Professional Documents
Culture Documents
Sarana - 01
HARGA SUB TOTAL
NO JENIS PEKERJAAN VOL SAT.
RP RP
III KONSTRUKSI JALAN PAVING BLOCK, t = 37 cm m2
Galian badan jalan + buang ex galian ± 0 – 1 km 0,50 m3 35.000,00 17.500,00
Perapian + pemadatan subgrade ( pembentukan kemiringan ) 1,00 m2 4.500,00 4.500,00
- Base course B ex sidomanik t 18cm + pemadatan 1,00 m2 31.500,00 31.500,00
Pasir urug t=4cm 1,00 m2 7.500,00 7.500,00
Paving block t=8cm ex kariyadinamika 1,00 m2 135.000,00 135.000,00
- Test CBR 0,05 ttk 85.000,00 4.250,00
Subgrade ad > 95% CBR min 6% -
CBR base course B > 60% -
CBR base course A > 80% -
- Test gradasi bahan subbase A 1,00 tls 1.500,00 1.500,00
SUB TOTAL III 201.750,00
Sarana - 02
HARGA SUB TOTAL
NO JENIS PEKERJAAN VOL SAT.
RP RP
VI SALURAN BATU KALI, 40X30cm ( lingkungan ) m1
Galian 0,14 m3 35.000,00 4.900,00
Batu kali belah 0,09 m3 180.000,00 16.200,00
semen cibinong 50kg/zak 0,43 zak 60.000,00 25.800,00
pasir beton 0,11 m3 220.000,00 24.200,00
Alat bantu profil , benang 1,00 ls 500,00 500,00
Upah pasang 1,00 ls 10.800,00 10.800,00
SUB TOTAL VI 82.400,00
Sarana - 03
HARGA SUB TOTAL
NO JENIS PEKERJAAN VOL SAT.
RP RP
X SALURAN UDITCH, 1000X1000 MM / M1
Galian 1,00 m3 35.000,00 35.000,00
Pemadatan tanah 1,00 m2 5.000,00 5.000,00
Uditch 1x1 ex dusaspun 1,00 m1 1.080.000,00 1.080.000,00
lantai kerja / bantalan 0,05 m3 550.000,00 27.500,00
Sirdam t 7,5cm 0,08 m3 180.000,00 13.500,00
Urug tanah kembali 0,04 m3 5.000,00 200,00
Buang tanah sisa galian 1,00 m3 10.000,00 10.000,00
upah pasang excavator 1,00 m1 25.000,00 25.000,00
upah pasang tenaga 1,00 m1 15.000,00 15.000,00
SUB TOTAL X 1.211.200,00
Sarana - 04