxic conditions. Nitrification occurs during the aerated periods of operation,
and denitrification occurs during the non-aerated periods of operation. Although BOD5
reduction normally occurs under aerobic and anoxic conditions, the rate of BOD5 reduction
is much greater during the aerated periods of operation. The wastewater that has entered
(and continues to enter) the reactor represents a certain potential oxygen demand. The
oxygen demand is due to the aerobic metabolism of the organic constituents (i.e. BOD5
reduction) and the nitrification of NH3-N. The aeration system has been sized to meet this
oxygen demand. The dissolved oxygen (D.O.)
67
concentration profile in the reactor will normally reveal a pattern of increasing D.O.
concentration during the aerated periods, followed by decreasing D.O. concentration (to
near-zero) during the non-aerated periods. In other words, the D.O. concentration will reach
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 84
The concentration of total nitrogen present in the reactor will steadily decline as the React
Fill phase is completed. The nitrification and denitrification processes typically reduce total
nitrogen concentrations in the reactor as the raw waste flow continues to enter the reactor
with additional nitrogen. In other words, the rates of nitrification and denitrification are
typically more than sufficient to offset the rate of nitrogen entering the reactor. The amount
of soluble organic material (as evidenced by the BOD5concentration) in the reactor will
typically decrease during the React Fill phase. During this phase, biological oxidation
occurs simultaneously with the addition of organic material to the reactor. The decline in
BOD5 concentration will closely parallel the pattern observed for the total nitrogen
concentration.
During the initial period of the React Fill phase, the onset of aerobic conditions in the
reactor allows the microorganisms to "take in" phosphorus. Therefore, the phosphorus that
was previously released into solution (during the Mix Fill phase) is now taken back into the
cell mass. The phosphorus present in the influent is also taken in by the biomass. Sincethe
microorganisms were previously "depleted" of phosphorus, they have a tendency to take in
more phosphorus than the amount that is necessary to meet their nutritional requirements.
The term used to describe this phenomenon is "enhanced biological phosphorus removal".
The anoxic periods during the React Fill and React phases are not long enough to allow a
re-release of phosphorus from the biomass into the liquid medium.Therefore, the effluent
from the reactor will contain a low concentration of total phosphorus.
68
B. NON FILL PHASES:
3. React (Aeration/Anoxic mixing under true batch conditions) :
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 85
Influent flow is terminated, while mixing and aeration continue. Intermittent operation of
the aeration system may continue to complete the nitrification/denitrification process, or to
conserve energy.
The introduction of oxygen converts the reactor from an anoxic environment to anaerobic
environment. Since the SBR was designed to achieve nitrification and denitrification, the
aeration system is cycled on and off during the React Fill phase. This alternately creates
aerobic and anoxic conditions. Nitrification occurs during the aerated periods of operation,
and denitrification occurs during the non-aerated periods of operation. Although BOD5
reduction normally occurs under aerobic and anoxic conditions, the rate of BOD5 reduction
is much greater during the aerated periods of operation. The wastewater that has entered
(and continues to enter) the reactor represents a certain potential oxygen demand. The
oxygen demand is due to the aerobic metabolism of the organic constituents (i.e. BOD5
reduction) and the nitrification of NH3-N. The aeration system has been sized to meet this
oxygen demand. The dissolved oxygen (D.O.) concentration profile in the reactor will
normally reveal a pattern of increasing D.O. concentration during the aerated periods,
followed by decreasing D.O. concentration (to near-zero) during the non-aerated periods.
In other words, the D.O. concentration will reach a peak value at the end of each aeration
period.
The concentration of total nitrogen present in the reactor will steadily decline as the React
Fill phase is completed. The nitrification and denitrification processes typically reduce
69
total nitrogen concentrations in the reactor as the raw waste flow continues to enter the
reactor with additional nitrogen. In other words, the rates of nitrification and denitrification
are typically more than sufficient to offset the rate of nitrogen entering the reactor. The
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 86
amount of soluble organic material (as evidenced by the BOD5concentration) in the reactor
will typically decrease during the React Fill phase. During this phase, biological oxidation
occurs simultaneously with the addition of organic material to the reactor. The decline in
BOD5 concentration will closely parallel the pattern observed for the total nitrogen
concentration.
During the initial period of the React Fill phase, the onset of aerobic conditions in the
reactor allows the microorganisms to "take in" phosphorus. Therefore, the phosphorus that
was previously released into solution (during the Mix Fill phase) is now taken back into the
cell mass. The phosphorus present in the influent is also taken in by the biomass. Sincethe
microorganisms were previously "depleted" of phosphorus, they have a tendency to take in
more phosphorus than the amount that is necessary to meet their nutritional requirements.
The term used to describe this phenomenon is "enhanced biological phosphorus removal".
The anoxic periods during the React Fill and React phases are not long enough to allow a
re-release of phosphorus from the biomass into the liquid medium.Therefore, the effluent
from the reactor will contain a low concentration of total phosphorus.
70
During the React phase of operation, wastewater is not entering the reactor. The mixer
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 87
continues to operate and completely mix the reactor, and the aeration system continues to
be cycled on and off. This alternately creates aerobic and anoxic conditions.
The importance of this phase should be recognized by the operator with respect to the
"opportunity" that this phase provides to "reduce the concentration levels of all wastewater
parameters without the influence of additional wastewater entering the reactor." In effect,
the React phase provides a period of time in which wastewater contaminants are
"polishedoff" to the desired or required concentration levels. In summary, the React phase
features a reactor that is always in a completely mixed condition which alternates between
an aerobic and an anoxic environment. The absence of flow and organic loading provides
a unique opportunity to "polish off" wastewater contaminants. This results in a reduction
oforganic material (BOD5) and total nitrogen present in the reactor to very low effluent
concentrations. Since the majority of the biological phosphorus removal normally will
havealready taken place during the React Fill phase, the React phase does not have a major
effect on the effluent total phosphorus concentration.
During the Settle phase, wastewater is not entering the reactor. Also, the mixer and the
aeration system are both turned "off". The absence of flow, mixing, and aeration activity
produces an ideal quiescent environment in the reactor for solids-liquid separation.
71
At this point in time, the preceding phases have accomplished all of the process objectives
related to the reduction of organic compounds (BOD5), total nitrogen and totalphosphorus.
The reactor acts as a "static clarifier" as opposed to a "flow-through clarifier". Since there
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 88
is no flow entering or exiting the reactor, the settling of solids is simply not affected by
system hydraulics. During this stage, sludge is removed from the reactor by a stationary
sludge pump after the completion of the Settle phase. Settling is not affected by any type
of stirring action caused by a mechanical sludge collector.
72
configuration of a weir suspended below a floating structure provides an effluent
withdrawal point that is located just below the surface of the reactor. The positioning of
this withdrawal point provides effluent from the uppermost region of the stratified reactor
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 89
without allowing any surface scum or foam to be drawn into the effluent. The vertical
distance from the top of the settled sludge layer to the effluent withdrawal point is also
maximized.
As the Decant phase progresses, the decanter units maintain this optimum position of
effluent withdrawal by simply floating on the surface and descending with the reactor water
level. The Decant phase of operation is terminated at the predetermined minimum reactor
water level that is controlled by a level sensor system. The settled sludge mass is typically
well below the reactor surface water level as the Decant phase starts, and sedimentation
continues throughout the Decant phase.
5.6.1SBR BASED TREATMENT SYSTEM:
73
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 90
74
6. Sludge Thickener
7. Centrifuge
8. Sludge Storage yard
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 91
9. Effluent channel
10. Treated water tank
ADVANTAGES OF SBR
i. One single reactor basin provides all of the unit operations and processes that require
two separate basins in a conventional activated sludge plant configuration that can provide
an effluent quality suitable for reuse. Equalization, primary clarification (in most cases),
biological treatment, and secondary clarification can be achieved in a single reactor vessel.
ii. This process can be operated and controlled with flexibility for efficient removal of
organic matter, suspended solids, nitrogen, and phosphorus under all loading conditions.
Provides enhanced organic phosphorus removal with or without chemical augmentation.
iii. This process can control the growth of filamentous bacteria and hence prevent bulking
of activated sludge
Iv.This process saves capital cost by eliminating final sedimentation tanks. As secondary
sedimentation tanks are not required in this process, footprint area needed is also minimal
as simultaneous multiprocessing takes place in a single reactor basin (approximately 100m2
/1000m3 only needed for SBR Tanks).
Allows for easy modular expansion for population growth, modular configurations and
cyclic operation is easily managed to provide continuous inflow and outflow hydraulic
profiles, dispensing with the need for outflow hydraulic balancinG
Sarovaram Project:
KWA had acquired 93 acres of this wet land in 1983-1986 period for the construction of
STP. Later a Bio-Park was planned in the area. 87 acres of KWA land which included high
quality wet land was transferred to the Tourism department for establishment of a Bio-park.
The remaining land is retained by KWA and part of this is utilised for construction of JBIC
control room. This Bio-park is now a tourist attraction. Proposed STP site about 600m away
from Bio-park
75
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 92
The STP is to be located within the bought in Lav land which is about 13 acres inextent .Earlier
it was proposed to locate the STP in the vacant land near to the Sarovaram Bio-Park‘. For 27mld
STP based on modern technology land requirement isonly 2.6 Acres. Subsequently consequent to
a meeting chaired by the Tourism Secretaryand followed by a joint inspection of site it was decided
to relocate the STP in the 13 Acres of Bought in Lav land about 500m away from the park.
Immediate requirement for STPwill be almost 2.6 Acres and the rest can be utilized for future
expansion. Orders transferring 13Acres of land to the Corporation from the above 18acres have
been issuedby G.O(MS)No.122/2009/TSM dt.01-06-2009(Tourism (A) Department). The above
landis in Survey No. 64/1 & 63/1 of Vengeri Village. In between this land and the canoly canallies
the KWA and Tourism Dept land.
76
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 93
77
5.7.1 Topography
The 13 Acres land available for STP is water logged. Out of this about 2.6 acres of land
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 94
is developed and finished to a level of +3.50m.The proposed STP is to be sited in this land.
Balance land of is reserved for future expansion. Maximum flood level is +2.50m.
5.6.1 Location:
a) The plant site is not having any trees or other vegetation.
b) The location is away from the Tourism Park.
c) There are no habitants in immediate vicinity (100m)
d) Effluent disposal does not pause any problem.
e) Utility shifting is practically nil.
f) Both the wet lands on all the 3 sides and mangroves beyond the wet land
Provide a natural green belt and acts as a buffer zone.
g) There are no mangroves in the proposed location of the plant & hence no
loss of mangroves.
h) There are no drinking water resources in the vicinity of the STP.
Canolly canal is the receiving water body for the proposed STP which is an artificial
wetland which runs through the Kozhikode city, is the part of the west coast canal network.
It was constructed in the year 1848 under the orders of then Collector of Malabar Mr. R.
Canolly. The Canolly canal is 11.4 Km and connects Korapuzha on the north and Kallai
Puzha in the South. The width of the canal varies between 6 to 20 M and the water depth
during monsoon ranges between 1 to 3 M. During rainy season storm water from the
hinterland reach canal and the water level is then observed to rise more than a meter. The
flow in the canal is entirely tidal except for the storm water. During high tide saline water
from Korapuzha in the North and Kallai Puzha in the south enter the canal. During low tide
the water in the canal flows out both ways. On both occasions mixing of these waters take
place in the middle (stretch between Eranhipalam and Arayedathupalam).
78
Unit Sizein metres Number
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 95
13 ThickenedSludgeSump 3.4ɸX2.50 1
79
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 96
80
5.8 SELECTION OF TECHNOLOGY FOR THE PROPOSED STP
SBR Technology is opted for secondary treatment in this project for following reasons.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 97
1. SBR has been in existence for a long time, also in India is approved technology.
2. Minimum footprint
5. Less sophisticated
Raw sewage from LS7, LS8 and PH6 will be pumped through individual pumping mains to the
inlet chamber of the STP in the primary treatment section. The following treatment steps shall
comprise treatment of the sewage:
Screening and Collection of Raw Sewage
Raw Sewage from the pumping mains will be received in the receiving chamber from where it
will flow through Mechanical Coarse screens. Here all floating material above 20-mm size
including rags, plastics, debris etc. is removed. Screened sewage shall be collected into Wet
well from where it shall be pumped to downstream treatment units.
Fine Screening of Sewage
The raw sewage will be screened to remove floating particles, rags, leaves, plastic bags and large
suspended particles using fine 6-mm mechanical screens. Two numbers of parallel screen
chambers shall be provided to screen the sewage. Each screen will be complete with a raking
mechanism and conveyor system to remove the screenings. A manual screen shall also be
provided to cater to maintenance operations of mechanical screens
Grit Removal Mechanism
Inorganic particles like sand and silt will be removed in Grit removal tanks. Each Grit removal
tank shall be equipped with a raking mechanism to separate the settled particles. These fines
will be washed in an organic wash chamber and disposed off using conveyor belt system. 75 to
81
80% of all silt particles larger than 150 micron will be removed here, to prevent accumulation
in any of the downstream units, pipes and channels.
A Parshall flume is a fixed, hydraulic structure that is placed in a flow stream to determine
the flow of water. The flume accelerates flow by both a contraction of the parallel sidewalls
and a drop in the floor elevation in the throat. It is used to measure volumetric flow rate in
industrial discharges, municipal sewer lines, and influent/effluent flows in waste water
treatment plants.
The primary treated sewage shall be conveyed to the basins. These basins work in sequence
and influent flow shall be controlled using motorized sluice gates. The SBR basins are
complete with air blowers, diffusers, grid piping, return activated sludge (RAS) pumps,
Surplus activated sludge pumps (SAS), Stainless steel Decanters, Auto valves, PLC etc. All
cycles will be automatically controlled using PLC. Excess sludge at a consistency level of
0.8 to 1.0 % will be pumped intermittently from SAS pump. This can be taken further for
sludge dewatering or drying as per process requirement. The treated effluent from the Basins
will have TSS – 10 - 25 - ppm, BOD – 10 ppm and COD – 50 ppm. The system is operated
in a batch reactor mode, which ensures near 100% treatment. Four or moremodules are
provided to ensure continuous treatment.
82
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 99
The complete process takes place in a single reactor, within which all biological treatment
steps take place sequentially. No additional settling unit/ secondary clarifier are required.
The complete biological operation is divided into cycles. Each cycle is of 3 – 5 hrs duration,
during which all treatment steps take place. A basic cycle comprises the following:
_ Fill-Aeration (F/A)
_ Settlement (S)
_ Decanting (D)
- 26 -
These phases in a sequence constitute a cycle which is repeated. During the cycle, liquid is
filled in the Basin up to a set operating water level. Aeration Blowers are started for
aeration of the sewage. After the aeration cycle, the biomass settles under perfect settling
83
Once settled the supernatant is removed from the top using a decanter. Solids are wasted
from the tanks during the decanting phase.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 100
5.9.2SLUDGE SUMP
. Sludge sump is designed to have a hydraulic retention time of 2hrs. One number of sludge sump
having circular shape with diameter 5 m and depth 3 m is provided.
5.9.2 THICKENER FEED PUMP
The major function of sludge thickener feed pump is to transfer the sludge from sludge sump to
sludge thickener. Two numbers (1W+1SB) of non-clog, submersible pumps are provided.
Sludge thickening normally refers to the process of reducing the free water content of sludge or
Thickening is a procedure used to increase the solids content of sludge by removing a portion of
the liquid fraction. Sludge thickener with diameter 14.8 m and depth 2.5m provided.
5.9.4 DISINFECTION
Treated sewage from the basins shall be conveyed to the Chlorination Tank for disinfection.
Here, chlorine will be dosed at the inlet of chlorination tank using Gas Chlorination System.
The Chlorination Tank is designed for adequate retention time to facilitate disinfection
reactions. Baffle walls shall be provided in the tank to ensure proper mixing of chlorine with
treated sewage. Disinfected sewage from the chlorination tank will be then disposed suitably
84
5.9.5 SLUDGE DEWATERING
Excess Sludge from the process basins shall be pumped out at suitable intervals. It will be
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 101
collected in a sludge sump from where it will be pumped on continuous basis for mechanical
dewatering of sludge. Solid Bowl centrifuge shall be used for continuous sludge dewatering
operation. Online dosing of Polymer provided prior to Centrifuge shall increase dewatering
efficiency of centrifuge. The dewatered sludge at truck able consistency (> 20%) shall be
achieved at the outlet of centrifuge. Dewatered sludge shall be collected in a trolley and will be
suitably disposed off in the adjoining proposed composting facility to be coupled with
composted municipality solid waste and ultimately sold as finished compost.
85
5.9.6 ACTIVATED CARBON FILTER(ACF)
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 102
Filtered wastewater from Pressure sand filter is then passed through the Activated Carbon Filter.
They are generally employed in the process of removing organic compounds and/or extracting free
chlorine from water, thereby making the water suitable for discharge.
Activated carbon is commonly used for removing organic constituents and residual disinfectants in
water supplies. This not only improves taste and minimizes health hazards; it protects other water
treatment units such as reverse osmosis membranes and ion exchange resins from possible damage
due to oxidation or organic fouling. Activated carbon is a favored water treatment
Filtered wastewater from Pressure sand filter is then passed through the Activated Carbon Filter.
They are generally employed in the process of removing organic compounds and/or extracting free
chlorine from water, thereby making the water suitable for discharge.
Activated carbon is commonly used for removing organic constituents and residual disinfectants in
water supplies. This not only improves taste and minimizes health hazards; it protects other water
treatment units such as reverse osmosis membranes and ion exchange resins from possible damage
due to oxidation or organic fouling. Activated carbon is a favored water treatment
86
technique because of its multifunctional nature and the fact that it adds nothing detrimental to the
treated water. Most activated carbons are made from raw materials such as nut shells, wood, coal
and petroleum.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 103
Carbon filtering is a method of filtering that uses a bed of activated carbon to remove contaminant
sand impurities, using chemical adsorption. Each particle/granule of carbon provides a large surface
area/pore structure, allowing contaminants the maximum possible exposure to the active sites
within the filter media.
87
5.9.8 TREATED WATER TANK
The treated water is finally fed in to the treated water tank having a capacity of176.40 m3. Treated
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 104
water from Activated Carbon filter is pumped in to the treated water tank of dimension
6.6x6.6x3.35m. Hydraulic retention time of 60 minutes is given in the treatedwater tank.
OUT FALL
The disinfected clear effluent shall be let out to the stream through a RCC covered channel of
adequate slope.
5.10 SEPTAGE
Septage or septic tank waste refers to the partially treated matter stored in and pumped out of a
septic tank. In other words, faecal sludge from septic tanks is known as Septage, but faecal sludge
and Septage are interchangeably used in India. Septage is a by- product of pretreatment of
household wastewater in a septic tank where it accumulates over time. It is generally pumpedout
of a septic tank or onsite sanitation system using a vacuum tanker. Septage is the liquid andsolid
material that is pumped from a septic tank, cesspool, or other such onsite treatment facilitiesafter
it has accumulated over a period of time.
Transportation is a very vital stage in the sanitation value chain and so are safety measures involved in it.
Vehicles that carry Septage act as mobile sewer networks for OSS. Ideally, an ultimate discharge point of
collected Septage is an STP or Septage treatment plant. The two main types of vehicles used in India are:
Truck-mounted vacuum tankers: These trucks have vacuum pumps with sizes based on lift elevation,
88
pumping distance, volume of sludge to be removed, and volume of the tank. Their capacity varies
between 3,000–10,000 liters.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 105
Tractor-mounted tankers: These vehicles are locally made across India, but their capacity is similar to that of
vacuum trucks. The motor, the tank and the tractor are assembled according to the complimenting capacity of
each module.
Tractor-mounted tankers: These vehicles are locally made across India, but their capacity is similar to that of
vacuum trucks. The motor, the tank and the tractor are assembled according to the complimenting capacity of
each module.
89
Septage transportation is one of the most important components of Septage management. There is need for
evolving a standard method of collection, handling and transportation of Septage. Desludging trucks act as a
―mobile sewer network‖ for onsite sanitation systems. They collect the Septage at the household level and
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 106
transport it to treatment or disposal sites, thereby complimenting the functions of underground sewer network.
It may be assumed that one vehicle having a capacity of 2,000 liters shall clean 3 to 10 septic tanks per day. This
is based on the frequency of cleaning of septic tanks (once in 2 – 3 years) and also the distance from the location
of septic tanks to the Septage treatment facility. The vehicles are available in different capacities from2,000 up
to 12,000 liters. It is to be noted that the requirement of machines also varies depending upon the capacity of
vehicles, road width etc. In case of bigger cities having sufficient width of roads, vehicles having larger capacities
may be adopted. Adequate provision for standby machines for cleaning of septic tanks may also be made. Small
scale vacuum trucks called Vacutug (from 200 up to 2,000 Liters capacity) also are recommendedfor use in areas
inaccessible to large desludging vehicles. The Vacutug is mounted on wheels and can be attached to a small
vehicle. It can be manufactured locally to offer flexibility and mobility without losing the capacity tocollect a
substantial volume of fecal sludge within one operation.
For the purpose of planning sewerage /septage management systems for this proposal septage area is proposed
where there is no sewerage network. Septage load from the entire corporation except beypure area is proposed
to be transported to the 27 MLD STP with SBR technology near Sarovaram bio Park where co treatment
facility will be provide.
90
5.10.3 OTHER FACILITIES
Following provisions are also included in the proposal
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 107
Internal Roads
Providing Lawns
Bye-passing Arrangements
Walkways/ground pavements
Laboratory
b] Landscape irrigation
91
d] groundwater recharge, groundwater replenishment and saltwater intrusion control
e] recreational/environmental uses
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 108
g) Construction Purposes: This could be achieved by installing vending points near the Sewage
Treatment Plant.
j) Fire protection
Treated Water disposal: The treated water can be used for gardening and floor washing in Sewage
Treatment Plant. Treated water can be supplied to agricultural nurseries, industrial purposes, etc on
demand. Surplus water can be discharged to nearest water body.
Sludge disposal & handling: The washed screenings, grit etc. will be daily removed to the disposal
sites. Suitable arrangements will be made for disposal of sludge. Dewatering and packing unit after
making cakes is proposed in the estimate. Sludge may be used as bio- compost (Fertilizer)on
demand
92
environment like sewage, non-corrosive coating for reinforcing steel and water proofing application
for the inner side of reinforced concrete structures are recommended. These provisionsare already
given in the detailed estimates. During the execution stage, a detailed structural analysis of the
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 109
components can be performed. However, the dimensions are expected to fall within the limitsof the
values obtained from the preliminary analysis. In the case of foundations, simple raft and beam-
slab type raft is adopted for safety considerations. Since the soil nature is observed to be satisfactory
to withstand medium loading conditions, deep foundations are not suggested. Soil analysis reports
available for the locality has been examined to arrive at a decision. However, during the execution
stage, detailed soil investigations can be performed. Cover for the reinforced concrete elements is
to be given in accordance with the exposure conditions given in the IS 456 Code of practice.
93
Sl Components Area required in Latitude and Longitude
No cents
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 110
For the sewerage treatment plant, a network of various sensors can capture the variations of values
of parameters like temperature, dissolved oxygen, chemical composition, TDS etc. at different
control points of the system. The continuous data obtained through IoT is used by a customized
algorithm for synthesis to impart a decision-making procedure. A centralized information
processing system (CIPS) can be formed for this task. In addition to this smart water flow meters
can also be coupled to this digital environment. IoT in wastewater management can also be used to
calculate residual chemicals after the treatment. This data can be further used to calculate the
efficiency of the treatment process and ensure that water quality standards are met before it is
discharged in a waterbody.
By using real-time data gathered through different embedded sensors, performance characteristics
of machines can be monitored that further increase the productivity of equipment and boost
94
maintenance tasks. In the present study for the hospital, provision for implementing a IoT based
control of the units in STP have been suggested.
Odours are a complex combination of a wide variety of compounds; however, the certain
compounds and groups of compounds that contribute specifically to sewage odours, and
significantly determine the selection of the control technology. These include the following:
Odor control is a complex and time-consuming challenge, often requiring a combination of methods
for treating odorous gases and for removing or reducing the potential causes of the odours.If an odor
problem is severe enough to affect the community, an emergency response and solution to the
problem must be carried out quickly. The approach for selecting an odour control method or
technology includes the following steps:
A. Identify the odour source and characteristics through sampling and analysis.
B. List and assign priorities to controlling a specific odour problem, recognizing considerations
such as cost, plant location, future upgrading of various sewage processes, severity of the odour
problem, and the nature of the affected area.
C. Select one or more odour control method or technology for implementation to meet the
objectives of steps ―a‖ and ―b‖ taking in to consideration the advantages and disadvantage of each.
D. Monitor odour missions from the treated air for process adjustments and for feedback to evaluate
the solution‘s effectiveness.
Hydrogen sulphide (H2 S) is the most common odorous gas found in sewage collection and
treatment systems and results from the reduction of sulphate by bacteria under an aerobic condition.
Its characteristic rotten-egg odour is well known. The gas is corrosive, toxic and soluble in sewage.
Hydrogen sulphide is considered a broad-spectrum poison, meaning it can poison several different
systems in the body.
95
5.14 PREVENTION OF ODOUR
Hydrogen sulphide production can be controlled by maintaining conditions that prevent the build-
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 112
up of sulphides in the sewage. The presence of oxygen at concentrations of more than 1.0 mg/L in
the sewage prevents sulphide build-up because sulphide produced by anaerobic bacteria is
aerobically oxidized. Maintaining anaerobic environment inhibits the anaerobic degradation
process, which contributes to the generation of hydrogen sulphide. A check list is given below:
• Prevent corrosion in the collection well of the facility by blowing air through the facility
• Avoid storing screenings and grit generated in the grit chamber for a long time. Dispose of
screenings and grit at appropriate intervals
• Retention time of sludge in the sludge treatment facilities should be appropriate (Do not retain
sludge for a long time)
• Maintain sewage at neutral pH range because most of the sulphide is present at a pH value of
lessthan7.
• Wash weirs and other points where floatable and slime collect. Some facilities use submerged
pipes with holes rather than effluent troughs. The submerged pipes do not splash the primary
effluent, thereby reducing the release of hydrogen sulphide.
• When draining a tank, immediately flush it completely. If sludge does not drain quickly, spray
lime, calcium hypochlorite, or potassium permanganate on the sludge surface to reduce odours.
Because even a clean tank can produce odours, flushing the tank with a chlorine solution or keeping
the tank floor covered with a low concentration of chlorine solution will reduce odours.
96
• If the sewage is septic, add chemicals in the collection system or at the plant, as appropriate, to
reduce sulphides.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 113
• If tanks are covered for odour control, keep plates and access hatches in place.
• Routinely check any odour scrubbers or deodorizers for plugging, adequate supply of chemicals,
proper pressures for demisting, and/or effectiveness of carbon.
• The splashing of primary sewage into weir troughs and effluent channels can result in the release
of hydrogen sulphide. If possible, try to minimize the splashing of primary sewage in to the channel
or weirs. I fit cannot be accomplished operationally, then installing submerged sewer pipes may be
necessary. This will require tank modifications to verify the plant hydraulics and provide proper
control to avoid fluctuations in the tank levels.
• Minimize the stripping of hydrogen sulphide from the sewage when using channel air diffuser
systems. Adoption of the following regular practices will not only increase removal efficiency but
will provide better working conditions for the operator:
• Regularly remove accumulations from the inlet baffles and outlet weirs with a hose or a broom
with stiff bristles. Only experience will determine the necessary frequency.
Cleans cum removal equipment regularly; otherwise, obnoxious odours and a nun slightly
appearance will result.
• Keep cover plates in place except when operations or maintenance require the irremovable.
• Immediately flush and remove all sewage and sludge spills. Avoid hosing down motors and
enclosed control devices.
• Establish a house keeping schedule for the primary treatment area, including galleries, stairwells,
control rooms, and related buildings, and assign responsibility for each item to a specific employee.
97
5.15 CONTROLOF ODOUR BY CHEMICAL ADDITION
Chemical addition can control odors in STP by preventing anaerobic conditions or controlling the
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 114
Oxidizers
Sodium and calcium hypochlorite Hydrogen sulphide and other reduced sulphur
compounds
98
CHAPTER 6
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 115
6.1.1 GENERAL
The detailed estimate for the STP components and Network components is prepared in
accordance with the Delhi Schedule of Rates (DSR) 2018 provisions after applying District
Cost Index. For certain items, market rates are adopted. The estimate prepared in Kerala Water
Authority Price software.
6.1.2 DETAILED ESTIMATE OF COMPONENTS
The detailed estimates have been divided into components as Raw sewage well, Receiving
Chamber, Screen Chamber, Grit chamber, Equalization Tank, Aeration/MBBR Tank,
Secondary Settling Tank, Filter Feed Tank, Treated Water tank, Sludge sump, Sludge
Thickener, Thickened sludge Centrifuge Structure, Centrate sump, Chlorinator room, Air
blower room, Administrative Building, Well and pump house, Sewer network, Control room,
etc., Mechanical works, Electrical installations and instrumentation, Operation and
maintenance. The total estimate amount comes to Rs. 161 Crores including O&M for 10 years.
Salient features of the estimate are detailed below
• The estimate is prepared with DSR 2018 and cost index 36.44%
• Sulphate Resistant Cement is proposed for the structures above plinth level
• Proposed STP site is low lying area, hence earth filling is proposed
• Odour control system by Activated Carbon (re-generable type) Scrubbers is proposed (100
Lakhs provided)
99
PWD approved rates are taken for PWD/NH road reformation
1. Sewerage Network.
2. Pumping Stations.
For the efficient operation and maintenance of sewerage system, proper planning, staff/labor,
tools & equipment and spares are required. For estimating the O&M cost for the Sewerage
system, the cost is broadly categorized into
1. Establishment Charges
All the new connections shall be given under the supervision of O&M staff. No unauthorized
connection shall be given to the sewerage system. Sewer inspections and maintenance should
be planned. The whole sewerage system should be marked on a plan and divided into sections
and areas.
Quality maintenance shall be the most important step in smooth functioning of the proposed
sewers. This includes the optimum use of labour, equipment and material to keep the system
in good condition.
100
6.4 TYPES OF MAINTENANCE
There are two types of maintenance of an underground sewerage system - preventive and
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 117
emergency. It is necessary that preventive or routine maintenance are carried out to prevent
any breakdown of the system and to avoid emergency operations to deal with clogged sewer
lines or over flowing manholes or backing up of sewage into a house or structural failure of
the system. Preventive maintenance is more economical and provides for reliability in
operations of the sewer facilities. Emergency repairs, which would be very rare if proper
maintenance is carried out will also have to be provided for proper inspection and preventive
maintenance is a necessity.
The organization required for the maintenance of the sewerage system will vary with the size
and type of the sewerage system and the relative age of the system. The larger the
municipality, the larger and more complex will be its maintenance organization. The size of
the organization will vary from a couple of employees to several hundred regular employees.
The primary effort of the staff is to maintain sewers free flowing and unobstructed.
6.4.1 STEPS TO BE TAKEN FOR OPERATION AND MAINTENANCE OF THE
SEWERAGE NETWORK DETAILED IN THIS SECTION ARE AIMED AT
6.4.1.1 Regular maintenance of the system for proper functioning
6.4.1.2 Preventing any breakdown of the system
6.4.1.3 Emergency operations to deal with clogged sewer lines or overflowing manholes
6.4.1.4 Preventing back flow of sewage into residence sand
The following list gives the duties that are to be performed for proper sewer maintenance:
6.4.2.5 Raising the manhole cover for the construction of culverts, resurfacing etc.
101
102
6.4.2.11 Disposal of silt, garbage removed after cleanings ewer, manholes and treatment
plants.
6.4.2.12 Removal of debris, brick bats etc. After any repair work.
6.4.2.14 Ensuring work is carried out correctly and safely with due regards to health and
safety regulations.
6.4.2.15 Adopting preventive maintenance within the sub division as a whole, conducting
periodic staff meeting and record of the proceedings.
6.4.3 PREVENTIVE MAINTENANCE
In order to maintain the sewer system in satisfactory manner, desilting of manholes and sewers
is to be done by any of the following methods suitable for the purpose.
1) The house sewer obstruction and main sewer obstruction or any other related complaints
to be attended with high priority.
3) Any silt or mud removed during sewer cleaning operation shall be removed from the
roads within 24 hours to approved location.
It shall be the responsibility of the O&M division to arrange for traffic control and to obtain
permission from concerned agencies for traffic diversion etc. for purpose of maintenance. All
necessary precautions shall be taken. After the maintenance works are completed roads,
cables, utilities etc shall be restored to the original condition.
102
6.4.5 PERFORMANCE LEVEL TO BE ACHIEVED
a) Collection system shall be maintained without over flows from manholes/sewers on to
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 119
b) Silt and trash removed from sewers during removal of block ages/routine cleaning of
sewers shall be disposed of hygienically within 24hours.
d) Duration of break down maintenance shall not exceed the specified norms.
103
6.6 O &M CHARGES
35013384
Electricity Charges for 1 years including GST
393710910.9
Total
104
CHAPTER 7
IMPLIMENTATION OF THE PROJECT
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 121
105
unawareness of the local people about the treatment process, disposal of sludge and re-use of
treated sewage etc. In this regard, it is essential to educate the consumers to make them aware
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 122
of the waste management process thereby encouraging them to come up with sewerage
connections. The state government is promoting the waste management concept in all the
possible ways. More support is needed from the Local Self Government Departments,
Suchitwa Mission Kerala, Haritha Keralam Mission Kerala and all the other departments by
organizing programmers for motivation public through seminars and awareness classes.
2 2 2024
0 0
2 2
2 3
4 Civilworks
5 Mechanical works
During the construction phase, the emissions from movement of vehicles used for project
activity may affect the air quality due to the particulate matter generated during loading,
transporting, unloading of materials during construction. Movement of heavy vehicles and
concrete mixer would generate considerable noise in the surrounding environment. Hence a
proper traffic management plan is recommended during the construction activities.
106
Sludge generated in the STP must be properly disposed off by transforming it into fertilizer
products or bricks for low impact construction activities. Recycled water generated from the
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 123
Regarding the positive impacts, it is to be noted that water quality of the rivers and streams
will be greatly improved along with the general environment. The large quantity of recycled
water will be useful for multiple purposes including agriculture.
107
.
CHAPTER 8
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 124
• This proposal includes 27 MLD STP with SBR technology near Sarovarm Bio park in
Kozhikode corporation, a sewer network, 846 manholes, 3 pumping stations are proposed in
the initial stage. Manholes at 30 m intervals and at all intersections are proposed to facilitate
maintenance operations.
• The cost estimate of the project is excluding land cost. The fund for land has to be provided
by the local bodies /Government, according to the source of funding for the scheme.
• If sufficient funds and lands are made available, the projects can be taken up by KWA and
can be completed in 2 years. For efficient control of operation and maintenance a monitoring
cell at institutional level is to be formed.
• For better performance of the system testing of influent samples, effluent samples after
treatment from each unit is to be tested at regular intervals and modifications if any shall be
made at the initial stage itself so as to ensure efficiency of individual units and effluent
standards as per design.
• Better and advanced technology for treatment to be considered for STP while implementing
the project.
108
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 125
APPENDICES
PROCESS CALCULATION FOR 27 MLD STP, KOZHIKODE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 126
PROCESS CALCULATIONS
INLET CHAMBER
Design Basis
Design Flow Future Average Flow
Future Average Flow 27 MLD 0.31m3/sec
Time in inlet chamber 45 sec
Volume of the inlet Chamber required 14.06 m3
Side water depth 2m
Plan area required 7.03 m2
Dimensioning 7.03 m2
Length provided 4.50 m
Width provided 1.50 m
Width provided 2.00 m
Volume of the chamber provided 17.60 m3
Freeboard 0.50 m
Number 1.0
4.5mLength x 2 m Width x 2 m SWD + 0.5 m FB
Note: The dimension can be changed as per civil requirement keeping volume the same
Checks
Velocity at peak flow in the channel 0.54 m/s
Velocity at average flow in the channel 0.44 m/s
Velocity at peak flow through the racks 1.18 m/s
Velocity at avergage flow through the racks 0.96 m/s
Number of Screens 1
Material of Constrution
Type Manual
Clearance 100 mm
Width of screen channel provided 1000 mm
GRIT CHAMBER
DISTRIBUTION CHAMBER FOR GRIT SEPARATOR UNIT
Design Flow Future Peak Flow
Future Peak Flow 60.75 MLD
0.70 m3/s
Retention Time 10 sec
Volume required 7.03 m3
SWD (assumed) 1.00 m
Area required 7.03 m2
Length required 1.60 m
Width required 4.39 m
Width Provided 4.40 m
FB 0.50 m
Flow 0.70m3/s
Settling velocity as per Stoke's Law,Vs 0.02 m/s
Check for Reynold's Number , R 3
If the value of the Reynold's Number is greater than 0.5, then Stoke's Law does not apply.
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 129
Now,
Surface Overflow Rate (For 100% removal
efficiency of an ideal grit chamber) Settling Velocity of the minimum size of particle to be removed
0.018m/s
or 1555.2 m3/m2/day
To determine actual flow rate, use correction factor 0.60 Range : 0.5-0.67
Permissible Overflow Rate (Q/A) 933.12 m/s
Overflow rate considered 1100 m3/m2/d
Dimensioning
check
The critical displacement velocity to initiate resusp0.161 m/sec
The horizontal velocity flow should be kept less than the critical displacement velocity
Horizontal Velocity 0.13 m/sec [O.K]
Hydraulic retention time (at average flow) 79 sec
PARSHALL FLUME
OPEN CHANNEL FROM GRIT CHAMBER TO SBR TANK
Design flow Future Peak Flow
Future peak flow 30.375 MLD
Width 1.0 m
SWD 0.7 m
Velocity 1.0 m/s
Approx length of open channel up to PF 20 m
Slope required
V=1/nR2/3S1/2
Hydralic Radius 0.29
Maaning's coefficient 0.013
Slope, S 0.000882
DIMENSION OF CHANNEL
1000 mm Wide x 700 mm SWD + 500 mm FB
PARSHALL FLUME
using table 5.7 of CHEEO mnual, for upto 100 MLD flow
Selected throat width,
W 300 mm
A 1350 mm
B 1322 mm
C 600 mm
D 831 mm
F 600 mm
G 900 mm
K 75 mm
Z 225 mm
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 130
Design Basis
Consider
No. of SBR Basins (n) 2 Nos.
cycle time (t) 4.8 hrs
No. of cycles per day (c) 5 Nos.
F/M 0.1
MLSS in SBR Tank 4000 mg/l
SRT 20 days
SVI 140 ml/g
Yeild Coefficient (Y) 5
Decay Coefficient (kd) 0.05
Design
Volume to be treated per cycle per Basin (Decant V=Q/nxc
BWLavg 4.84
Oxygen Requirement
Yobs = Y / (1+kdǾ)
Yobs = 0.25
Excess Sludge 843.75 kg
O2 3436.20 kg/d
Based on BOD removed
Oxygen required for BOD removal
For Nitrification
Inlet Tkn 60 mg/l
Outlet NH3-N 10 mg/l
Nitrogen assimilated during BOD oxidation 11.5 mg/l
NH3-N nitrified 38.5 mg/l
amount of NH3-N nitrified 519.75 kg/d
Oxygen required for nitrification 2375.26 kg/d
De-nitrification credit
NO3-N generated 28.88 mg/l
Concentration of NO3-N2 in the sewage 0 mg/l
Total NO3-N2 28.875 mg/l
Outlet NH3-N 10 mg/l
NO3-N denitrified 254.81 mg/l
Oxygen credit during dentrificaton 2.87 kg/ kg No3-N
Total oxygen required for BOD 731.31 kg/d
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 132
Air Requirement
Air requirement at 37oc 5084.64 kg/hr
4233.67 nm3/Hour
Air Requirement 14oc 5177.74 kg/hr
4311.19 Nm3/Hour
Air required {for mixing} 1.8-2.7 m3/hr/m2
Based on air req/unit volume of tank
Tank area 1298.08 m2
Air required for mixing 2920.67 m3/hr
Type Submersible
No. of Pump 1 W + 1S
Pumping duration/ cycle 25 min
Capacity required 72 m3/hr
capacity provide 72 m3/hr
Head 5 mtr
AIR REQUIREMENT
Air Requirement at 37 0 C
Oxygen required 5369.95 Kg/Day
223.75 Kg/Hour
Density of air 1.201 Kg/m3
Oxygen fraaction in air (%by weight) 23.20 Kg/m3
Oxygen fraaction in air (%by volumn) 21.00 Kg/m3
Dessign temperature 37°
Value for "α" factor 0.65
Value for "β" factor 0.95
SOTE value for diffusers 36.25
D.O. saturation concentration for tap water at field 9.080 mg/l
D.O. saturation concentration for sewage at field 6.720 mg/l
Min. D.O. to be maintained in tank (Cw) 1.50 mg/l
Value for factor "θ" 1.024
Field oxygen transfer efficiency (OTE1) =[ SOTE x (β.Cs-Cw) x θ ɣ-20 x α]‚Cs20
Calculation field oxygen transfer eff. (OTE1) 18.97%
Actual oxygen required at field condition, (O2)x10 1179.64 Kg/Hour
Total quantity of air required 5084.6 Kg/Hour
4233.7 Nm3/Hour
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 133
Air requirement at 14 0 C
Oxygen required 5369.95 Kg/Day
223.75 Kg/Hour
Density of air 1.201 Kg/m3
Oxygen fraaction in air (%by weight) 23.20 Kg/m3
Oxygen fraaction in air (%by volumn) 21.00 Kg/m3
Dessign temperature 14°
Value for "α" factor 0.65
Value for "β" factor 0.95
SOTE value for diffusers 36.25
D.O. saturation concentration for tap water at field 9.080 mg/l
D.O. saturation concentration for sewage at field 10.290 mg/l
Min. D.O. to be maintained in tank (Cw) 1.50 mg/l
Value for factor "θ" 1.024
Field oxygen transfer efficiency (OTE1) =[ SOTE x (β.Cs-Cw) x θ ɣ-20 x α]‚Cs20
Calculation field oxygen transfer eff. (OTE1) 18.63%
Actual oxygen required at field condition, (O2)x10 1201.24 Kg/Hour
Total quantity of air required 5177.7 Kg/Hour
4311.2 Nm3/Hour
SUPERNATANT & CENTRATE SUMP 286.46 m3/day
Supernatant & Centrate flow 0.20 m3/min
Retention Time 30 min
Volume required 5.97
SWD assumed 2m
Dia required 1.95 m
Dia provided 2.0 m
Supernatant & Centrate Pump
Type of Pump Submersible
No. of thickened sludge pump 1 W+15
Pumping duration 24 hrs
Capacity of Pump required 11.9 m3/hr
Capacity of Pump provided 12.0 m3/hr
Pump Head 10.0 m
GENERAL ABSTRACT
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 136
Rounded Total(Rs)
441983804.5
0
Rupees Forty Four Crore Nineteen Lakh Eighty Three Thousand Eight Hundred and
Four
DETAILED ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 138
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityRoutine test
Vertical load testing of piles in accordance with IS 2911(part IV)
1 1.000
Total 1.000
Total Quantity in per test 1.000
1.005 5.22.2
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Steel reinforcement for RCC work including Straightening, cutting ,bending, placing
in position
For 500 Dia pile - 100.00 8203.000
@ 100 Kg/ Cum 1 82.030 0000
of CC
Total 8203.000
Total Quantity in kilogram 8203.000
1.006 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade
Pipe cap footing 25 1.000 1.000 0.100 2.500
plinth bottom 2 1.300 0.400 0.100 0.104
plinth bottom 1 1.800 0.400 0.100 0.072
plinth bottom 5 2.850 0.400 0.100 0.570
plinth bottom 2 4.450 0.400 0.100 0.356
plinth bottom 1 4.200 0.400 0.100 0.168
plinth bottom 2 1.950 0.400 0.100 0.156
plinth bottom 1 3.400 0.400 0.100 0.136
plinth bottom 1 4.980 0.400 0.100 0.199
plinth bottom 4 3.500 0.400 0.100 0.560
plinth bottom 4 4.700 0.400 0.100 0.752
plinth bottom 2 0.350 0.400 0.100 0.028
plinth bottom 2 1.420 0.400 0.100 0.114
plinth bottom 2 2.580 0.400 0.100 0.206
plinth bottom 4 2.000 0.400 0.100 0.320
plinth bottom 2 3.150 0.400 0.100 0.252
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Cover slab portion (Deduction)
Cover slab -1 2.460 2.490 0.150 -0.919
portion
Total -0.919
Stair case
Wast slab 3 3.800 1.000 0.175 1.995
Wast slab 1 1.270 1.000 0.175 0.222
Wast slab 1 2.540 1.000 0.175 0.445
Landing 3 2.100 1.200 0.175 1.323
Landing 2 2.100 1.725 0.175 1.268
Landing 1 2.100 1.200 0.175 0.441
Beam 3 2.100 0.300 0.175 0.331
Step 24 1.000 0.275 0.175 1.155
Step at channel 4.5 1.500 0.275 0.175 0.325
cover slab
Total 7.505
Beam
Beam X 2 3.300 0.300 0.200 0.396
Direction
Beam X 1 3.300 0.300 0.300 0.297
Direction
Beam X 2 3.300 0.300 0.340 0.673
Direction
Beam X 2 4.300 0.300 0.200 0.516
Direction
Beam X 4 5.150 0.300 0.200 1.236
Direction
Beam X 2 0.800 0.300 0.200 0.096
Direction
Beam X 2 5.300 0.300 0.200 0.636
Direction
Side Wall
Side wall 2 3.450 0.250 3.200 5.520
side wall 2 3.100 0.250 3.200 4.960
side wall 4 5.000 0.250 1.650 8.250
side wall 4 5.250 0.250 1.950 10.238
side wall 2 2.100 0.250 2.350 2.468
side wall 2 12.000 0.250 1.860 11.160
side wall 2 6.000 0.250 1.860 5.580
side wall 2 7.400 0.250 1.860 6.882
For channel side 2 5.600 0.250 1.050 2.940
wall
For channel side 2 9.050 0.250 1.860 8.417
wall
For channel side 2 7.450 0.250 1.600 5.960
wall
Total 72.375
Base slab
Slab 1 1 15.350 3.950 0.200 12.127
Middle portion 1 12.500 7.450 0.200 18.625
Cantilever 2 5.950 0.750 0.200 1.785
Cantilever 2 1.600 0.750 0.200 0.480
Cantilever 1 12.500 0.500 0.200 1.250
Channel 1 5.610 1.500 0.200 1.683
Total 35.950
Total Quantity in tonne 117.842
1.012 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting , etc
Pile cap 100 0.800 0.750 60.000
Total 60.000
Total Quantity in sqm 60.000
1.013 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering
side wall 4 3.450 3.200 44.160
side wall 4 3.100 3.200 39.680
side wall 8 5.000 1.650 66.000
2.004 100.7.2
Bailing out water with engine and pump set above 5HP up to 10HP including
conveyance to the site, erecting, dismantling and taking back of engine and pump, cost
of fuel lubricating oil and other stores pay of staff etc., complete.
septage receiving tank
For Foundation 2 75.000 10*0.746 5.000 5595.000
work
Total 5595.000
Total Quantity in Kwh 5595.000
2.005 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
septage receiving tank
Base PCC 3.14 3.200 3.200 0.200 6.431
Ramp base 1 5.000 3.000 0.200 3.000
Total 9.431
Total Quantity in cum 9.431
2.006 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
septage receiving tank
Base RCC 3.14 3.100 3.100 0.400 12.070
Ramp 1 5.000 3.000 0.600 0.5000 4.500
00
Side wall 3.14 5.300 0.300 4.500 22.467
Total 39.037
Total Quantity in cum 39.037
2.007 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
septage receiving tank
Cover slab 3.14 2.800 2.800 0.150 3.693
Total 3.693
Total Quantity in cum 3.693
2.008 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
septage receiving tank
base 3.14 3.100 3.100 0.400 12.070
Side wall 3.14 5.300 0.300 4.500 22.467
Total 34.537
Total Quantity in cum 34.537
2.009 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
septage receiving tank
340.00 11742.58
1 34.537 0000 0
11742.58
Total 0
2.010 OD60991/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level.
septage receiving tank
1 34.537 34.537
Total 34.537
Total Quantity in cum 34.537
2.011 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
septage receiving tank
120.00 5127.600
12 0Kg / Cum 1 42.730 0000
Total 5127.600
Total Quantity in kilogram 5127.600
2.012 OD60989/2022-2023
Extra for providing epoxy coating for reinforcement bars
septage receiving tank
1 5127.600 5127.600
Total 5127.600
Total Quantity in kilogram 5127.600
2.013 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
septage receiving tank
Base 3.14 6.200 0.400 7.787
0.5000
Ramp side 2 5.000 0.600 3.000
00
Total 10.787
Total Quantity in sqm 10.787
2.014 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
septage receiving tank
Side wall - inside 3.14 5.000 4.500 70.650
Side wall - Outer 3.14 5.600 4.500 79.128
Total 149.778
Total Quantity in sqm 149.778
2.015 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
septage receiving tank
Cover slab 3.14 2.500 2.500 19.625
Cover slab side 3.14 5.600 0.150 2.638
Total 22.263
3.002 2.26.1
Extra for every additional lift 1.5 m or part there of in excavation / banking excavated
or stacked materials.All kinds of soil
Extra for every additional lift 1.5 m (SBR 2Nos)
For base 1 45.800 41.700 0.670 2.0000 00 2559.212
For Wall- W1 2 45.800 3.950 0.430 2.0000 311.165
00
For Wall- W1 2 14.930 3.950 0.430 2.0000 101.434
00
2.0000
For Wall- W2 1 45.800 3.950 0.430 155.583
00
2.0000
For Wall- W5 2 14.930 3.950 0.430 101.434
00
Total 3228.828
Total Quantity in cum 3228.828
3.003 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade (SBR 2
Nos)
For wall W1 2 45.800 3.950 0.150 2.0000 108.546
00
For wall W1 2 14.930 3.950 0.150 2.0000 35.384
00
For wall W2 1 45.800 3.950 0.150 2.0000 54.273
00
For wall W5 2 14.930 3.950 0.150 2.0000 35.384
00
For wall W6 2 14.930 0.700 0.150 2.0000 6.271
00
Beam B1 14 14.930 0.700 0.150 2.0000 43.894
00
Beam B2 2 14.930 0.700 0.150 2.0000 6.271
00
Stair footing 1 1.200 1.200 0.150 2.0000 0.432
00
Stair footing 1 1.750 1.750 0.150 2.0000 0.919
00
Base bottom 2 3.550 6.150 0.150 2.0000 13.100
00
Base bottom 2 3.300 6.150 0.150 2.0000 12.177
00
Base bottom 2 3.500 6.150 0.150 2.0000 12.915
00
Base bottom 2 6.700 6.150 0.150 2.0000 24.723
00
Base 14 17.000 3.300 0.150 2.0000 235.620
00
Base 2 17.000 3.450 0.150 2.0000 35.190
00
Base 2 17.000 3.500 0.150 2.0000 35.700
00
Total 660.799
Total Quantity in cum 660.799
3.004 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Bailing out of water
For sbr 12.000 2.0000 134280.0
10 150.000 5*0.746
Foundation work 00 00
134280.0
Total 00
3.006 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mix M-25 grade concrete for RCC work
(SBR 2 Nos)
Wall footing-
W1( A1-G1,A11- 2 45.600 3.750 0.300 2.0000 205.200
00
G11)
Wall footing- 2.0000
W1( A1-G1,A11- 1 45.600 1.800 0.450 73.872
00
G11)
2.0000
W/ slab 1 3.100 1.000 0.120 0.744
00
2.0000
W/ slab 1 1.400 1.000 0.120 0.336
00
2.0000
W/ slab 1 1.100 1.000 0.120 0.264
00
2.0000
Landing 2 2.200 1.000 0.120 1.056
00
2.0000
Landing 1 1.500 1.000 0.120 0.360
00
2.0000
Landing 1 1.000 1.000 0.120 0.240
00
2.0000
Step 13 1.000 0.250 0.180 1.170
00
Total 6.481
Providing and laying in position ready mixed M-25 grade concrete for RCC
work (SBR 2 Nos)
For base slab 1 38.050 42.150 0.300 2.0000 962.285
00
Wall above base 2 35.450 (0.75+0.2 6.450 2.0000 457.305
slab W1 5)/2 00
Wall above base 2 35.450 0.250 0.850 2.0000 30.133
slab W1 00
C/F 8 1.800 0.500 3.000 2.0000 43.200
00
Wall-W1 2 18.000 (0.75+0.2 6.450 2.0000 232.200
5)/2 00
Wall-W1 2 18.000 0.250 0.850 2.0000 15.300
00
C/f 4 1.800 0.500 3.000 2.0000 21.600
00
Wall-W2 1 34.450 (0.75+0.2 6.450 2.0000 222.203
5)/2 00
Wall-W2 1 34.450 0.250 0.850 2.0000 14.641
00
C/F 8 1.000 0.500 3.000 2.0000 24.000
00
Wall W3 & W4 3 6.350 (0.65+0.2 6.450 2.0000 110.585
5)/2 00
Wall W3 & W4 3 6.350 0.250 0.850 2.0000 8.096
00
Wall -W7 4 6.350 (0.65+0.2 7.300 2.0000 157.607
0)/2 00
Wall -W8 4 2.900 0.250 7.300 2.0000 42.340
00
2.0000
For base slab 1 38.050 42.150 0.300 962.285
00
Wall above base (0.75+0.2 2.0000
2 35.450 6.450 457.305
slab W1 5)/2 00
Wall above base 2.0000
2 35.450 0.250 0.850 30.133
slab W1 00
2.0000
C/F 8 1.800 0.500 3.000 43.200
00
(0.75+0.2 2.0000
Wall-W1 2 18.000 6.450 232.200
5)/2 00
2.0000
Wall-W1 2 18.000 0.250 0.850 15.300
00
2.0000
C/f 4 1.800 0.500 3.000 21.600
00
(0.75+0.2 2.0000
Wall-W2 1 34.450 6.450 222.203
5)/2 00
2.0000
Wall-W2 1 34.450 0.250 0.850 14.641
00
2.0000
C/F 8 1.000 0.500 3.000 24.000
00
(0.65+0.2 2.0000
Wall W3 & W4 3 6.350 6.450 110.585
5)/2 00
2.0000
Wall W3 & W4 3 6.350 0.250 0.850 8.096
00
(0.65+0.2 2.0000
Wall -W7 4 6.350 7.300 157.607
0)/2 00
2.0000
Wall -W8 4 2.900 0.250 7.300 42.340
00
Inside column- 2.0000
32 0.400 0.675 7.300 126.144
C1 00
Inside column- 2.0000
4 0.500 0.500 7.300 14.600
C4 00
2.0000
Brace beam 14 16.650 0.300 0.450 62.937
00
2.0000
Brace beam 2 18.000 0.300 0.450 9.720
00
2.0000
Brace beam 4 3.000 0.300 0.450 3.240
00
Walk way brace 2.0000
28 3.400 0.300 0.300 17.136
beam 00
Walk way brace 2.0000
4 1.760 0.300 0.300 1.267
beam 00
Walk way brace 2.0000
2 5.330 0.300 0.300 1.919
beam 00
2.0000
Walk way slab 1 38.100 1.450 0.150 16.574
00
2.0000
Walk way slab 3 38.100 1.200 0.150 41.148
00
2.0000
Walk way slab 2 7.070 1.200 0.150 5.090
00
2.0000
Walk way slab 3 38.770 1.200 0.150 41.872
00
2.0000
Walk way slab 4 27.790 1.200 0.150 40.018
00
Total 2723.160
Total Quantity in kg 2723.160
3.010 OD6250/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing sulphate resistant cement for structures above plinth level (SBR
2 Nos)
For base slab 1 38.050 42.150 0.300 2.0000 962.285
00
Wall above base 2 35.450 (0.75+0.2 6.450 2.0000 457.305
slab W1 5)/2 00
Wall above base 2 35.450 0.250 0.850 2.0000 30.133
slab W1 00
C/F 8 1.800 0.500 3.000 2.0000 43.200
00
Wall-W1 2 18.000 (0.75+0.2 6.450 2.0000 232.200
5)/2 00
Wall-W1 2 18.000 0.250 0.850 2.0000 15.300
00
C/f 4 1.800 0.500 3.000 2.0000 21.600
00
Wall-W2 1 34.450 (0.75+0.2 6.450 2.0000 222.203
5)/2 00
Wall-W2 1 34.450 0.250 0.850 2.0000 14.641
00
C/F 8 1.000 0.500 3.000 2.0000 24.000
00
Wall W3 & W4 3 6.350 (0.65+0.2 6.450 2.0000 110.585
5)/2 00
Wall W3 & W4 3 6.350 0.250 0.850 2.0000 8.096
00
Wall -W7 4 6.350 (0.65+0.2 7.300 2.0000 157.607
0)/2 00
Wall -W8 4 2.900 0.250 7.300 2.0000 42.340
00
514080.0 514080.0
As per ite No 9 1 00 00
514080.0
Total 00
514080.0
Total Quantity in kg 00
3.013 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting, etc. and removal of form for:
Foundations, footings, bases of columns, etc (SBR -2Nos)
For wall Footing 2 45.600 0.300 2.0000 54.720
- outer 00
For wall Footing 2 41.500 0.300 2.0000 49.800
- outer 00
Inner 4 38.250 0.300 2.0000 91.800
00
Inner 2 15.300 0.300 2.0000 18.360
00
Stair footing 4 1.200 0.200 2.0000 1.920
00
Stair footing 4 1.750 0.200 2.0000 2.800
00
Total 219.400
Total Quantity in sqm 219.400
3.014 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, etc. (SBR -2Nos)
Wall up base 2 42.150 1.380 2.0000 232.668
bottom W1&W5 00
Wall up base 2 38.050 1.380 2.0000 210.036
bottom W1&W5 00
C/F 56 1.800 1.605 2.0000 323.568
00
Inner wall up to 4 34.120 0.980 2.0000 267.501
Base slab 00
C/F 32 1.000 1.205 2.0000 77.120
00
Inner wall up to 4 18.000 0.980 2.0000 141.120
Base Slab 00
Inner wall up to 4 6.150 0.980 2.0000 48.216
Base Slab 00
Total 1300.229
Wall above Base - (SBR -2Nos)
Wall above base 2.0000
2 42.150 7.300 1230.780
slab -outer 00
Wall above base 2.0000
2 38.050 7.300 1111.060
slab -outer 00
1.0000
C/F 56 1.800 3.000 302.400
00
2.0000
Inner 4 33.870 7.300 1978.008
00
1.0000
C/F 32 1.800 3.000 172.800
00
2.0000
C/F 4 18.000 7.300 1051.200
00
2.0000
Inner 12 6.150 7.300 1077.480
00
2.0000
Inner 4 17.100 7.300 998.640
00
Total 7922.368
Total Quantity in sqm 9222.597
3.015 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Centering and shuttering including strutting, etc. (SBR -2Nos)
2.0000
Walk way Slab 1 38.100 1.200 91.440
00
2.0000
Walk way Slab 3 38.100 0.950 217.170
00
2.0000
Walk way Slab 2 7.070 0.950 26.866
00
2.0000
Walk way Slab 3 38.770 0.950 220.989
00
2.0000
Walk way Slab 4 27.790 0.950 211.204
00
Slab edge 2 65.450 0.150 2.0000 39.270
00
Slab edge 2 65.200 0.150 2.0000 39.120
00
Slab edge 2 65.850 0.150 2.0000 39.510
00
Slab edge 2 45.020 0.150 2.0000 27.012
00
Slab edge 1 82.050 0.150 2.0000 24.615
00
2.0000
Outer 1 164.750 0.150 49.425
00
Total 986.621
Total Quantity in sqm 986.621
3.016 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Brace beam (SBR -2Nos)
Brace beam 14 16.650 1.200 2.0000 559.440
00
Brace beam 2 18.000 1.200 2.0000 86.400
00
Brace beam 4 3.000 1.200 2.0000 28.800
00
Walk way brace 28 3.400 0.900 2.0000 171.360
beam 00
Walk way brace 4 1.760 0.900 2.0000 12.672
beam 00
Walk way brace 2 5.330 0.900 2.0000 19.188
beam 00
Total 877.860
Centering and shuttering including strutting, etc. (SBR -2Nos)
Base Beam -B1 36 17.000 0.700 2.0000 856.800
00
Base Beam -B1 8 6.150 0.700 2.0000 68.880
00
Base Beam -B3 8 3.300 0.700 2.0000 36.960
00
Stair plinth 2 5.000 0.450 2.0000 9.000
00
Total 971.640
Total Quantity in sqm 1849.500
3.017 5.9.6
Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Centering and shuttering including strutting, etc. (SBR -2Nos)
Inside column - 32 2.150 7.300 2.0000
C1 00 1004.480
Inside column - 4 2.000 7.300 2.0000 116.800
C4 00
Stair column 1 1.200 4.260 2.0000 10.224
00
2.0000
Stair column 1 1.200 6.180 14.832
00
Total 1146.336
Total Quantity in sqm 1146.336
3.018 5.9.7
Centering and shuttering including strutting, etc. and removal of form for:Stairs,
(excluding landings ) except spiral - staircases)
Centering and shuttering including strutting, etc. (SBR -2Nos)
Stair beam 2 2.200 0.900 2.0000 7.920
00
2.0000
Wl Slab 1 3.100 1.000 6.200
00
2.0000
Wl Slab 1 1.400 1.000 2.800
00
2.0000
Wl Slab 1 1.100 1.000 2.200
00
Wl Slab edge 2 5.600 0.120 2.0000 2.688
00
2.0000
Landing 2 2.200 1.000 8.800
00
2.0000
Landing 1 1.500 1.000 3.000
00
2.0000
Landing 1 1.000 1.000 2.000
00
Step face 26 1.000 0.180 2.0000 9.360
00
Side 52 0.250 0.180 1.0000 2.340
00
Total 47.308
Total Quantity in sqm 47.308
3.019 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix: 1:3 -
(SBR -2Nos)
Wall above base 2 42.150 7.300 2.0000
slab -outer 00 1230.780
Wall above base 2 38.050 7.300 2.0000
slab -outer 00 1111.060
C/F 56 1.800 3.000 1.0000 302.400
00
Inner 4 33.870 7.300 2.0000 00 1978.008
1.0000
C/F 32 1.800 3.000 172.800
00
2.0000
C/F 4 18.000 7.300 1051.200
00
2.0000
Inner 12 6.150 7.300 1077.480
00
2.0000
Inner 4 17.100 7.300 998.640
00
2.0000
Base slab 2 18.000 34.000 2448.000
00
2.0000
Base slab 2 11.350 6.150 279.210
00
2.0000
Base slab 4 2.900 5.950 138.040
00
10787.61
Total 8
12mm cement plaster finished with a floating coat of neat cement of mix - (SBR -
2Nos)
Stair beam 2 2.200 0.900 2.0000 7.920
00
2.0000
Waist slab 1 3.100 1.000 6.200
00
2.0000
Waist slab 1 1.400 1.000 2.800
00
2.0000
Waist slab 1 1.100 1.000 2.200
00
Waist slab Edge 2 5.600 0.120 2.0000 2.688
00
2.0000
Landing 2 2.200 1.000 8.800
00
2.0000
Landing 1 1.500 1.000 3.000
00
2.0000
Landing 1 1.000 1.000 2.000
00
Step face 26 1.000 0.180 2.0000 9.360
00
1.0000
Side 52 0.250 0.180 2.340
00
Total 47.308
Walk way slab - (SBR -2Nos)
2.0000
Walk way Slab 1 38.100 1.200 91.440
00
2.0000
Walk way Slab 3 38.100 0.950 217.170
00
2.0000
Walk way Slab 2 7.070 0.950 26.866
00
2.0000
Walk way Slab 3 38.770 0.950 220.989
00
2.0000
Walk way Slab 4 27.790 0.950 211.204
00
Walk way Slab 2.0000
1 38.100 1.450 110.490
top 00
Walk way Slab 2.0000
3 38.100 1.200 274.320
top 00
Walk way slab 2.0000
2 7.070 1.200 33.936
Top 00
Walk way slab 2.0000
2 38.770 1.200 186.096
Top 00
Walk way slab 2.0000
4 27.790 1.200 266.784
Top 00
2.0000
Slab edge 2 65.450 0.150 39.270
00
2.0000
Slab edge 2 65.200 0.150 39.120
00
2.0000
Slab edge 2 65.850 0.150 39.510
00
2.0000
Slab edge 2 45.020 0.150 27.012
00
2.0000
Slab edge 1 82.050 0.150 24.615
00
2.0000
Outer 1 164.750 0.150 49.425
00
Total 1858.247
12mm cement plaster finished with a floating coat of neat cement of mix - (SBR -
2Nos)
Brace beam 14 16.650 1.500 2.0000 699.300
00
Brace beam 2 18.000 1.500 2.0000 108.000
00
Brace beam 4 3.000 1.500 2.0000 36.000
00
Walkway Brace 28 3.400 0.900 2.0000 171.360
beam 00
Walkway Brace 4 1.760 0.900 2.0000 12.672
beam 00
Walkway Brace 2 5.330 0.900 2.0000 19.188
beam 00
Total 1046.520
12mm cement plaster finished with a floating coat of neat cement of mix (SBR -
2Nos)
Inside column - 32 2.150 7.300 2.0000
C1 00 1004.480
Inside column - 4 2.000 7.300 2.0000 116.800
C4 00
Stair column 1 1.200 3.260 2.0000 7.824
00
Stair column 1 1.200 5.180 2.0000 12.432
00
Total 1141.536
3.020 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as
per manufacturer's specifications including appropriate priming coat, preparation of
surface, etc. complete.On concrete work
Finishing with Epoxy paint - (SBR -2Nos)
Slab edge 2 65.450 0.150 2.0000 39.270
00
Slab edge 2 65.200 0.150 2.0000 39.120
00
Slab edge 2 65.850 0.150 2.0000 39.510
00
Slab edge 2 45.020 0.150 2.0000 27.012
00
Slab edge 1 82.050 0.150 2.0000 24.615
00
Outer 1 164.750 0.150 2.0000 49.425
00
Total 218.952
Finishing with Epoxy paint -(SBR -2Nos)
Wall above base 2 42.150 7.300 2.0000
slab -outer 00 1230.780
Wall above base 2 38.050 7.300 2.0000
slab -outer 00 1111.060
C/F 56 1.800 3.000 1.0000 302.400
00
Total 2644.240
finishing with epoxy - (SBR -2Nos)
Stair beam 2 2.200 0.900 2.0000 7.920
00
2.0000
Waist slab 1 3.100 1.000 6.200
00
2.0000
Waist slab 1 1.400 1.000 2.800
00
2.0000
Waist slab 1 1.100 1.000 2.200
00
2.0000
Waist slab Edge 2 5.600 0.120 2.688
00
2.0000
Landing 2 2.200 1.000 8.800
00
2.0000
Landing 1 1.500 1.000 3.000
00
2.0000
Landing 1 1.000 1.000 2.000
00
2.0000
Step face 26 1.000 0.180 9.360
00
1.0000
Side 52 0.250 0.180 2.340
00
Total 47.308
Finishing with Epoxy paint - (SBR -2Nos)
2.0000
Stair column 1 1.200 3.260 7.824
00
2.0000
Stair column 1 1.200 5.180 12.432
00
Total 20.256
Total Quantity in sqm 2930.756
3.021 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofin - (SBR -2Nos)
Tank innerwall 2 33.870 7.300 2.0000 989.004
00
Tank innerwall 4 18.000 7.300 2.0000 00 1051.200
2.0000
Inner 2 6.150 7.300 179.580
00
Total 2219.784
Total Quantity in sqm 2219.784
3.022 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment - (SBR -2Nos)
2.0000 2448.000
Base slab 2 18.000 34.000 00
2.0000
Base slab 2 11.350 6.150 279.210
00
2.0000
Base slab 4 2.900 5.950 138.040
00
Total 2865.250
Total Quantity in sqm 2865.250
3.023 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a distance
of 5 km (average) to the reservoir site and pumping the water into the reservoir of
height not less than 3 m using 5 HP diesel engine pump set , hire for tanker lorry, tools
and other appliences and cost of water etc. complete.
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) - (SBR -2Nos)
Tank inside 1 34.000 18.000 6.950 2.0000 00 8506.800
Tank inside 1 6.150 18.000 6.950 2.0000 00 1538.730
10045.53
Total 0
3.024 10.26.3
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat of
approves steel primer.G.I. pipes
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing - (SBR -2Nos)
walk way slab 7.0000 1649.340
4 65.450 0.900
edge 00
walk way slab 7.0000 1643.040
4 65.200 0.900
edge 00
walk way slab 7.0000 1659.420
4 65.850 0.900
edge 00
walk way slab 7.0000 1134.504
4 45.020 0.900
edge 00
walk way slab 7.0000 1033.830
2 82.050 0.900
edge 00
walk way slab 7.0000 2075.850
2 164.750 0.900
edge 00
Total 9195.984
Total Quantity in kg 9195.984
4 FILTER FEED TANK
4.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Centering and shuttering including strutting, etc. and removal of form for:
1 7.200 7.200 0.500 25.920
Total 25.920
Total Quantity in cum 25.920
4.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and
1 7.200 7.200 0.200 10.368
Total 10.368
Total Quantity in cum 10.368
4.003 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using
1 7.000 7.000 0.300 14.700
Total 14.700
Total Quantity in cum 14.700
4.004 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using
LONG WALL 2 6.400 0.300 3.500 13.440
SHORT WALL 2 5.800 0.300 3.500 12.180
Total 25.620
Total Quantity in cum 25.620
4.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content
1 14.7+25. 40.320
62
Total 40.320
4.007 OD6184/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing sulphate resistant cement for the structures above plinth level
1 40.320 40.320
Total 40.320
Total Quantity in cum 40.320
4.008 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all
@120KG/M3 1 40.320 120.000 4838.400
Total 4838.400
Total Quantity in kilogram 4838.400
4.009 OD6185/2022-2023
Extra for providing epoxy coating for reinforcement bars
Extra for providing epoxy coating for reinforcement bars
@120KG/M3 1 40.320 120.000 4838.400
Total 4838.400
Total Quantity in kg 4838.400
4.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting, etc. and removal of form for:
PCC 4 7.200 0.200 5.760
BASE 4 7.000 0.300 8.400
Total 14.160
Total Quantity in sqm 14.160
4.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, etc. and removal of form for:
C/C 8 6.100 3.500 170.800
Total 170.800
Total Quantity in sqm 170.800
4.012 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix:
C/C 8 6.100 3.500 170.800
FLOOR SLAB 1 5.800 5.800 33.640
INSIDE
Total 204.440
Total Quantity in sqm 204.440
4.013 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as
per manufacturer's specifications including appropriate priming coat, preparation of
surface, etc. complete.On concrete work
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's
OUTSIDE 4 6.400 3.500 89.600
WALL
Total 89.600
Total Quantity in sqm 89.600
4.014 22.23.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work
For base slab 0.785 5.200 5.200 0.300 6.368
Total 6.368
Total Quantity in cum 6.368
5.005 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
deduction
Manhole -1 0.500 0.500 0.200 -0.050
Total -0.050
Providing and laying in position ready mixed M-25 grade concrete for RCC work
FOR TANK 3.14 5.300 0.300 3.500 17.474
WALLS
COVER SLAB 0.785 5.600 5.600 0.200 4.924
Total 22.398
Total Quantity in cum 22.348
5.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for RCC work including straitening, cutting, bending, placing in
position
@120Kg/m3 1 28.720 120.000 3446.400
Total 3446.400
Total Quantity in kilogram 3446.400
5.007 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Extra for providing richer mixes at all floor levels.
1 28.716 28.716
Total 28.716
Total Quantity in cum 28.716
5.008 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material in cement concrete work
1 28.716 330.000 9476.280
Total 9476.280
Total Quantity in kg 9476.280
5.009 OD5139/2022-2023
Extra for providing epoxy coating for reinforcement bars
Epoxy coating
@120Kg/m3 1 28.716 120.000 3445.920
Total 3445.920
Total Quantity in kg 3445.920
5.010 OD5140/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing sulphate resistant cement for the structures above plinth level
1 28.716 28.716
Total 28.716
Total Quantity in tonne 28.716
5.011 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting etc.
FOR PCC 3.14 6.400 0.100 2.010
FOR FLOOR 3.14 6.200 0.300 5.840
SLAB
Total 7.850
Filling water with 5000 litre tankers fited in lorry and conveying water from a distance
of 5 km (average) to the reservoir site and pumping the water into the reservoir of
height not less than 3 m using 5 HP diesel engine pump set , hire for tanker lorry, tools
and other appliences and cost of water etc. complete.
Filling water 5000 litre tankers fitted in lorry
TANK IN SIDE 0.785 5.000 5.000 3.500 68.688
VOLUMN
Total 68.688
Total Quantity in Kilo litre 68.688
6 SLUDGE THICKNER
6.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Earth work in excavation by mechanical means (Hydraulic excavator)
0.785 16.200 16.200 1.500 1.1200 346.106
00
Total 346.106
Total Quantity in cum 346.106
6.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding cost of
centering
0.785 16.200 16.200 0.200 1.1200 46.147
00
Total 46.147
Total Quantity in cum 46.147
6.003 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for RCC work
1.1200
0.785 16.000 16.000 0.350 78.776
00
Total 78.776
Total Quantity in cum 78.776
6.004 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for RCC work
Wall 3.14 15.100 0.300 3.500 49.785
Inside channel 3.14 14.200 0.600 0.100 2.675
base
Wall 3.14 13.700 0.100 0.300 1.291
Walk way 3.14 15.800 0.700 0.120 4.167
Centre shaft 3.14 0.650 0.150 6.000 1.837
Shaft base 1 2.000 2.000 0.350 1.400
Cantilever beam 2 0.700 0.250 0.250 0.088
Step 8 1.000 0.275 0.185 0.407
Step waist 1 5.000 1.000 0.120 0.600
Total 62.250
Total Quantity in cum 62.250
6.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Extra providing richer mixes at all floor levels
Qty vide item No. 1 78.766+6 141.016
3&4 2.25
Total 141.016
Total Quantity in cum 141.016
6.006 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material in cement concrete work
3.400 360.00 17410.42
Wall 3.14 15.100 0.300 0000 1
Inside channel 3.14 14.200 0.600 0.100 360.00 963.101
base 0000
Wall 3.14 13.700 0.100 0.300 360.00 464.594
0000
Center shaft 3.14 0.650 0.150 6.000 360.00 661.284
0000
Shaft base 1 2.000 2.000 0.350 360.00 504.000
0000
20003.40
Total 0
Extra for providing and mixing water proofing material in cement concrete work
0.350 360.00 25320.96
Base 0.785 16.000 16.000 0000 0
25320.96
Total 0
6.007 OD5996/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing sulphate resistant cement for the structures above plinth level
Base 0.785 16.000 16.000 0.350 70.336
Total 70.336
Extra for providing sulphate resistant cement for the structures above plinth level
Wall 3.14 15.100 0.300 3.500 49.785
Inside channel 3.14 14.200 0.600 0.100 2.675
base
Wall 3.14 13.700 0.100 0.300 1.291
Centre shaft 3.14 0.650 0.150 6.000 1.837
Shaft base 1 2.000 2.000 0.350 1.400
Total 56.988
Total Quantity in cum 127.324
6.008 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for RCC work including straitening, cutting, bending, placing in
position
Qty vide item No, 78.766+6 16921.92
3&4@ 1 120.000
2.25 0
120km/m3
16921.92
Total 0
16921.92
Total Quantity in kilogram 0
6.009 OD5997/2022-2023
Extra for providing epoxy coating for reinforcement bars
Extra for providing epoxy coating for reinforcement bars
Qty vide item No,
1 16921.920 2030630.
3&4@ 120.000 400
120km/m3
2030630.
Total 400
2030630.
Total Quantity in kg 400
6.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting etc.
Base side 3.14 16.200 0.350 17.804
Centre shaft base- 4 2.000 0.350 2.800
side
Total 20.604
Total Quantity in sqm 20.604
6.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting etc.
Wall inside 3.14 14.800 3.500 162.652
Outside 3.14 15.400 3.500 169.246
Inside channel 3.14 13.800 0.300 13.000
wall
Inside channel 3.14 13.600 0.420 17.936
wall
Centre shaft 3.14 0.800 6.000 15.072
Total 377.906
Total Quantity in sqm 377.906
6.012 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Centering and shuttering including strutting etc.
Inside channel 3.14 14.200 0.600 26.753
base slab
Walkway 3.14 15.800 0.700 34.728
Side 3.14 16.800 0.120 6.330
Stair step 16 0.185 1.000 2.960
0.5000
Side 32 0.275 0.185 0.814
00
stair waist 1 5.000 1.000 5.000
Beam 4 0.700 0.250 0.700
Total 77.285
Total Quantity in sqm 77.285
6.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12mm cement plaster finished with a floating coat of neat cement of mix
1.1200
Floor 0.785 14.800 14.800 192.580
00
Wall inside 3.14 14.800 3.500 162.652
Center shaft 3.14 0.800 5.000 12.560
Channel 6.28 14.200 0.600 53.506
Channel wall 3.14 13.600 0.300 12.811
Channel wall 3.14 13.400 0.420 17.672
Total 451.781
Total Quantity in sqm 451.781
6.014 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
12mm cement plaster of mix
Wall outside 3.14 15.400 3.500 169.246
Walk way top 3.14 15.800 1.000 49.612
Bottom 3.14 16.200 0.700 35.608
Edge 3.14 16.800 0.120 6.330
Stair 1 5.000 1.000 5.000
Step 16 1.000 0.460 7.360
side 2 5.000 0.150 1.500
side 16 0.275 0.185 0.814
Total 275.470
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using
cover slab 0.785 4.000 4.000 0.120 1.507
side wall 3.14 3.700 0.300 2.500 8.714
Total 10.221
RCC WORK
MANHOLE -1 0.500 0.500 0.120 -0.030
Total -0.030
Total Quantity in cum 10.191
7.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using
1 15.206 15.206
Total 15.206
Total Quantity in cum 15.206
7.006 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as
1 15.206 330.000 5017.980
Total 5017.980
Total Quantity in kg 5017.980
7.007 OD5174/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing and mixing water proofing material in cement concrete work in
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Centering and shuttering including strutting, etc. and removal of form for:
FOR
COVERING 0.785 4.000 4.000 12.560
SLAB
Total 12.560
CENTERING &SHUTTERING
MANHOLE -1 0.500 0.500 -0.250
Total -0.250
Total Quantity in sqm 12.310
7.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Centering and shuttering including strutting, etc. and removal of form for:
FLOOR SLAB 0.785 3.400 3.400 9.075
TANK WALL 6.28 3.700 2.500 58.090
COVERING 1.57 3.700 3.700 21.493
SLAB
Total 88.658
Total Quantity in sqm 88.658
7.014 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as
per manufacturer's specifications including appropriate priming coat, preparation of
surface, etc. complete.On concrete work
Centering and shuttering including strutting, etc. and removal of form for:
TANK WALL 3.14 4.000 2.620 32.907
OUTSIDE
COVERING 0.785 4.000 4.000 12.560
SLAB TOP
Total 45.467
Total Quantity in sqm 45.467
7.015 22.23.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a distance
of 5 km (average) to the reservoir site and pumping the water into the reservoir of
height not less than 3 m using 5 HP diesel engine pump set , hire for tanker lorry, tools
and other appliences and cost of water etc. complete.
Centering and shuttering including strutting, etc. and removal of form for:
0.785 3.400 3.400 2.500 22.687
Total 22.687
Total Quantity in Kilo litre 22.687
8 CENTRATE SUMP
8.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5
0.785 3.400 3.400 0.500 4.537
Total 4.537
Total Quantity in cum 4.537
8.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to
0.785 3.400 3.400 0.200 1.815
Total 1.815
Total Quantity in cum 1.815
8.003 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
0.785 3.200 3.200 0.300 2.412
Total 2.412
Total Quantity in cum 2.412
8.004 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
COVER SLAB 0.785 2.600 2.600 0.120 0.637
SIDE WALL 3.14 2.300 0.300 3.000 6.500
Total 7.137
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
MANHOLE -1 0.500 0.500 0.120 -0.030
Total -0.030
Total Quantity in cum 7.107
8.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
1 7.107+2. 9.519
412
Total 9.519
Total Quantity in cum 9.519
8.006 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's
1 9.519 340.000 3236.460
Total 3236.460
8.012 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Centering and shuttering including strutting, etc. and removal of form for:
FOR
COVERING 0.785 2.000 2.000 3.140
SLAB
Total 3.140
Centering and shuttering including strutting, etc. and removal of form for:
MANHOLE -1 0.500 0.500 -0.250
Total -0.250
Total Quantity in sqm 2.890
8.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix:
FOR FLOOR 0.785 2.000 2.000 3.140
SLAB
TANK WALL
INSIDE 6.28 2.300 3.000 43.332
&OUTSIDE
COVERING 3.144 2.600 2.600 21.253
SLAB
COVERING 3.144 2.000 2.000 12.576
SLAB
Total 80.301
Total Quantity in sqm 80.301
8.014 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as
per manufacturer's specifications including appropriate priming coat, preparation of
surface, etc. complete.On concrete work
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including
TANK WALL 3.14 2.600 3.000 2.500 61.230
OUTSIDE
COVERING 0.785 2.600 2.600 5.307
SLAB Top
Total 66.537
Total Quantity in sqm 66.537
8.015 22.23.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a distance
of 5 km (average) to the reservoir site and pumping the water into the reservoir of
height not less than 3 m using 5 HP diesel engine pump set , hire for tanker lorry, tools
and other appliences and cost of water etc. complete.
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and
TANK INSIDE 0.785 2.000 2.000 3.000 9.420
VOLUME
Total 9.420
Total Quantity in Kilo litre 9.420
9 CHLORINATOR CONTACT TANK
9.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm i
Tank foundation 1 25.650 13.150 3.500 1180.541
Total 1180.541
Total Quantity in cum 1180.541
9.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost
of centering
Tank outerwall 2 26.100 3.150 0.150 24.665
basebottom
Tank outerwall 2 7.300 3.150 0.150 6.899
basebottom
Beam bottom 5 10.000 0.700 0.150 5.250
Beam bottom 1 2.800 0.700 0.150 0.294
Beam bottom 1 1.250 0.700 0.150 0.131
Base bottom 1 20.000 10.000 0.150 30.000
Total 67.239
Total Quantity in cum 67.239
9.003 OD7428/2022-2023
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20cm in depth, consolidation each deposited layer by ramming and
watering, with all lead and lift as per direction of site Engineer-in-charge
Deductions
Total 336.232
Total Quantity in cum 336.232
9.007 OD18128/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level.
Extra for providing sulphate resistant cement for the structures above plinth level.
1 336.232 336.232
Total 336.232
Total Quantity in cum 336.232
9.008 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material i
SUM OF ITEM
NUMBER 1 211.94+1 336.232
24.292
5.37.2+5.37.1
Total 336.232
Total Quantity in kg 336.232
9.009 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting, etc. and removal of form for:
TANK OUTER 2 25.900 0.300 15.540
WALL BASE
TANK OUTER 2 13.100 0.300 7.860
WALL BASE
TANK OUTER 2 20.100 0.300 12.060
WALL BASE
TANK OUTER 2 7.600 0.300 4.560
WALL BASE
BASE 1 68.600 0.300 20.580
Total 60.600
Total Quantity in sqm 60.600
9.010 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, etc. and removal of form for:
TANK OUTER 1 68.600 3.500 240.100
WALL
TANK OUTER 1 65.000 3.500 227.500
WALL
INTER
MEDIATE 10 8.500 3.500 297.500
WALL
INTER
MEDIATE 2 3.000 3.500 21.000
WALL
INTER
MEDIATE 2 1.500 3.500 10.500
WALL
Total 796.600
Centering and shuttering including strutting, etc. and removal of form for:
WALL 2 23.400 1.600 74.880
WALL 2 22.500 1.600 72.000
WALL 2 10.900 1.600 34.880
WALL 2 10.000 1.600 32.000
BEAM 10 10.000 0.200 20.000
BEAM 2 3.000 0.200 1.200
BEAM 2 1.350 0.200 0.540
Total 235.500
Total Quantity in sqm 1032.100
9.011 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and
120.00 25433.52
ITEM 5.37.1 1 211.946 0000 0
120.00 14915.04
ITEM 5.37.2 1 124.292 0000 0
40348.56
Total 0
9.012 OD7447/2022-2023
Extra for providing epoxy coating for reinforcement bars
Extra for providing epoxy coating for reinforcement bars
120.00 25433.52
ITEM 5.37.1 1 211.946 0000 0
120.00 14915.04
ITEM 5.372 1 124.292 0000 0
40348.56
Total 0
40348.56
Total Quantity in kg 0
9.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix: 1:3 ( 1
cement : 3 fine sand)
FLOOR 1 20.000 10.000 200.000
WALL 2 22.500 3.500 157.500
WALL 2 10.000 3.500 70.000
INTERMEDIAT 10 8.500 3.500 297.500
E WALL
INTERMEDIAT 2 3.000 3.500 21.000
E WALL
INTERMEDIAT 2 1.500 3.500 10.500
E WALL
WALL OUTER 2 23.400 4.000 187.200
WALL OUTER 2 10.900 4.000 87.200
WALLTOP 1 65.000 0.230 14.950
WALLTOP 5 8.500 0.200 8.500
WALLTOP 1 3.000 0.200 0.600
WALLTOP 1 1.500 0.200 0.300
Total 1055.250
Total Quantity in sqm 1055.250
9.014 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as
per manufacturer's specifications including appropriate priming coat, preparation of
surface, etc. complete.On concrete work
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's
WALL 2 22.500 0.500 22.500
WALL 2 10.000 0.500 10.000
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse
sand : 6 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to
1 11.400 11.400 0.200 25.992
Total 25.992
Total Quantity in cum 25.992
10.00 5.37.1
3 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
1 11.200 11.200 0.300 37.632
Total 37.632
Total Quantity in cum 37.632
10.00 5.37.2
4 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per
LONG WALL 2 10.600 0.300 3.600 22.896
SHORT WALL 2 10.000 0.300 3.600 21.600
Total 44.496
Total Quantity in cum 44.496
10.00 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/
1 44.496+3 82.128
7.632
Total 82.128
Total Quantity in cum 82.128
10.00 4.12
6 Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's
27102.24
1 82.128 330.000 0
27102.24
Total 0
10.00 OD6604/2022-2023
7 Extra for providing sulphate resistant cement for the structures above plinth level
Extra for providing sulphate resistant cement for the structures above plinth level
1 82.128 82.128
Total 82.128
Total Quantity in cum 82.128
10.00 5.22.6
8 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth
@120KG/M3 1 82.128 120.000 9855.360
Total 9855.360
Total Quantity in kilogram 9855.360
10.00 OD6605/2022-2023
9 Extra for providing epoxy coating for reinforcement bars
Extra for providing epoxy coating for reinforcement bars
@120KG/M3 1 82.128 120.000 9855.360
Total 9855.360
10.01 22.23.1
4 Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like
FOR WALLS 4 10.000 3.600 144.000
Total 144.000
Total Quantity in sqm 144.000
10.01 22.23.2
5 Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like
FOR BASE 1 10.000 10.000 100.000
SLAB INSIDE
Total 100.000
Total Quantity in sqm 100.000
10.01 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a distance
of 5 km (average) to the reservoir site and pumping the water into the reservoir of
height not less than 3 m using 5 HP diesel engine pump set , hire for tanker lorry, tools
and other appliences and cost of water etc. complete.
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and
1 10.000 10.000 3.600 360.000
Total 360.000
Total Quantity in Kilo litre 360.000
11 CENTRIFUGE BUILDING
11.00 2.3.1
1 Banking excavated earth in layers not exceeding 20 cm in depth, breaking clods,
watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and
rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and
dressing up, in embankments for roads, flood banks, marginal banks, and guide banks
etc., lead up to 50 m and lift up to 1.5 m :All kinds of soil
Clearing jungle
Building area 1 18.000 15.000 270.000
Total 270.000
Total Quantity in cum 270.000
11.00 20.2.4
2 Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe working
load not less than specified, excluding the cost of steel reinforcement but including the
cost of boring, with bentonite solution and temporary casing of appropriate length for
setting out and removal of same and the length of the pile to be embedded in the pile
cap etc. all complete, including removal of excavated earth with all lifts and leads
(Length of pile for payment shall be measured upto bottom of pile cap).500 mm dia
piles
Boring
500mm dia 6 18.000 108.000
Total 108.000
Total Quantity in metre 108.000
11.00 5.22.2
3 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Steel reinforcement for RCC work
for pile @ 18.84 0.250 0.250 18.000 120.00
120kg/Cum 0000 2543.400
Total 2543.400
Total Quantity in kilogram 2543.400
11.00 20.6.2.1
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityInitial test
Vertical load testing of piles
500mm dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
11.00 20.6.2.2
5 Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityRoutine test
Vertical load testing of piles
500mm dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
11.00 2.8.1
6 Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting
out the excavated soil and disposal of surplus excavated soil as directed, within a lead
of 50 m.All kinds of soil
Earth work in excavation
For pile cap 6 1.100 1.100 0.500 3.630
Plinth beam 3 5.450 0.350 0.100 0.572
Plinth beam 2 4.010 0.350 0.100 0.281
2 3.540 0.350 0.100 0.248
Ramp 1 3.000 2.200 0.100 0.660
Total 5.391
Total Quantity in cum 5.391
11.00 4.1.8
7 Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
Providing and laying in position cement concrete
Pile cap 6 1.100 1.100 0.100 0.726
Plinth bottom 3 5.450 0.350 0.100 0.572
Plinth bottom 2 4.010 0.350 0.100 0.281
Providing and laying in position machine batched and machine mixed design mix M-
20 grade cement concrete for reinforced cement concrete work, using cement content
as per approved design mix, including pumping of concrete to site of laying but
excluding the cost of centering, shuttering, finishing and reinforcement, including
admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of
concrete, improve workability without impairing strength and durability as per
direction of Engineer-in-charge. Note:- Cement content considered in this item is @
330 kg/cum. Excess or less cement used as per design mix is payable or recoverable
separately. All work above plinth level upto floor V level
Ground Floor
GF column 4 0.350 0.350 4.725 2.315
2 0.350 0.450 4.725 1.488
Floor beam FB1 2 6.000 0.300 0.325 1.170
& FB 1A
Floor beam FB3 2 4.860 0.300 0.325 0.948
Floor beam FB3 2 4.040 0.300 0.325 0.788
Floor beam FB2 1 6.000 0.450 0.325 0.878
2 8.550 0.450 0.325 2.501
Slab 1 11.700 6.700 0.125 9.799
Pedestal 12 0.300 0.300 0.450 0.486
Outer lintel 1 6.000 0.200 0.200 0.240
Outer lintel 2 4.860 0.200 0.200 0.389
Outer lintel 2 4.040 0.200 0.200 0.323
Dosing tank 1 3.400 1.900 0.250 1.615
Side wall 2 3.400 0.200 2.350 3.196
Side wall 3 1.500 0.200 2.350 2.115
Slab 1 4.400 0.770 0.125 0.424
Star case wst slab 1 4.200 1.200 0.150 0.756
Landing 2 1.200 1.000 0.150 0.360
star case wst slab 1 3.550 1.200 0.150 0.639
Landing beam 2 1.200 0.230 0.200 0.110
Steps 12 1.200 0.275 0.175 0.693
Ramp 1 3.000 2.200 0.125 0.825
Total 32.058
First floor
FF Column 4 0.350 0.350 4.425 2.168
2 0.350 0.450 4.425 1.394
Roof Beam RB 1 2 6.000 0.300 0.325 1.170
Roof beam RB3 2 4.860 0.300 0.325 0.948
Roof beam RB3 2 4.040 0.300 0.325 0.788
Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Centering and shuttering including strutting, etc.
GF column 4 1.400 4.730 26.488
GF column 2 1.600 4.730 15.136
FF column 4 1.400 4.430 24.808
FF column 2 1.600 4.430 14.176
Total 80.608
Total Quantity in sqm 80.608
11.01 5.22.6
5 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for R.C.C work
@120kg/1Cum 1 12.770+4 120.00 7456.440
CC 9.367 0000
Total 7456.440
Total Quantity in kilogram 7456.440
11.01 50.6.7.2
6 Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Laterate masonry
Wall 2 4.040 0.200 4.200 6.787
Wall 1 4.040 0.200 4.725 3.818
Wall 1 4.770 0.200 4.200 4.007
Wall 2 6.000 0.200 4.200 10.080
Wall 2 4.500 0.200 4.200 7.560
FF wall 2 4.510 0.200 1.000 1.804
FF wall 2 4.040 0.200 1.000 1.616
FF wall 1 8.300 0.200 1.000 1.660
Parapet wall 2 10.300 0.200 0.600 2.472
Parapet wall 2 6.900 0.200 0.600 1.656
Total 41.460
Laterate masonry deduction
tank side wall -1 3.400 0.200 2.350 -1.598
tank side wall -1 4.510 0.200 1.850 -1.669
RS -1 3.000 0.200 3.000 -1.800
Door -1 1.200 0.200 2.400 -0.576
Total -5.643
Total Quantity in cum 35.817
11.01 13.1.1
7 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Inside plastering
GF wall 1 4.730 4.520 21.380
GF wall 2 6.000 4.520 54.240
Tank outer 1 4.730 2.350 11.116
Tank outer 2 1.700 2.350 7.990
Room 2 4.440 4.520 40.138
Room 2 4.240 4.520 38.330
Room 1 4.570 4.520 20.656
FF inside 2 10.700 1.000 21.400
FF inside 1 6.700 1.000 6.700
Total 221.950
Outside plastering
Ground floor 2 9.700 4.650 90.210
Ground floor 2 6.700 4.650 62.310
Column 12 0.100 4.650 5.580
First floor 2 10.700 1.230 26.322
First floor 1 6.700 1.230 8.241
Column 2 1.600 3.450 11.040
Column 4 1.400 3.450 19.320
Parapet wall 1 35.200 1.500 52.800
Total 275.823
12 mm cement plaster of mix: 1:4 Deduction
Rolling Shutter -2 3.000 3.000 -18.000
Door -1 1.200 2.400 -2.880
Total -20.880
Total Quantity in sqm 476.893
11.01 13.7.1
8 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat
Slab top 1 9.900 6.900 68.310
Tank inside 2 1.400 1.500 4.200
Wall 2 5.800 2.350 27.260
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end by
end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS: 4454
- part 1 and M.S. top cover of required thickness for rolling shutters.80x1.20 mm M.S.
laths with 1.20 mm thick top cover
Supplying and fixing rolling shutters
Rolling shutter 1 3.000 3.000 9.000
Total 9.000
Total Quantity in sqm 9.000
11.02 10.3
2 Providing and fixing in position collapsible steel shutters with vertical channels
20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom
rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts,
nuts,locking arrangement, stoppers, handles, including applying a priming coat of
approved steel primer .
Providing and fixing in position collapsible steel shutters
Front Op. 1 1.200 2.400 2.880
Total 2.880
Total Quantity in sqm 2.880
11.02 10.26.3
3 Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat of
approves steel primer.G.I. pipes
Providing and fixing hand rail
Vertical post
50mm GI-B 13 0.900 5.100 59.670
Class
Horizontal 40 GI 2 18.650 3.610 134.653
Total 194.323
Total Quantity in kg 194.323
11.02 13.61.1
4 Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:Two or more coats on new work
Painting with synthetic enamel paint
2.5000
rolling shutter 1 3.000 3.000 22.500
00
Stair hand rail 1 9.750 0.900 8.775
Passage hand rail 1 8.900 0.900 8.010
Collapsible gate 1 1.200 2.400 2.880
Total 42.165
Total Quantity in sqm 42.165
11.02 13.43.1
5 Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Deduction
Rolling Shutter -2 3.000 3.000 -18.000
Door -1 1.200 2.400 -2.880
Total -20.880
Outside plastering
Ground floor 2 9.700 4.650 90.210
Ground floor 2 6.700 4.650 62.310
Column 12 0.100 4.650 5.580
First floor 2 10.700 1.230 26.322
First floor 1 6.700 1.230 8.241
Column 2 1.600 3.450 11.040
Column 4 1.400 3.450 19.320
Parapet wall 1 35.200 1.500 52.800
Total 275.823
Slab and beam
Slab bottom 1 4.730 6.000 28.380
Slab bottom 1 4.040 4.570 18.463
Slab bottom 1 4.240 1.200 5.088
Slab bottom 2 6.700 1.000 13.400
Stair bottom 1 9.750 1.200 11.700
Beam side 2 1.200 0.200 0.480
Slab edge 2 1.200 0.150 0.360
FF slab bottom 1 10.300 6.700 69.010
Beam side 6 6.000 0.350 12.600
Beam side 4 4.860 0.350 6.804
Beam side 4 4.040 0.350 5.656
Beam side 2 8.700 0.350 6.090
Total 178.031
Inside plastering
GF wall 1 4.730 4.520 21.380
GF wall 2 6.000 4.520 54.240
Tank outer 1 4.730 2.350 11.116
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Steel reinforcement for RCC work including straightening, cutting, bending
120 kg/ Cum of 25.12 0.200 0.200 18.000 120.00
cc 0000 2170.368
Total 2170.368
Total Quantity in kilogram 2170.368
12.00 20.6.1.1
4 Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile upto 50 tonne capacityInitial test
vertical load testing of pile
400mm Dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
12.00 20.6.1.2
5 Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile upto 50 tonne capacityRoutine test
vertical load testing of pile
400mm Dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
12.00 2.8.1
6 Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting
out the excavated soil and disposal of surplus excavated soil as directed, within a lead
of 50 m.All kinds of soil
Earth work in excavation by mechanical means
Pile cap 8 1.000 1.000 0.350 2.800
Ramp 1 3.200 1.000 0.100 0.320
Plinth beam 3 6.000 0.350 0.100 0.630
Plinth beam 2 3.220 0.350 0.100 0.225
Plinth beam 4 4.110 0.350 0.100 0.575
Neutralization pit 1 2.900 2.900 1.500 12.615
Total 17.165
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20 cm in depth, consolidating each deposited layer by ramming and
watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-
charge.
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20 cm in depth, consolidating each deposited layer
Basement Inside 1 10.000 7.000 0.400 28.000
Basement Inside 1 4.000 7.000 0.400 11.200
Ramp 0.5 3.000 1.000 0.400 0.600
Total 39.800
Total Quantity in cum 39.800
12.01 5.37.1
3 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for RCC work
Pile cap 8 0.800 0.800 0.750 3.840
Plinth beam 3 6.200 0.250 0.450 2.093
Plinth beam 2 3.420 0.250 0.450 0.770
Plinth beam 4 4.310 0.250 0.450 1.940
Ramp 1 3.000 1.500 0.150 0.675
Neutralization pit 1 2.900 2.900 0.200 1.682
Neutralization pit 4 2.700 0.200 1.800 3.888
Tanner base 2 5.000 0.300 0.450 1.350
Tanner base 2 2.500 0.300 0.450 0.675
Mottor base 4 0.800 0.800 0.200 0.512
Total 17.425
Total Quantity in cum 17.425
12.01 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M-25 grade concrete for RCC work
Column above 8 0.250 0.400 5.000 4.000
plinth
Lintel 3 6.200 0.200 0.150 0.558
Lintel 4 4.310 0.200 0.150 0.517
Lintel 2 3.420 0.200 0.150 0.205
Shade 2 14.600 0.600 0.100 1.752
Shade 1 8.600 0.600 0.100 0.516
Shade 1 8.600 0.750 0.100 0.645
Beam 3 6.400 0.250 0.500 2.400
Beam 1 7.000 0.250 0.500 0.875
Beam 4 4.310 0.250 0.400 1.724
Beam 2 3.420 0.250 0.400 0.684
Slab 1 15.200 8.000 0.120 14.592
Corbell 6 0.250 0.400 0.200 0.120
Corbell 3 0.250 0.400 0.250 0.075
Tie beam 2 10.400 0.300 0.300 1.872
Total 30.535
Total Quantity in cum 30.535
12.01 5.22.6
5 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
@120kg 1 Cum 1 17.429+3 120.00 5747.160
of cc 0.464 0000
Total 5747.160
Total Quantity in kilogram 5747.160
12.01 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Laterate masonry with neatly dressed laterate stone (Deduction)
Window -3 1.500 0.200 1.500 -1.350
Door -1 1.000 0.200 2.100 -0.420
Rs -1 3.000 0.200 3.000 -1.800
Jally space -1 3.420 0.200 1.800 -1.231
Jally space -2 4.310 0.200 1.800 -3.103
Lintel -1 43.280 0.200 0.150 -1.298
Total -9.202
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6
Wall 3 6.400 0.200 4.500 17.280
Wall 2 3.420 0.200 4.500 6.156
Wall 4 4.310 0.200 4.500 15.516
Ramp side 1 1.500 0.200 0.450 0.135
Parapet 1 2*15.2+2 0.200 0.400 3.648
*7.6
Total 42.735
Total Quantity in cum 33.533
12.01 13.1.1
7 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
12 mm cement plaster of mix: 1:4 (Deduction)
Window -3 1.500 1.500 -6.750
Door -1 1.000 2.100 -2.100
Rs -2 3.000 3.000 -18.000
Op -2 3.420 1.800 -12.312
Op -4 4.310 1.800 -31.032
Total -70.194
12 mm cement plaster of mix: 1:4 ( 1 cement : 4 fine sand)
Outer wall 1 2*14.6+2 5.500 242.000
*7.4
Column 16 0.050 5.000 4.000
projection
Inner wall 1 34.000 5.500 187.000
Inner wall 1 22.000 5.500 121.000
Corbel 6 0.400 1.050 2.520
Tie beam 2 10.000 0.900 18.000
2*15.2+2
Parapet 1 1.000 45.600
*7.6
Pit inside 1 2.500 2.500 6.250
Pit inside 4 2.500 1.800 18.000
Tunnr stand 2 2.500 1.200 6.000
Tunnr stand 2 5.000 1.200 12.000
Side 8 0.300 0.450 1.080
Shade top 2 14.600 0.600 17.520
Shade top 1 8.600 0.600 5.160
Shade top 1 8.600 0.750 6.450
Edge 8 0.600 0.100 0.480
Total 693.060
Total Quantity in sqm 622.866
12.01 13.7.1
8 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix:
Slab top 1 14.800 7.600 112.480
Tunner room 1 10.000 7.000 70.000
floor
Ramp 1 3.000 2.000 6.000
Total 188.480
Total Quantity in sqm 188.480
12.01 13.16.1
9 6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
6 mm cement plaster of mix: 1:3
Shade bottom 1 2*14.6+8 0.600 22.680
.6
Shade bottom 1 8.600 0.750 6.450
Ceiling 1 10.000 7.000 70.000
Ceiling 1 4.000 7.000 28.000
Beam 2 7.000 0.600 8.400
Slab projection 1 45.200 0.300 13.560
SlabEdge 1 46.400 0.120 5.568
Total 154.658
Total Quantity in sqm 154.658
12.02 9.48.2
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel primer
all complete.Fixed to openings/ wooden frames with rawl plugs screws etc
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc.
20.000
Window grill 3 1.500 1.500 135.000
000
Total 135.000
Total Quantity in kg 135.000
12.02 21.1.1.1
1 Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
For fixed portionAnodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard
Window outer 4.5000
3 1.500 1.500 30.375
frame 00
4.0000
Door outer frame 1 1.000 2.100 8.400
00
Total 38.775
Total Quantity in kg 38.775
12.02 21.1.2.1
2 For shutters of doors, windows & ventilators including providing and fixing hinges /
pivots and making provision for fixing of fittings wherever required including the cost
of EPDM rubber/ neoprene gasket required (Fittings shall be paid for
separately)Anodised aluminium ( anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
For shutters of doors, windows & ventilators including providing and fixing
hinges / pivots and making provision
Shutter frame 6 0.750 1.470 3.0000 19.845
00
Door 1 0.900 2.000 3.0000 5.400
00
Total 25.245
Total Quantity in kg 25.245
12.02 21.3.1
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc.
For window 3.0000
6 0.640 1.420 16.358
shutter 00
3.0000
Doors 2 1.020 0.880 5.386
00
Total 21.744
Total Quantity in sqm 21.744
12.02 11.41.2
4 Providing and laying vitrified floor tiles in different sizes (thickness to be specified by
the manufacturer) with water absorption less than 0.08% and conforming to IS :
15622, of approved make, in all colours and shades, laid on 20 mm thick cement
mortar 1:4(1 cement : 4 coarse sand), including grouting the joints with white cement
and matching pigments etc., complete.Size of Tile 600 x 600 mm.
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by
the manufacturer)
Floor finishing 1 7.200 4.200 30.240
Step 1 1.200 1.050 1.260
Side 2 0.600 0.450 0.540
Total 32.040
Total Quantity in sqm 32.040
12.02 13.43.1
5 Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Applying one coat of water thinnable cement
Shade bottom 1 2*14.6+8 0.600 22.680
.6
Shade bottom 1 8.600 0.750 6.450
Ceiling 1 10.000 7.000 70.000
Ceiling 1 4.000 7.000 28.000
Beam 2 7.000 0.600 8.400
Slab projection 1 45.200 0.300 13.560
SlabEdge 1 46.400 0.120 5.568
Total 154.658
Deduction
Window -3 1.500 1.500 -6.750
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end by
end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS: 4454
- part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S.
laths with 1.25 mm thick top cover
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths
Front gate 1 3.000 3.000 9.000
Total 9.000
Total Quantity in sqm 9.000
12.02 13.63.1
8 Painting with aluminium paint of approved brand and manufacture to give an even
shade.Two or more coats on new work
Painting with aluminium paint of approved brand and manufacture to give an even
shade.
Window 3 1.500 1.500 6.750
Rs 1 3.000 3.000 2.5000 22.500
00
Total 29.250
Total Quantity in sqm 29.250
13 AIR BLOWER BUILDING
13.00 2.31
1 Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
Clearing jungle
Building area 1 10.000 15.000 150.000
Total 150.000
Total Quantity in sqm 150.000
13.00 20.2.2
2 Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe working
load not less than specified, excluding the cost of steel reinforcement but including the
cost of boring, with bentonite solution and temporary casing of appropriate length for
setting out and removal of same and the length of the pile to be embedded in the pile
cap etc. all complete, including removal of excavated earth with all lifts and leads
(Length of pile for payment shall be measured upto bottom of pile cap).400 mm dia
piles
Boring
400mm Dia 6 18.000 108.000
Total 108.000
Total Quantity in metre 108.000
13.00 5.22.2
3 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Steel reinforcement for RCC work
120 kg/Cum of cc 18.84 0.200 0.200 18.000 120.00
0000 1627.776
Total 1627.776
Total Quantity in kilogram 1627.776
13.00 20.6.2.1
4 Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityInitial test
Vertical load testing of piles
400mm dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
13.00 20.6.2.2
5 Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete as per specification & the direction
of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityRoutine test
Vertical load testing of piles
400mm dia pile 1 1.000
Total 1.000
Total Quantity in per test 1.000
13.00 2.8.1
6 Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting
out the excavated soil and disposal of surplus excavated soil as directed, within a lead
of 50 m.All kinds of soil
Earth work in excavation
Pile cap 6 1.000 1.000 0.350 2.100
Ramp 1 3.200 1.000 0.100 0.320
Plinth beam 4 4.300 0.350 0.100 0.602
Plinth beam 2 4.550 0.350 0.100 0.319
20.000
Ventilator 6 1.000 0.600 72.000
000
Total 297.000
Total Quantity in kg 297.000
13.02 21.1.1.1
3 Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
For fixed portionAnodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Providing and fixing aluminium work for doors, windows, ventilators and partitions
4.5000
Windows 5 1.500 1.500 50.625
00
4.5000
Ventilator 6 1.000 0.600 16.200
00
Total 66.825
Total Quantity in kg 66.825
13.02 21.1.2.1
4 For shutters of doors, windows & ventilators including providing and fixing hinges /
pivots and making provision for fixing of fittings wherever required including the cost
of EPDM rubber/ neoprene gasket required (Fittings shall be paid for
separately)Anodised aluminium ( anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
For shutters of doors, windows & ventilators including providing and fixing
hinges / pivots
3.0000
Window shutter 10 0.700 1.480 31.080
00
Total 31.080
Total Quantity in kg 31.080
13.02 21.3.1
5 Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions
conveyance
Cable trench 1 9.850 1.000 9.850
Total 9.850
Total Quantity in sqm 9.850
ADMINISTRATIVE / LABORATORY / CHEMICAL HOUSE / CONTROL ROOM
14 BUILDING
14.00 2.31
1 Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height
building area 1 30.000 15.000 450.000
Total 450.000
Total Quantity in sqm 450.000
14.00 20.2.2
2 Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe working
load not less than specified, excluding the cost of steel reinforcement but including the
cost of boring, with bentonite solution and temporary casing of appropriate length for
setting out and removal of same and the length of the pile to be embedded in the pile
cap etc. all complete, including removal of excavated earth with all lifts and leads
(Length of pile for payment shall be measured upto bottom of pile cap).400 mm dia
piles
Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and
PILE-P2-400 9 18.000 162.000
DIA
Total 162.000
Total Quantity in metre 162.000
14.00 20.2.4
3 Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe working
load not less than specified, excluding the cost of steel reinforcement but including the
cost of boring, with bentonite solution and temporary casing of appropriate length for
setting out and removal of same and the length of the pile to be embedded in the pile
cap etc. all complete, including removal of excavated earth with all lifts and leads
(Length of pile for payment shall be measured upto bottom of pile cap).500 mm dia
piles
Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and
PILE P1 500 DIA 4 14.000 56.000
Total 56.000
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering including strutting, etc. and removal of form for:
FOR PILE CAP 52 0.900 1.350 63.180
Total 63.180
Total Quantity in sqm 63.180
14.01 5.9.3
5 Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Centering and shuttering including strutting, etc. and removal of form for:
OPENING -1 3.680 2.500 -9.200
Total -9.200
G - FLOOR &F - FLOOR
STAIRE CASE 3 1.700 1.000 5.100
WASTE SLAB
SIDE 6 1.700 0.125 1.275
LANDING 2 1.200 1.200 2.880
ROOF SLAB 1 12.300 7.800 95.940
SLAB 1 8.000 1.200 9.600
ROOF SLAB 1 12.700 8.200 104.140
SLAB EDGE 1 41.800 0.125 5.225
SLAB OPENING 1 12.560 0.125 1.570
SIDE
STAIRE HEAD 1 4.800 4.980 23.904
ROOM SLAB
SLAB EDGE 1 19.560 0.125 2.445
Total 252.079
Total Quantity in sqm 242.879
14.01 5.9.5
6 Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
G -FLOOR$ F- FLOOR
SUN SHADE RS 1 3.000 0.750 2.250
SUN SHADEW 10 1.800 0.600 10.800
SUN SHADE 1 1.000 0.600 0.600
EDGE 22 0.600 0.080 1.056
EDGE 2 0.750 0.080 0.120
LINTELS 4 10.900 0.200 8.720
LINTELS 2 10.600 0.200 4.240
Total 121.200
Total Quantity in sqm 121.200
14.01 50.6.7.2
8 Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Supplying and providing Chequred plate 7mm thick including all cost and conveyance
of all materials and labour charges etc.
GF WALLS 2 10.900 0.200 3.050 13.298
GF WALLS 1 10.600 0.200 3.050 6.466
GF WALLS 3 6.700 0.200 3.050 12.261
GF WALLS 2 3.500 0.200 3.050 4.270
GF WALLS 1 3.200 0.200 3.050 1.952
FF WALLS 2 3.290 0.200 3.050 4.014
FF WALLS 2 3.850 0.200 3.050 4.697
FF WALLS 4 3.750 0.200 3.050 9.150
FF WALLS 1 6.840 0.200 3.050 4.172
TOILET WALL 1 3.000 0.200 3.050 1.830
CROSS WALL 4 3.300 0.200 3.050 8.052
4 3.500 0.200 3.050 8.540
1 2.500 0.200 3.050 1.525
PARAPET 1 41.000 0.200 0.450 3.690
HEAD ROOM 2 3.500 0.200 2.100 2.940
HEAD ROOM 2 3.680 0.200 2.100 3.091
Total 89.948
LATERATE MASONRY
DOORS -1 1.200 0.200 2.100 -0.504
DOORS -9 0.900 0.200 2.100 -3.402
DOORS -2 0.800 0.200 2.100 -0.672
HEAD ROOM -1 1.000 0.200 2.100 -0.420
DOORS
W -15 1.200 0.200 1.500 -5.400
-2 3.750 0.200 2.400 -3.600
-1 3.500 0.200 2.400 -1.680
-1 2.300 0.200 2.400 -1.104
V -2 0.600 0.200 0.500 -0.120
ROLLING -1 2.000 0.200 2.400 -0.960
SHUTTER
Total -17.862
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
For fixed portionAnodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/
FOR WINDOW 4.5000
15 1.200 1.500 121.500
FRAMES 00
4.5000
VENTILATOR 2 0.600 0.500 2.700
00
4.5000
DOORS 1 1.200 2.100 11.340
00
4.5000
DOORS 9 0.900 2.100 76.545
00
4.5000
DOORS 1 1.000 2.100 9.450
00
Total 221.535
Total Quantity in kg 221.535
14.02 21.1.2.1
9 For shutters of doors, windows & ventilators including providing and fixing hinges /
pivots and making provision for fixing of fittings wherever required including the cost
of EPDM rubber/ neoprene gasket required (Fittings shall be paid for
separately)Anodised aluminium ( anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
For shutters of doors, windows & ventilators including providing and fixing
hinges / pivots and making provision for fixing of fitting
FOR WINDOW 3.0000
30 0.570 1.470 75.411
SHUTTER 00
3.0000
VENTILATOR 2 0.570 0.470 1.607
00
3.0000
DOORS 1 1.120 1.960 6.586
00
3.0000
DOORS 9 0.820 1.960 43.394
00
3.0000
DOORS 1 0.920 1.960 5.410
00
Total 132.408
Total Quantity in kg 132.408
14.03 21.3.1
0 Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gaske
FOR WINDOW 3.0000
30 0.510 1.410 64.719
SHUTTER 00
3.0000
VENTILATOR 2 0.510 0.410 1.255
00
3.0000
DOORS 2 1.020 0.880 5.386
00
3.0000
DOORS 18 0.720 0.880 34.214
00
3.0000
DOORS 2 0.820 0.880 4.330
00
Total 109.904
Total Quantity in sqm 109.904
14.03 9.48.2
1 Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel primer
all complete.Fixed to openings/ wooden frames with rawl plugs screws etc
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including
FOR WINDOW 20.000
15 1.200 1.500 540.000
FRAMES 000
20.000
VENTILATOR 2 0.600 0.500 12.000
000
Total 552.000
Total Quantity in kg 552.000
14.03 10.28
2 Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding, buffing, polishing and making
curvature (wherever required) and fitting the same with necessary stainless steel nuts
and bolts complete, i/c fixing the railing with necessary accessories & stainless steel
dash fasteners, stainless steel bolts etc., of required size on the top of the floor or the
side of waist slab with suitable arrangement as per approval of Engineer-in-charge,
(for payment purpose only weight of stainless steel members shall be considered
excluding fixing accessories such as nuts, bolts, fasteners etc.)
Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding,
STAIR HAND 14.000
1 15.000 0.800 168.000
RAIL 000
14.03 13.60.1
6 Wall painting with acrylic emulsion paint of approved brand and manufacture to give
an even shade:Two or more coats on new work
Wall painting with acrylic emulsion paint of approved brand and manufacture to give
an even shade: Two or more coats on new work
QTY SAME AS
ITEM NO 1 1143.000 1143.000
13.43.1
Total 1143.000
Total Quantity in sqm 1143.000
14.03 13.61.1
7 Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:Two or more coats on new work
Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:
WINDOW 15 1.200 1.500 27.000
GRILL
VENTIL 2 0.600 0.500 0.600
COLLAPSIBLE 1 1.500 2.100 3.150
GATE
ROLLING 2.5000
1 2.000 2.400 12.000
SHUTTER 00
Total 42.750
Total Quantity in sqm 42.750
14.03 17.2.1
8 Providing and fixing white vitreous china pedestal type water closet (European type
W.C. pan) with seat and lid, 10 litre low level white P.V.C. flushing cistern, including
flush pipe, with manually controlled device (handle lever), conforming to IS : 7231,
with all fittings and fixtures complete, including cutting and making good the walls
and floors wherever required:W.C. pan with ISI marked white solid plastic seat and lid
Providing and fixing white vitreous china pedestal type water closet (European type
W.C. pan) with seat and lid, 10 litre low level white
FOR TOILET 2 2.000
Total 2.000
Total Quantity in each 2.000
14.03 17.7.2
9 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32
mm C.P. brass waste of standard pattern, including painting of fittings and brackets,
cutting and making good the walls wherever require:White Vitreous China Wash basin
size 630 x 450 mm with a single 15 mm C.P. brass pillar tap
Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32
mm C.P. brass waste of standard pattern, including
1 1.000
Total 1.000
Total Quantity in each 1.000
14.04 18.49.1
4 Providing and fixing C.P brass bib cock of approved quality conforming to IS:
8931.15 mm nominal bore
Providing and fixing C.P brass bib cock of approved quality conforming to IS: 8931.
2 2.000
Total 2.000
Total Quantity in each 2.000
14.04 18.58.2.1
5 Providing and fixing PTMT grating of approved quality and colour.
Rectangular type with openable circular lid150 mm nominal size square 100 mm
diameter of the inner hinged round grating
Providing and fixing PTMT grating of approved quality and colour. Rectangular type
with openable circular lid
2 2.000
Total 2.000
Total Quantity in each 2.000
14.04 17.31
6 Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved
quality) complete with 6 mm thick hard board ground fixed to wooden cleats with C.P.
brass screws and washers complete.
Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved
quality) complete with 6 mm thick hard board
2 2.000
Total 2.000
Total Quantity in each 2.000
14.04 18.48
7 Providing and placing on terrace (at all floor levels) polyethylene water storage tank
:ISI 12701 marked, with cover and suitable locking arrangement and making
necessary holes for inlet, outlet and overflow pipes but without fittings and the base
support for tank.
Providing and placing on terrace (at all floor levels) polyethylene
AT ROOF 1 1000.000 1000.000
Total 1000.000
Total Quantity in Litre 1000.000
14.04 OD6727/2022-2023
8 Supplying and providing Chequred plate 7mm thick including all cost and
conveyance of all materials and labour charges etc. complete
Supplying and providing Chequred plate 7mm thick including all cost and
conveyance of all materials and labour charges etc.
FOR CABLE 1 6.600 1.400 9.240
TRENCH
Total 9.240
Total Quantity in sqm 9.240
15 SLUDGE SHED
15.00 2.8.1
1 Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting
out the excavated soil and disposal of surplus excavated soil as directed, within a lead
of 50 m.All kinds of soil
Earth work in excavation by mechanical means
9 1.700 1.700 1.600 41.616
Total 41.616
Total Quantity in cum 41.616
15.00 4.1.8
2 Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
Providing and laying in position cement concrete
column footing 9 1.700 1.700 0.100 2.601
Floor PCC 4 4.900 4.900 0.100 9.604
Plinth Bottom 12 4.750 0.350 0.100 1.995
Total 14.200
Total Quantity in cum 14.200
15.00 2.25
3 Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited
layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Filling
Plinth inside 1 10.000 10.000 0.350 35.000
filling
Total 35.000
Total Quantity in cum 35.000
15.00 50.6.7.1
4 Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for foundation and basement including all cost of materials,
labour charges etc.
Laterate masonry
Total 5.401
Column Footing-column
Column Pedestal 9 0.200 0.300 0.900 0.486
Total 0.486
Plinth beam
PB1 12 4.750 0.200 0.450 5.130
Total 5.130
Total Quantity in cum 11.017
15.00 5.22.6
7 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for RCC
@100Kg/Cum of 1 8.128+11 100.000 1914.600
concrete Qty. ie .018
Total 1914.600
Total Quantity in kilogram 1914.600
15.00 5.9.1
8 Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Centering and shuttering
Column footing 36 1.500 0.150 8.100
Total 8.100
Total Quantity in sqm 8.100
15.00 5.9.6
9 Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Centering and shuttering
9 1.200 4.500 48.600
Total 48.600
Total Quantity in sqm 48.600
15.01 5.9.5
0 Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Lintel
over wall 16 4.750 0.150 11.400
Bottom 1 3.000 0.200 0.600
Shade 1 4.000 0.600 2.400
Tie beam 16 4.750 0.400 30.400
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering
Column footing 15 1.900 1.900 0.100 5.415
Ramp 3 3.000 2.000 0.100 1.800
Cable Trench 1 20.000 1.000 0.100 2.000
Total 9.215
Total Quantity in cum 9.215
16.00 5.1.2
3 Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Providing and laying in position specified grade of reinforced cement concrete
Column Footing 15 1.700 1.700 0.250 10.838
Trapezoidal 5 1.700 1.700 0.500 7.225
portion
Column pedestal 15 0.200 0.500 1.100 1.650
Plinth beam 2 3.700 0.200 0.450 0.666
Plinth beam 3 4.900 0.200 0.450 1.323
Plinth beam 12 3.150 0.200 0.450 3.402
Ramp Top 3 3.000 3.000 0.100 2.700
Total 27.804
Total Quantity in cum 27.804
16.00 50.5.33.2
4 Providing and laying in position machine batched and machine mixed design mix M-
20 grade cement concrete for reinforced cement concrete work, using cement content
as per approved design mix, including pumping of concrete to site of laying but
excluding the cost of centering, shuttering, finishing and reinforcement, including
admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of
concrete, improve workability without impairing strength and durability as per
direction of Engineer-in-charge. Note:- Cement content considered in this item is @
330 kg/cum. Excess or less cement used as per design mix is payable or recoverable
separately. All work above plinth level upto floor V level
Providing and laying in position machine batched and machine mixed design mix
M-20 grade
Column above 15 0.200 0.500 5.000 7.500
plinth
Lintel 2 8.600 0.200 0.200 0.688
Lintel 12 3.150 0.200 0.200 1.512
16.01 10.6.1
5 Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end by
end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS: 4454
- part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S.
laths with 1.25 mm thick top cover
Supplying and fixing rolling shutters of approved make, made of required size
Rolling shutter 2 3.000 3.000 18.000
Rolling shutter 1 3.000 2.400 7.200
Total 25.200
Total Quantity in sqm 25.200
16.01 9.48.1
6 Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel primer
all complete.Fixed to steel windows by welding
Providing and fixing M.S. Grills of required pattern in frames of windows etc
16.000
Window grill 9 1.500 1.500 324.000
000
16.000
Ventilator 14 0.900 0.600 120.960
000
Total 444.960
Total Quantity in kg 444.960
16.01 21.11.1
7 Providing and fixing stainless steel (SS 304 grade) adjustable friction window stays of
approved quality with necessary stainless steel screws etc. to the side hung windows
as per direction of Engineer - in-Charge complete.205 x 19 mm
Providing and fixing stainless steel (SS 304 grade)
4.5000
Window 9 1.500 1.500 91.125
00
4.5000
Ventilator 14 0.900 0.600 34.020
00
Total 125.145
Total Quantity in no 125.145
16.01 21.3.1
8 Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc.
Window 18 0.720 1.420 18.403
Ventilator 14 0.820 0.520 5.970
Total 24.373
Total Quantity in sqm 24.373
16.01 13.43.1
9 Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Deduction
Window -9 1.500 1.500 -20.250
Rs -4 3.000 3.000 -36.000
Rs -2 3.000 2.400 -14.400
Ope -4 1.500 2.400 -14.400
Ope -1 4.900 1.500 -7.350
Ventilator -14 0.900 0.600 -7.560
Total -99.960
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface
Inside 2 13.200 5.000 132.000
Inside 2 4.000 5.000 40.000
Inside 4 6.500 5.000 130.000
Inside 4 5.500 5.000 110.000
Column 7 0.800 5.000 28.000
Cable Top 2 42.400 0.230 19.504
Out side 2 13.600 5.450 148.240
Out side 2 10.100 5.450 110.090
Ramp side 3 3.000 0.450 4.050
Ramp side 1 49.000 1.000 49.000
Total 770.884
Applying one coat of water thinnable cement primer of approved
Roof Bottom 1 13.200 4.000 52.800
Roof Bottom 2 6.500 5.500 71.500
Beam 6 3.700 0.500 11.100
Beam 6 4.900 0.500 14.700
Shade bottom 1 14.800 0.600 8.880
Shade bottom 1 14.800 0.750 11.100
Shade bottom 2 10.100 0.600 12.120
Total 182.200
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Random rubble masonry with hard stone in foundation
Foundation 2 3.650 0.600 0.600 2.628
Foundation 2 2.550 0.600 0.600 1.836
Basement 2 3.500 0.450 0.300 0.945
Basement 2 2.700 0.450 0.300 0.729
Step 1 3.000 0.450 0.450 0.608
Total 6.746
Total Quantity in cum 6.746
17.00 50.6.7.2
4 Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Laterate masonry with neatly dressed laterate stone
Wall 4 3.200 0.200 2.850 7.296
Parapet 4 3.800 0.200 0.300 0.912
Step 1 1.000 0.600 0.200 0.120
Step 1 1.000 0.300 0.200 0.060
Total 8.388
Deduction
Door -1 1.000 0.200 2.100 -0.420
window -2 1.500 0.200 1.500 -0.900
Total -1.320
Total Quantity in cum 7.068
17.00 5.37.1
5 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M25grade concrete for RCC work
Plinth belt 4 3.250 0.250 0.150 0.488
Total 0.488
Total Quantity in cum 0.488
17.00 5.37.2
6 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All work above plinth level upto
floor V level
Providing and laying in position ready mixed M25grade concrete for RCC work
Lintel 4 3.200 0.200 0.150 0.384
Shade 1 3.400 0.600 0.100 0.204
Shade 2 1.900 0.600 0.100 0.228
Roof slab 1 4.000 4.000 0.120 1.920
Total 2.736
Total Quantity in cum 2.736
17.00 5.22.6
7 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Steel reinforcement for RCC work including straightening, cutting ,bending
@80 KG/1Cum 1 2.738+.4 80.000 258.080
of CC 88 000
Total 258.080
Total Quantity in kilogram 258.080
17.00 5.9.3
8 Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
centering and shuttering including strutting etc
Slab Bottom 1 3.000 3.000 9.000
Proj. 4 3.700 0.300 4.440
Edge 4 4.000 0.120 1.920
Shade 1 3.400 0.600 2.040
Shade 2 1.900 0.600 2.280
Edge 6 0.600 0.100 0.360
Total 20.040
Total Quantity in sqm 20.040
17.00 5.9.5
9 Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
centering and shuttering including strutting etc
Lintel 4 3.000 0.150 1.800
Lintel 4 3.400 0.150 2.040
Bottom 1 1.000 0.200 0.200
Bottom 2 1.500 0.200 0.600
P-beam 4 3.000 0.150 1.800
P-beam 4 3.100 0.150 1.860
Total 8.300
Total Quantity in sqm 8.300
17.01 13.1.1
0 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
12 mm cement plaster of mix
inside wall 4 3.000 3.000 36.000
outside 4 3.400 3.000 40.800
basement 4 3.500 0.450 6.300
parapet 4 3.800 0.850 12.920
Total 96.020
Deduction
door -1 1.000 2.100 -2.100
window -2 1.500 1.500 -4.500
Total -6.600
Total Quantity in sqm 89.420
17.01 13.7.1
1 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
12 mm cement plaster finished with a floating coat of neat cement of mix
Roof top 1 3.600 3.600 12.960
Shade top 1 3.400 0.600 2.040
Shade top 2 1.900 0.600 2.280
Total 17.280
Total Quantity in sqm 17.280
17.01 13.16.1
4.5000
window 2 1.500 1.500 20.250
00
Total 29.700
Total Quantity in kg 29.700
17.01 21.3.1
5 Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and fixing glazing in aluminium door,window,ventilator shutters and
partitions etc
Door 2 0.880 0.900 1.584
Window 4 0.920 1.430 5.262
Total 6.846
Total Quantity in sqm 6.846
17.01 9.48.2
6 Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel primer
all complete.Fixed to openings/ wooden frames with rawl plugs screws etc
Providing and fixing M.S.Grills of required pattern in frames of windows etc.
20.000
Window grill 2 1.500 1.500 90.000
000
Total 90.000
Total Quantity in kg 90.000
17.01 13.43.1
7 Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Deduction
Door -1 1.000 2.100 -2.100
window -2 1.500 1.500 -4.500
Total -6.600
Applying one coat of water thinnable cement primer of approved brand
inside wall 4 3.000 3.000 36.000
out side 4 3.400 3.000 40.800
basement 4 3.500 0.450 6.300
parapet 4 3.800 0.850 12.920
Total 96.020
Applying one coat of water thinnable cement primer of approved brand
slab bottom 1 3.000 3.000 9.000
Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved
quality) complete with 6 mm thick hard board ground fixed to wooden cleats with C.P.
brass screws and washers complete.
Providing and fixing 600 x450 mm beveled edge mirror of superior glass
1 1.000
Total 1.000
Total Quantity in each 1.000
18 PSF/ACF Foundation
18.00 2.6.1
1 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas
Foundation 1 24.200 8.200 0.600 119.064
Total 119.064
Total Quantity in cum 119.064
18.00 4.1.6
2 Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:
Base 1 24.200 8.200 0.200 39.688
Total 39.688
Total Quantity in cum 39.688
18.00 5.37.1
3 Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended proportions
as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without
impairing strength and durability as per direction of the Engineer - in -charge. Note:-
Cement content considered in this item is @330 kg/cum. Excess /less cement used as
per design mix is payable/recoverable separately.All wiork upto plinth level
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work
RCC Base 1 24.000 8.000 0.400 76.800
Total 76.800
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
drain bottom
drain bottom 1 120.000 1.400 0.100 16.800
Total 16.800
Total Quantity in cum 16.800
19.00 5.1.3
3 Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Providing and laying in position specified grade of RCC
Drain bottom 1 120.000 1.400 0.200 33.600
side wall 2 120.000 0.200 1.200 57.600
cover slab (Pre- 1 120.000 1.400 0.200 33.600
cast)
Total 124.800
Total Quantity in cum 124.800
19.00 5.22.6
4 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
steel reinforcement for RCC
80 Kg/ Cum of 1 124.800 80.000 9984.000
CC
Total 9984.000
Total Quantity in kilogram 9984.000
19.00 5.9.2
5 Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
centering & shuttering
Drain side wall 2 120.000 1.200 288.000
Cover slab 120 4.800 0.200 115.200
Total 403.200
Total Quantity in sqm 403.200
19.00 13.1.1
6 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
12mm cement plaster of mix
Total 630.000
Total Quantity in cum 630.000
20.00 OD6778/2022-2023
5 Construction of granular sub-base by providing graded material, spreading in uniform
layers with a motor grader on a prepared surface, mixing by mix in-place method with
rotavator at OMC and compacting with a vibratory roller to achieve the desireddensity,
complete as per clause 401. Grading-V - For sub-base cum drain age layer - Mix in
Place Method
Construction of granular sub-base by providing graded material
Internal road base 1 100.000 6.000 0.300 180.000
,, 1 300.000 5.000 0.300 450.000
Total 630.000
Total Quantity in cum 630.000
20.00 OD15389/2022-2023
6 Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface
of granular<br>Base including clearing of road surface and spraying primer at
the rate of 0.70 - 1.0 kg/sqm using<br>mechanical means
Providing and applying primer coat with bitumen emulsion ( SS)
Internal road 1 100.000 5.000 500.000
Internal road 1 300.000 4.000 1200.000
Total 1700.000
Total Quantity in sqm 1700.000
20.00 OD15390/2022-2023
7 Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure
distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom
Providing and applying tack coat with bitumen emulsion
Internal road 1 100.000 5.000 500.000
Internal road 1 300.000 4.000 1200.000
Total 1700.000
Total Quantity in sqm 1700.000
20.00 OD10703/2022-2023
8 Providing, laying and rolling of open graded premix carpet of 20 mm thickness with
0.27 cum of 12 mm departmental aggregates premixed with 12.96 kg of bitumen per
10 sqm using penetration grade bitumen to required line, grade and level on a
previously prepared base, after priming the existing surface with 5 kg of bitumen (VG
30) 10 sqm including mixing in a suitable plant, laying and rolling with a three wheel
static roller of 80-100 KN capacity, finished to required level and grades,followed by a
seal coat of 0.09 cum of 6 mm departmental aggregates premixed with 8.64 kg of
bitumen per 10 sqm.By Manual Means.
Providing, laying and rolling of open graded premix carpet of 20 mm thickness
Providing and laying in position cement concrete of specified grade excluding the
cost of centering
Compound wall 1 30.000 0.500 0.100 1.500
foundation
Gate pillar 4 1.000 1.000 0.100 0.400
Total 1.900
Total Quantity in cum 1.900
21.00 7.1.1
3 Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete
Compound wall 1 30.000 0.500 0.600 9.000
foundation
Total 9.000
Total Quantity in cum 9.000
21.00 50.6.7.2
4 Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size
in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6
Wall 1 30.000 0.200 1.800 10.800
Pillar addl 80 0.350 0.150 1.800 7.560
Total 18.360
Total Quantity in cum 18.360
21.00 5.1.2
5 Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Providing and laying in position specified grade of reinforced cement concrete
Gate pillar 4 1.000 1.000 0.150 0.600
footing
Gate pillar 4 0.800 0.800 0.300 0.768
footing
Total 1.368
Total Quantity in cum 1.368
21.00 5.2.2
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:
As per item no 1 172.740 172.740
13.11
Total 172.740
Total Quantity in sqm 172.740
21.01 13.60.1
1 Wall painting with acrylic emulsion paint of approved brand and manufacture to give
an even shade:Two or more coats on new work
Wall painting with acrylic emulsion paint of approved brand
As per item no 1 172.740 172.740
13.11
Total 172.740
Total Quantity in sqm 172.740
21.01 10.25.2
2 Item Shifted to Sub head 14 as item 14.73
Item Shifted to head 14 as item 14.74
Steel work welded in built up sections/framed work, including cutting, hoisting, fixing
in position and applying a priming coat of approved steel primer using structural steel
etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and
similar works
Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel
work welded in built up
30.000
MAIN GATE 1 4.000 1.800 216.000
000
20.000
VICAT GATE 1 1.000 1.800 36.000
000
Total 252.000
Total Quantity in kg 252.000
21.01 13.62.1
3 Painting with synthetic enamel paint of approved brand and manufacture of required
colour to give an even shade:Two or more coats on new work over an under coat of
suitable shade with ordinary paint of approved brand and manufacture .
Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel
work welded in built up
MAIN GATE 1 4.000 1.800 7.200
VICAT GATE 1 1.000 1.800 1.800
Total 9.000
Total Quantity in sqm 9.000
22 Landscaping, green belt formation and re-use of treated water
22.00 OD45301/2022-2023
1 LANDSCAPING AND GREENBELT FORMATION AROUND THE STP SITE
Landscaping and green belt
1 1.000
Total 1.000
Total Quantity in L.S 1.000
23 Providing solar energy system
23.00 OD45305/2022-2023
1 Supplying and Installing Solar panel with all accessories at STP
Supplying and installing solar panel
1 1.000
Total 1.000
Total Quantity in no 1.000
24 Odour control system
24.00 OD45157/2022-2023
1 Providing Odour Controle System
Providing Odour control system
Providing Odour 1 1.000
control system
Total 1.000
Total Quantity in no 1.000
25 ELECTRICAL ESTIMATE FOR STP
25.00 OD58173/2022-2023
1 500 kVA Indoor Transformer and 11 kv indoor free standing cubcle type vcb switch
gear panel of suitable capacity<br>Supplying, installation, testing and
commissioning of 250KVA, 11KV/433V, 3<br>Phase, 50 Hz, Dyn 11, indoor
ONAN type, copper wound transformer with OFF load tap changing arrangement on
HV and LV side complete with all accessories i/c first filling of filtered dehydrated oil
and confirming to IS 2026 (Part 1 to Part 5) & as per specification attached
complete in all respects as required at site or as directed by the Engineer In Charge
including suuply installation commissioning of suitable rated 11kv
cubicle type vcb panel and suitable rated 11kv cable and termination
500 kVA Indoor Transformer and 11 kv indoor free standing cubcle type vcb switch
gear panel of suitable capacity<br>Supplying, installation, testing and
commissioning of 250KVA, 11KV/433V, 3<br>Phase, 50 Hz, Dyn 11, indoor
ONAN type
500KVA TFR 2 2.000
Total 2.000
Total Quantity in no 2.000
25.00 OD58174/2022-2023
Earthing 1 1.000
Equipments
Total 1.000
Total Quantity in set 1.000
25.00 OD58178/2022-2023
6 500 KVA Diesel Generator Providing, Installing, Testing and Commissioning of
Silent Type Diesel Generating set alongwith having Prime Power Rating of 250 KVA,
415 volts at 1500 RPM, 0.8 lagging power factor at 415 V suitable for 50 Hz, 3 phase
system& for 0.85 Load Factor .
500 KVA Diesel Generator Providing, Installing, Testing and Commissioning of
Silent Type Diesel Generating set alongwith having Prime Power Rating of 250 KVA,
415 volts
500 KVA Diesel 1 1.000
Generator
Total 1.000
Total Quantity in no 1.000
25.00 OD58179/2022-2023
7 Auto Mains Failure Unit (AMF Panel) Fabricating, Installing, Testing &
Commissioning of automatic mains failure control including auto bypass panel,
suitable for 500 KVA silent type DG set complete with relays, timers, set of CTs for
metering & protection and energy analyser to indicate currents, phase and line
voltages, frequency, power factor, KWH, KVARH & provision for overload,
short circuit, restricted earth fault, under frequency, control cabling from AMF panel
to diesel engine and elsewhere if required, all complete
Auto Mains Failure Unit (AMF Panel) Fabricating, Installing, Testing &
Commissioning of automatic mains failure control including auto bypass panel,
suitable for 500 KVA silent type DG set
AMF Panel 1 1.000
Total 1.000
Total Quantity in set 1.000
25.00 OD58180/2022-2023
8 Earthing Equipments for DG Earthing with copper earth plate 600 mm X 600 mm X 3
mm thick including accessories, and providing masonry enclosure with cover plate
having locking arrangement and watering pipe of 2.7 meter long etc. with charcoal/
coke and salt as required."
Earthing Equipments for DG Earthing with copper earth plate 600 mm X 600 mm X 3
mm thick including accessories
Earthing
Equipments for 1 1.000
DG
Total 1.000
Total Quantity in set 1.000
25.00 OD58181/2022-2023
Power Distribution Board (Control Room & Centrifuge Building) Supplying and
fixing of following ways surface/ recess mounting, vertical type, 415 V, TPN MCB
distribution board of sheet steel, dust protected, duly powder painted, inclusive of 200
A, tinned copper bus bar, common neutral link, earth bar, din bar for mounting MCBs
(but without MCBs and incomer) as
required. (Note : Vertical type MCB TPDB is normally used where 3 phase outlets are
required.) 12 way (4 + 36), Double door (i) Incoming - 63A MCCB & 63A ,
100mA RCCB ii) Outgoing Feeders - 4Nos of 25A MCCB with 25A, 30mA RCCBs
iii) Outgoing Feeders - 1Nos of 6A MCB iv) Outgoing Feeders - 2Nos Spares
Power Distribution Board (Control Room & Centrifuge Building) Supplying and
fixing of following ways surface/ recess mounting, vertical type, 415 V, TPN MCB
distribution board
1 1.000
Total 1.000
Total Quantity in set 1.000
25.01 OD58185/2022-2023
3 Wiring & Lighting accessories :- Wiring for circuit/submain wiring along with
earthwire with required sizes of FRLS PVC insulated copper conductor,supply and
fitting of GI boxes along with modular base and cover plates,supplying and fixing
following modular switch/ sockets,supply,installation,testing and commissioning of all
accessories and fixtures as approved by dept.
Wiring & Lighting accessories :- Wiring for circuit/submain wiring along with
earthwire with required sizes of FRLS PVC insulated copper conductor,supply and
fitting of GI boxes along with modular base
1 1.000
Total 1.000
Total Quantity in set 1.000
25.01 OD58186/2022-2023
4 EXTERNAL LIGHTING Providing external lighting arrangements by supplying and
laying of PVC insulated and PVC sheathed / XLPE power cable of Copper conductor
XLPE control cables as per is:7098/Part-I/88 with latest amendments 1.1 kv grade of
required size direct in ground including MCCB/MCB/RCCB,supply and erection of
mettalic poles,strret light poles,earthing and safety equipments ,fire extinguishers ,etc .
complete including necessary excavation, sand cushioning, protective covering and
refilling the trench etc. as required in the specifications or as directed by the Engineer
in Charge."
EXTERNAL LIGHTING Providing external lighting arrangements by supplying and
laying of PVC insulated and PVC sheathed / XLPE power cable of Copper conductor
XLPE control cables
EXTERNAL 1 1.000
LIGHTING
Total 1.000
Total Quantity in L.S 1.000
26 MECHANICAL COMPONENTS FOR STP
26.00 OD58224/2022-2023
Bubble Diffuser for SBR Tank Supplying at site, erection, testing &
commissioning of Fine Bubble Diffuser (retrievable type using rope and pulley
arrangement) for the aeration system of the MBBR Tansk (2Nos) with diffusers of
sufficient size and length made of EPDM make with SS tee 1"" x 1
"", SS lifting hook 8 mm, SS foundation bolt 6 mm, SS C clamp suitable
for 1"" O.D, hose, PP Rope, PP swivel nut, PP sleeve, Silicone Washer,
SS hose clamp, RCC block complete at a minimum rating of 95m/hr as per technical
specification or as directed by the Engineer in Charge" for four basigns
Bubble Diffuser for SBR Tank Supplying at site, erection, testing &
commissioning of Fine Bubble Diffuser
4 4.000
Total 4.000
Total Quantity in set 4.000
26.00 OD58231/2022-2023
8 Air Grid Pipe Supply and installation of air pipes (ss) aly into valves and other
acessories as required for the blowers to various tanks as a complete unit"
Air Grid Pipe Supply and installation of air pipes (ss) aly into valves and other
acessories as required for the blowers to various tanks as a complete unit"
4 4.000
Total 4.000
Total Quantity in no 4.000
26.00 OD58232/2022-2023
9 Gas Chlorinator system Supply at site, erection, testing and commissioning of
electronic chlorine dosing system (gas filled Chlorine) with all wetted parts in PP
construction suitable for pumping Chlorine gas including booster pumps, valves,
suctions and delivery lines using heavy duty PVC tubes, gas line diffusers, emergency
repair kit, FRP motor cover etc.complete with all accessories. Capacity : 500gm to
1kg/hr with 2nos of chlorine tonners"
Gas Chlorinator system Supply at site, erection, testing and commissioning of
electronic chlorine dosing system
2 2.000
Total 2.000
Total Quantity in no 2.000
26.01 OD58233/2022-2023
0 Electromagnetic flow meter
Supply, installation, testing and commissioning of electro magnetic/ Ultra Sonic D/F
permanent conduit
flow meter with flow recorder, digital flow indicator, flow integrator with sensors,
7digit totaliser, transmittal
and digital display arrangements and all accessories including housing arrangements,
internal data
logger, to save upto 2000 linesof data etc. complete to fix as per the specifications .
Flow range of 10 to 600LPS, One display shall be installed at the main control centre
Electromagnetic flow meter Supply, installation, testing and commissioning of electro
magnetic/ Ultra Sonic D/F permanent conduit flow meter with flow recorde
3 3.000
Total 3.000
Total Quantity in no 3.000
26.01 OD58234/2022-2023
1 SS Gates Supplying at site, installation testing and commissioning of all materials,
fabricating, fixing and commissioning of spindle operated open channel sluice
gates/shutter of DI make with a peak flow of 145LPS and velocity less than 1m/s at
the inleta and outlet of the screen channel to suit the channel sizes as per drawings,
tender specifications and as directed by Engineer in Charge
SS Gates Supplying at site, installation testing and commissioning of all materials,
fabricating, fixing and commissioning of spindle operated open channel sluice
gates/shutter
9 9.000
Total 9.000
Total Quantity in no 9.000
26.01 OD58235/2022-2023
2 Sludge Thickener Mechanism Supplying all materials, fabricating, fixing and
commissioning of Bridge mounted central driven type sludge thickening mechanism
for the full diameter of the Sludge Thickener tank as per drawings including all feed
well, drive and rake mechanism with removable scrappers with sufficient 3phase
motor and gears etc complete as per tender specifications and as directed by Engineer
in Charge"
Sludge Thickener Mechanism Supplying all materials, fabricating, fixing and
commissioning of Bridge mounted central driven type sludge thickening mechanism
for the full diameter of the Sludge Thickener
4 4.000
Total 4.000
Total Quantity in set 4.000
26.01 OD58236/2022-2023
3 Supplying and fixing of electronic dosing pump with all wetted parts in PP
construction suitable for pumping Poly Electrolyte solution including cost of suitable
agitators, control gears, valve, suction and delivery lines using heavy duty PVC tubes,
HD, FRP motor cover etc. and complete with all accessories to prepare 5% solution of
0.2kg/hr"
Supplying and fixing of electronic dosing pump with all wetted parts in PP
construction suitable for pumping Poly Electrolyte solution
4 4.000
Total 4.000
Total Quantity in no 4.000
26.01 OD58237/2022-2023
"High Pressure Jet Pump Supply and commissioning of portable high pressure
water pumps (along with 500litre water tanks to supply water to the pumps) all
mounted on a suitable medium vehicle platform for clearing the wells, pumps, and
other equipments using high pressure gauges, safety arrangements etc complete as per
standards"
High Pressure Jet Pump Supply and commissioning of portable high pressure water
pumps (along with 500litre water tanks to supply water to the pumps)
4 4.000
Total 4.000
Total Quantity in no 4.000
26.01 OD58238/2022-2023
5 "Portable Hoist - 500kg Supply and commissioning of portable Monkey type
Hoist with capacity upto 500kg, with lifting height of 6m, 5HP Motor, 415V 50Hz all
mounted on a suitable medium vehicle patform for easy shifting of equipments and
materials whenever required with complete set as per standards" 1 1.000
Portable Hoist - 500kg Supply and commissioning of portable Monkey type Hoist with
capacity upto 500kg, with lifting height of 6m, 5HP Motor, 415V 50Hz
2 2.000
Total 2.000
Total Quantity in no 2.000
26.01 OD58239/2022-2023
6 "Aluminium Ladder Supply, Installation of aluminium ladders with caging on
each elevated structures of required height as per the drawings or as directed by the
Engineer in Charges"
Aluminium Ladder Supply, Installation of aluminium ladders with caging on each
elevated structures of required height as per the drawings or as directed by the
Engineer in Charges"
4 4.000
Total 4.000
Total Quantity in no 4.000
26.01 OD58240/2022-2023
7 "FRP Ladder Supply, Installation of FRP ladders with caging on each elevated
structures of required height as per the drawings or as directed by the Engineer in
Charges"
FRP Ladder Supply, Installation of FRP ladders with caging on each elevated
structures of required height as per the drawings or as directed by the Engineer in
Charges"
8 8.000
Total 8.000
Total Quantity in no 8.000
26.01 OD58241/2022-2023
Total 6.000
Total Quantity in set 6.000
26.02 OD58244/2022-2023
1 Supply at site, installation and commissioning of filter press /centrifuge system. Filter
Press shall be automated, recessed type press with SS fabricated structure pipe button
surface and SS flat parallel bar, with PP cloth. Filter operations to be mechanical.
Outlet cake consistency should not be more than 35% moisture. The capacity of the
filter press shall be 1cum/hr. The Filter Press Unit shall be mounted on a platform and
all around drain system to be provided to prevent the filtrate water from contaminating
the entire surroundings as per the specifications or as directed by the engineer in
charge"
Supply at site, installation and commissioning of filter press /centrifuge system. Filter
Press shall be automated, recessed type press with SS fabricated structure pipe button
surface
4 4.000
Total 4.000
Total Quantity in no 4.000
26.02 OD58245/2022-2023
2 SLUDGE DEWATERING and Packing UNIT -Volute is a dewatering unit for
convenient sludge
dewatering.Machine is available for dry sludge (DS) output of 1.0kg/hr to 750kg/hr
the Sludge to be dried from 70% moisture content to 10%.The similar type can be
suggested.The Packing of the dried sludge to be packed in the packing machine.The
necessary electrification civil works,cost of packing machine,cost of gunny bags for
6months.The machines suggested should be cost effective
SLUDGE DEWATERING and Packing UNIT -Volute is a dewatering unit for
convenient sludge dewatering.Machine is available for dry sludge (DS) output of
1.0kg/hr to 750kg/hr
4 4.000
Total 4.000
Total Quantity in set 4.000
26.02 OD58246/2022-2023
3 Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding, buffing, polishing and making
curvature (wherever required) and fitting the same with necessary stainless steel nuts
and bolts complete, i/c fixing the railing with necessary accessories & stainless
steel dash fasteners, stainless steel bolts etc., of required size on the top of the floor or
the side of waist slab with suitable arrangement as per approval of Engineer-in-charge,
(for payment purpose only weight of stainless steel members shall be considered
excluding fixing accessories such as nuts, bolts, fasteners etc.)kg
Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding, buffing, polishing and making
curvature
30 30.000
Total 30.000
ABSTRACT ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 328
1.006 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size)
Net Total 7.483cum @7413.74/cum 55477.02
1.007 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 25.208cum @9947.98/cum 250768.68
1.008 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 154.134cum @11610.44/cum 1789563.56
1.009 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 108.325kg @1.35/kg 146.24
1.010 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 21521.040kil
ogram @98.92/kilogram 2128861.28
1.011 OD4985/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 289.494sqm @573.84/sqm 166123.24
1.022 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 160.680sqm @442.30/sqm 71068.76
1.023 10.26.3
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat
of approves steel primer.G.I. pipes
Net Total 4597.992kg @187.17/kg 860606.16
Heading Total(Rs) 8929761.20
2 SEPTAGE RECEIVING TANK
2.001 2.8.1
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including
getting out the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.All kinds of soil
Net Total 158.820cum @298.84/cum 47461.77
2.002 2.26.2
Extra for every additional lift 1.5 m or part there of in excavation / banking excavated
or stacked materials.Ordinary or hard rock
Net Total 45.216cum @191.98/cum 8680.57
2.003 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 11936.000Kwh @37.17/Kwh 443661.12
2.004 100.7.2
Bailing out water with engine and pump set above 5HP up to 10HP including
conveyance to the site, erecting, dismantling and taking back of engine and pump,
cost of fuel lubricating oil and other stores pay of staff etc., complete.
Net Total 5595.000Kwh @18.60/Kwh 104067.00
2.005 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size)
Net Total 9.431cum @7413.74/cum 69918.98
2.006 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 39.037cum @9947.98/cum 388339.30
2.007 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 3.693cum @11610.44/cum 42877.35
2.008 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 34.537cum @82.60/cum 2852.76
2.009 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 11742.580kg @1.35/kg 15852.48
2.010 OD60991/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level.
Net Total 34.537cum @1899.46/cum 65601.65
2.011 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 5127.600kilo
gram @98.92/kilogram 507222.19
2.012 OD60989/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 5127.600kilo
gram @2.32/kilogram 11896.03
2.013 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 10.787sqm @337.42/sqm 3639.75
2.014 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 149.778sqm @721.70/sqm 108094.78
2.015 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 22.263sqm @820.86/sqm 18274.81
2.016 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 196.659sqm @403.74/sqm 79399.10
2.017 2.25
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited
layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Net Total 30.144cum @260.18/cum 7842.87
2.018 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat,
preparation of surface, etc. complete.On concrete work
Net Total 33.284sqm @224.33/sqm 7466.60
2.019 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant,
tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 70.650sqm @573.84/sqm 40541.80
2.020 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant,
tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
3.002 2.26.1
Extra for every additional lift 1.5 m or part there of in excavation / banking excavated
or stacked materials.All kinds of soil
Net Total 3228.828cum @107.05/cum 345646.04
3.003 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size)
Net Total 660.799cum @7413.74/cum 4898991.98
3.004 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 134280.000K wh @37.17/Kwh 4991187.60
3.005 100.7.2
Bailing out water with engine and pump set above 5HP up to 10HP including
conveyance to the site, erecting, dismantling and taking back of engine and pump,
cost of fuel lubricating oil and other stores pay of staff etc., complete.
Net Total 89520.000Kwh @18.60/Kwh 1665072.00
3.006 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
15459509.1
Net Total 1554.035cum @9947.98/cum 0
3.007 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
31692333.0
Net Total 2729.641cum @11610.44/cum 5
3.008 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 4284.000cum @82.60/cum 353858.40
3.009 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 2723.160kg @1.35/kg 3676.27
3.010 OD6250/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Net Total 2723.160cum @1899.46/cum 5172533.49
3.011 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 599760.000ki 59328259.2
logram @98.92/kilogram 0
3.012 OD6281/2022-2023
3.020 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat, preparation
of surface, etc. complete.On concrete work
Net Total 2930.756sqm @224.33/sqm 657456.49
3.021 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 2219.784sqm @573.84/sqm 1273800.85
3.022 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 2865.250sqm @442.30/sqm 1267300.08
3.023 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
Net Total 10045.530Kil @185.72/Kilo 1865655.83
o litre litre
3.024 10.26.3
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat
of approves steel primer.G.I. pipes
Net Total 9195.984kg @187.17/kg 1721212.33
4.009 OD6185/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 4838.400kg @2.32/kg 11225.09
4.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 14.160sqm @337.42/sqm 4777.87
4.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 170.800sqm @721.70/sqm 123266.36
4.012 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 204.440sqm @403.74/sqm 82540.61
4.013 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat, preparation
of surface, etc. complete.On concrete work
Net Total 89.600sqm @224.33/sqm 20099.97
4.014 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 81.200sqm @573.84/sqm 46595.81
4.015 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 33.640sqm @442.30/sqm 14878.97
4.016 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
Net Total 117.740Kilo @185.72/Kilo 21866.67
litre litre
Heading Total(Rs) 1428432.25
5 SLUDGE SUMP
5.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Net Total 12.861cum @215.37/cum 2769.87
5.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size)
Net Total 3.215cum @7413.74/cum 23835.17
5.003 100.7.2
Bailing out water with engine and pump set above 5HP up to 10HP including
conveyance to the site, erecting, dismantling and taking back of engine and pump,
cost of fuel lubricating oil and other stores pay of staff etc., complete.
Net Total 559.500Kwh @18.60/Kwh 10406.70
5.004 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 6.368cum @9947.98/cum 63348.74
5.005 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 22.348cum @11610.44/cum 259470.11
5.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 3446.400kilo
gram @98.92/kilogram 340917.89
5.007 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 28.716cum @82.60/cum 2371.94
5.008 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 9476.280kg @1.35/kg 12792.98
5.009 OD5139/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 3445.920kg @2.32/kg 7994.53
5.010 OD5140/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Net Total 28.716tonne @1899.46/tonne 54544.89
5.011 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 7.850sqm @337.42/sqm 2648.75
5.012 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 116.494sqm @721.70/sqm 84073.72
5.013 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 23.142sqm @820.86/sqm 18996.34
5.014 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 160.737sqm @403.74/sqm 64895.96
5.015 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat, preparation
of surface, etc. complete.On concrete work
Net Total 65.061sqm @224.33/sqm 14595.13
5.016 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 78.776cum @9947.98/cum 783662.07
6.004 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 62.250cum @11610.44/cum 722749.89
6.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 141.016cum @82.60/cum 11647.92
6.006 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 45324.360kg @1.35/kg 61187.89
6.007 OD5996/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Net Total 127.324cum @1899.46/cum 241846.85
6.008 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 16921.920kil @98.92/kilogram 1673916.33
ogram
6.009 OD5997/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 2030630.400kg @2.32/kg 4711062.53
6.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 20.604sqm @337.42/sqm 6952.20
6.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 377.906sqm @721.70/sqm 272734.76
6.012 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 77.285sqm @820.86/sqm 63440.17
6.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 451.781sqm @403.74/sqm 182402.06
6.014 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 275.470sqm @316.08/sqm 87070.56
6.015 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat, preparation
of surface, etc. complete.On concrete work
Net Total 217.618sqm @224.33/sqm 48818.25
6.016 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 255.886sqm @573.84/sqm 146837.62
6.017 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 192.580sqm @442.30/sqm 85178.13
6.018 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
Net Total 601.812Kilo @185.72/Kilo 111768.52
litre litre
6.019 10.26.3
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing,
balcony railing, staircase railing and similar works, including applying priming coat
of approves steel primer.G.I. pipes
Net Total 393.359kg @187.17/kg 73625.00
Heading Total(Rs) 9701563.46
7 THICKENED SLUDGE SUMP
7.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Net Total 9.043cum @215.37/cum 1947.59
7.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 1824.720kilo
gram @98.92/kilogram 180501.30
7.009 OD5178/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 1824.720kg @2.32/kg 4233.35
7.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 7.347sqm @337.42/sqm 2479.02
7.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 60.878sqm @721.70/sqm 43935.65
7.012 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 12.310sqm @820.86/sqm 10104.79
7.013 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 88.658sqm @403.74/sqm 35794.78
7.014 13.52.2
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied
as per manufacturer's specifications including appropriate priming coat, preparation
of surface, etc. complete.On concrete work
Net Total 45.467sqm @224.33/sqm 10199.61
7.015 22.23.1
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For vertical surface two coats @0.70 kg per sqm
Net Total 33.158sqm @573.84/sqm 19027.39
7.016 22.23.2
Providing and applying integral crystalline slurry of hydrophilic in nature for
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 9.075sqm @442.30/sqm 4013.87
7.017 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
22.687Kilo @185.72/Kilo
Net Total 4213.43
litre litre
Heading Total(Rs) 548072.53
8 CENTRATE SUMP
8.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Net Total 4.537cum @215.37/cum 977.13
8.002 4.1.5
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3
coarse sand : 6 graded stone aggregate 20 mm nominal size)
Net Total 1.815cum @7413.74/cum 13455.94
8.003 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
8.009 OD6632/2022-2023
waterproofing treatment to the RCC structures like retaining walls of the basement,
water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels
/ subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts
integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts
integral crystalline slurry : 1 part water) for horizontal surfaces and applying the
same from negative (internal) side with the help of synthetic fiber brush. The material
shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing
permeability of concrete by more than 90% compared with control concrete as per
DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The
crystalline
slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work
shall be carried out all complete as per specification and the direction of the
engineerin-
charge. The product performance shall carry guarantee for 10 years against any
leakage.For horizontal surface one coat @1.10 kg per sqm.
Net Total 3.140sqm @442.30/sqm 1388.82
8.017 100.36.1
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
9.420Kilo @185.72/Kilo
Net Total 1749.48
litre litre
Heading Total(Rs) 356502.68
9 CHLORINATOR CONTACT TANK
9.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Net Total 1180.541cum @215.37/cum 254253.12
9.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3
coarse sand : 6 graded stone aggregate 40 mm nominal size)
Net Total 67.239cum @7256.34/cum 487909.05
9.003 OD7428/2022-2023
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20cm in depth, consolidation each deposited layer by ramming and
watering, with all lead and lift as per direction of site Engineer-in-charge
Net Total 588.463cum @384.47/cum 226246.37
9.004 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 211.946cum @9947.98/cum 2108434.57
9.005 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 124.292cum @11610.44/cum 1443084.81
9.006 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 336.232cum @82.60/cum 27772.76
9.007 OD18128/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level.
Net Total 336.232cum @1899.46/cum 638659.23
9.008 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 336.232kg @1.35/kg 453.91
9.009 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 60.600sqm @337.42/sqm 20447.65
9.010 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
10.004 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 44.496cum @11610.44/cum 516618.14
10.005 5.34.1
Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the
specified cement content used is payable/ recoverable separately.Providing M-30
grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered
in M-30 is @ 340 kg/cum).
Net Total 82.128cum @82.60/cum 6783.77
10.006 4.12
Extra for providing and mixing water proofing material in cement concrete work in
doses by weight of cement as per manufacturer's specification .
Net Total 27102.240kg @1.35/kg 36588.02
10.007 OD6604/2022-2023
Extra for providing sulphate resistant cement for the structures above plinth level
Net Total 82.128cum @1899.46/cum 155998.85
10.008 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 9855.360kilo
gram @98.92/kilogram 974892.21
10.009 OD6605/2022-2023
Extra for providing epoxy coating for reinforcement bars
Net Total 9855.360kg @2.32/kg 22864.44
10.010 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 22.960sqm @337.42/sqm 7747.16
10.011 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Filling water with 5000 litre tankers fited in lorry and conveying water from a
distance of 5 km (average) to the reservoir site and pumping the water into the
reservoir of height not less than 3 m using 5 HP diesel engine pump set , hire for
tanker lorry, tools and other appliences and cost of water etc. complete.
Net Total 360.000Kilo @185.72/Kilo 66859.20
litre litre
Heading Total(Rs) 2909726.28
11 CENTRIFUGE BUILDING
11.001 2.3.1
Banking excavated earth in layers not exceeding 20 cm in depth, breaking clods,
watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and
rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and
dressing up, in embankments for roads, flood banks, marginal banks, and guide
banks etc., lead up to 50 m and lift up to 1.5 m :All kinds of soil
Net Total 270.000cum @557.37/cum 150489.90
11.002 20.2.4
Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe
working load not less than specified, excluding the cost of steel reinforcement but
including the cost of boring, with bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be
embedded in the pile cap etc. all complete, including removal of excavated earth with
all lifts and leads (Length of pile for payment shall be measured upto bottom of pile
cap).500 mm dia piles
Net Total 108.000metre @2515.72/metre 271697.76
11.003 5.22.2
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Net Total 2543.400kilo @101.43/kilogra 257977.06
gram m
11.004 20.6.2.1
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test
cap and dismantling of test cap after test etc. complete as per specification & the
direction of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityInitial test
Net Total 1.000per test @71313.78/per 71313.78
test
11.005 20.6.2.2
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test
cap and dismantling of test cap after test etc. complete as per specification & the
direction of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityRoutine test
@36449.26/per
Net Total 1.000per test 36449.26
test
11.006 2.8.1
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including
getting out the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.All kinds of soil
Net Total 5.391cum @298.84/cum 1611.05
11.007 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Net Total 7.761cum @6857.60/cum 53221.83
11.008 2.25
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited
layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Net Total 8.571cum @260.18/cum 2230.00
11.009 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 12.770cum @9947.98/cum 127035.70
11.010 50.5.33.2
Providing and laying in position machine batched and machine mixed design mix M-
20 grade cement concrete for reinforced cement concrete work, using cement content
as per approved design mix, including pumping of concrete to site of laying but
excluding the cost of centering, shuttering, finishing and reinforcement, including
admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting
of concrete, improve workability without impairing strength and durability as per
direction of Engineer-in-charge. Note:- Cement content considered in this item is @
330 kg/cum. Excess or less cement used as per design mix is payable or recoverable
separately. All work above plinth level upto floor V level
Net Total 49.358cum @11135.02/cum 549602.32
11.011 5.9.1
11.016 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 35.817cum @7968.73/cum 285416.00
11.017 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 476.893sqm @316.08/sqm 150736.34
11.018 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 101.701sqm @403.74/sqm 41060.76
11.019 13.16.1
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
Net Total 178.031sqm @269.26/sqm 47936.63
11.020 11.41.2
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by
the manufacturer) with water absorption less than 0.08% and conforming to IS :
15622, of approved make, in all colours and shades, laid on 20 mm thick cement
mortar 1:4(1 cement : 4 coarse sand), including grouting the joints with white cement
12.008 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 36.340sqm @337.42/sqm 12261.84
12.009 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 144.508sqm @820.86/sqm 118620.84
12.010 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Net Total 131.410sqm @653.88/sqm 85926.37
12.011 5.9.6
Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Net Total 98.880sqm @869.03/sqm 85929.69
12.012 50.2.26.1
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20 cm in depth, consolidating each deposited layer by ramming and
watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-
charge.
Net Total 39.800cum @297.36/cum 11834.93
12.013 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 17.425cum @9947.98/cum 173343.55
12.014 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
12.016 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 33.533cum @7968.73/cum 267215.42
12.017 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 622.866sqm @316.08/sqm 196875.49
12.018 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 188.480sqm @403.74/sqm 76096.92
12.019 13.16.1
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
Net Total 154.658sqm @269.26/sqm 41643.21
12.020 9.48.2
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel
primer all complete.Fixed to openings/ wooden frames with rawl plugs screws etc
Net Total 135.000kg @217.34/kg 29340.90
12.021 21.1.1.1
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
12.028 13.63.1
Painting with aluminium paint of approved brand and manufacture to give an even
shade.Two or more coats on new work
Net Total 29.250sqm @132.95/sqm 3888.79
Heading Total(Rs) 3106182.70
13 AIR BLOWER BUILDING
13.001 2.31
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
Net Total 150.000sqm @14.84/sqm 2226.00
13.002 20.2.2
Boring, providing and installing bored cast-in-situ reinforced cement concrete piles of
grade M-25 of specified diameter and length below the pile cap to carry a safe
working load not less than specified, excluding the cost of steel reinforcement but
including the cost of boring, with bentonite solution and temporary casing of
appropriate length for setting out and removal of same and the length of the pile to be
embedded in the pile cap etc. all complete, including removal of excavated earth with
all lifts and leads (Length of pile for payment shall be measured upto bottom of pile
cap).400 mm dia piles
Net Total 108.000metre @2515.72/metre 271697.76
13.003 5.22.2
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelHard drawn steel wire
Net Total 1627.776kilo @101.43/kilogra 165105.32
gram m
13.004 20.6.2.1
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test
cap and dismantling of test cap after test etc. complete as per specification & the
direction of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityInitial test
Net Total 1.000per test @71313.78/per 71313.78
test
13.005 20.6.2.2
Vertical load testing of piles in accordance with IS 2911( Part IV) including
installation of loading platform and preparation of pile head or construction of test
cap and dismantling of test cap after test etc. complete as per specification & the
direction of engineer -in-Charge.
Single pile above 50 tonne and upto 100 tonne capacityRoutine test
Net Total 1.000per test @36449.26/per 36449.26
test
13.006 2.8.1
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 18.286cum @11610.44/cum 212308.51
13.014 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 3079.700kilo
gram @98.92/kilogram 304643.92
13.015 50.2.26.1
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20 cm in depth, consolidating each deposited layer by ramming and
watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-
charge.
Net Total 11.820cum @297.36/cum 3514.80
13.016 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 28.652cum @7968.73/cum 228320.05
13.017 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 366.600sqm @316.08/sqm 115874.93
13.018 13.16.1
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
Net Total 146.737sqm @269.26/sqm 39510.40
13.019 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 91.150sqm @403.74/sqm 36800.90
13.020 11.41.2
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by
the manufacturer) with water absorption less than 0.08% and conforming to IS :
15622, of approved make, in all colours and shades, laid on 20 mm thick cement
mortar 1:4(1 cement : 4 coarse sand), including grouting the joints with white cement
and matching pigments etc., complete.Size of Tile 600 x 600 mm.
Net Total 52.220sqm @1777.36/sqm 92813.74
13.021 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end
by end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS:
4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25
mm M.S. laths with 1.25 mm thick top cover
Net Total 9.000sqm @3487.22/sqm 31384.98
13.022 9.48.2
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel
primer all complete.Fixed to openings/ wooden frames with rawl plugs screws etc
Net Total 297.000kg @217.34/kg 64549.98
13.023 21.1.1.1
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
For fixed portionAnodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Net Total 66.825kg @502.18/kg 33558.18
13.024 21.1.2.1
For shutters of doors, windows & ventilators including providing and fixing hinges /
pivots and making provision for fixing of fittings wherever required including the
cost of EPDM rubber/ neoprene gasket required (Fittings shall be paid for
separately)Anodised aluminium ( anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Net Total 31.080kg @608.10/kg 18899.75
13.025 21.3.1
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
14.013 14.12
Providing and fixing 16 mm M.S. Fan clamps of standard shape and size in existing
R.C.C. slab, including cutting chase, anchoring clamp to reinforcement bar, including
cleaning, refilling, making good the chase with matching concrete, plastering and
painting the exposed portion of the clamps complete.
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved
make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick
cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with
white cement and matching pigment etc., complete.
Net Total 8.400sqm @1097.89/sqm 9222.28
14.024 11.38
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of Ist quality conforming to IS : 15622, of approved
make, in all colours, shades, except White, Ivory, Grey, Fume Red Brown, laid on 20
mm thick bed of cement mortar 1:4 ( 1 cement : 4 Coarse sand), including pointing
the joints with white cement and matching pigments etc., complete.
Net Total 47.040sqm @1180.56/sqm 55533.54
14.025 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end
by end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS:
4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25
mm M.S. laths with 1.25 mm thick top cover
Net Total 4.800sqm @3487.22/sqm 16738.66
14.026 10.7
Providing and fixing ball bearing for rolling shutters.
Net Total 1.000no @497.32/no 497.32
14.027 10.3
Providing and fixing in position collapsible steel shutters with vertical channels
20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom
rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts,
nuts,locking arrangement, stoppers, handles, including applying a priming coat of
approved steel primer .
Net Total 3.150sqm @10269.95/sqm 32350.34
14.028 21.1.1.1
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other
sections of approved make conforming to IS : 733 and IS: 1285, fixing with dash
fasteners of required dia and size, including necessary filling up the gaps at junctions,
i.e. at top, bottom and sides with required EPDM rubber/ neoprene gasket etc.
Aluminium sections shall be smooth, rust free, straight, mitred and jointed
mechanically wherever required including cleat angle, Aluminnium snap beading for
glazing /paneling, C.P. brass/ stainless steel screws, all complete as per architectural
drawings and the directions of Engineer-in-charge.(Glazing, paneling and dash
fasteners to be paid for separately):
For fixed portionAnodised aluminium (anodised transparent or dyed to required shade
according to IS : 1868, Minimum anodic coating of grade AC 15)
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer-
in-Charge. External work25 mm nominal outer dia pipes
Net Total 25.000metre @386.90/metre 9672.50
14.042 18.9.4
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer-
in-Charge. External work32 mm nominal outer dia pipes
Net Total 50.000metre @490.02/metre 24501.00
14.043 18.19.1.2
Providing and fixing gun metal non-return valve of approved quality (screwed end):
25 mm nominal boreVertical
Net Total 1.000each @597.51/each 597.51
14.044 18.49.1
Providing and fixing C.P brass bib cock of approved quality conforming to IS:
8931.15 mm nominal bore
Net Total 2.000each @496.25/each 992.50
14.045 18.58.2.1
Providing and fixing PTMT grating of approved quality and colour.
Rectangular type with openable circular lid150 mm nominal size square 100 mm
diameter of the inner hinged round grating
Net Total 2.000each @200.18/each 400.36
14.046 17.31
Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved
quality) complete with 6 mm thick hard board ground fixed to wooden cleats with
C.P. brass screws and washers complete.
Net Total 2.000each @1519.71/each 3039.42
14.047 18.48
Providing and placing on terrace (at all floor levels) polyethylene water storage tank
:ISI 12701 marked, with cover and suitable locking arrangement and making
necessary holes for inlet, outlet and overflow pipes but without fittings and the base
support for tank.
Net Total 1000.000Litre @10.44/Litre 10440.00
14.048 OD6727/2022-2023
Supplying and providing Chequred plate 7mm thick including all cost and
conveyance of all materials and labour charges etc. complete
Net Total 9.240sqm @6039.80/sqm 55807.75
Heading Total(Rs) 5961501.20
15 SLUDGE SHED
15.001 2.8.1
Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including
getting out the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.All kinds of soil
Net Total 41.616cum @298.84/cum 12436.53
15.002 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Net Total 14.200cum @6857.60/cum 97377.92
15.003 2.25
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited
layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Net Total 35.000cum @260.18/cum 9106.30
15.004 50.6.7.1
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for foundation and basement including all cost of materials,
labour charges etc.
Net Total 28.220cum @7216.85/cum 203659.51
15.005 50.5.33.2
Providing and laying in position machine batched and machine mixed design mix M-
20 grade cement concrete for reinforced cement concrete work, using cement content
as per approved design mix, including pumping of concrete to site of laying but
excluding the cost of centering, shuttering, finishing and reinforcement, including
admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting
of concrete, improve workability without impairing strength and durability as per
direction of Engineer-in-charge. Note:- Cement content considered in this item is @
330 kg/cum. Excess or less cement used as per design mix is payable or recoverable
separately. All work above plinth level upto floor V level
Net Total 8.125cum @11135.02/cum 90472.04
15.006 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 11.017cum @9947.98/cum 109596.90
15.007 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 1914.600kilo
gram @98.92/kilogram 189392.23
15.008 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 8.100sqm @337.42/sqm 2733.10
15.009 5.9.6
Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Net Total 48.600sqm @869.03/sqm 42234.86
15.010 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Net Total 103.700sqm @653.88/sqm 67807.36
15.011 12.1.1
Providing corrugate G.S. sheet roofing including vertical/ curved surface fixed with
polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I.
limpet washers or with G.I. limpet washers filled with white lead, including a coat of
approved steel primer and two coats of approved paint on overlapping of sheets
complete ( up to any pitch in horizontal / vertical or curved surfaces), excluding the
cost of purlins, rafters and trusses and including cutting to size and shape wherever
required.1.00 mm thick with zinc coating not less than 275 gm/m2
Net Total 162.400sqm @1461.95/sqm 237420.68
15.012 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 387.730sqm @316.08/sqm 122553.70
15.013 13.9.2
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.20 mm cement plaster
Net Total 100.000sqm @545.65/sqm 54565.00
15.014 10.2
Structural steel work riveted, bolted or welded in built up sections, trusses and framed
work, including cutting, hoisting, fixing in position and applying a priming coat of
approved steel primer all complete.
16.010 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 54.062cum @7968.73/cum 430805.48
16.011 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 702.724sqm @316.08/sqm 222117.00
16.012 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 201.240sqm @403.74/sqm 81248.64
16.013 13.16.1
6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
Net Total 182.200sqm @269.26/sqm 49059.17
16.014 11.41.2
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by
the manufacturer) with water absorption less than 0.08% and conforming to IS :
15622, of approved make, in all colours and shades, laid on 20 mm thick cement
mortar 1:4(1 cement : 4 coarse sand), including grouting the joints with white cement
and matching pigments etc., complete.Size of Tile 600 x 600 mm.
Net Total 120.540sqm @1777.36/sqm 214242.97
16.015 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end
by end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS:
4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25
mm M.S. laths with 1.25 mm thick top cover
Net Total 25.200sqm @3487.22/sqm 87877.94
16.016 9.48.1
Providing and fixing M.S. Grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. including priming coat with approved steel
primer all complete.Fixed to steel windows by welding
Net Total 444.960kg @195.81/kg 87127.62
16.017 21.11.1
Providing and fixing stainless steel (SS 304 grade) adjustable friction window stays
of approved quality with necessary stainless steel screws etc. to the side hung
windows as per direction of Engineer - in-Charge complete.205 x 19 mm
Net Total 125.145no @302.91/no 37907.67
16.018 21.3.1
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the
architectural drawings and the directions of Engineer - in -Charge. ( Cost of
aluminium snap beading shall be paid in basic item):With float glass panes of 4.0 mm
thickness
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 0.488cum @9947.98/cum 4854.61
17.006 5.37.2
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All work above
plinth level upto floor V level
Net Total 2.736cum @11610.44/cum 31766.16
17.007 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 258.080kilogr
am @98.92/kilogram 25529.27
17.008 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 20.040sqm @820.86/sqm 16450.03
17.009 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Net Total 8.300sqm @653.88/sqm 5427.20
17.010 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 89.420sqm @316.08/sqm 28263.87
17.011 13.7.1
Wall painting with acrylic emulsion paint, having VOC (Volatile Organic Compound)
content less than 50 grams/ litre, of approved brand and manufacture including
applying additional coats wherever required, to achieve even shade and colour.Two
coats
Net Total 109.460sqm @126.53/sqm 13849.97
17.019 13.62.1
Painting with synthetic enamel paint of approved brand and manufacture of required
colour to give an even shade:Two or more coats on new work over an under coat of
suitable shade with ordinary paint of approved brand and manufacture .
Net Total 4.500sqm @209.84/sqm 944.28
17.020 17.7.2
Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32
mm C.P. brass waste of standard pattern, including painting of fittings and brackets,
cutting and making good the walls wherever require:White Vitreous China Wash
basin size 630 x 450 mm with a single 15 mm C.P. brass pillar tap
Net Total 1.000each @3258.81/each 3258.81
17.021 18.9.2
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer-
in-Charge. External work20 mm nominal outer dia pipes
Net Total 25.000metre @300.52/metre 7513.00
17.022 18.9.3
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer-
in-Charge. External work25 mm nominal outer dia pipes
Net Total 25.000metre @386.90/metre 9672.50
17.023 18.9.4
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal
stability for hot & cold water supply including all CPVC plain & brass threaded
fittings. This includes jointing of pipes & fittings with one step CPVC solvent
cement, trenching , refilling & testing of joints complete as per direction of Engineer-
in-Charge. External work32 mm nominal outer dia pipes
Net Total 25.000metre @490.02/metre 12250.50
17.024 17.31
Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved
quality) complete with 6 mm thick hard board ground fixed to wooden cleats with
C.P. brass screws and washers complete.
Net Total 1.000each @1519.71/each 1519.71
Heading Total(Rs) 363322.37
18 PSF/ACF Foundation
18.001 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means
over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed
earth to be levelled and neatly dressed.All kinds of soil
Net Total 119.064cum @215.37/cum 25642.81
18.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3
coarse sand : 6 graded stone aggregate 40 mm nominal size)
Net Total 39.688cum @7256.34/cum 287989.62
18.003 5.37.1
Providing and laying in position ready mixed M-25 grade concrete for reinforced
cement concrete work, using cement content as per approved design mix,
manufactured in fully automatic batching plant and transported to site of work in
transit mixer for all leads, having continuous agitated mixer, manufactured as per mix
design of specified grade for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures in recommended
proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per direction of the Engineer
- in -charge. Note:- Cement content considered in this item is @330 kg/cum. Excess
/less cement used as per design mix is payable/recoverable separately.All wiork upto
plinth level
Net Total 76.800cum @9947.98/cum 764004.86
18.004 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 3072.000kilo
gram @98.92/kilogram 303882.24
18.005 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 38.560sqm @337.42/sqm 13010.92
18.006 13.7.1
12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1
cement : 3 fine sand)
Net Total 217.600sqm @403.74/sqm 87853.82
Heading Total(Rs) 1482384.27
19 EFFLUENT DISPOSAL AND STORM WATER DRAINS
19.001 2.8.1
19.005 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 403.200sqm @721.70/sqm 290989.44
19.006 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 456.000sqm @316.08/sqm 144132.48
Heading Total(Rs) 2691818.59
20 STP LAND DEVELOPMENT & INTERNAL SERVICE ROADS
20.001 2.32
Clearing grass and removal of the rubbish up to a distance of 50 m outside the
periphery of the area cleared.
Net Total 5000.000sqm @7.57/sqm 37850.00
20.002 2.33.3
Felling trees of the girth (measured at a height of 1 m above ground level) including
cutting of trunks and branches, removing the roots and stacking of serviceable
material and disposal of unserviceable material.Beyond 120 cm girth up to and
including 240 cm girth
Net Total 15.000each @9310.60/each 139659.00
20.003 OD6765/2022-2023
Filling with contractor own earth (excluding rock) in open areas in layers not
exceeding 20cm in depth, consolidation each deposited layer by ramming and
watering, with all lead and lift as per direction of site Engineer-in-charge
Net Total 7000.000cum @384.47/cum 2691290.00
20.004 100.41.39
Supply, stacking, spreading and consolidating of Quarry Muck in the trench of pipe
line, including carriage, loading, unloading & stacking up to any lead.
Net Total 630.000cum @549.44/cum 346147.20
20.005 OD6778/2022-2023
Construction of granular sub-base by providing graded material, spreading in uniform
layers with a motor grader on a prepared surface, mixing by mix in-place method with
rotavator at OMC and compacting with a vibratory roller to achieve the
desireddensity, complete as per clause 401. Grading-V - For sub-base cum drain age
layer - Mix in Place Method
Net Total 630.000cum @3729.38/cum 2349509.40
20.006 OD15389/2022-2023
Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface
of granular<br>Base including clearing of road surface and spraying primer at
the rate of 0.70 - 1.0 kg/sqm using<br>mechanical means
Net Total 1700.000sqm @68.56/sqm 116552.00
20.007 OD15390/2022-2023
Providing and applying tack coat with bitumen emulsion( RS) using emulsion
pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous
surface cleaned with mechanical broom
Net Total 1700.000sqm @10.41/sqm 17697.00
20.008 OD10703/2022-2023
Providing, laying and rolling of open graded premix carpet of 20 mm thickness with
0.27 cum of 12 mm departmental aggregates premixed with 12.96 kg of bitumen per
10 sqm using penetration grade bitumen to required line, grade and level on a
previously prepared base, after priming the existing surface with 5 kg of bitumen (VG
30) 10 sqm including mixing in a suitable plant, laying and rolling with a three wheel
static roller of 80-100 KN capacity, finished to required level and grades,followed by
a seal coat of 0.09 cum of 6 mm departmental aggregates premixed with 8.64 kg of
bitumen per 10 sqm.By Manual Means.
1700.0001 @205.03/1 sqm
Net Total 348551.00
sqm
20.009 OD10704/2022-2023
Seal Coat - Manual Means - Type C - Bitumen S-65 Providing and laying seal coat
sealing the voids in a bituminous surface laid to the specified levels, grade and cross
fall using Type A, Type B and Type C as per Technical Specification Clause 510
A.By Manual Means:-Case - III : Type C
1700.0001 @90.60/1 sqm
Net Total 154020.00
sqm
20.010 16.91.2
Providing and laying factory made chamfered edge Cement Concrete paver blocks
in footpath, parks, lawns, drive ways or light traffic parking etc, of required strength,
thickness & size/ shape, made by table vibratory method using PU mould, laid in
required colour & pattern over 50mm thick compacted bed of sand, compacting and
proper embedding/laying of inter locking paver blocks into the sand bedding layer
through vibratory compaction by using plate vibrator, filling the joints with sand and
cutting of paver blocks as per required size and pattern, finishing and sweeping
extra sand. complete all as per direction of Engineer-in-Charge.80 mm thick C.C.
paver block of M-30 grade with approved color design and pattern.
Net Total 240.000sqm @1128.81/sqm 270914.40
20.011 16.59.1
Manufacturing, supplying and fixing retro reflective sign boards made up of 2 mm
thick aluminium sheet, face to be fully covered with high intensity encapsulated
type heat activated retro reflective sheeting conforming to type - IV of ASTM-D
4956-01 in blue and silver white or other colour combination including subject
matter, message (bi-lingual), symbols and borders etc. as per IRC: 67- 2001, pasted
on substrate by an adhesive backing which shall be activated by applying heat
and pressure conforming to class-2 of ASTM-D-4956-01 and fixing the same with
suitable sized aluminium alloy rivets @ 20 cm c/c to back support frame of M.S.
angle iron of size 25x25x3 mm along with theft resistant measures, mounted and
fixed with 2 Nos M.S. angles of size 35x35x5 mm to a vertical post made up to M.S.
Tee section ISMT 50x50x6 mm welded with base plate of size 100x100x 5 mm at the
bottom end and including making holes in pipes, angles flats, providing & fixing
M.S. message plate of required size, steel work to be painted with two or more
coats of synthetic enamel paint of required shade and of approved brand &
manufacture over priming coat of zinc chromate yellow primer (vertical MS-Tee
support to be painted in black and white colours). Backside of aluminium sheet to
be painted with two or more coats of epoxy paint over and including appropriate
priming coat including all leads and lifts etc. complete as per drawing , specification
and direction of Engineer-in-Charge.Mandatory / Regulatory sign boards of 900 mm
diametre with support length of 3750 mm
Net Total 3.000each @7103.90/each 21311.70
20.012 16.59.2
Manufacturing, supplying and fixing retro reflective sign boards made up of 2 mm
thick aluminium sheet, face to be fully covered with high intensity encapsulated
type heat activated retro reflective sheeting conforming to type - IV of ASTM-D
4956-01 in blue and silver white or other colour combination including subject
matter, message (bi-lingual), symbols and borders etc. as per IRC: 67- 2001, pasted
on substrate by an adhesive backing which shall be activated by applying heat
and pressure conforming to class-2 of ASTM-D-4956-01 and fixing the same with
suitable sized aluminium alloy rivets @ 20 cm c/c to back support frame of M.S.
angle iron of size 25x25x3 mm along with theft resistant measures, mounted and
fixed with 2 Nos M.S. angles of size 35x35x5 mm to a vertical post made up to M.S.
Tee section ISMT 50x50x6 mm welded with base plate of size 100x100x 5 mm at the
bottom end and including making holes in pipes, angles flats, providing & fixing
M.S. message plate of required size, steel work to be painted with two or more
coats of synthetic enamel paint of required shade and of approved brand &
manufacture over priming coat of zinc chromate yellow primer (vertical MS-Tee
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 18.360cum @7968.73/cum 146305.88
21.005 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Net Total 1.368cum @9142.08/cum 12506.37
21.006 5.2.2
Reinforced cement concrete work in walls (any thickness), including attached
pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,
abutments, posts and struts etc. up tot floor five level excluding cost of centering,
shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded
stone aggregate 20 mm nominal size)
Net Total 0.756cum @11022.69/cum 8333.15
21.007 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 6.240sqm @337.42/sqm 2105.50
21.008 5.9.2
Centering and shuttering including strutting, etc. and removal of form for:Walls (any
thickness) including attached pilasters, butteresses, plinth and string courses etc.
Net Total 10.080sqm @721.70/sqm 7274.74
21.009 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 172.740sqm @316.08/sqm 54599.66
21.010 13.43.1
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Net Total 172.740sqm @71.10/sqm 12281.81
21.011 13.60.1
Wall painting with acrylic emulsion paint of approved brand and manufacture to give
an even shade:Two or more coats on new work
Net Total 172.740sqm @152.38/sqm 26322.12
21.012 10.25.2
Item Shifted to Sub head 14 as item 14.73
Item Shifted to head 14 as item 14.74
Steel work welded in built up sections/framed work, including cutting, hoisting,
fixing in position and applying a priming coat of approved steel primer using
structural steel etc. as required.In gratings, frames, guard bar, ladder, railings,
brackets, gates and similar works
25.014 OD58186/2022-2023
EXTERNAL LIGHTING Providing external lighting arrangements by supplying and
laying of PVC insulated and PVC sheathed / XLPE power cable of Copper conductor
XLPE control cables as per is:7098/Part-I/88 with latest amendments 1.1 kv grade of
required size direct in ground including MCCB/MCB/RCCB,supply and erection of
mettalic poles,strret light poles,earthing and safety equipments ,fire extinguishers ,etc
. complete including necessary excavation, sand cushioning, protective covering and
refilling the trench etc. as required in the specifications or as directed by the Engineer
in Charge."
Net Total 1.000L.S @1000000.00/L. 1000000.00
S
26.004 OD58227/2022-2023
Griting Mechanism :- Supplying at site all electro-mechanical equipments,
fabricating, fixing and commissioning of the griting mechanism to suit gritting
chamber sizes to remove grit,consisting of sand,gravel,cinders with specific gravity
greater than those of the organic solids in waste water, protecting the moving
mechanical equioments and pump elements from abrasion and accompanying
abnormal wear and tear, it consists of grit scrapper,classifier and organic return pump
as directed by the Engineer in Charge."
Net Total 2.000set @275000.01/set 550000.02
26.005 OD58228/2022-2023
Supplying and fixing of mono block centrifugal pump, for rated continuous duty and
best efficiency CI construction, CI impeller, complete with 3 phase motor,FRP motor
cover, pressure gauge, operation on 415 /-10% volts, 50 HZ, AC power supply etc
including sluice valves, Pressure gauges, NRVs with DI/I/Pipes connecting common
delivery suitable for complete in all respects as required by the standard specifications
and shall suit following capacities complete with all accessories as per technical
specification.Pumps shall have dry run protection & high/ low level alarm.
Electrical Control panel shall be supplied with the pump as per the specifications in
the Electrical BOQMotor : three phase motor with IP
68 Protection"- Pump for clarifier to PSF 4 4.00
Net Total 4.000no @542000.00/no 2168000.00
26.006 OD58229/2022-2023
"Air Blower Supply,erection, testing and commissioning of twin lobe air
blower for indoor application complete with acoustic canopy, air filter, motor of 1500
rpm , pulleys, pressure gauges, pressure relief valve, acoustic hood, suction silencer
with suitable flanges, common motor and compressor base frame with motor belt
tightening arrangement interconnecting line with flanges including all accessories
complete as per technical specification or as Directed by Engineer in Charge
Capacity: 2763 m3/hr.Pressure: 0.6 kg/sqcm Motor : three phase motor with IP 68
Protection (4W 1 S)"90HP
Net Total 5.000set @425000.00/set 2125000.00
26.007 OD58230/2022-2023
Bubble Diffuser for SBR Tank Supplying at site, erection, testing &
commissioning of Fine Bubble Diffuser (retrievable type using rope and pulley
arrangement) for the aeration system of the MBBR Tansk (2Nos) with diffusers of
sufficient size and length made of EPDM make with SS tee 1"" x 1
"", SS lifting hook 8 mm, SS foundation bolt 6 mm, SS C clamp suitable
for 1"" O.D, hose, PP Rope, PP swivel nut, PP sleeve, Silicone Washer,
SS hose clamp, RCC block complete at a minimum rating of 95m/hr as per technical
specification or as directed by the Engineer in Charge" for four basigns
Net Total 4.000set @426000.00/set 1704000.00
26.008 OD58231/2022-2023
Air Grid Pipe Supply and installation of air pipes (ss) aly into valves and other
acessories as required for the blowers to various tanks as a complete unit"
Net Total 4.000no @290375.00/no 1161500.00
26.009 OD58232/2022-2023
26.020 OD58243/2022-2023
"Activated Carbon filter Supply at site, erection and commissioning of
Activated Carbon filter vertical type pressure vessel fabricated with MS construction
with epoxy coating inside and anti corrosive treatment outside, two coats of paint
outside ( pain quality as instructed by Engineer) withstand a minimum test pressure of
7.0Kg/cm with as operating pressure of 3.5 Kg/cm, complete with valves and filter
media including activated carbon of approved grade and quality , frontal piping,
butteryfly valves, internals, pressure gauges, strainers, supporting structure, back
wash arrangement, etc and all other accessories tested twice the working pressure
supported over pebble/gravel with inspection manholes etc complete as per
specification or as directed by Engineer in Charge. The scope shall include complete
piping with MS fabricated pipes and specials including valves<br>Flow rate -
250 m/hr
Net Total 6.000set @2206848.00/set 13241088.00
26.021 OD58244/2022-2023
Supply at site, installation and commissioning of filter press /centrifuge system. Filter
Press shall be automated, recessed type press with SS fabricated structure pipe button
surface and SS flat parallel bar, with PP cloth. Filter operations to be mechanical.
Outlet cake consistency should not be more than 35% moisture. The capacity of the
filter press shall be 1cum/hr. The Filter Press Unit shall be mounted on a platform and
all around drain system to be provided to prevent the filtrate water from
contaminating the entire surroundings as per the specifications or as directed by the
engineer in charge"
Net Total 4.000no @668450.00/no 2673800.00
26.022 OD58245/2022-2023
SLUDGE DEWATERING and Packing UNIT -Volute is a dewatering unit for
convenient sludge
dewatering.Machine is available for dry sludge (DS) output of 1.0kg/hr to 750kg/hr
the Sludge to be dried from 70% moisture content to 10%.The similar type can be
suggested.The Packing of the dried sludge to be packed in the packing machine.The
necessary electrification civil works,cost of packing machine,cost of gunny bags for
6months.The machines suggested should be cost effective
Net Total 4.000set @1200000.00/set 4800000.00
26.023 OD58246/2022-2023
Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes,
channels, plates etc., including welding, grinding, buffing, polishing and making
curvature (wherever required) and fitting the same with necessary stainless steel nuts
and bolts complete, i/c fixing the railing with necessary accessories & stainless
steel dash fasteners, stainless steel bolts etc., of required size on the top of the floor or
the side of waist slab with suitable arrangement as per approval of Engineer-in-
charge, (for payment purpose only weight of stainless steel members shall be
considered excluding fixing accessories such as nuts, bolts, fasteners etc.)kg
Net Total 30.000kg @681.59/kg 20447.70
26.024 OD58247/2022-2023
Providing and laying Double Flanged ( Screwed / Welded ) Centrifugally (Spun)
Ductile Iron Pipes of Class K - 9 conforming to IS: 8329 :100 mm dia Ductile Iron
Double Flanged
Net Total 1.000L.S @1000000.00/L. 1000000.00
S
26.025 OD58249/2022-2023
Supply at site,erection, testing and commissioning of self priming, non clog
centrifugal submersible sewage transfer pump for rated continuous duty and
efficiency (from reputed manufacturers complying to IS 1520 and conforming to
other relevant standards), CI construction, bronze impeller,complete with 3 phase
motor, SS shaft, with automatic pedestal coupling, delivery bend, required wire chain,
washers, SS bolts etc including Double Flange DI/CI PN 1 rating sluice valves,
Pressure gauges, Double Flange DI/CI PN 1 rating NRVs with DI/I/Pipes connecting
common delivery suitable for operation on 415 /-10% volts, 50 HZ, AC power supply
etc. complete in all respects with detachable arrangements, level indicators for
automatic switch on & switch off as required by the standard specifications
complete with all accessories as per technical specification or as directed by Engineer
In Charge.Pumps shall have dry run protection & high/ low level alarm.
Electrical Control panel shall be supplied with the pump as per the specifications in
the Electrical BOQ Three phase Motor with IP 68 protection (1W 1S)"- septage
feed pump- 12m3/hr,12m
Net Total 2.000no @129753.01/no 259506.02
26.026 OD58250/2022-2023
Supply at site,erection, testing and commissioning of self priming, non clog
centrifugal submersible sewage transfer pump for rated continuous duty and
efficiency (from reputed manufacturers complying to IS 1520 and conforming to
other relevant standards), CI construction, bronze impeller,complete with 3 phase
motor, SS shaft, with automatic pedestal coupling, delivery bend, required wire chain,
washers, SS bolts etc including Double Flange DI/CI PN 1 rating sluice valves,
Pressure gauges, Double Flange DI/CI PN 1 rating NRVs with DI/I/Pipes connecting
common delivery suitable for operation on 415 /-10% volts, 50 HZ, AC power supply
etc. complete in all respects with detachable arrangements, level indicators for
automatic switch on & switch off as required by the standard specifications
complete with all accessories as per technical specification or as directed by Engineer
In Charge.Pumps shall have dry run protection & high/ low level alarm.
Electrical Control panel shall be supplied with the pump as per the specifications in
the Electrical BOQ Three phase Motor with IP 68 protection (1W 1S)"-
Dilution water pump 60m3/hr,12m
Net Total 2.000no @426000.00/no 852000.00
26.027 OD58251/2022-2023
Supply at site,erection, testing and commissioning of self priming, non clog
centrifugal submersible sewage transfer pump for rated continuous duty and
efficiency (from reputed manufacturers complying to IS 1520 and conforming to
other relevant standards), CI construction, bronze impeller,complete with 3 phase
motor, SS shaft, with automatic pedestal coupling, delivery bend, required wire chain,
washers, SS bolts etc including Double Flange DI/CI PN 1 rating sluice valves,
Pressure gauges, Double Flange DI/CI PN 1 rating NRVs with DI/I/Pipes connecting
common delivery suitable for operation on 415 /-10% volts,
50 HZ, AC power supply etc. complete in all respects with detachable arrangements,
level indicators for automatic switch on & switch off as required by the standard
specifications complete with all accessories as per technical specification or as
directed by Engineer In Charge.Pumps shall have dry run protection & high/ low
level alarm. Electrical Control panel shall be supplied with the pump as per the
specifications in the Electrical BOQ<br>Motor : three phase motor with IP 68
Protection"-Sludge Thickener Feed Pump & Clarifier to sludge sump
72m3/hr
GENERAL ABSTRACT
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 405
Rounded Total(Rs)
134453273.8
4
Rupees Thirteen Crore Forty Four Lakh Fifty Three Thousand Two Hundred and
Seventy Three
DETAILED ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 406
1.002 15.43.2
Dismantling manually / by mechanical means including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead as per direction
of Engineer -in-Charge:Bituminous road
Laying of sewer network
Sewer 2 3278.000 1.000 6556.000
Inspection
chamber to 1 2700.000 0.600 1620.000
manhole
Total 8176.000
Total Quantity in sqm 8176.000
1.003 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
demoloshing cement concrete manually
Demolishin
g o f cement
concrete ( 1 295.000 1.000 0.100 29.500
Municipality
roads)
Inspection
Chamber to 1 291.000 0.600 0.100 17.460
Manhole
Total 46.960
Total Quantity in cum 46.960
1.004 4.1.2
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2 coarse
sand : 3 graded stone aggregate 20 mm nominal size)
Laying of sewer network
Demolishin
g o f cement
concrete ( 1 295.000 1.000 0.100 29.500
Municipality
roads)
Inspection
Chamber to 1 291.000 0.600 0.100 17.460
Manhole
Total 46.960
Total Quantity in cum 46.960
1.005 100.8.2
Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with
coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
fencing
sewer 2 1700.000 0.600 2040.000
Inspection
Chamber to 1 1350.000 0.600 810.000
Manhole
Total 2850.000
Total Quantity in metre 2850.000
1.006 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape
in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
fencing
Sewer 1 1700.000 0.200 340.000
Inspection
Chamber to 1 1350.000 0.200 270.000
Manhole
Total 610.000
Total Quantity in metre 610.000
1.007 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
excavation of trenches all kinds of soil
Quantityfro 0.8000 4939.608
m calculation 1 6174.510 00
sheet
Inspection 0.8000
Chamber to 1 2700.000 0.600 1.100 1425.600
00
Manhole
Total 6365.208
Total Quantity in cum 6365.208
1.008 100.1.2
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in all kinds of soil.
Laying of sewer network
Quantity from 0.8000 1269.702
1 1587.128
calculation sheet 00
Total 1269.702
Total Quantity in cum 1269.702
1.009 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
excavation of trenches ordinary rock up to 1.5 m depth
Quantity from 0.2000 1234.902
1 6174.510
calculation sheet 00
Inspection
Chamber to 1 2700.000 0.600 1.100 0.2000 356.400
00
Manhole
Total 1591.302
Total Quantity in cum 1591.302
1.010 100.1.6
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in Ordinary Rock.
excavation of trenches above 1.5 m depth ordinary rock
Quantity from 0.2000
1 1587.128 317.426
calculation sheet 00
Total 317.426
Total Quantity in cum 317.426
1.011 2.17.2
Close timbering in case of shafts, wells, cesspits, manholes and the like including
strutting, shoring and packing cavities (wherever required) etc. complete
(Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not
exceeding 3 m
Laying of sewer network
2 2112.000 2.250 9504.000
Total 9504.000
Total Quantity in sqm 9504.000
1.012 2.23
Extra for planking and strutting in open timbering if required to be left permanently in
position (Face area of the timber permanently left to be measured).
extra forplanking
1 1500.000 2.800 4200.000
Total 4200.000
Total Quantity in sqm 4200.000
1.013 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
providing and laying cement concrete
RCCbeddin
g concrete where 1 900.000 0.600 0.100 54.000
ever necessary
Total 54.000
Total Quantity in cum 54.000
1.014 100.98.226
Supply of PVC Pipe, 8kg/cm2, 160mm Dia.
Laying of sewer network 160 pvc
Supply of PE Pipe, PE100, PN8, 400mm dia, conforming to IS 1433 (Sewerage Pipe)
supply of 400 pe
1 319.800 319.800
Total 319.800
Total Quantity in metre 319.800
1.024 OD46021/2022-2023
Supply of PE Pipe, PE100, PN8, 450mm dia, conforming to IS 1433 (Sewerage Pipe)
Laying of sewer network
1 597.000 597.000
Total 597.000
Total Quantity in metre 597.000
1.025 OD48967/2022-2023
Supply of PE pipe ,PE 100, PN 8,500mm dia .conforming to IS 1433(sewerage pipe)
Supply of PE pipe, 500 mm dia.
1 17.500 17.500
Total 17.500
Total Quantity in metre 17.500
1.026 OD46024/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.60m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for levelling course below foundation including earth work
excavation in all classes of soil,, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
construction of inspection chamber
150 150.000
Total 150.000
Total Quantity in cum 150.000
1.027 OD46025/2022-2023
Conveying to site, lowering into trenches, laying to correct line and grade using CC
holding clamps, 160mm PVC SN 8 (8 Kg/Cm2) S & S Sewerage pipes
conforming to I.S.15328, including jointing the pipes using rubber rings as per
approved methods with rubber gasket for flexible joints as per specification including
cost of gasket, to correct line , de watering with all rates of recuperation etc, providing
bedding for pipe line trenches with available earth, hydraulic testing the line to the
required test pressure as per IS, CPHEEO specifications, lighting, watching, providing
caution boards etc. wherever required, during laying and jointing the pipes including
hire for all tools etc complete including commissioning for the following diamters
conveying 160 pvc
1 4759.500 4759.500
Total 4759.500
Total Quantity in metre 4759.500
1.028 OD46026/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.45m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, , plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 150.000 150.000
Total 150.000
Total Quantity in no 150.000
1.029 OD46027/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.90m deep with
RCC M20 using
20mm broken stone for floor slab ,RCC M20 slab using 20mm broken stone for
removable cover slab,
Brick work in CM 1:6 for walls, PCC 1:4:8 using 20mm broken stone for leveling
course below foundation
including earth work excavation in all classes of soil, plastering the inside with CM
1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing
provision for connecting main sewer and service connections, conveying, lifting,
placing the cover slab in
position by suitable means, conveying and disposing the surplus earth with all lead and
lift as per
drawings and specifications , including the cost of reinforcement , testing the chamber
and sulphate
resistant cement shall be used for the the construction of inspection chamber
1.034 100.10.11
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead
and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 315mm Nominal
Outside Diameter Pipes.
laying 315 mm HDPE
1 1 123.000 123.000
Total 123.000
Total Quantity in metre 123.000
2 corporation Road Restoration work of laying of sewers and pumping main.
2.001 OD46042/2022-2023
Excavation for roadwork in soil with hydraulic excavator of 0.9Cum bucket capacity
including cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections and transporting to
the embankment location within all lifts and lead up to 1000m
Road restoration work of laying of sewers and pumping
sewer-
municipality 1 1466.900 2.500 0.300 1100.175
roads
Manhole to
inspection 1 1265.000 1.000 0.300 379.500
chamber
Total 1479.675
Total Quantity in cum 1479.675
2.002 OD67672/2022-2023
MoRD-Spec.No:4.1.A.1.
Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with smooth wheel roller to achieve the
desired density, complete as per Technical Specification Clause 401.
(i) For Grading I Material
granular sub base
open 1 1466.900 2.500 0.200 733.450
ic to mh 1 1265.000 1.000 0.200 253.000
Total 986.450
Total Quantity in cum 986.450
2.003 OD67671/2022-2023
MoRD Spec No-4.9.
Wet Mix Macadam
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and compacting
with smooth wheel roller of 80 to 100kN weight to achieve the desired density
including lighting, barricading and maintenance of diversion, etc as per Tables 400.11
& 400.12 and Technical Specification Clause 406.
By Mechanical Means with 1 km lead
wet mix
1 1 1466.900 2.500 0.150 550.088
ic to mh 1 1265.000 1.000 0.150 189.750
Total 739.838
Total Quantity in cum 739.838
2.004 OD67670/2022-2023
MoRD Spec.No-5.1.1a.
Prime Coat :- Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
tack coat
open 1 1466.900 2.500 3667.250
ic to mh 1 1265.000 1.000 1265.000
Total 4932.250
Total Quantity in sqm 4932.250
2.005 OD67669/2022-2023
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
clear ing jungle
1 12.500 11.500 143.750
Total 143.750
Total Quantity in sqm 143.750
3.002 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Construction of pumping stations
1 5000.000 5000.000
Total 5000.000
Total Quantity in Kwh 5000.000
3.003 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
centering and huttering
1.2000
Curb PH1 1 3.140 5.500 20.724
00
Total 20.724
Total Quantity in sqm 20.724
3.004 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Construction of pumping stations
COVER SLAB- 1 3.14/4 5.500 5.500 23.746
PH1
Total 23.746
Total Quantity in sqm 23.746
3.005 5.9.12
Centering and shuttering including strutting, etc. and removal of form for:Well
steining
Construction of pumping stations
PH1 2 3.140 4.900 8.800 270.794
Total 270.794
Total Quantity in sqm 270.794
3.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Construction of pumping stations
15953.20
1 199.415 80.000 0
15953.20
Total 0
3.007 OD46047/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.Initial depth upto 1.5m
Construction pumping station
PH1 1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.008 OD46048/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 1.5m
to 3.0m
Construction pumping station
PH1 1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.009 OD46049/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 3.0m
to 4.5m
Construction pumping station
PH1 1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.010 OD46050/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m
to 6.0m
Construction pumping station
PH2 1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.011 OD46051/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Construction pumping station
PH1 1 3.14/4 (5.5*5.5)- 8.800 69.080
(4.5*4.5)
Bottom plug 1 3.14/4 (5.5*5.5) 0.500 11.873
Curb top 1 3.140 (4.9*0.5) 0.200 1.539
rectangular
Curb triangular 1 3.140/2 (4.9*0.5) 0.500 1.923
Cover slab 1 3.140/4 (5.5*5.5) 0.200 4.749
Total 89.164
Total Quantity in cum 89.164
3.012 OD46052/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the engineer
in-charge.
Construction pumping station
ph1 1 52.000 52.000
Total 52.000
Total Quantity in no 52.000
3.013 OD48974/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 7.5 m
to 9.0m
Sinking wells above up to 3.5 m dia. and up to 6 m(7.5-9)
1 0.300 0.300
Total 0.300
Total Quantity in metre 0.300
3.014 OD48975/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 6.0m
to 7.5m
Sinking wells above up to 3.5 m dia. and up to 6 m(6-7.5)
1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
4 Compound wall with gate for Pumping stations
4.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Compound wall with gate for Pumping stations
1 30.000 0.600 0.800 14.400
Total 14.400
Total Quantity in cum 14.400
4.002 7.1.1
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Compound wall with gate for Pumping stations
1 30.000 0.450 0.450 6.075
Total 6.075
Total Quantity in cum 6.075
4.003 6.1.2
Brick work with common burnt clay F.P.S (non modular) bricks of class designation
7.5 in foundation and plinth in:Cement mortar 1:6 (1 cement : 6 coarse sand)
Compound wall with gate for Pumping stations
1 30.000 0.220 1.800 11.880
Total 11.880
Total 40.000
Total Quantity in no 40.000
5.008 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
CONSTRUCTION OF SCREEN CHAMBER AND VALVE CHAMBER
1 5000.000 5000.000
Total 5000.000
Total Quantity in Kwh 5000.000
5.009 13.7.2
12 mm cement plaster finished with a floating coat of neat cement of mix:1:4 ( 1
cement : 4 fine sand)
CONSTRUCTION OF SCREEN CHAMBER AND VALVE CHAMBER
WELL 1 SIDE 2 2*(3+2) 6.000 120.000
WALL
WORKING 1 2.500 0.150 0.375
PLATFORM
Total 120.375
Total Quantity in sqm 120.375
5.010 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
CONSTRUCTION OF SCREEN CHAMBER AND VALVE CHAMBER
WELL 1 SIDE 2 2*(3+2) 6.000 120.000
WALL
WORKING 1 2.500 0.150 0.375
PLATFORM
Total 120.375
Total Quantity in sqm 120.375
5.011 13.65.1
Painting with black anti- corrosive bitumastic paint of approved brand and
manufacture to give an even shade:Two or more coats on new work
CONSTRUCTION OF SCREEN CHAMBER AND VALVE CHAMBER
WELL 1 SIDE 2 2*(3+2) 6.000 120.000
WALL
WORKING 1 2.500 0.150 0.375
PLATFORM
Total 120.375
Total Quantity in sqm 120.375
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Construction of control room and generator room
Column footing 8 1.700 1.700 1.600 36.992
Total 36.992
Total Quantity in cum 36.992
7.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Construction of control room and generator room
For column 8 1.700 1.700 0.100 2.312
footing
floor 1 5.000 4.000 0.150 3.000
floor 1 5.000 4.000 0.080 1.600
Total 6.912
Total Quantity in cum 6.912
7.003 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Construction of control room and generator room
footing 8 1.500 1.500 0.200 3.600
Isolated portion 2.667 1.500 1.500 0.450 2.700
column pedastal 8 0.200 0.400 1.200 0.768
grade slab 1 5.000 4.000 0.150 3.000
plinth beam 6 3.270 0.200 0.450 1.766
plinth beam 2 3.600 0.200 0.450 0.648
plinth beam 1 4.000 0.200 0.450 0.360
ramp 2 3.000 1.500 0.100 0.900
Total 13.742
Total Quantity in cum 13.742
7.004 5.2.2
7.012 50.13.1
9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of
materials, labour charges etc complete
Construction of control room and generator room
ceiling 2 5.000 4.000 40.000
Beam sides 4 4.000 0.330 5.280
slab proj. 1 31.500 0.300 9.450
edge 1 32.400 0.150 4.860
shade bottom 2 11.800 0.750 17.700
&top
shade bottom 2 11.800 0.600 14.160
&top
shade bottom 4 4.400 0.600 10.560
&top
vertical 4 0.600 0.900 2.160
Roof top 1 10.200 4.000 40.800
Total 144.970
Total Quantity in sqm 144.970
7.013 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end by
end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS: 4454
- part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S.
laths with 1.25 mm thick top cover
Construction of control room and generator room
2 3.270 3.000 19.620
Total 19.620
Total Quantity in sqm 19.620
7.014 4.1.3
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand
(zone-III) : 4 graded stone aggregate 20 mm nominal size)
Construction of control room and generator room
Screading
Concrete (Panel 1 4.000 5.000 0.040 0.800
Room)
Total 0.800
Total Quantity in cum 0.800
7.015 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Construction of control room and generator room
Floor Finishing 2 4.000 5.000 40.000
Ramp 2 3.000 1.500 9.000
Total 49.000
Total Quantity in sqm 49.000
7.016 13.43.1
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Construction of control room and generator room
Room inside 2 18.000 4.900 176.400
Column sides 8 0.200 4.900 7.840
Op. sides 2 9.270 0.200 3.708
Op. sides 1 6.300 0.200 1.260
out sides 1 30.000 4.900 147.000
parapet wall 1 31.600 1.000 31.600
window -4 1.500 1.500 -9.000
open -2 1.500 2.400 -7.200
Rs -4 3.270 3.000 -39.240
Ceiling 2 5.000 4.000 40.000
beam sides 4 4.000 0.330 5.280
slab proj. 1 31.500 0.300 9.450
edge 1 32.400 0.150 4.860
shade bottom 2 11.800 0.750 17.700
&top
shade bottom 2 11.800 0.600 14.160
&top
shade bottom 4 4.400 0.600 10.560
&top
vertical 4 0.600 0.900 2.160
Total 416.538
Total Quantity in sqm 416.538
7.017 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
Construction of control room and generator room
room inside 2 18.000 4.900 176.400
column sides 8 0.200 4.900 7.840
7.020 OD46064/2022-2023
Supplying and providing aluminium window with powder coated aluminium sections
for frames and
shutters with 4mm thick glass panels as per drawings and specifications including all
fittings and fixing
charges
Supplying and providing aluminium window
windows 4 1.500 1.500 9.000
Total 9.000
Total Quantity in sqm 9.000
8 Providing cable trenches
8.001 4.1.8
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
Providing cable trenches
1 6.000 1.050 0.100 0.630
Total 0.630
Total Quantity in cum 0.630
8.002 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Providing cable trenches
1 6.000 1.050 0.100 0.630
Total 0.630
Total Quantity in cum 0.630
8.003 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Providing cable trenches
1 6.000 1.050 1.050 6.615
Total 6.615
Total Quantity in sqm 6.615
8.004 OD46053/2022-2023
supplying and providing checkered plate 6mm thick over the cable trench including
painting with a coat of iron primer
Providing cable trenches
1 30.000 0.800 24.000
Total 24.000
Total Quantity in sqm 24.000
9 Bath cum toilet
9.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Bath cum toilet
wall 1 9.920 0.900 0.700 6.250
steps 1 1.000 0.750 0.150 0.113
Total 6.363
Total Quantity in cum 6.363
9.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Bath cum toilet
wall 1 9.920 0.900 0.100 0.893
step 1 1.000 0.750 0.100 0.075
Total 0.968
Total Quantity in cum 0.968
9.003 7.1.1
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Bath cum toilet
Foundation 2 9.920 0.600 0.600 7.142
Basement 2 9.920 0.450 0.450 4.018
Total 11.160
Total Quantity in cum 11.160
9.004 6.4.1
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation
7.5 in superstructure above plinth level up to floor V level in all shapes and sizes
in:Cement mortar 1:4 ( 1 cement : 4 coarse sand)
Bath cum toilet
wall 2 9.920 0.230 2.700 12.321
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved
make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick
cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with white
cement and matching pigment etc., complete.
Bath cum toilet
2 3.000 1.500 9.000
Total 9.000
Total Quantity in sqm 9.000
9.014 13.37.1
White washing with lime to give an even shade:New work (three or more coats)
Bath cum toilet
side wall 2 3.000 1.800 10.800
top 2 3.000 1.500 9.000
Total 19.800
Total Quantity in sqm 19.800
9.015 13.40
Distempering with dry distemper of approved brand and manufacture (two or more
coats) of required shade on new work, over and including water thinnable priming coat
to give an even shade:
Bath cum toilet
side wall 2 3.000 1.800 10.800
side wall 2 3.000 1.500 9.000
Total 19.800
Total Quantity in sqm 19.800
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
10 &allied works complete
10.00 OD46070/2022-2023
Supply, delivery and erection of non-clog sewage submersible pump sets with
stainless steel impeller to pass soft solids upto 50mm size per separate special
specification. including cost of required submersible cable to suit the site condition
,starter with control board, Submersible cables required as per site conditions should
be supplied with two capacitance type level guards for operating automatically
autocoupler SS chain ,guide rail etc for the following duty condition. MSB(Separate
pannels for H&C PS 1,Asramom and H&C PS 2 pump
houses)<br>Fabrication supply,conveyance,installation testing and
commissioning of floor/wall mounting dust and vermin proof cubicle type MV panel
board confirming of the fallowing components/devicess and complying to IS
8623<br>Fabrication of fully partitioned ,dust and vermin proof enclosure for
panel assemby as per form 4 of IS 8623 using 2mm CRCA sheet as per approved
design and requirement, with front and rear accessembly ,bus bar chembers,hinged
doors for all switch gear components ,earthing the door using 4sq.mm braided copper
conductor, providing necessary cut-outs for mounting meters,relays,indication
lamps,bus bar inter connections etc,detachable covers for busbar chember and cable
alley,power coating the assembly after subjecting to 7 tank process etc as required.
CRCA sheet alone be used for the fabrication.Angles/flats/slotted angles etc shall not
be used forthe fabrication of panel assembly. The panel shaii be provided with base
frame from ISMS 75.Necessary barriers and shrouding with 2mm/3mm SMC Sheets
shall be provided.Heavy duty neoprene beeding of apropriate sizes shall be used to
make the panel dust and vermin proof. The control board should have necessary
tripping devices and indicating devices for safety of motor and pumpsets with
necessary isolator near the wet well site - lpd and head in m as follow as per actual site
condition.>Outgoing<br>(i)H&C PS2: 150A TP MCCB to control the
submersible pump set-5Nos, <br>(b). 150 A TP MCCB to control the capacitor
bank - 1 no(c)Providing suitable rating capacitor bank with APFC Panel-1No.(d)150A
25Ka TP MCCB spare -1No.<br> (ii)ASRAMOM: a,150A 16KA TP MCCB to
control submersible pump sets at Asramom-5Nos,b,150A 16 KA TPMCCB to control
the capacitor bank-1No c, Providing suitable rating capacitor bank with APFC Panel
(d) (iii)IH&C PS1(a)150A 25 KA TPMCCB -2 Nos,(b) 150A 25KA TPMCCB-
2Nos,(c)150A 25 KA TPMCCB-2Nos (d) Providing suitable ratings(3Nos 40Kvar)
capacitor bank with APFC Panel-1No.<br>N.B (a) Necessary CTs should be
provided for safe guarding the instruments wherever necessary .Interlocking should be
provided for standby pump sets.<br>(b) <br>Cabling <br> Supply
,delivery and laying of following size L.T cable (1.1KV Grade)including jointing
material,cable carrier system like trenches,cable trays pipe sleeves etc as per IE rules
including cost of flat submersible cable connecting main panel board and submersible
pump sets thro starter control board and isolator 3 ½ core 95 sq mm armourd
aluminum conductor cable length as per site condition.connection from suction up to
header line.(three year additional replacement warranty additional to 2 years = total 5
year -Including replacement of parts or pump,motors,panel board fully.)
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
PH1 2 12.000 24.000
Total 24.000
Total Quantity in HP (Horse power) 24.000
10.00 OD46071/2022-2023
Supply, delivery and erection of Multistage force Pump 600LPM X 30M head suitable
for cleaning the screen chamber,Pumpset during servicing with 16 m of 20 mm dia
hose required for operating the pump .
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in set 1.000
10.00 OD46072/2022-2023
3 Supply and delivery of 200 mm CI Sluice Valves suitable for the sewage pump sets
one no. for each pump sets
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.00 OD46073/2022-2023
4 Supply and delivery of 250 mm suitable flexible joint coupling for easy dismantling of
delivery pipes and valves with Tie bolts with angular deflection 5 Degree
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
3 3.000
Total 3.000
Total Quantity in no 3.000
10.00 OD46074/2022-2023
5 Supply and delivery of breathing apparatus with Oxygen cylinder mask etc. complete .
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in set 1.000
10.00 OD46075/2022-2023
6 Supply and delivery of Diaphragm type pressure gauge with necessary S.S tubes and
isolating valves
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
&allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.00 OD46076/2022-2023
Supply and fixing of Electro magnetic flow meter suitable for remote sensing
operation with required pipes,specials and accessories at laminar flow region (full
flow)including cost of pit cover slab etc
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.00 OD46077/2022-2023
8 Supply, delivery and erecting of following safety items ,including cost of
same.<br>I. Fire extinguisher of 5 Kg capacity (powder type 2
no’s)<br> II. Fire buckets with stand 5no’s<br> III.
Electric quality Rubber mat to be laid in front of all the panel boards including starter
panels<br>
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.00 100.98.460
9 Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice
Valve with Cap PN 1.6, Size 150mm.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
&allied works complete
2 2.000
Total 2.000
Total Quantity in no 2.000
10.01 100.31.1.5
0 Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber
insertions etc., complete, but excluding the cost of the valve (tail pieces, if required,
will be paid separately): 200mm diameter, Class I.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
&allied works complete
2 2.000
Total 2.000
Total Quantity in no 2.000
10.01 100.98.461
1 Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice
Valve with Cap PN 1.6, Size 200mm.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
2 2.000
Total 2.000
Total Quantity in no 2.000
10.01 OD46078/2022-2023
2 Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.01 OD46079/2022-2023
3 Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in kg 1.000
10.01 OD46080/2022-2023
4 Supply and delivery of 200 mm Non-Return Ball valve made up of DI and ball of
Aluminum with MVR coated for the common header.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
&allied works complete
2 2.000
Total 2.000
Total Quantity in no 2.000
10.01 OD46081/2022-2023
5 Supply and fixing of stainless steel screen made of bars of size 50 mm x 10 mm for
fixing across the screen chamber channel (fixed type ) at 45 degree inclination for a
clear passage of 40 mm solids and suitable for manual cleaning including cost of of
screen ,Grab bucket and lifting arrangement material and fixing charges for 1.00m x
1.30m size.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.01 OD46082/2022-2023
6 Supply , delivery , erecting and maintenance of 2 ton or suitable capacity hand
operated pulley block hoist with mono rail traveling on single girder with over head
traveling trolley for a clear lift according to site condition for a travel of 9 (well
dia+3m) meters or suitable design for erection and easy loading and unloading of
Pumps and specials from trucks.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
One for each 1 1.000
pump house
Total 1.000
Total Quantity in no 1.000
10.01 OD46083/2022-2023
Estimate for Mechanical and Allied Electrical works - ELECTRICAL PANELS AND
CABLES Supply, Delivery of M.V control panel of wall mounting type made up of 14
SWG M.S Sheet of size to suit the L.T metering arrangements by KSEB. The board is
to be supplied with 3 Nos of fuse carriers, MCCB with neutral and earthing
arrangements as per I.E rules. Supply and delivery of floor mounting type MV control
panel of vermin proof, dust proof, modular type consisting of the following
accessories and controls. The control panel shall be of enclosed type and built with
compartmentalized modular type cubical. All cubical shall be constructed from 14
SWG, M.S sheet at the bottom and rear and 12 SWG M.S Sheet at front. . The interior
and exterior of the panels and compartment shall be treated with one coat of primer
and two coats of stove enameled light gray shade suitable for electric applications. The
panel should be supplied with 4 nos of copper bus bars of ample carrying capacity
properly sleeved with respective colour codes. Set 1 Incoming 1. 150 A MCCB /
35KA with over load, short circuit protection 2. (0-500 v) Voltmeter (w) selector
switch -1set3. Ammeter 0-300A with phase selector switch – 1 set 4. 3 phase /
4 wire KWH meter – 1 no5. Earth fault relay – 1 set 6. Slide locking
type fuses – 1set Supply and installation of suitable starters in the above pump
houseses(7). 63 A TPN MCCB for lighting control and spare – 2noN.B (a)
Necessary CTs should be provided for safe guarding the instruments wherever
necessary(b) The supply should be terminated through A.M.F panel of Genset offered
for Auto start operation during EB power failure with in 15 secs Twin earthing the
plant and equipment as per IE roles including cost of GI flats (continuous earthing) etc
complete. set 1Cabling Supply ,delivery and laying of following size L.T cable
(1.1KV Grade)including jointing material,cable carrier system like trenches,cable trays
pipe sleeves etc as per IE rules excluding cost of flat submersible cable connecting
main panel board and submersible pump sets thro starter control board and isolator 3
½ core 35 sq mm armourd aluminum conductor cable of suitable length as per
site condition connecting EB pole and EB meter and control panel board m 30
SupplyLighting LoadSupply and completion of required house wiring for
accommodating the following including DB panels, cost of wire, cost of PVC
conduits, earthing etc. 1. SV lamp to be fixed on the top of control room -1no
(250w)2. Industrial type tube lights inside the control room.-8 nos (40w)3. 4 Nos CFL
(not exceeding 25 W) at suitable locations with fittings.4. 15 A plug and socket with
control switch – 2 nos5. 5 A plug and socket with control switch – 2
nos6. Portable lamp with 25W CFL bulb and 15 M cable-1 no7. Pedestal fan -1 no
<br>The above electrical items as per IE rules includes cost of materials such as
bulbs and fittings etc. <br>Supply and delivery of silent diesel generator set of
82.5 Kva with AMF panel with suitable engine capacity conforming to relevent IS
specifications, water cooled, six cylinders comprising of suitable altemator 3 phase,
0.8PF, 4 pole with panel board, digital type voltmeter, anneter, Hertz meter, kwh
meter, MCCB with acoustic enclosure as per CPCP norms including cost of battery
charger, cost of battery etc. complete, including cost of cabling, earthing, etc. suitable
for outdoor application as per IE rules including cost of platform etc. complete. set
1<br>Air valves<br>Supply and delivery of following safety items
,including cost of same. L SI. Fire extinguisher of required capacity (powder type 2
no’s) II. Fire buckets with stand 5no’s III. Rubber mat to be laid in front
of all the panel boards including starter panelsSupply and delivery of tools required for
maintenance works including double end spanners, ring spanners, screw drivers,etc
including suppley and erection of Diesel Generator
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
10.01 OD46084/2022-2023
8 Supply and delivery of suitable flexible joint coupling upto 200mm for easy
dismantling of delivery pipes and valves with tie bolts with angular deflection 5 degree
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
&allied works complete
3 3.000
Total 3.000
Total Quantity in no 3.000
11 Pumping mains
11.00 100.1.1
1 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Excavating trenches(upto 1.5 m)
PH1 to manhole 1 820.000 0.800 1.200 0.8000 629.760
(N2974) 00
Total 629.760
Total Quantity in cum 629.760
11.00 100.1.5
2 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Pumping mains
PH1 to manhole 1 820.000 0.800 1.200 0.1800 141.696
(N2974) 00
Total 141.696
Total Quantity in cum 141.696
11.00 100.1.9
3 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in Hard Rock Requiring Blasting.
Pumping mains
PH1 to manhole 0.0200
1 820.000 0.800 1.500 19.680
(N2974) 00
Total 19.680
Total Quantity in cum 19.680
11.00 15.2.1
4 Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Pumping mains
concrete road 1 820.000 1.000 0.150 123.000
Total 123.000
Total Quantity in cum 123.000
11.00 100.98.118
5 Supply of DI K9 Pipe Conforming to IS 8329/2000, 250mm Dia.
supply of pipe
PH3 1 820.000 820.000
Total 820.000
Total Quantity in metre 820.000
11.00 100.14.4
6 Conveying and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming
to IS: 8329 excluding cost of pipes and specials: 250mm diameter Ductile Iron Class
K-9 Pipes.
Conveying and laying S&S ductile iron pipe -250mm
PH1 1 820.000 820.000
Total 820.000
Total Quantity in metre 820.000
11.00 100.8.1
7 Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape
in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Pumping mains
1 820.000 820.000
Total 820.000
Total Quantity in metre 820.000
11.00 18.70.4
8 Providing push - on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron
Pipes including testing of joints and including the cost of rubber gasket:250 mm dia
pipes
Pumping mains
1 164.000 164.000
Total 164.000
Total Quantity in joint 164.000
11.00 18.68.1
9 Providing and laying D.I specials of class K - 12 suitable for push - on jointing as per
IS : 9523 :Upt 600 mm dia
Pumping mains
1 10.000 10.000
Total 10.000
Total Quantity in quintal 10.000
11.01 18.83.6
0 Labour for cutting C.I. pipe with steel saw.250 mm diameter C.I. pipe
Labour for cutting C l pipe-250mm diameter
8 8.000
Total 8.000
Total Quantity in Each Cut 8.000
11.01 100.35.4
1 Testing 250mm DI/CI pipeline with potable water to the required test pressure .
250 mm dia
Observed Data derived from item no.1022 of PHED DATA
Testing 250 mm DI/Cl pipeline -250mm diameter
1 820.000 820.000
Total 820.000
Total Quantity in metre 820.000
11.01 5.1.3
2 Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Pumping mains
pipe supports/ 10 1.000 1.000 1.000 10.000
anchor blocks
Total 10.000
Total Quantity in cum 10.000
11.01 5.9.1
3 Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Pumping mains
10 4.000 40.000
Total 40.000
Total Quantity in sqm 40.000
11.01 5.22.6
4 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Pumping mains
1 10.000 80.000 800.000
Total 800.000
Total Quantity in kilogram 800.000
12 Laying PE pipes via HDD Method above 3m depth
12.00 OD46066/2022-2023
1 Installation of PE -250mm-315mm mm dia PE pipe by horizontal directional drilling
method<br>in all types of soil above /below water table for pumping /gravity
/distribution main including preparing and setting up<br>the plat and equipment,
installing new pipe work, testing and commissioning including cost of pipe (6 m line
pipe with<br>butt joint all related civil /mechanical works like entry /exits pit as
necessary. De watering ,drilling stringing, reaming,<br>pulling back the new
pipe on the designed alignment and monitoring by approved guidance system. wastage
of<br>pipes, proper disposal of drilling fluid /bentonite slurry. Proper back
filling og pit and holes by approved borrow<br>material as per specification
approved method statement or as directed by engineer in
charge.<br><br>also using<br>Ground penetrating radar survey in
corridor<br>with to detect buried utilities on the map of<br>corridor
with<br>information of locations and<br>depths to the top of various
utilities detected<br>.work to be conducted using<br>500MHZ
and<br>300MHZ antenna or latest for the best possible<br>resolution and
penetration including hydrolic<br>testing
Laying PE pipes via HDD Method above 3m depth
250MM HDPE 1 46.000 46.000
315MM HDPE 1 378.500 378.500
Total 424.500
Total Quantity in metre 424.500
12.00 OD46067/2022-2023
Installation of PE pipe between 110mm & 225mm outer dia by HDD method for
on grade<br>gravity sewer including preparing and setting up the plant and
equipment,preparing new pipe work material making of<br>entry pit and exit pit
up to required depth installing new pipe work and commissioning system or making
the system<br>or making the system ready for commissioning by HDD
operating including all related civil and mechanical works like<br>excavation
shoring/strutting etc drilling stringing reaming and pulling back the new pipe work on
the designed borne<br>path alignment proper disposal of drilling fluid and back
fill of site after completion all inclusive as per Conditions<br>HDPE pipes also
using Ground penetrating radar survey in corridor<br>with to detect buried
utilities on the map<br>of<br>corridor with information of locations
and<br>depths to the top of various utilities detected<br>.work to
be<br>conducted using 500MHZ and<br>300MHZ antenna or latest forthe
best possible<br>resolution and penetration
Laying PE pipes via HDD Method above 3m depth
160 pvc 1 203.000 203.000
Total 203.000
Total Quantity in metre 203.000
12.00 OD46068/2022-2023
3 Installation of PE -355mm-500mm mm dia PE pipe by horizontal directional drilling
method in all<br>types of soil above /below water table for pumping /gravity
/distribution main including preparing and<br>setting up the plant and
equipment, installing new pipe work, testing and commissioning excluding cost
of<br>pipe (6 m line pipe with butt joint all related civil /mechanical works like
entry /exits pit as necessary.<br>Dewatering, drilling stringing, reaming, pulling
back the new pipe on the designed alignment and<br>monitoring by approved
guidance system. wastage of pipes, proper disposal of drilling fluid
/bentonite<br>slurry. Proper back filling pit and holes by approved borrow
material as per specification approved<br>method statement or as directed by
engineer in charge. Also using Ground penetrating radar survey in<br>corridor
with to detect buried utilities on the map of corridor with information of locations and
depths to the<br>top of various utilities detected. Work to be conducted using
500MHZ and 300MHZ antenna or latest for<br>the best possible resolution and
penetration including hydraulic testing
Laying PE pipes via HDD Method above 3m depth
400MM HDPE 1 115.500 115.500
450MM HDPE 1 597.000 597.000
500MM HDPE 1 17.500 17.500
Total 730.000
Total Quantity in metre 730.000
13 Construction of manholes
13.00 OD46037/2022-2023
15.00 5.6.2.a
6 Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified grading,
premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level, and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects For Grading - II (13.2
mm Nominal Size)
bc
open 1 1516.100 3.000 0.030 136.449
pumping 1 820.000 2.000 0.030 49.200
ic to mh 1 1144.000 1.500 0.030 51.480
Total 237.129
Total Quantity in cum 237.129
15.00 5.1.a
7 Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface
of granular Base including clearing of road surface and spraying primer at the rate of
0.70 - 1.0 kg/sqm using mechanical means.
primer coat
open 1 1516.100 3.000 4548.300
pumping 1 820.000 2.500 2050.000
ic to mh 1 1144.000 1.500 1716.000
Total 8314.300
Total Quantity in sqm 8314.300
16 Kwa connection charge RS 16107/connections
16.00 OD63801/2022-2023
1 sewer connection charge @10000/connections
sewer connection charge
1 1000 1000.000
Total 1000.000
Total Quantity in no 1000.000
ABSTRACT ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 456
1.002 15.43.2
Dismantling manually / by mechanical means including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead as per direction
of Engineer -in-Charge:Bituminous road
Net Total 8176.000sqm @339.50/sqm 2775752.00
1.003 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Net Total 46.960cum @1923.75/cum 90339.30
1.004 4.1.2
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2
coarse sand : 3 graded stone aggregate 20 mm nominal size)
Net Total 46.960cum @7983.68/cum 374913.61
1.005 100.8.2
Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with
coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
Net Total 2850.000metre @90.44/metre 257754.00
1.006 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution
tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Net Total 610.000metre @26.31/metre 16049.10
1.007 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Net Total 6365.208cum @522.57/cum 3326266.74
1.008 100.1.2
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in all kinds of soil.
Net Total 1269.702cum @622.63/cum 790554.56
1.009 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Net Total 1591.302cum @758.84/cum 1207543.61
1.010 100.1.6
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in Ordinary Rock.
Net Total 317.426cum @938.31/cum 297843.99
1.011 2.17.2
Close timbering in case of shafts, wells, cesspits, manholes and the like including
strutting, shoring and packing cavities (wherever required) etc. complete
(Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not
exceeding 3 m
Net Total 9504.000sqm @179.95/sqm 1710244.80
1.012 2.23
Extra for planking and strutting in open timbering if required to be left permanently in
position (Face area of the timber permanently left to be measured).
Net Total 4200.000sqm @908.53/sqm 3815826.00
1.013 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
1.015 100.10.9
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 250mm Nominal
Outside Diameter Pipes.
Net Total 651.000metre @415.58/metre 270542.58
1.016 100.10.13
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 400mm Nominal
Outside Diameter Pipes.
Net Total 204.500metre @686.93/metre 140477.19
1.017 7.6.1
Coursed rubble masonry (first sort) with hard stone in foundation and plinth
with:Cement mortar 1:6 (1 cement : 6 coarse sand)
Net Total 11.160cum @8096.19/cum 90353.48
1.018 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Net Total 15.925cum @8545.86/cum 136092.82
1.019 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 1260.000kilo
gram @92.47/kilogram 116512.20
1.020 OD46017/2022-2023
Supplying, Providing bedding with m sand for sewer lines as per specifications to be
laid wherever
1.028 OD46026/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.45m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, , plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 150.000no @3434.07/no 515110.50
1.029 OD46027/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.90m deep with
RCC M20 using
20mm broken stone for floor slab ,RCC M20 slab using 20mm broken stone for
removable cover slab,
Brick work in CM 1:6 for walls, PCC 1:4:8 using 20mm broken stone for leveling
course below foundation
including earth work excavation in all classes of soil, plastering the inside with CM
1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing
provision for connecting main sewer and service connections, conveying, lifting,
placing the cover slab in
position by suitable means, conveying and disposing the surplus earth with all lead
and lift as per
drawings and specifications , including the cost of reinforcement , testing the chamber
and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 50.000no @7399.73/no 369986.50
1.030 OD46028/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.60m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 90.000no @6972.85/no 627556.50
1.031 OD46029/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.75m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 100.000no @7181.38/no 718138.00
1.032 OD46030/2022-2023
Providing and drilling with Horizontal drilling machine and air compressor for
inserting 800 mm MS casing pipe through the hole formed including cost of pipes,
cost of mobilization installation and all labour charges etc.
Net Total 10.000metre @37391.30/metr 373913.00
e
1.033 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 21447.500Kwh @34.75/Kwh 745300.63
1.034 100.10.11
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 315mm Nominal
Outside Diameter Pipes.
Net Total 123.000metre @546.51/metre 67220.73
2.007 OD67667/2022-2023
MoRD Spec.No-5.12.A.3.2a. Seal Coat - Manual Means - Type C - Bitumen S-65
Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A, Type B and Type C as per
Technical Specification Clause 510
A. By Manual Means :- Case - III : Type C
(II) Bitumen (S-65)
Net Total 6298.200sqm @95.65/sqm 602422.83
Heading Total(Rs) 8050135.77
3 Construction of Pumping stations
3.001 2.31
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
Net Total 143.750sqm @13.88/sqm 1995.25
3.002 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 5000.000Kwh @34.75/Kwh 173750.00
3.003 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 20.724sqm @315.41/sqm 6536.56
3.004 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 23.746sqm @767.34/sqm 18221.26
3.005 5.9.12
Centering and shuttering including strutting, etc. and removal of form for:Well
steining
Net Total 270.794sqm @272.80/sqm 73872.60
3.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 15953.200kil
ogram @92.47/kilogram 1475192.40
3.007 OD46047/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.Initial depth upto
1.5m
Net Total 1.500metre @39933.94/metr 59900.91
e
3.008 OD46048/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 1.5m
to 3.0m
Net Total 1.500metre @43333.03/metr 64999.55
e
3.009 OD46049/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 3.0m
to 4.5m
Net Total 1.500metre @46732.14/metr 70098.21
e
3.010 OD46050/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m
to 6.0m
Net Total 1.500metre @50131.25/metr 75196.88
e
3.011 OD46051/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Net Total 89.164cum @8931.99/cum 796411.96
3.012 OD46052/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the
engineer in-charge.
Net Total 52.000no @397.18/no 20653.36
3.013 OD48974/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 7.5 m
to 9.0m
Net Total 0.300metre @56929.44/metr 17078.83
e
3.014 OD48975/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 6.0m
to 7.5m
Net Total 1.500metre @53530.33/metr 80295.50
e
Heading Total(Rs) 2934203.27
4 Compound wall with gate for Pumping stations
4.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Net Total 14.400cum @826.87/cum 11906.93
4.002 7.1.1
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Net Total 6.075cum @6777.10/cum 41170.88
4.003 6.1.2
Brick work with common burnt clay F.P.S (non modular) bricks of class designation
7.5 in foundation and plinth in:Cement mortar 1:6 (1 cement : 6 coarse sand)
Net Total 11.880cum @6817.66/cum 80993.80
4.004 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 120.000sqm @295.46/sqm 35455.20
4.005 13.43.1
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Net Total 120.000sqm @66.46/sqm 7975.20
4.006 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
Net Total 120.000sqm @100.99/sqm 12118.80
4.007 10.25.2
Item Shifted to Sub head 14 as item 14.73
Item Shifted to head 14 as item 14.74
Steel work welded in built up sections/framed work, including cutting, hoisting,
fixing in position and applying a priming coat of approved steel primer using
structural steel etc. as required.In gratings, frames, guard bar, ladder, railings,
brackets, gates and similar works
Net Total 800.000kg @145.04/kg 116032.00
Heading Total(Rs) 305652.81
5 Construction of screen chamber and Valve chamber
5.001 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 120.375sqm @315.41/sqm 37967.48
5.002 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 3196.900kilogram @92.47/kilogram 295617.34
5.003 OD46031/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Net Total 31.969cum @8931.99/cum 285546.79
5.004 OD46032/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking
of useful materials and disposal of the surplus earth/unsuitable material as directed by
the engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead
and lift etc as per the direction of Engineer for upto 6.00m beyond initial 4.50m
depth.
Net Total 1.500metre @22620.92/metr 33931.38
e
5.005 OD46033/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking
of useful materials and disposal of the surplus earth/unsuitable material as directed by
the engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead
and lift etc as per the direction of Engineer for upto 4.50m beyond initial 3.00m
depth.
Net Total 1.500metre @14722.11/metr 22083.17
e
5.006 OD46034/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking
of useful materials and disposal of the surplus earth/unsuitable material as directed by
the engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead
and lift etc as per the direction of Engineer for upto 3.00m below ground level
Net Total 3.000metre @13867.78/metr 41603.34
e
5.007 OD46035/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the
engineer in-charge.
Net Total 40.000no @397.18/no 15887.20
5.008 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
7.011 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 312.368sqm @295.46/sqm 92292.25
7.012 50.13.1
9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of
materials, labour charges etc complete
Net Total 144.970sqm @274.01/sqm 39723.23
7.013 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end
by end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS:
4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25
mm M.S. laths with 1.25 mm thick top cover
Net Total 19.620sqm @3259.80/sqm 63957.28
7.014 4.1.3
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse
sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Net Total 0.800cum @7516.53/cum 6013.22
7.015 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Net Total 49.000sqm @387.67/sqm 18995.83
7.016 13.43.1
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Net Total 416.538sqm @66.46/sqm 27683.12
7.017 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
Net Total 416.688sqm @100.99/sqm 42081.32
7.018 10.25.2
Item Shifted to Sub head 14 as item 14.73
Item Shifted to head 14 as item 14.74
Steel work welded in built up sections/framed work, including cutting, hoisting,
fixing in position and applying a priming coat of approved steel primer using
structural steel etc. as required.In gratings, frames, guard bar, ladder, railings,
brackets, gates and similar works
Net Total 144.000kg @145.04/kg 20885.76
7.019 13.61.1
Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:Two or more coats on new work
Net Total 58.050sqm @134.56/sqm 7811.21
7.020 OD46064/2022-2023
Supplying and providing aluminium window with powder coated aluminium sections
for frames and
shutters with 4mm thick glass panels as per drawings and specifications including all
fittings and fixing
charges
Net Total 9.000sqm @3601.23/sqm 32411.07
Heading Total(Rs) 1801757.06
8 Providing cable trenches
8.001 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Reinforced cement concrete work in beams, suspended floors, roofs, having slope up
to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window
sills, staircases and spiral stair cases up to floor five level excluding the cost of
centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse
sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
Net Total 3.516cum @10810.73/cum 38010.53
9.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 280.000kilogr am @92.47/kilogram 25891.60
9.007 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Net Total 1.000cum @6410.36/cum 6410.36
9.008 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 104.616sqm @295.46/sqm 30909.84
9.009 13.33.1
Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand):Flush/ Ruled
pointing
Net Total 20.832sqm @316.02/sqm 6583.33
9.010 50.13.1
9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of
materials, labour charges etc complete
Net Total 40.342sqm @274.01/sqm 11054.11
9.011 5.18.1
Providing precast cement concrete jali 1:2:4 ( 1 cement : 2 coarse sand : 4 graded
stone aggregate 6 mm nominal size) reinforced with 1.6 mm dia mild steel wire
including centering and shuttering, roughening cleaning, fixing and finishing in
cement mortar 1:3 (1 cement : 3 fine sand ) etc. complete excluding plastering of the
jambs, sills and soffits.50 mm thick
Net Total 3.000sqm @1632.14/sqm 4896.42
9.012 OD46065/2022-2023
Supplying and fixing PVC door of size 0.8x2.10m as per the standard specification
including all fittings and labour charges ,etc. .complete
Net Total 2.000no @4502.26/no 9004.52
9.013 11.37
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved
make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick
cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with
white cement and matching pigment etc., complete.
Net Total 9.000sqm @1026.29/sqm 9236.61
9.014 13.37.1
White washing with lime to give an even shade:New work (three or more coats)
Net Total 19.800sqm @31.60/sqm 625.68
9.015 13.40
Distempering with dry distemper of approved brand and manufacture (two or more
coats) of required shade on new work, over and including water thinnable priming
coat to give an even shade:
Net Total 19.800sqm @130.35/sqm 2580.93
Heading Total(Rs) 334339.27
dia+3m) meters or suitable design for erection and easy loading and unloading of
Pumps and specials from trucks.
Net Total 1.000no @380012.50/no 380012.50
10.017 OD46083/2022-2023
Estimate for Mechanical and Allied Electrical works - ELECTRICAL PANELS AND
CABLES Supply, Delivery of M.V control panel of wall mounting type made up of
14 SWG M.S Sheet of size to suit the L.T metering arrangements by KSEB. The
board is to be supplied with 3 Nos of fuse carriers, MCCB with neutral and earthing
arrangements as per I.E rules. Supply and delivery of floor mounting type MV control
panel of vermin proof, dust proof, modular type consisting of the following
accessories and controls. The control panel shall be of enclosed type and built with
compartmentalized modular type cubical. All cubical shall be constructed from 14
SWG, M.S sheet at the bottom and rear and 12 SWG M.S Sheet at front. . The interior
and exterior of the panels and compartment shall be treated with one coat of primer
and two coats of stove enameled light gray shade suitable for electric applications.
The panel should be supplied with 4 nos of copper bus bars of ample carrying
capacity properly sleeved with respective colour codes. Set 1 Incoming 1. 150 A
MCCB / 35KA with over load, short circuit protection 2. (0-500 v) Voltmeter (w)
selector switch -1set3. Ammeter 0-300A with phase selector switch – 1 set 4. 3
phase / 4 wire KWH meter – 1 no5. Earth fault relay – 1 set 6. Slide
locking type fuses – 1set Supply and installation of suitable starters in the
above pump houseses(7). 63 A TPN MCCB for lighting control and spare –
2noN.B (a) Necessary CTs should be provided for safe guarding the instruments
wherever necessary(b) The supply should be terminated through A.M.F panel of
Genset offered for Auto start operation during EB power failure with in 15 secs Twin
earthing the plant and equipment as per IE roles including cost of GI flats (continuous
earthing) etc complete. set 1Cabling Supply ,delivery and laying of following size L.T
cable (1.1KV Grade)including jointing material,cable carrier system like
trenches,cable trays pipe sleeves etc as per IE rules excluding cost of flat submersible
cable connecting main panel board and submersible pump sets thro starter control
board and isolator 3 ½ core 35 sq mm armourd aluminum conductor cable of
suitable length as per site condition connecting EB pole and EB meter and control
panel board m 30 SupplyLighting LoadSupply and completion of required house
wiring for accommodating the following including DB panels, cost of wire, cost of
PVC conduits, earthing etc. 1. SV lamp to be fixed on the top of control room -1no
(250w)2. Industrial type tube lights inside the control room.-8 nos (40w)3. 4 Nos CFL
(not exceeding 25 W) at suitable locations with fittings.4. 15 A plug and socket with
control switch – 2 nos5. 5 A plug and socket with control switch – 2
nos6. Portable lamp with 25W CFL bulb and 15 M cable-1 no7. Pedestal fan -1 no
<br>The above electrical items as per IE rules includes cost of materials such as
bulbs and fittings etc. <br>Supply and delivery of silent diesel generator set of
82.5 Kva with AMF panel with suitable engine capacity conforming to relevent IS
specifications, water cooled, six cylinders comprising of suitable altemator 3 phase,
0.8PF, 4 pole with panel board, digital type voltmeter, anneter, Hertz meter, kwh
meter, MCCB with acoustic enclosure as per CPCP norms including cost of battery
charger, cost of battery etc. complete, including cost of cabling, earthing, etc. suitable
for outdoor application as per IE rules including cost of platform etc. complete. set
1<br>Air valves<br>Supply and delivery of following safety items
,including cost of same. L SI. Fire extinguisher of required capacity (powder type 2
no’s) II. Fire buckets with stand 5no’s III. Rubber mat to be laid in
front of all the panel boards including starter panelsSupply and delivery of tools
required for maintenance works including double end spanners, ring spanners, screw
drivers,etc including suppley and erection of Diesel Generator
Net Total 1.000no @868600.00/no 868600.00
10.018 OD46084/2022-2023
Supply and delivery of suitable flexible joint coupling upto 200mm for easy
dismantling of delivery pipes and valves with tie bolts with angular deflection 5
degree
Net Total 3.000no @9771.75/no 29315.25
Heading Total(Rs) 2706777.94
11 Pumping mains
11.001 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Net Total 629.760cum @522.57/cum 329093.68
11.002 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Net Total 141.696cum @758.84/cum 107524.59
11.003 100.1.9
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in Hard Rock Requiring Blasting.
Net Total 19.680cum @1074.70/cum 21150.10
11.004 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Net Total 123.000cum @1923.75/cum 236621.25
11.005 100.98.118
Supply of DI K9 Pipe Conforming to IS 8329/2000, 250mm Dia.
Net Total 820.000metre @3259.07/metre 2672437.40
11.006 100.14.4
Conveying and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes conforming
to IS: 8329 excluding cost of pipes and specials: 250mm diameter Ductile Iron Class
K-9 Pipes.
Net Total 820.000metre @153.40/metre 125788.00
11.007 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution
tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Net Total 820.000metre @26.31/metre 21574.20
11.008 18.70.4
Providing push - on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron
Pipes including testing of joints and including the cost of rubber gasket:250 mm dia
pipes
Net Total 164.000joint @297.25/joint 48749.00
11.009 18.68.1
Providing and laying D.I specials of class K - 12 suitable for push - on jointing as per
IS : 9523 :Upt 600 mm dia
Net Total 10.000quintal @18927.20/quint 189272.00
al
11.010 18.83.6
Labour for cutting C.I. pipe with steel saw.250 mm diameter C.I. pipe
8.000Each @503.85/Each
Net Total 4030.80
Cut Cut
11.011 100.35.4
Testing 250mm DI/CI pipeline with potable water to the required test pressure .
250 mm dia
Observed Data derived from item no.1022 of PHED DATA
Net Total 820.000metre @47.88/metre 39261.60
11.012 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Net Total 10.000cum @8078.71/cum 80787.10
11.013 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 40.000sqm @315.41/sqm 12616.40
11.014 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth 3.5m ( internal diameter - 1500mm )
Net Total 19.000no @143964.72/no 2735329.68
13.004 OD46040/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth upto 4.5m ( internal diameter-1500mm)
Net Total 25.000no @183683.02/no 4592075.50
13.005 OD46041/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth upto 5.50m (internal diameter-1500mm)
Net Total 9.000no @221055.57/no 1989500.13
16299416.6
Heading Total(Rs) 1
16 Kwa connection charge RS 16107/connections
16.001 OD63801/2022-2023
sewer connection charge @10000/connections
16107450.0
Net Total 1000.000no @16107.45/no 0
16107450.0
Heading Total(Rs) 0
GENERAL ABSTRACT
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 485
Rounded Total(Rs)
263007585.8
5
Rupees Twenty Six Crore Thirty Lakh Seven Thousand Five Hundred and Eighty
Five
DETAILED ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 486
1.002 15.43.2
Dismantling manually / by mechanical means including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead as per direction
of Engineer -in-Charge:Bituminous road
Laying of sewer network
Sewer 1 7259.000 1.000 7259.000
Inspection
chamber to 1 3400.000 0.600 2040.000
manhole
Total 9299.000
Total Quantity in sqm 9299.000
1.003 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Laying of sewer network
Demolishin
g o f cement
concrete ( 1 896.000 1.000 0.100 89.600
Municipality
roads)
Inspection
Chamber to 1 71.810 0.600 0.100 4.309
Manhole
Total 93.909
Total Quantity in cum 93.909
1.004 100.8.2
Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with
coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
Laying of sewer network
sewer 1 7259.000 0.600 4355.400
Inspection
Chamber to 1 3400.000 0.600 2040.000
Manhole
Total 6395.400
Total Quantity in metre 6395.400
1.005 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape
in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Laying of sewer network
Sewer 1 7217.400 0.200 1443.480
Inspection
Chamber to 1 3410.000 0.200 682.000
Manhole
Total 2125.480
Total Quantity in metre 2125.480
1.006 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Excavating trenches(upto 1.5 m)
Quantityfro
1 10624.684 0.8000 8499.747
m calculation 00
sheet
Inspection 0.8000
Chamber to 1 3400.000 0.600 1.100 1795.200
00
Manhole
10294.94
Total 7
10294.94
Total Quantity in cum 7
1.007 100.1.2
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in all kinds of soil.
Excavating trenches(above 1.5 m)
Quantity from 0.8000 2638.734
1 3298.418
calculation sheet 00
Total 2638.734
Total Quantity in cum 2638.734
1.008 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Laying of sewer network
Quantity from 1 10624.684 0.2000 2124.937
calculation sheet 00
Inspection
Chamber to 1 3400.000 0.600 1.100 0.2000 448.800
00
Manhole
Total 2573.737
Total Quantity in cum 2573.737
1.009 100.1.6
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in Ordinary Rock.
Laying of sewer network
Quantity from 0.2000
1 3298.418 659.684
calculation sheet 00
Total 659.684
Total Quantity in cum 659.684
1.010 2.17.2
Close timbering in case of shafts, wells, cesspits, manholes and the like including
strutting, shoring and packing cavities (wherever required) etc. complete
(Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not
exceeding 3 m
close timpering
15502.05
2 3444.900 2.250 0
15502.05
Total 0
1.011 2.23
Extra for planking and strutting in open timbering if required to be left permanently in
position (Face area of the timber permanently left to be measured).
Laying of sewer network
1 750.000 2.800 2100.000
Total 2100.000
Total Quantity in sqm 2100.000
1.012 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Laying of sewer network
RCCbeddin
g concrete where 1 2000.000 0.600 0.100 120.000
ever necessary
Total 120.000
Total Quantity in cum 120.000
1.013 100.98.226
Supply of PVC Pipe, 8kg/cm2, 160mm Dia.
Laying of sewer network
MH to IC 1 3400.000 3400.000
Total 3400.000
Total Quantity in metre 3400.000
1.014 100.10.7
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead
and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 200mm Nominal
Outside Diameter Pipes.
Laying ofHDPE 200 mm
Open cut 1 5135.000 5135.000
Total 5135.000
Total Quantity in metre 5135.000
1.015 100.10.9
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead
and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 250mm Nominal
Outside Diameter Pipes.
Laying hdpe 250mm
Open cut 1 410.900 410.900
Total 410.900
Total Quantity in metre 410.900
1.016 100.10.13
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead
and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 400mm Nominal
Outside Diameter Pipes.
Laying of sewer network
1 483.200 483.200
Total 483.200
Total Quantity in metre 483.200
1.017 100.10.14
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial lead
and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 450mm Nominal
Outside Diameter Pipes.
Laying of hdpe 450
1 618.100 618.100
Total 618.100
Total Quantity in metre 618.100
1.018 4.1.2
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2 coarse
sand : 3 graded stone aggregate 20 mm nominal size)
Laying of sewer network
Demolishin
g o f cement
concrete ( 1 896.000 1.000 0.100 89.600
Municipality
roads)
Inspection
Chamber to 1 71.810 0.600 0.100 4.309
Manhole
Total 93.909
Total Quantity in cum 93.909
1.019 7.6.1
Coursed rubble masonry (first sort) with hard stone in foundation and plinth
with:Cement mortar 1:6 (1 cement : 6 coarse sand)
Laying of sewer network
Culvert regions / 1 8.000 0.400 0.450 1.440
RR portions
8 6.000 0.450 0.450 9.720
Total 11.160
Total Quantity in cum 11.160
1.020 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Laying of sewer network
(0.5+0.8)/
Anchor required 50 0.700 0.700 15.925
2
Total 15.925
Total Quantity in cum 15.925
1.021 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Laying of sewer network
60.000
steel 1 15.900 954.000
000
Total 954.000
Total Quantity in kilogram 954.000
1.022 OD43025/2022-2023
Supplying, Providing bedding with m sand for sewer lines as per specifications to be
laid wherever
necessary with all lead and lift.
Supplying, Providing bedding with m sand
Beding for lines 1 2000.000 0.800 0.100 160.000
Total 160.000
Total Quantity in cum 160.000
1.023 OD43026/2022-2023
Supply of PE Pipe PE 100 (IS 14333/ sewerage pipe with latest IS), 8kg, 200mm
Outer Dia.
Laying of sewer network
1 5674.700 5674.700
Total 5674.700
Total Quantity in metre 5674.700
1.024 OD43027/2022-2023
Supply of PE Pipe, PE100, PN8, 400mm dia, conforming to IS 1433 (Sewerage Pipe)
Laying of sewer network
1 794.000 794.000
Total 794.000
Total Quantity in metre 794.000
1.025 OD43028/2022-2023
Supply of PE Pipe PE 100 (IS 14333), 8kg, 250mm Outer Dia
Laying of sewer network
1 635.500 635.500
Total 635.500
Conveying to site, lowering into trenches, laying to correct line and grade using CC
holding clamps, 160mm PVC SN 8 (8 Kg/Cm2) S & S Sewerage pipes
conforming to I.S.15328, including jointing the pipes using rubber rings as per
approved methods with rubber gasket for flexible joints as per specification including
cost of gasket, to correct line , de watering with all rates of recuperation etc, providing
bedding for pipe line trenches with available earth, hydraulic testing the line to the
required test pressure as per IS, CPHEEO specifications, lighting, watching, providing
caution boards etc. wherever required, during laying and jointing the pipes including
hire for all tools etc complete including commissioning for the following diamters
Laying of sewer network
1 3400.000 3400.000
Total 3400.000
Total Quantity in metre 3400.000
1.031 OD43034/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.45m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, , plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 300.000 300.000
Total 300.000
Total Quantity in no 300.000
1.032 OD43035/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.90m deep with
RCC M20 using
20mm broken stone for floor slab ,RCC M20 slab using 20mm broken stone for
removable cover slab,
Brick work in CM 1:6 for walls, PCC 1:4:8 using 20mm broken stone for leveling
course below foundation
including earth work excavation in all classes of soil, plastering the inside with CM
1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing
provision for connecting main sewer and service connections, conveying, lifting,
placing the cover slab in
position by suitable means, conveying and disposing the surplus earth with all lead and
lift as per
drawings and specifications , including the cost of reinforcement , testing the chamber
and sulphate
resistant cement shall be used for the the construction of inspection chamber
Manhole to
inspection 1 920.000 1.000 0.300 276.000
chamber
Total 1770.750
Total Quantity in cum 1770.750
2.002 OD67519/2022-2023
MoRD-Spec.No:4.1.A.1.
Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with smooth wheel roller to achieve the
desired density, complete as per Technical Specification Clause 401.
(i) For Grading I Material
granular sub base
open 1 1993.000 2.500 0.200 996.500
ic to mh 1 920.000 1.000 0.200 184.000
Total 1180.500
Total Quantity in cum 1180.500
2.003 OD67518/2022-2023
MoRD Spec No-4.9.
Wet Mix Macadam
Providing, laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and compacting
with smooth wheel roller of 80 to 100kN weight to achieve the desired density
including lighting, barricading and maintenance of diversion, etc as per Tables 400.11
& 400.12 and Technical Specification Clause 406.
By Mechanical Means with 1 km lead
wet mix
open 1 1993.000 2.500 0.150 747.375
ic to mh 1 920.000 1.000 0.150 138.000
Total 885.375
Total Quantity in cum 885.375
2.004 OD67517/2022-2023
MoRD Spec.No-5.1.1a.
Prime Coat :- Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
prime coat
open 1 1993.000 2.500 4982.500
2.007 OD67514/2022-2023
MoRD Spec.No-5.12.A.3.2a. Seal Coat - Manual Means - Type C - Bitumen S-65
Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A, Type B and Type C as per
Technical Specification Clause 510
A. By Manual Means :- Case - III : Type C
(II) Bitumen (S-65)
seal coat
open 1 1993.000 3.000 5979.000
3.007 OD43059/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Construction pumping station
PH1 1 3.14/4 (7.5*7.5)- 8.890 97.701
(6.5*6.5)
Bottom plug 1 3.14/4 (7.5*7.5) 0.500 22.078
Curb top 1 3.140 (7*0.5) 0.200 2.198
rectangular
Curb triangular 1 3.140/2 (7*0.5) 0.500 2.748
Cover slab 1 3.140/4 (7.5*7.5) 0.200 8.831
Total 133.556
Total Quantity in cum 133.556
3.008 OD43060/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the engineer
in-charge.
Construction pumping station
ph1 1 53.000 53.000
Total 53.000
Total Quantity in no 53.000
3.009 OD47065/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.Initial depth upto 1.5m
Sinking wells above up to 6 m dia. and up to 7.5 m (1.5m)
PH 1 1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.010 OD47073/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 1.5m
to 3.0m
Sinking wells above up to 6 m dia. and up to 7.5 m(1.5-3)
1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.011 OD47085/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 3.0m
to 4.5m
Sinking wells above up to 6 m dia. and up to 7.5 m(3-4.5)
1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.012 OD47086/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m
to 6.0m
Sinking wells above up to 6 m dia. and up to 7.5 m(4.5-6)
1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.013 OD47103/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 6m to
7.5m
Sinking wells above up to 6 m dia. and up to 7.5 m(6-7.5)
1 1.500 1.500
Total 1.500
Total Quantity in metre 1.500
3.014 OD47107/2022-2023
Sinking wells above up to 6 m dia. and up to 7.5 m inside and depth up to 3.00 m
below spring level
in in 50% all kind of soil and 50% ordinary rocksoil (specify type of soil) to lines and
levels and plumb by scooping out earth from inside and below the steining using
necessary appliances including hire and labour for the same including dumping the
spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m to 6.0m
Sinking wells above up to 6 m dia. and up to 7.5 m(7.5-9)
1 0.390 0.390
Total 0.390
Total Quantity in metre 0.390
4 Construction of screen chamber and Valve chamber
4.001 5.9.1
Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Construction of screen chamber and Valve chamber
Well 1 side 2 2*(3+2) 3.070 61.400
Working 3 2.500 0.150 1.125
platform
Total 62.525
Total Quantity in sqm 62.525
4.002 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Construction of screen chamber and Valve chamber
100.00 1788.200
1 17.882 0000
Total 1788.200
Total Quantity in kilogram 1788.200
4.003 OD43039/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Construction of screen chamber and Valve chamber
Well 1 side wall 1 0.500 2*(3+2) 3.070 15.350
Working 3 0.750 2.500 0.150 0.844
platform
Bottom plug 1 1.500 2.500 0.450 1.688
Total 17.882
Total Quantity in cum 17.882
4.004 OD43041/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking of
useful materials and disposal of the surplus earth/unsuitable material as directed by the
engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead and
lift etc as per the direction of Engineer for upto 4.50m beyond initial 3.00m depth.
Construction of screen chamber and Valve chamber
PH1 1 0.070 0.070
Total 0.070
Total Quantity in metre 0.070
4.005 OD43042/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking of
useful materials and disposal of the surplus earth/unsuitable material as directed by the
engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead and
lift etc as per the direction of Engineer for upto 3.00m below ground level
4.010 13.65.1
Painting with black anti- corrosive bitumastic paint of approved brand and
manufacture to give an even shade:Two or more coats on new work
CONSTRUCTION OF SCREEN CHAMBER AND VALVE CHAMBER
WELL 1 SIDE 2 2*(3+2) 3.070 61.400
WALL
WORKING 1 2.500 0.150 0.375
PLATFORM
Total 61.775
Total Quantity in sqm 61.775
5 Construction of valve chamber
5.001 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Construction of valve chamber
Well 1 - Qty- 1 6.500 2.000 1.800 23.400
valve chamber 1
qty - valve 1 2.000 1.600 1.800 5.760
chamber 2
Total 29.160
Total Quantity in cum 29.160
5.002 100.1.2
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in all kinds of soil.
Construction of valve chamber
Well 1 - Qty- 1 6.500 2.000 0.300 3.900
valve chamber 1
qty - valve 1 2.000 1.600 0.300 0.960
chamber 2
Total 4.860
Total Quantity in cum 4.860
5.003 5.1.2
6.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Construction of control room and generator room
Column footing 8 1.700 1.700 1.600 36.992
Total 36.992
Total Quantity in cum 36.992
6.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Construction of control room and generator room
For column 8 1.700 1.700 0.100 2.312
footing
floor 1 5.000 4.000 0.150 3.000
floor 1 5.000 4.000 0.080 1.600
Total 6.912
Total Quantity in cum 6.912
6.003 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Construction of control room and generator room
footing 8 1.500 1.500 0.200 3.600
Isolated portion 2.667 1.500 1.500 0.450 2.700
column pedastal 8 0.200 0.400 1.200 0.768
grade slab 1 5.000 4.000 0.150 3.000
plinth beam 6 3.270 0.200 0.450 1.766
plinth beam 2 3.600 0.200 0.450 0.648
plinth beam 1 4.000 0.200 0.450 0.360
ramp 2 3.000 1.500 0.100 0.900
Total 13.742
Total Quantity in cum 13.742
6.004 5.2.2
6.012 50.13.1
9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of
materials, labour charges etc complete
Construction of control room and generator room
ceiling 2 5.000 4.000 40.000
Beam sides 4 4.000 0.330 5.280
slab proj. 1 31.500 0.300 9.450
edge 1 32.400 0.150 4.860
shade bottom 2 11.800 0.750 17.700
&top
shade bottom 2 11.800 0.600 14.160
&top
shade bottom 4 4.400 0.600 10.560
&top
vertical 4 0.600 0.900 2.160
Roof top 1 10.200 4.000 40.800
Total 144.970
Total Quantity in sqm 144.970
6.013 10.6.1
Supplying and fixing rolling shutters of approved make, made of required size M.S.
laths, interlocked together through their entire length and jointed together at the end by
end locks, mounted on specially designed pipe shaft with brackets, side guides and
arrangements for inside and outside locking with push and pull operation complete,
including the cost of providing and fixing necessary 27.5 cm long wire springs
manufactured from high tensile steel wire of adequate strength conforming to IS: 4454
- part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S.
laths with 1.25 mm thick top cover
Construction of control room and generator room
2 3.270 3.000 19.620
Total 19.620
Total Quantity in sqm 19.620
6.014 4.1.3
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand
(zone-III) : 4 graded stone aggregate 20 mm nominal size)
Construction of control room and generator room
Screading
Concrete (Panel 1 4.000 5.000 0.040 0.800
Room)
Total 0.800
Total Quantity in cum 0.800
6.015 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Construction of control room and generator room
Floor Finishing 2 4.000 5.000 40.000
Ramp 2 3.000 1.500 9.000
Total 49.000
Total Quantity in sqm 49.000
6.016 13.43.1
Applying one coat of water thinnable cement primer of approved brand and
manufacture on wall surface:Water thinnable cement primer
Construction of control room and generator room
Room inside 2 18.000 4.900 176.400
Column sides 8 0.200 4.900 7.840
Op. sides 2 9.270 0.200 3.708
Op. sides 1 6.300 0.200 1.260
out sides 1 30.000 4.900 147.000
parapet wall 1 31.600 1.000 31.600
window -4 1.500 1.500 -9.000
open -2 1.500 2.400 -7.200
Rs -4 3.270 3.000 -39.240
Ceiling 2 5.000 4.000 40.000
beam sides 4 4.000 0.330 5.280
slab proj. 1 31.500 0.300 9.450
edge 1 32.400 0.150 4.860
shade bottom 2 11.800 0.750 17.700
&top
shade bottom 2 11.800 0.600 14.160
&top
shade bottom 4 4.400 0.600 10.560
&top
vertical 4 0.600 0.900 2.160
Total 416.538
Total Quantity in sqm 416.538
6.017 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
Construction of control room and generator room
room inside 2 18.000 4.900 176.400
column sides 8 0.200 4.900 7.840
6.020 OD43072/2022-2023
Supplying and providing aluminium window with powder coated aluminium sections
for frames and
shutters with 4mm thick glass panels as per drawings and specifications including all
fittings and fixing
charges
Construction of control room and generator room
windows 4 1.500 1.500 9.000
Total 9.000
Total Quantity in sqm 9.000
7 Providing cable trenches
7.001 4.1.8
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse
sand : 8 graded stone aggregate 40 nominal size)
Providing cable trenches
1 6.000 1.050 0.100 0.630
Total 0.630
Total Quantity in cum 0.630
7.002 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Providing cable trenches
1 6.000 1.050 0.100 0.630
Total 0.630
Total Quantity in cum 0.630
7.003 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Providing cable trenches
1 6.000 1.050 1.050 6.615
Total 6.615
Total Quantity in sqm 6.615
7.004 OD43061/2022-2023
supplying and providing checkered plate 6mm thick over the cable trench including
painting with a coat of iron primer
Providing cable trenches
1 30.000 0.800 24.000
Total 24.000
Total Quantity in sqm 24.000
8 Bath cum toilet
8.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Bath cum toilet
wall 1 9.920 0.900 0.700 6.250
steps 1 1.000 0.750 0.150 0.113
Total 6.363
Total Quantity in cum 6.363
8.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse
sand : 6 graded stone aggregate 40 mm nominal size)
Bath cum toilet
wall 1 9.920 0.900 0.100 0.893
step 1 1.000 0.750 0.100 0.075
Total 0.968
Total Quantity in cum 0.968
8.003 7.1.1
Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand)
Bath cum toilet
Foundation 2 9.920 0.600 0.600 7.142
Basement 2 9.920 0.450 0.450 4.018
Total 11.160
Total Quantity in cum 11.160
8.004 6.4.1
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation
7.5 in superstructure above plinth level up to floor V level in all shapes and sizes
in:Cement mortar 1:4 ( 1 cement : 4 coarse sand)
Bath cum toilet
wall 2 9.920 0.230 2.700 12.321
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved
make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick
cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with white
cement and matching pigment etc., complete.
Bath cum toilet
2 3.000 1.500 9.000
Total 9.000
Total Quantity in sqm 9.000
8.014 13.37.1
White washing with lime to give an even shade:New work (three or more coats)
Bath cum toilet
side wall 2 3.000 1.800 10.800
top 2 3.000 1.500 9.000
Total 19.800
Total Quantity in sqm 19.800
8.015 13.40
Distempering with dry distemper of approved brand and manufacture (two or more
coats) of required shade on new work, over and including water thinnable priming coat
to give an even shade:
Bath cum toilet
side wall 2 3.000 1.800 10.800
side wall 2 3.000 1.500 9.000
Total 19.800
Total Quantity in sqm 19.800
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer &
9 allied works complete
9.001 OD43078/2022-2023
Supply, delivery and erection of non-clog sewage submersible pump sets with
stainless steel impeller to pass soft solids upto 50mm size per separate special
specification. including cost of required submersible cable to suit the site condition
,starter with control board, Submersible cables required as per site conditions should
be supplied with two capacitance type level guards for operating automatically
autocoupler SS chain ,guide rail etc for the following duty condition. MSB(Separate
pannels for H&C PS 1,Asramom and H&C PS 2 pump houses)Fabrication
supply,conveyance,installation testing and commissioning of floor/wall mounting dust
and vermin proof cubicle type MV panel board confirming of the fallowing
components/devicess and complying to IS 8623 Fabrication of fully partitioned ,dust
and vermin proof enclosure for panel assemby as per form 4 of IS 8623 using 2mm
CRCA sheet as per approved design and requirement, with front and rear accessembly
,bus bar chembers,hinged doors for all switch gear components ,earthing the door
using 4sq.mm braided copper conductor, providing necessary cut-outs for mounting
meters,relays,indication lamps,bus bar inter connections etc,detachable covers for
busbar chember and cable alley,power coating the assembly after subjecting to 7 tank
process etc as required. CRCA sheet alone be used for the
fabrication.Angles/flats/slotted angles etc shall not be used forthe fabrication of panel
assembly. The panel shaii be provided with base frame from ISMS 75.Necessary
barriers and shrouding with 2mm/3mm SMC Sheets shall be provided.Heavy duty
neoprene beeding of apropriate sizes shall be used to make the panel dust and vermin
proof. The control board should have necessary tripping devices and indicating
devices for safety of motor and pumpsets with necessary isolator near the wet well site
- lpd and head in m as follow as per actual site condition.Outgoing(i)H&C PS2:
150A TP MCCB to control the submersible pump set-5Nos, (b). 150 A TP MCCB to
control the capacitor bank - 1 no(c)Providing suitable rating capacitor bank with
APFC Panel-1No.(d)150A 25Ka TP MCCB spare -1No.(ii)ASRAMOM: a,150A
16KA TP MCCB to control submersible pump sets at Asramom-5Nos,b,150A 16 KA
TPMCCB to control the capacitor bank-1No c, Providing suitable rating capacitor
bank with APFC Panel (d) (iii)IH&C PS1(a)150A 25 KA TPMCCB -2 Nos,(b)
150A 25KA TPMCCB-2Nos,(c)150A 25 KA TPMCCB-2Nos (d) Providing suitable
ratings(3Nos 40Kvar) capacitor bank with APFC Panel-1No.N.B (a) Necessary CTs
should be provided for safe guarding the instruments wherever necessary .Interlocking
should be provided for standby pump sets.Cabling Supply ,delivery and laying of
following size L.T cable (1.1KV Grade)including jointing material,cable carrier
system like trenches,cable trays pipe sleeves etc as per IE rules including cost of flat
submersible cable connecting main panel board and submersible pump sets thro starter
control board and isolator 3 ½ core 95 sq mm armourd aluminum conductor
cable length as per site condition.connection from suction up to header line.(three year
additional replacement warranty additional to 2 years = total 5 year -Including
replacement of parts or pump,motors,panel board fully.)
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
PH1 2 85.000 170.000
Total 170.000
Total Quantity in HP (Horse power) 170.000
9.002 OD43079/2022-2023
Supply, delivery and erection of Multistage force Pump 600LPM X 30M head suitable
for cleaning the screen chamber,Pumpset during servicing with 16 m of 20 mm dia
hose required for operating the pump .
9.012 OD43086/2022-2023
Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
9.013 OD43087/2022-2023
Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in kg 1.000
9.014 OD43088/2022-2023
Supply and delivery of 200 mm Non-Return Ball valve made up of DI and ball of
Aluminum with MVR coated for the common header.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
2 2.000
Total 2.000
Total Quantity in no 2.000
9.015 OD43089/2022-2023
Supply and fixing of stainless steel screen made of bars of size 50 mm x 10 mm for
fixing across the screen chamber channel (fixed type ) at 45 degree inclination for a
clear passage of 40 mm solids and suitable for manual cleaning including cost of of
screen ,Grab bucket and lifting arrangement material and fixing charges for 1.00m x
1.30m size.
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
9.016 OD43090/2022-2023
Estimate for Mechanical and Allied Electrical works - ELECTRICAL PANELS AND
CABLES Supply, Delivery of M.V control panel of wall mounting type made up of 14
SWG M.S Sheet of size to suit the L.T metering arrangements by KSEB. The board is
to be supplied with 3 Nos of fuse carriers, MCCB with neutral and earthing
arrangements as per I.E rules. Supply and delivery of floor mounting type MV control
panel of vermin proof, dust proof, modular type consisting of the following
accessories and controls. The control panel shall be of enclosed type and built with
compartmentalized modular type cubical. All cubical shall be constructed from 14
SWG, M.S sheet at the bottom and rear and 12 SWG M.S Sheet at front. . The interior
and exterior of the panels and compartment shall be treated with one coat of primer
and two coats of stove enameled light gray shade suitable for electric applications. The
panel should be supplied with 4 nos of copper bus bars of ample carrying capacity
properly sleeved with respective colour codes. Set 1 Incoming 1. 150 A MCCB /
35KA with over load, short circuit protection 2. (0-500 v) Voltmeter (w) selector
switch -1set3. Ammeter 0-300A with phase selector switch – 1 set 4. 3 phase /
4 wire KWH meter – 1 no5. Earth fault relay – 1 set 6. Slide locking
type fuses – 1set Supply and installation of suitable starters in the above pump
houseses(7). 63 A TPN MCCB for lighting control and spare – 2noN.B (a)
Necessary CTs should be provided for safe guarding the instruments wherever
necessary(b) The supply should be terminated through A.M.F panel of Genset offered
for Auto start operation during EB power failure with in 15 secs Twin earthing the
plant and equipment as per IE roles including cost of GI flats (continuous earthing) etc
complete. set 1Cabling Supply ,delivery and laying of following size L.T cable
(1.1KV Grade)including jointing material,cable carrier system like trenches,cable trays
pipe sleeves etc as per IE rules excluding cost of flat submersible cable connecting
main panel board and submersible pump sets thro starter control board and isolator 3
½ core 35 sq mm armourd aluminum conductor cable of suitable length as per
site condition connecting EB pole and EB meter and control panel board m 30
SupplyLighting LoadSupply and completion of required house wiring for
accommodating the following including DB panels, cost of wire, cost of PVC
conduits, earthing etc. 1. SV lamp to be fixed on the top of control room -1no
(250w)2. Industrial type tube lights inside the control room.-8 nos (40w)3. 4 Nos CFL
(not exceeding 25 W) at suitable locations with fittings.4. 15 A plug and socket with
control switch – 2 nos5. 5 A plug and socket with control switch – 2
nos6. Portable lamp with 25W CFL bulb and 15 M cable-1 no7. Pedestal fan -1 no
<br>The above electrical items as per IE rules includes cost of materials such as
bulbs and fittings etc. <br>Supply and delivery of silent diesel generator set of
82.5 Kva with AMF panel with suitable engine capacity conforming to relevent IS
specifications, water cooled, six cylinders comprising of suitable altemator 3 phase,
0.8PF, 4 pole with panel board, digital type voltmeter, anneter, Hertz meter, kwh
meter, MCCB with acoustic enclosure as per CPCP norms including cost of battery
charger, cost of battery etc. complete, including cost of cabling, earthing, etc. suitable
for outdoor application as per IE rules including cost of platform etc. complete. set 1
Air valvesSupply and delivery of following safety items ,including cost of same. L SI.
Fire extinguisher of required capacity (powder type 2 no’s) II. Fire buckets
with stand 5no’s III. Rubber mat to be laid in front of all the panel boards
including starter panelsSupply and delivery of tools required for maintenance works
including double end spanners, ring spanners, screw drivers,etc including suppley and
erection of Diesel Generator
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
1 1.000
Total 1.000
Total Quantity in no 1.000
9.018 OD43092/2022-2023
Supply and delivery of suitable flexible joint coupling upto 200mm for easy
dismantling of delivery pipes and valves with tie bolts with angular deflection 5 degree
Mechanical, Electrical - Pumpsets, grit chamber screen, generator, transformer
& allied works complete
3 3.000
Total 3.000
Total Quantity in no 3.000
10 Pumping mains
10.00 100.1.1
1 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Pumping mains
PH1 to manhole 1 1800.000 1.500 1.350 0.8000
(N2974) 00 2916.000
Total 2916.000
Total Quantity in cum 2916.000
10.00 100.1.5
2 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Pumping mains
PH1 to (MH 1 1800.000 1.500 1.350 0.1800 656.100
283) 00
Total 656.100
Total Quantity in cum 656.100
10.00 100.1.9
3 Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in Hard Rock Requiring Blasting.
Pumping mains
0.0200
PH1 to MH 283 1 1800.000 1.500 1.350 72.900
00
Total 72.900
Total Quantity in cum 72.900
10.00 15.2.1
4 Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Pumping mains
concrete road 1 1800.000 1.000 0.150 270.000
Total 270.000
Total Quantity in cum 270.000
10.00 100.8.1
5 Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape
in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Pumping mains
1 900.000 900.000
Total 900.000
Total Quantity in metre 900.000
10.00 18.68.1
6 Providing and laying D.I specials of class K - 12 suitable for push - on jointing as per
IS : 9523 :Upt 600 mm dia
Pumping mains
1 12.000 12.000
Total 12.000
Total Quantity in quintal 12.000
10.00 5.1.3
7 Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Pumping mains
pipe supports/ 10 1.000 1.000 1.000 10.000
anchor blocks
Total 10.000
Total Quantity in cum 10.000
10.00 5.9.1
8 Centering and shuttering including strutting, etc. and removal of form for:Foundations,
footings, bases of columns, etc for mass concrete
Pumping mains
10 4.000 40.000
Total 40.000
Total Quantity in sqm 40.000
10.00 5.22.6
9 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Pumping mains
1 10.000 80.000 800.000
Total 800.000
Total Quantity in kilogram 800.000
10.01 100.98.122
0 Supply of DI K9 Pipe Conforming to IS 8329/2000, 450mm Dia.
Supply of DI K9 PIPE
1 1800.000 1800.000
Total 1800.000
Total Quantity in metre 1800.000
10.01 100.14.8
1 Conveying and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes
conforming to IS: 8329 excluding cost of pipes and specials: 450mm diameter Ductile
Iron Class K-9 Pipes.
Conveying and laying S&S ductile iron pipe -450mm
1 1800.000 1800.000
Total 1800.000
Total Quantity in metre 1800.000
10.01 18.70.8
2 Providing push - on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron
Pipes including testing of joints and including the cost of rubber gasket:450 mm dia
pipes
Providing push on joint -450mm dia pipe
200 200.000
Total 200.000
Total Quantity in joint 200.000
10.01 100.35.8
3 Testing 450mm DI/CI pipeline with potable water to the required test pressure.
450 mm dia
Observed Data derived from item no.1027 of PHED DATA
Testing 450mm DI/Cl pipeline
1800 1800.000
Total 1800.000
Total Quantity in metre 1800.000
10.01 18.83.10
4 Labour for cutting C.I. pipe with steel saw.450 mm diameter C.I. pipe
Labour for cutting C l pipe
54 54.000
Total 54.000
Total Quantity in each 54.000
11 Laying PE pipes via HDD Method above 3m depth
11.00 OD43074/2022-2023
1 Installation of PE -250mm-315mm mm dia PE pipe by horizontal directional drilling
method in all types of soil above /below water table for pumping /gravity /distribution
main including preparing and setting up the plat and equipment, installing new pipe
work, testing and commissioning including cost of pipe (6 m line pipe with butt joint
all related civil /mechanical works like entry /exits pit as necessary. De watering
,drilling stringing, reaming, pulling back the new pipe on the designed alignment and
monitoring by approved guidance system. wastage of pipes, proper disposal of drilling
fluid /bentonite slurry. Proper back filling og pit and holes by approved borrow
material as per specification approved method statement or as directed by engineer in
charge. also using Ground penetrating radar survey in corridor with to detect buried
utilities on the map of corridor with information of locations and depths to the top of
various utilities detected .work to be conducted using 500MHZ and 300MHZ antenna
or latest for the best possible resolution and penetration including hydrolic testing
Laying PE pipes via HDD Method above 3m depth
250MM HDPE 1 224.600 224.600
315MM HDPE 1 182.200 182.200
Total 406.800
Total Quantity in metre 406.800
11.00 OD43075/2022-2023
2 Installation of PE pipe between 110mm & 225mm outer dia by HDD method for
on grade brgravity sewer including preparing and setting up the plant and
equipment,preparing new pipe work material making of entry pit and exit pit up to
required depth installing new pipe work and commissioning system or making the
system or making the system ready for commissioning by HDD operating including all
related civil and mechanical works like excavation shoring/strutting etc drilling
stringing reaming and pulling back the new pipe work on the designed borne path
alignment proper disposal of drilling fluid and back fill of site after completion all
inclusive as per Conditions HDPE pipes also using Ground penetrating radar survey in
corridor with to detect buried utilities on the map of corridor with information of
locations and depths to the top of various utilities detected .work to be conducted using
500MHZ and 300MHZ antenna or latest for the best possible resolution and
penetration
Laying PE pipes via HDD Method above 3m depth
wet mix bm
open 1 4370.000 2.500 0.250 2731.250
pm 1 1800.000 2.500 0.250 1125.000
ic to mh 1 2408.000 1.000 0.250 602.000
Total 4458.250
Total Quantity in cum 4458.250
14.00 5.2.b
3 Providing and applying tack coat with bitumen emulsion (RS) using emulsion pressure
distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared Granular Surface
cleaned with mechanical broom.
tack coat
13110.00
open cut 1 4370.000 3.000 0
pm 1 1800.000 3.000 5400.000
ic to mh 1 2408.000 1.500 3612.000
22122.00
Total 0
14.00 5.3.2.a
4 Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified grading
premixed with a bituminous binder (VG 30), transported to the site, laid over a
previously prepared surface with paver finisher to the required grade, level, and
alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction
For Grading II - (19 mm nominal size)
macardum
open 1 4370.000 0.050 3.000 655.500
pumping main 1 1800.000 0.050 3.000 270.000
ic to mh 1 2408.000 0.050 1.500 180.600
Total 1106.100
Total Quantity in cum 1106.100
14.00 5.2.a
5 Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure
distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.
tack coat
13110.00
open 1 4370.000 3.000 0
pm 1 1800.000 3.000 5400.000
ic to mh 1 2408.000 1.500 3612.000
22122.00
Total 0
22122.00
Total Quantity in sqm 0
14.00 5.6.2.a
6 Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified grading,
premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level, and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects For Grading - II (13.2
mm Nominal Size)
bc
open cut 1 4370.000 3.000 0.030 393.300
pumping main 1 1800.000 3.000 0.030 162.000
ic to mh 1 2408.000 1.500 0.030 108.360
Total 663.660
Total Quantity in cum 663.660
14.00 5.1.a
7 Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface
of granular Base including clearing of road surface and spraying primer at the rate of
0.70 - 1.0 kg/sqm using mechanical means.
primer coat
13110.00
open 1 4370.000 3.000 0
pm 1 1800.000 3.000 5400.000
ic to mh 1 2408.000 1.500 3612.000
22122.00
Total 0
ABSTRACT ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 535
1.002 15.43.2
Dismantling manually / by mechanical means including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead as per direction
of Engineer -in-Charge:Bituminous road
Net Total 9299.000sqm @339.50/sqm 3157010.50
1.003 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Net Total 93.909cum @1923.75/cum 180657.44
1.004 100.8.2
Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with
coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
Net Total 6395.400metre @90.44/metre 578399.98
1.005 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution
tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Net Total 2125.480metre @26.31/metre 55921.38
1.006 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
1.011 2.23
Extra for planking and strutting in open timbering if required to be left permanently in
position (Face area of the timber permanently left to be measured).
Net Total 2100.000sqm @908.53/sqm 1907913.00
1.012 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Net Total 120.000cum @8078.71/cum 969445.20
1.013 100.98.226
1.014 100.10.7
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 200mm Nominal
Outside Diameter Pipes.
Net Total 5135.000metre @300.89/metre 1545070.15
1.015 100.10.9
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 250mm Nominal
Outside Diameter Pipes.
Net Total 410.900metre @415.58/metre 170761.82
1.016 100.10.13
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 400mm Nominal
Outside Diameter Pipes.
Net Total 483.200metre @686.93/metre 331924.58
1.017 100.10.14
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 450mm Nominal
Outside Diameter Pipes.
Net Total 618.100metre @763.72/metre 472055.33
1.018 4.1.2
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2
coarse sand : 3 graded stone aggregate 20 mm nominal size)
Net Total 93.909cum @7983.68/cum 749739.41
1.019 7.6.1
Coursed rubble masonry (first sort) with hard stone in foundation and plinth
with:Cement mortar 1:6 (1 cement : 6 coarse sand)
Net Total 11.160cum @8096.19/cum 90353.48
1.020 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Net Total 15.925cum @8545.86/cum 136092.82
1.021 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 954.000kilogram @92.47/kilogram 88216.38
1.022 OD43025/2022-2023
Supplying, Providing bedding with m sand for sewer lines as per specifications to be
laid wherever
necessary with all lead and lift.
Net Total 160.000cum @2153.61/cum 344577.60
1.023 OD43026/2022-2023
Supply of PE Pipe PE 100 (IS 14333/ sewerage pipe with latest IS), 8kg, 200mm
Outer Dia.
Net Total 5674.700metre @1186.04/metre 6730421.19
1.024 OD43027/2022-2023
Supply of PE Pipe, PE100, PN8, 400mm dia, conforming to IS 1433 (Sewerage Pipe)
Net Total 794.000metre @6514.50/metre 5172513.00
1.025 OD43028/2022-2023
Supply of PE Pipe PE 100 (IS 14333), 8kg, 250mm Outer Dia
Net Total 635.500metre @1943.49/metre 1235087.90
1.026 OD43029/2022-2023
Supply of PE Pipe, PE100, PN8, 450mm dia, conforming to IS 1433 (Sewerage Pipe)
Net Total 845.600metre @5103.03/metre 4315122.17
1.027 OD43030/2022-2023
Supply of PE Pipe, PE100, PN8, 560mm dia, conforming to IS 1433 (Sewerage Pipe)
1.031 OD43034/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.45m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, , plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 300.000no @3434.07/no 1030221.00
1.032 OD43035/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.90m deep with
RCC M20 using
20mm broken stone for floor slab ,RCC M20 slab using 20mm broken stone for
removable cover slab,
Brick work in CM 1:6 for walls, PCC 1:4:8 using 20mm broken stone for leveling
course below foundation
including earth work excavation in all classes of soil, plastering the inside with CM
1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing
provision for connecting main sewer and service connections, conveying, lifting,
placing the cover slab in
position by suitable means, conveying and disposing the surplus earth with all lead
and lift as per
drawings and specifications , including the cost of reinforcement , testing the chamber
and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 150.000no @7399.73/no 1109959.50
1.033 OD43036/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.60m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 100.000no @6972.85/no 697285.00
1.034 OD43037/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.75m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main
sewer, providing provision for connecting main sewer and service connections,
conveying, lifting, placing the cover slab in position by suitable means, conveying
and disposing the surplus earth with all lead and lift as per drawings and
specifications , including the cost of reinforcement , testing the chamber and sulphate
resistant cement shall be used for the the construction of inspection chamber
Net Total 50.000no @7181.38/no 359069.00
1.035 OD43038/2022-2023
Providing and drilling with Horizontal drilling machine and air compressor for
inserting 800 mm MS casing pipe through the hole formed including cost of pipes,
cost of mobilization installation and all labour charges etc.
Net Total 10.000metre @37391.30/metr 373913.00
e
1.036 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 364607.500K 12670110.6
wh @34.75/Kwh 3
1.037 100.10.11
Laying HDPE pipes (IS : 4984) on land portion including conveying within initial
lead and aligning the pipes, electro-fusion welding using automatic or semi-automatic
electrofusion machines, testing the pipeline thus fabricated to suit the hydraulic
working pressure and after testing, aligning the pipeline, lowering the pipe in position
into the trenches already made, testing the line to suitable pressure with potable water
before back filling and levelling the trenches including all labour charge, hire for
appliances etc., complete but excluding cost of pipe and fittings: 315mm Nominal
Outside Diameter Pipes.
Net Total 611.800metre @546.51/metre 334354.82
1.038 OD63476/2022-2023
Supply of PE Pipe, PE100, PN8, 710mm dia, conforming to IS 1433 (Sewerage Pipe)
Net Total 515.600metre @9760.89/metre 5032714.88
2.007 OD67514/2022-2023
MoRD Spec.No-5.12.A.3.2a. Seal Coat - Manual Means - Type C - Bitumen S-65
Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A, Type B and Type C as per
Technical Specification Clause 510
A. By Manual Means :- Case - III : Type C
(II) Bitumen (S-65)
Net Total 7359.000sqm @95.65/sqm 703888.35
3.001 2.31
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground level and
removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
Net Total 400.000sqm @13.88/sqm 5552.00
3.002 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 5000.000Kwh @34.75/Kwh 173750.00
3.003 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 28.260sqm @315.41/sqm 8913.49
3.004 5.9.3
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform
Net Total 44.156sqm @767.34/sqm 33882.67
3.005 5.9.12
Centering and shuttering including strutting, etc. and removal of form for:Well
steining
Net Total 418.719sqm @272.80/sqm 114226.54
3.006 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 10684.480kil
ogram @92.47/kilogram 987993.87
3.007 OD43059/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Net Total 133.556cum @8931.99/cum 1192920.86
3.008 OD43060/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the
engineer in-charge.
Net Total 53.000no @397.18/no 21050.54
3.009 OD47065/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.Initial depth upto
1.5m
Net Total 1.500metre @46739.13/metr 70108.70
e
3.010 OD47073/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 1.5m
to 3.0m
Net Total 1.500metre @54217.38/metr 81326.07
e
3.011 OD47085/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 3.0m
to 4.5m
Net Total 1.500metre @59826.08/metr 89739.12
e
3.012 OD47086/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m
to 6.0m
Net Total 1.500metre @64500.00/metr 96750.00
e
3.013 OD47103/2022-2023
Sinking wells above up to 3.50 m dia. and up to 6.00 m inside and depth up to 3.00 m
below spring level in in 50% all kind of soil and 50% ordinary rocksoil (specify type
of soil) to lines and levels and plumb by scooping out earth from inside and below the
steining using necessary appliances including hire and labour for the same including
dumping the spoil beyond the initial lead of 50 m etc. complete.First depth upto 6m to
7.5m
Net Total 1.500metre @69173.91/metr 103760.87
e
3.014 OD47107/2022-2023
Sinking wells above up to 6 m dia. and up to 7.5 m inside and depth up to 3.00 m
below spring level
in in 50% all kind of soil and 50% ordinary rocksoil (specify type of soil) to lines and
levels and plumb by scooping out earth from inside and below the steining using
necessary appliances including hire and labour for the same including dumping the
spoil beyond the initial lead of 50 m etc. complete.First depth upto 4.5m to 6.0m
Net Total 0.390metre @72913.05/metr 28436.09
e
Heading Total(Rs) 3008410.82
4 Construction of screen chamber and Valve chamber
4.001 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 62.525sqm @315.41/sqm 19721.01
4.002 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 1788.200kilo
gram @92.47/kilogram 165354.85
4.003 OD43039/2022-2023
Reinforcement cement concrete M-30using 20mm&down size (nominal size)
broken stone using SRC for raft slab ,well kerb and steining excluding
formwork,curing etc complete.as per the specifications and drawings with alllead and
lift
Net Total 17.882cum @8931.99/cum 159721.85
4.004 OD43041/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking
of useful materials and disposal of the surplus earth/unsuitable material as directed by
the engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead
and lift etc as per the direction of Engineer for upto 4.50m beyond initial 3.00m
depth.
Net Total 0.070metre @14722.11/metr 1030.55
e
4.005 OD43042/2022-2023
Sinking section for screen chamber of internal dimmension of 2.5 m x 1.5 m as per
approved design , drawing specification to the given alignment and to any depth in all
kinds of strata including soft rock, including excavation, dewatering until completion
of works application of knetledge for alround seating of well , removal of bouldars,
burried timbers, trunks,fossils, including depositingthe excavated stuff and stacking
of useful materials and disposal of the surplus earth/unsuitable material as directed by
the engineer with necessarry shoring and strutting, barricading etcincluding cost of
ringbunds/cofferdams/approved suitable arrangementys for diversion of water cours
etc. The rate include providing the required equipments, oil lubricants,labour and any
other mechanical operationthat may be required in all respects for succesfull
completion of work, including cost of materials , tools and plants, machinaries,
powersupply at site etc, including all necessarry safety arrangements like danger
lighting, fencing etc including cost of all materials and labour charges with all lead
and lift etc as per the direction of Engineer for upto 3.00m below ground level
Net Total 3.000metre @13867.78/metr 41603.34
e
4.006 OD43043/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the
engineer in-charge.
Net Total 21.000no @397.18/no 8340.78
4.007 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Net Total 5000.000Kwh @34.75/Kwh 173750.00
4.008 13.7.2
12 mm cement plaster finished with a floating coat of neat cement of mix:1:4 ( 1
cement : 4 fine sand)
Net Total 62.525sqm @363.44/sqm 22724.09
4.009 13.44.1
Finishing walls with water proofing cement paint of required shade:New work (Two
or more coats applied @ 3.84 kg/10 sqm)
Net Total 61.775sqm @100.99/sqm 6238.66
4.010 13.65.1
Painting with black anti- corrosive bitumastic paint of approved brand and
manufacture to give an even shade:Two or more coats on new work
Net Total 61.775sqm @117.41/sqm 7253.00
Heading Total(Rs) 605738.13
5 Construction of valve chamber
5.001 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
5.005 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Net Total 30.310sqm @387.67/sqm 11750.28
5.006 OD43044/2022-2023
Supplying providing and fixing CI encapsulated steps at 30.00cm c/c in a staggered
manner including all labour charges, etc complete as per the instruction of the
engineer in-charge.
Net Total 8.000no @397.18/no 3177.44
Heading Total(Rs) 245941.37
6 Construction of control room and generator room
6.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
of minimum 8 tonnes and dressing up in embankments for roads, flood banks,
marginal banks and guide banks or filling up ground depressions, lead up to 50 m and
lift up to 1.5 m:All kinds of soil
Net Total 36.992cum @826.87/cum 30587.58
6.002 4.1.6
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3
coarse sand : 6 graded stone aggregate 40 mm nominal size)
Net Total 6.912cum @6783.10/cum 46884.79
6.003 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Net Total 13.742cum @8545.86/cum 117437.21
6.004 5.2.2
Reinforced cement concrete work in walls (any thickness), including attached
pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,
abutments, posts and struts etc. up tot floor five level excluding cost of centering,
shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded
stone aggregate 20 mm nominal size)
Net Total 15.058cum @10303.83/cum 155155.07
6.005 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 5.912sqm @315.41/sqm 1864.70
6.006 5.9.5
Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers
Net Total 68.878sqm @611.22/sqm 42099.61
6.007 5.9.6
Centering and shuttering including strutting, etc. and removal of form for:Columns,
Pillars, Piers, Abutments, Posts and Struts
Net Total 54.240sqm @812.35/sqm 44061.86
6.008 5.9.20
Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform with water proof ply 12 mm
thick
Net Total 67.008sqm @862.83/sqm 57816.51
6.009 50.6.7.2
Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest
size in cement mortar 1:6 for super structure above plinth level up to floor two level
including all cost of materials, labour charges etc.
Net Total 20.803cum @7449.03/cum 154962.17
6.010 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
structural steel etc. as required.In gratings, frames, guard bar, ladder, railings,
brackets, gates and similar works
Net Total 144.000kg @145.04/kg 20885.76
6.019 13.61.1
Painting with synthetic enamel paint of approved brand and manufacture to give an
even shade:Two or more coats on new work
Net Total 58.050sqm @134.56/sqm 7811.21
6.020 OD43072/2022-2023
Supplying and providing aluminium window with powder coated aluminium sections
for frames and
shutters with 4mm thick glass panels as per drawings and specifications including all
fittings and fixing
charges
Net Total 9.000sqm @3601.23/sqm 32411.07
Heading Total(Rs) 1129796.06
7 Providing cable trenches
7.001 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Net Total 0.630cum @6410.36/cum 4038.53
7.002 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Net Total 0.630cum @8545.86/cum 5383.89
7.003 13.9.1
Cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with a floating coat of neat
cement.12 mm cement plaster
Net Total 6.615sqm @387.67/sqm 2564.44
7.004 OD43061/2022-2023
supplying and providing checkered plate 6mm thick over the cable trench including
painting with a coat of iron primer
Net Total 24.000sqm @6541.21/sqm 156989.04
Heading Total(Rs) 168975.90
8 Bath cum toilet
8.001 2.2.1
Earth work in rough excavation, banking excavated earth in layers not exceeding 20
cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or
wooden or steel rammers, and rolling every 3rd and top-most layer with power roller
8.007 4.1.8
Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4
coarse sand : 8 graded stone aggregate 40 nominal size)
Net Total 1.000cum @6410.36/cum 6410.36
8.008 13.1.1
12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Net Total 104.616sqm @295.46/sqm 30909.84
8.009 13.33.1
Pointing on stone work with cement mortar 1:3 ( 1 cement : 3 fine sand):Flush/ Ruled
pointing
Net Total 20.832sqm @316.02/sqm 6583.33
8.010 50.13.1
9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of
materials, labour charges etc complete
Net Total 40.342sqm @274.01/sqm 11054.11
8.011 5.18.1
Providing precast cement concrete jali 1:2:4 ( 1 cement : 2 coarse sand : 4 graded
stone aggregate 6 mm nominal size) reinforced with 1.6 mm dia mild steel wire
including centering and shuttering, roughening cleaning, fixing and finishing in
cement mortar 1:3 (1 cement : 3 fine sand ) etc. complete excluding plastering of the
jambs, sills and soffits.50 mm thick
Net Total 3.000sqm @1632.14/sqm 4896.42
8.012 OD43073/2022-2023
Supplying and fixing PVC door of size 0.8x2.10m as per the standard specification
including all fittings and labour charges ,etc. .complete
Net Total 2.000no @4502.26/no 9004.52
8.013 11.37
Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be
specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved
make, in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick
cement mortar 1:4 (1 Cement : 4 Coarse sand), including pointing the joints with
white cement and matching pigment etc., complete.
Net Total 9.000sqm @1026.29/sqm 9236.61
8.014 13.37.1
White washing with lime to give an even shade:New work (three or more coats)
Net Total 19.800sqm @31.60/sqm 625.68
8.015 13.40
Distempering with dry distemper of approved brand and manufacture (two or more
coats) of required shade on new work, over and including water thinnable priming
coat to give an even shade:
Net Total 19.800sqm @130.35/sqm 2580.93
Heading Total(Rs) 334339.27
autocoupler SS chain ,guide rail etc for the following duty condition. MSB(Separate
pannels for H&C PS 1,Asramom and H&C PS 2 pump houses)Fabrication
supply,conveyance,installation testing and commissioning of floor/wall mounting
dust and vermin proof cubicle type MV panel board confirming of the fallowing
components/devicess and complying to IS 8623 Fabrication of fully partitioned ,dust
and vermin proof enclosure for panel assemby as per form 4 of IS 8623 using 2mm
CRCA sheet as per approved design and requirement, with front and rear accessembly
,bus bar chembers,hinged doors for all switch gear components ,earthing the door
using 4sq.mm braided copper conductor, providing necessary cut-outs for mounting
meters,relays,indication lamps,bus bar inter connections etc,detachable covers for
busbar chember and cable alley,power coating the assembly after subjecting to 7 tank
process etc as required. CRCA sheet alone be used for the
fabrication.Angles/flats/slotted angles etc shall not be used forthe fabrication of panel
assembly. The panel shaii be provided with base frame from ISMS 75.Necessary
barriers and shrouding with 2mm/3mm SMC Sheets shall be provided.Heavy duty
neoprene beeding of apropriate sizes shall be used to make the panel dust and vermin
proof. The control board should have necessary tripping devices and indicating
devices for safety of motor and pumpsets with necessary isolator near the wet well
site - lpd and head in m as follow as per actual site condition.Outgoing(i)H&C
PS2: 150A TP MCCB to control the submersible pump set-5Nos, (b). 150 A TP
MCCB to control the capacitor bank - 1 no(c)Providing suitable rating capacitor bank
with APFC Panel-1No.(d)150A 25Ka TP MCCB spare -1No.(ii)ASRAMOM: a,150A
16KA TP MCCB to control submersible pump sets at Asramom-5Nos,b,150A 16 KA
TPMCCB to control the capacitor bank-1No c, Providing suitable rating capacitor
bank with APFC Panel (d) (iii)IH&C PS1(a)150A 25 KA TPMCCB -2 Nos,(b)
150A 25KA TPMCCB-2Nos,(c)150A 25 KA TPMCCB-2Nos (d) Providing suitable
ratings(3Nos 40Kvar) capacitor bank with APFC Panel-1No.N.B (a) Necessary CTs
should be provided for safe guarding the instruments wherever necessary
.Interlocking should be provided for standby pump sets.Cabling Supply ,delivery and
laying of following size L.T cable (1.1KV Grade)including jointing material,cable
carrier system like trenches,cable trays pipe sleeves etc as per IE rules including cost
of flat submersible cable connecting main panel board and submersible pump sets
thro starter control board and isolator 3 ½ core 95 sq mm armourd aluminum
conductor cable length as per site condition.connection from suction up to header
line.(three year additional replacement warranty additional to 2 years = total 5 year -
Including replacement of parts or pump,motors,panel board fully.)
170.000HP @23738.84/HP
Net Total (Horse 4035602.80
power) (Horse power)
9.002 OD43079/2022-2023
Supply, delivery and erection of Multistage force Pump 600LPM X 30M head
suitable for cleaning the screen chamber,Pumpset during servicing with 16 m of 20
mm dia hose required for operating the pump .
Net Total 1.000set @59716.25/set 59716.25
9.003 OD43080/2022-2023
Supply and delivery of 200 mm CI Sluice Valves suitable for the sewage pump sets
one no. for each pump sets
Net Total 1.000no @76002.50/no 76002.50
9.004 OD43081/2022-2023
Supply and delivery of 250 mm suitable flexible joint coupling for easy dismantling
of delivery pipes and valves with Tie bolts with angular deflection 5 Degree
Net Total 3.000no @11943.25/no 35829.75
9.005 OD43082/2022-2023
Supply and delivery of breathing apparatus with Oxygen cylinder mask etc. complete
.
Net Total 1.000set @81431.25/set 81431.25
9.006 OD43083/2022-2023
Supply and delivery of Diaphragm type pressure gauge with necessary S.S tubes and
isolating valves
Net Total 1.000no @6514.50/no 6514.50
9.007 OD43084/2022-2023
Supply and fixing of Electro magnetic flow meter suitable for remote sensing
operation with required pipes,specials and accessories at laminar flow region (full
flow)including cost of pit cover slab etc
Net Total 1.000no @325725.00/no 325725.00
9.008 OD43085/2022-2023
Supply, delivery and erecting of following safety items ,including cost of same.
Fire extinguisher of 5 Kg capacity (powder type 2 no’s) . Fire buckets with
stand 5no’s. Electric quality Rubber mat to be laid in front of all the panel
boards including starter panels
Net Total 1.000no @43430.00/no 43430.00
9.009 100.98.460
Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice
Valve with Cap PN 1.6, Size 150mm.
Net Total 2.000no @12523.04/no 25046.08
9.010 100.31.1.5
Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber
insertions etc., complete, but excluding the cost of the valve (tail pieces, if required,
will be paid separately): 200mm diameter, Class I.
Net Total 2.000no @1465.16/no 2930.32
9.011 100.98.461
Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice
Valve with Cap PN 1.6, Size 200mm.
Net Total 2.000no @22176.44/no 44352.88
9.012 OD43086/2022-2023
Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Net Total 1.000no @11400.38/no 11400.38
9.013 OD43087/2022-2023
Supply, delivery and erection of 200 mm CIDF Pipes and fittings suitable for the
pump set offered and as per drawings enclosed including cost of puddle collars
required
Net Total 1.000kg @162.86/kg 162.86
9.014 OD43088/2022-2023
Supply and delivery of 200 mm Non-Return Ball valve made up of DI and ball of
Aluminum with MVR coated for the common header.
Net Total 2.000no @24429.38/no 48858.76
9.015 OD43089/2022-2023
Supply and fixing of stainless steel screen made of bars of size 50 mm x 10 mm for
fixing across the screen chamber channel (fixed type ) at 45 degree inclination for a
clear passage of 40 mm solids and suitable for manual cleaning including cost of of
screen ,Grab bucket and lifting arrangement material and fixing charges for 1.00m x
1.30m size.
Net Total 1.000no @97717.50/no 97717.50
9.016 OD43090/2022-2023
Supply , delivery , erecting and maintenance of 2 ton or suitable capacity hand
operated pulley block hoist with mono rail traveling on single girder with over head
traveling trolley for a clear lift according to site condition for a travel of 9 (well
dia+3m) meters or suitable design for erection and easy loading and unloading of
Pumps and specials from trucks.
Net Total 1.000no @380012.50/no 380012.50
9.017 OD43091/2022-2023
Estimate for Mechanical and Allied Electrical works - ELECTRICAL PANELS AND
CABLES Supply, Delivery of M.V control panel of wall mounting type made up of
14 SWG M.S Sheet of size to suit the L.T metering arrangements by KSEB. The
board is to be supplied with 3 Nos of fuse carriers, MCCB with neutral and earthing
arrangements as per I.E rules. Supply and delivery of floor mounting type MV control
panel of vermin proof, dust proof, modular type consisting of the following
accessories and controls. The control panel shall be of enclosed type and built with
compartmentalized modular type cubical. All cubical shall be constructed from 14
SWG, M.S sheet at the bottom and rear and 12 SWG M.S Sheet at front. . The interior
and exterior of the panels and compartment shall be treated with one coat of primer
and two coats of stove enameled light gray shade suitable for electric applications.
The panel should be supplied with 4 nos of copper bus bars of ample carrying
capacity properly sleeved with respective colour codes. Set 1 Incoming 1. 150 A
MCCB / 35KA with over load, short circuit protection 2. (0-500 v) Voltmeter (w)
selector switch -1set3. Ammeter 0-300A with phase selector switch – 1 set 4. 3
phase / 4 wire KWH meter – 1 no5. Earth fault relay – 1 set 6. Slide
locking type fuses – 1set Supply and installation of suitable starters in the
above pump houseses(7). 63 A TPN MCCB for lighting control and spare –
2noN.B (a) Necessary CTs should be provided for safe guarding the instruments
wherever necessary(b) The supply should be terminated through A.M.F panel of
Genset offered for Auto start operation during EB power failure with in 15 secs Twin
earthing the plant and equipment as per IE roles including cost of GI flats (continuous
earthing) etc complete. set 1Cabling Supply ,delivery and laying of following size L.T
cable (1.1KV Grade)including jointing material,cable carrier system like
trenches,cable trays pipe sleeves etc as per IE rules excluding cost of flat submersible
cable connecting main panel board and submersible pump sets thro starter control
board and isolator 3 ½ core 35 sq mm armourd aluminum conductor cable of
suitable length as per site condition connecting EB pole and EB meter and control
panel board m 30 SupplyLighting LoadSupply and completion of required house
wiring for accommodating the following including DB panels, cost of wire, cost of
PVC conduits, earthing etc. 1. SV lamp to be fixed on the top of control room -1no
(250w)2. Industrial type tube lights inside the control room.-8 nos (40w)3. 4 Nos CFL
(not exceeding 25 W) at suitable locations with fittings.4. 15 A plug and socket with
control switch – 2 nos5. 5 A plug and socket with control switch – 2
nos6. Portable lamp with 25W CFL bulb and 15 M cable-1 no7. Pedestal fan -1 no
<br>The above electrical items as per IE rules includes cost of materials such as
bulbs and fittings etc. <br>Supply and delivery of silent diesel generator set of
82.5 Kva with AMF panel with suitable engine capacity conforming to relevent IS
specifications, water cooled, six cylinders comprising of suitable altemator 3 phase,
0.8PF, 4 pole with panel board, digital type voltmeter, anneter, Hertz meter, kwh
meter, MCCB with acoustic enclosure as per CPCP norms including cost of battery
charger, cost of battery etc. complete, including cost of cabling, earthing, etc. suitable
for outdoor application as per IE rules including cost of platform etc. complete. set 1
Air valvesSupply and delivery of following safety items ,including cost of same. L SI.
Fire extinguisher of required capacity (powder type 2 no’s) II. Fire buckets
with stand 5no’s III. Rubber mat to be laid in front of all the panel boards
including starter panelsSupply and delivery of tools required for maintenance works
including double end spanners, ring spanners, screw drivers,etc including suppley and
erection of Diesel Generator
Net Total 1.000no @868600.00/no 868600.00
9.018 OD43092/2022-2023
Supply and delivery of suitable flexible joint coupling upto 200mm for easy
dismantling of delivery pipes and valves with tie bolts with angular deflection 5
degree
Net Total 3.000no @9771.75/no 29315.25
Heading Total(Rs) 6172648.58
10 Pumping mains
10.001 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Net Total 2916.000cum @522.57/cum 1523814.12
10.002 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Net Total 656.100cum @758.84/cum 497874.92
10.003 100.1.9
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in Hard Rock Requiring Blasting.
Net Total 72.900cum @1074.70/cum 78345.63
10.004 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Net Total 270.000cum @1923.75/cum 519412.50
10.005 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution
tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Net Total 900.000metre @26.31/metre 23679.00
10.006 18.68.1
Providing and laying D.I specials of class K - 12 suitable for push - on jointing as per
IS : 9523 :Upt 600 mm dia
Net Total 12.000quintal @18927.20/quint 227126.40
al
10.007 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Net Total 10.000cum @8078.71/cum 80787.10
10.008 5.9.1
Centering and shuttering including strutting, etc. and removal of form
for:Foundations, footings, bases of columns, etc for mass concrete
Net Total 40.000sqm @315.41/sqm 12616.40
10.009 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Net Total 800.000kilogr
am @92.47/kilogram 73976.00
10.010 100.98.122
Supply of DI K9 Pipe Conforming to IS 8329/2000, 450mm Dia.
Net Total 1800.000metre @7406.99/metre 13332582.0
0
10.011 100.14.8
Conveying and laying S&S Centrifugally Cast (Spun) / Ductile Iron Pipes
conforming to IS: 8329 excluding cost of pipes and specials: 450mm diameter Ductile
Iron Class K-9 Pipes.
Net Total 1800.000metre @362.03/metre 651654.00
10.012 18.70.8
Providing push - on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron
Pipes including testing of joints and including the cost of rubber gasket:450 mm dia
pipes
Net Total 200.000joint @737.69/joint 147538.00
10.013 100.35.8
Testing 450mm DI/CI pipeline with potable water to the required test pressure.
450 mm dia
Observed Data derived from item no.1027 of PHED DATA
Net Total 1800.000metre @88.68/metre 159624.00
10.014 18.83.10
Labour for cutting C.I. pipe with steel saw.450 mm diameter C.I. pipe
Net Total 54.000each @904.01/each 48816.54
system or making the system ready for commissioning by HDD operating including
all related civil and mechanical works like excavation shoring/strutting etc drilling
stringing reaming and pulling back the new pipe work on the designed borne path
alignment proper disposal of drilling fluid and back fill of site after completion all
inclusive as per Conditions HDPE pipes also using Ground penetrating radar survey
in corridor with to detect buried utilities on the map of corridor with information of
locations and depths to the top of various utilities detected .work to be conducted
using 500MHZ and 300MHZ antenna or latest for the best possible resolution and
penetration
Net Total 539.700metre @4391.10/metre 2369876.67
11.003 OD43076/2022-2023
Installation of PE -355mm-500mm mm dia PE pipe by horizontal directional drilling
method in all types of soil above /below water table for pumping /gravity /distribution
main including preparing and setting up the plant and equipment, installing new pipe
work, testing and commissioning excluding cost of pipe (6 m line pipe with butt joint
all related civil /mechanical works like entry /exits pit as necessary. Dewatering,
drilling stringing, reaming, pulling back the new pipe on the designed alignment and
monitoring by approved guidance system. wastage of pipes, proper disposal of
drilling fluid /bentonite slurry. Proper back filling pit and holes by approved borrow
material as per specification approved method statement or as directed by engineer in
charge. Also using Ground penetrating radar survey in corridor with to detect buried
utilities on the map of corridor with information of locations and depths to the top of
various utilities detected. Work to be conducted using 500MHZ and 300MHZ
antenna or latest for the best possible resolution and penetration including hydraulic
testing
Net Total 319.700metre @6893.24/metre 2203768.83
11.004 OD43077/2022-2023
Installation of HDPE -560mm-710mm mm dia PE pipe by horizontal directional
drilling method in all types of soil above /below water table for pumping /gravity
/distribution main including preparing and setting up the plant and equipment,
installing new pipe work, testing and commissioning excluding cost of pipe (6 m line
pipe with butt joint all related civil /mechanical works like entry /exits pit as
necessary. Dewatering, drilling stringing, reaming, pulling back the new pipe on the
designed alignment and monitoring by approved guidance system. wastage of pipes,
proper disposal of drilling fluid /bentonite slurry. Proper back filling pit and holes by
approved borrow material as per specification approved method statement or as
directed by engineer in charge. Also using Ground penetrating radar survey in
corridor with to detect buried utilities on the map of corridor with information of
locations and depths to the top of various utilities detected. Work to be conducted
using 500MHZ and 300MHZ antenna or latest for the best possible resolution and
penetration including hydraulic testing
Net Total 577.500metre @8230.88/metre 4753333.20
12 Construction of manholes
12.001 OD43045/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy duty CI manhole
cover with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth 1.5m ( internal dia-1200mm)
Net Total 136.000no @54266.05/no 7380182.80
12.002 OD43046/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth 2.5m ( internal diameter 1200m)
Net Total 77.000no @71678.26/no 5519226.02
12.003 OD43047/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth 3.5m ( internal diameter - 1500mm )
10221495.1
Net Total 71.000no @143964.72/no 2
12.004 OD43048/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth upto 4.5m ( internal diameter-1500mm)
Net Total 25.000no @183683.02/no 4592075.50
12.005 OD43049/2022-2023
Constructing manholes of different depths as per drawings and specifications on
sewer lines and provided with tight fitting approved make heavy CI manhole cover
with frame 600 mm dia, embeded into the cover slab, providing provision of
encapsulated PVC/CI foot rests @ 30 cm apart in a staggered manner, bottom slab,
side wall and cover slabwith RCC M30 with a provision of PCC 1:3:6, 10 cm thick
below floor slab, inside to be plastered with CM. 1:3, 12mm thick one coat with a
neat cement flushing coat, two coats of anticorrossive bituminous paint to the outside
surfaces, providing benching and channelling inside the manhole with CC M30 as per
drawings and specifications. The rate shall include earthwork excavation for all leads
and lifts, backfilling, de-watering, side protection with steel shoring, provision of pipe
connection for inlet, outlet and service connection pipes, providing danger lights,
barricades etc.and disposing the surplus earth away with all leads and lifts as directed
upto manhole depth upto 5.50m (internal diameter-1500mm)
Net Total 31.000no @221055.57/no 6852722.67
14.004 5.3.2.a
Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified grading
premixed with a bituminous binder (VG 30), transported to the site, laid over a
previously prepared surface with paver finisher to the required grade, level, and
alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired
compaction For Grading II - (19 mm nominal size)
Net Total 1106.100cum @7845.94/cum 8678394.23
14.005 5.2.a
Providing and applying tack coat with bitumen emulsion( RS) using emulsion
pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous
surface cleaned with mechanical broom.
Net Total 22122.000sq m @10.84/sqm 239802.48
14.006 5.6.2.a
Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing
an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level, and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects For Grading - II (13.2
mm Nominal Size)
Net Total 663.660cum @12044.49/cum 7993446.23
14.007 5.1.a
Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface
of granular Base including clearing of road surface and spraying primer at the rate of
0.70 - 1.0 kg/sqm using mechanical means.
Net Total 22122.000sq m @66.78/sqm 1477307.16
16107450.0
Heading Total(Rs) 0
GENERAL ABSTRACT
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 564
Rounded Total(Rs)
236306079.8
7
Rupees Twenty Three Crore Sixty Three Lakh Six Thousand Seventy Nine
DETAILED ESTIMATE
Draft #1 of File KWA/WASCON/AEE V/KKD-B1/2022 Approved by Chief Engineer (Sewerage,PPD & Wascon) on 09-Nov-2022 05:04 PM - Page 565
1.002 15.43.2
Dismantling manually / by mechanical means including stacking of serviceable
material and disposal of unserviceable material within 50 metres lead as per direction
of Engineer -in-Charge:Bituminous road
Laying of sewer network
Sewer 1 8282.400 1.000 8282.400
Inspection
chamber to 1 2565.000 0.600 1539.000
manhole
Total 9821.400
Total Quantity in sqm 9821.400
1.003 15.2.1
Demolishing cement concrete manually / by mechanical means including disposal of
material within 50 metres lead as per direction of Engineer - in-Charge.Nominal
concrete 1:3:6 or richer mix (i/c equivalent design mix)
Laying of sewer network
Demolishin
g o f cement
concrete ( 1 190.000 1.000 0.150 28.500
Municipality
roads)
Inspection
Chamber to 1 128.000 0.600 0.150 11.520
Manhole
pm 1 100.000 0.600 0.150 9.000
Total 49.020
Total Quantity in cum 49.020
1.004 100.8.2
Fencing 1.50m high with two rows of casuarina poles (girth 15cm to 24cm) tied with
coir yarn on vertical casuarina pole (girth 15cm to 24cm) fixed at 1.5m intervals.
Laying of sewer network
sewer 1 8282.400 0.600 4969.440
Inspection
Chamber to 1 2565.000 0.600 1539.000
Manhole
pumping main 1 560.000 0.600 336.000
Total 6844.440
Total Quantity in metre 6844.440
1.005 100.8.1
Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape
in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
Laying of sewer network
Sewer 1 8282.400 0.200 1656.480
Inspection
Chamber to 1 3420.000 0.200 684.000
Manhole
Total 2340.480
Total Quantity in metre 2340.480
1.006 100.1.1
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of
50m, in all kinds of soil.
Laying of sewer network
Quantityfro
1 11042.374 0.8000 8833.899
m calculation 00
sheet
Inspection 0.8000
Chamber to 1 2565.000 0.600 1.100 1354.320
00
Manhole
10188.21
Total 9
10188.21
Total Quantity in cum 9
1.007 100.1.2
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in all kinds of soil.
Laying of sewer network
Quantity from 0.8000 2374.812
1 2968.515
calculation sheet 00
Total 2374.812
Total Quantity in cum 2374.812
1.008 100.1.5
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including
getting out the excavated soil, and then returning the soil as required, in layers not
exceeding 20cm in depth, including consolidating each deposited layer by ramming,
watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50
m, in Ordinary Rock.
Laying of sewer network
Quantity from 1 11042.374 0.2000 2208.475
calculation sheet 00
Inspection
Chamber to 1 3420.000 0.600 1.100 0.2000 451.440
00
Manhole
Total 2659.915
Total Quantity in cum 2659.915
1.009 100.1.6
Excavating trenches of required width for pipes, cables, etc., including excavation for
sockets, and dressing of sides, ramming of bottoms, depth exceeding 1.5m but not
exceeding 3m, including getting out the excavated soil, and then returning the soil as
required, in layers not exceeding 20cm in depth, including consolidating each
deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as
directed, within a lead of 50m, in Ordinary Rock.
Laying of sewer network
Quantity from 0.2000
1 2968.515 593.703
calculation sheet 00
Total 593.703
Total Quantity in cum 593.703
1.010 2.17.2
Close timbering in case of shafts, wells, cesspits, manholes and the like including
strutting, shoring and packing cavities (wherever required) etc. complete
(Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not
exceeding 3 m
Laying of sewer network
2 1493.000 2.250 6718.500
Total 6718.500
Total Quantity in sqm 6718.500
1.011 2.23
Extra for planking and strutting in open timbering if required to be left permanently in
position (Face area of the timber permanently left to be measured).
planking
1 750.000 2.800 2100.000
Total 2100.000
Total Quantity in sqm 2100.000
1.012 5.1.3
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
Laying of sewer network
RCCbeddin
g concrete where 1 2000.000 0.600 0.100 120.000
ever necessary
Total 120.000
Total Quantity in cum 120.000
1.013 100.98.226
Supply of PVC Pipe, 8kg/cm2, 160mm Dia.
Laying of sewer network
MH to IC 1 3420.000 3420.000
Total 3420.000
Total Quantity in metre 3420.000
1.014 100.9.9
Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already
made, placing in position aligning the pipeline to the lines and levels and jointing the
pipes and specials with solvent cement and testing the pipeline with water to the
required test pressure (excluding cost of pipes and specials): 110 mm nominal outside
diameter pipes.
Total 802.700
Total Quantity in metre 802.700
1.018 4.1.2
Providing and laying in position cement concrete of specified grade excluding the cost
of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2 coarse
sand : 3 graded stone aggregate 20 mm nominal size)
Laying of sewer network
Demolishin
g o f cement
concrete ( 1 190.000 1.000 0.100 19.000
Municipality
roads)
Inspection
Chamber to 1 104.000 0.600 0.100 6.240
Manhole
Total 25.240
Total Quantity in cum 25.240
1.019 7.6.1
Coursed rubble masonry (first sort) with hard stone in foundation and plinth
with:Cement mortar 1:6 (1 cement : 6 coarse sand)
Laying of sewer network
Culvert regions / 1 8.000 0.400 0.450 1.440
RR portions
8 6.000 0.450 0.450 9.720
Total 11.160
Total Quantity in cum 11.160
1.020 5.1.2
Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size
Laying of sewer network
Anchor required 50 0.700 (0.5+0.8)/2 0.700 15.925
Total 15.925
Total Quantity in cum 15.925
1.021 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more
Laying of sewer network
60.000
steel 1 15.900 954.000
000
Total 954.000
Total Quantity in kilogram 954.000
1.022 OD36603/2022-2023
Supplying, Providing bedding with m sand for sewer lines as per specifications to be
laid wherever
necessary with all lead and lift.
Laying of sewer network
Beding for lines 1 2000.000 0.800 0.100 160.000
Total 160.000
Total Quantity in cum 160.000
1.023 OD36606/2022-2023
Supply of PE Pipe PE 100 (IS 14333), 8kg, 250mm Outer Dia
Laying of sewer network
1 1399.300 1399.300
Total 1399.300
Total Quantity in metre 1399.300
1.024 OD36604/2022-2023
Supply of PE Pipe PE 100 (IS 14333/ sewerage pipe with latest IS), 8kg, 200mm
Outer Dia.
Laying of sewer network
1 7152.000 7152.000
Total 7152.000
Total Quantity in metre 7152.000
1.025 OD36605/2022-2023
Supply of PE Pipe, PE100, PN8, 400mm dia, conforming to IS 1433 (Sewerage Pipe)
Laying of sewer network
1 191.500 191.500
Total 191.500
Total Quantity in metre 191.500
1.026 OD36607/2022-2023
Supply of PE Pipe, PE100, PN8, 450mm dia, conforming to IS 1433 (Sewerage Pipe)
Laying of sewer network
1 120.400 120.400
Total 120.400
Total Quantity in metre 120.400
1.027 OD36609/2022-2023
Supply of PE Pipe, PE100, PN8, 315mm dia, conforming to IS 1433 (Sewerage Pipe)
Laying of sewer network
1 913.000 913.000
Total 913.000
Total Quantity in metre 913.000
1.028 OD36610/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.60m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for levelling course below foundation including earth work
excavation in all classes of soil,, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 100.000 100.000
Total 100.000
Total Quantity in cum 100.000
1.029 OD36611/2022-2023
Conveying to site, lowering into trenches, laying to correct line and grade using CC
holding clamps, 160mm PVC SN 8 (8 Kg/Cm2) S & S Sewerage pipes
conforming to I.S.15328, including jointing the pipes using rubber rings as per
approved methods with rubber gasket for flexible joints as per specification including
cost of gasket, to correct line , de watering with all rates of recuperation etc, providing
bedding for pipe line trenches with available earth, hydraulic testing the line to the
required test pressure as per IS, CPHEEO specifications, lighting, watching, providing
caution boards etc. wherever required, during laying and jointing the pipes including
hire for all tools etc complete including commissioning for the following diamters
Laying of sewer network
1 3240.000 3240.000
Total 3240.000
Total Quantity in metre 3240.000
1.030 OD36612/2022-2023
Constructing inspection chambers of size 0.45x0.45m (inside) and 0.45m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, , plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 100.000 100.000
Total 100.000
Total Quantity in no 100.000
1.031 OD36613/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.90m deep with
RCC M20 using
20mm broken stone for floor slab ,RCC M20 slab using 20mm broken stone for
removable cover slab,
Brick work in CM 1:6 for walls, PCC 1:4:8 using 20mm broken stone for leveling
course below foundation
including earth work excavation in all classes of soil, plastering the inside with CM
1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing
provision for connecting main sewer and service connections, conveying, lifting,
placing the cover slab in
position by suitable means, conveying and disposing the surplus earth with all lead and
lift as per
drawings and specifications , including the cost of reinforcement , testing the chamber
and sulphate
resistant cement shall be used for the the construction of inspection chamber
Laying of sewer network
1 213.000 213.000
Total 213.000
Total Quantity in no 213.000
1.032 OD36614/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.60m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 100.000 100.000
Total 100.000
Total Quantity in no 100.000
1.033 OD36615/2022-2023
Constructing inspection chambers of size 0.60x0.60m (inside) and 0.75m deep with
RCC M20 using 20mm broken stone for floor slab ,RCC M20 slab using 20mm
broken stone for removable cover slab, Brick work in CM 1:6 for walls, PCC 1:4:8
using 20mm broken stone for leveling course below foundation including earth work
excavation in all classes of soil, plastering the inside with CM 1:3, 9mm thick with
neat cement flush coat, providing necessary slope in the benching towards main sewer,
providing provision for connecting main sewer and service connections, conveying,
lifting, placing the cover slab in position by suitable means, conveying and disposing
the surplus earth with all lead and lift as per drawings and specifications , including
the cost of reinforcement , testing the chamber and sulphate resistant cement shall be
used for the the construction of inspection chamber
Laying of sewer network
1 100.000 100.000
Total 100.000
Total Quantity in no 100.000
1.034 OD36616/2022-2023
Providing and drilling with Horizontal drilling machine and air compressor for
inserting 800 mm MS casing pipe through the hole formed including cost of pipes,
cost of mobilization installation and all labour charges etc.
Laying of sewer network
NH Crossing 1 20.000 20.000
Total 20.000
Total Quantity in metre 20.000
1.035 100.7.1
Bailing out water with 5HP engine and pump set including conveyance to the site,
erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil
and other stores pay of staff etc., complete.
Bailing out of water with 5HP engine and pump set
21447.50
50 5*0.746 115.000 0
21447.50
Total 0
21447.50
Total Quantity in Kwh 0
2 Road Restoration work of laying of sewers and pumping main.
2.001 OD36628/2022-2023
Excavation for roadwork in soil with hydraulic excavator of 0.9Cum bucket capacity
including cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections and transporting to
the embankment location within all lifts and lead up to 1000m
Road restoration work of laying of sewers and pumping
sewer-
Corporation 1 2217.000 2.500 0.300 1662.750
roads
Manhole to
inspection 1 686.000 1.200 0.300 246.960
chamber
Total 1909.710
Total Quantity in cum 1909.710
2.002 OD67229/2022-2023
MoRD-Spec.No:4.1.A.1.
Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with smooth wheel roller to achieve the
desired density, complete as per Technical Specification Clause 401.
(i) For Grading I Material+cost index
granular sub base
open cut 1 2217.000 2.500 0.200 1108.500
ic to mh 1 686.000 1.000 0.200 137.200
Total 1245.700
Total Quantity in cum 1245.700