MICOPERI

HEAVY LIFTING
Client Project Description Location Completed Services

Nené Phase 2A - Offshore Installation Campaign for Platforms and Multiphase Export /
ENI CONGO S.A. Offshore Congo Ongoing E-P-C-I-T-DO-RO
Intrafield Sealines

ILVA Removal and dismantling of DM7 crane Port of Taranto - Italy 2016 D-T-DO-RO

SAIPEM Fauzia Project - Fauzia Deck installation Adriatic Sea - Offshore Italy 2014 E-C-I

COSTA CROCIERE Costa Concordia ship wreck removal Tyrrhenian Sea - Italy 2014 E-P-C-I-DO

SAIPEM Elettra Project - Elettra Deck installation Adriatic Sea - Offshore Italy 2014 E-C-I

Crane vessel activities and support works in connection with the installation of Elettra
SAIPEM Adriatic Sea - Offshore Italy 2014 I
jacket

SAIPEM Crane vessel activities and support works in connection with the installation of Fauzia jacket Adriatic Sea - Offshore Italy 2014 I

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

Guendalina platform and Tea platform 10”+3”+3” risers installation, Sub Sea Spools &
ENI SpA Adriatic Sea - Offshore Italy 2011 E-C-I-T
Mattress Installation

Denise-B Development Project: umbilical laying and submarine structures The umbilical is
approximately 6,3 Km long in two pieces, fully buried and connected to various SUTU. Part
PMS Egypt Mediterranean Sea - Offshore Egypt 2011 E-I-T
of the scope is also the metrology, fabrication and installation of three 6” steel spools
connecting three Gas Wells to the Tees valves of an existing 16” pipeline

Bonaccia Est Field Project: Bonaccia-Bonaccia Est 6” sealine laying, Bonaccia-Bonaccia Est
ENI SpA control umbilical installation (6.7 km). 6” steel spool connecting the Well Head to the Adriatic Sea - Offshore Italy 2010 E-C-I
pipeline

Tuna Field : transportation and installation of tuna platform (jacket & deck), ssiv, umbilical,
PETROBEL Mediterranean Sea - Offshore Egypt 2010 E-P-I-T
sub-sea spools, leak test and line dewatering

Port Fouad Gas Field: Installation of Deck (including shallow water diving works), Cold vent,
PETROBEL/PMS Mediterranean Sea - Offshore Egypt 2010 E-I-T
Stair and ladders, underwater 10” riser

Izabela Field Development Project -Sealines Laying: Izabela N to Ivana K (16”, 26km long) &
ED-INA d.o.o. Izabela N to Izabela S (10”+3”, 2,97km long). Part of the scope was a Power Cable 3,1 Km Adriatic Sea - Offshore Croatia 2010 E-P-I
long laid and buried between the two platforms Izabela North and Izabela South

Temsah Gas PLEM Replacement – Preliminary Activities, Lifting Activities, Sub Sea Spools &
PETROBEL/PMS Mediterranean Sea - Offshore Egypt 2009 E-P-I-T
Mattress Installation and Start-Up Operations

PETROBEL/PMS North Bardawil 14” Closing Spool Installation Mediterranean Sea - Offshore Egypt 2009 E-P-I-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

PETROBEL/PMS Temsah-4 Vibro Hammering Services Mediterranean Sea - Offshore Egypt 2009 E-P-I-T

Subsea Tapping on 14” - 24” and 32”.


PETROBEL/AGIP Mediterranean Sea - Offshore Egypt 2009 E-I
Stopple & Folding Stopple Operation

SSIV 32”/24” Valve Skid Off-shore Transportation Sub Sea Installation. Sub Sea Spools &
PETROBEL/PMS Mediterranean Sea - Offshore Egypt 2008 E-P-I-T
Mattress Installation

North Bardawil Riser & J-tubes off-shore Transportation & Installation & Barboni-1 decks
PETROBEL/PMS Mediterranean Sea - Offshore Egypt 2008 E-P-I-T
Upgrading & Skids Installation. Closing Spools Installation

PETROBEL/PMS Thekah North Project: Installation and Transportation of Monopod Jacket and Deck Mediterranean Sea - Offshore Egypt 2008 E-I-T

PETROBEL/PMS Thekah 2 Project: Installation and Transportation of Monopod Jacket and Deck Mediterranean Sea - Offshore Egypt 2008 E-I-T

PETROBEL/PMS Thekah PLEM-1 Base Frame Transportation & Sub Sea Installation Mediterranean Sea - Offshore Egypt 2008 E-I-T

PETROBEL/PMS Thekah PLEM-2 Base Frame Transportation & Sub Sea Installation Mediterranean Sea - Offshore Egypt 2008 E-I-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

INAgip d.o.o ANA, VESNA & IRINA monopod jackets installation Adriatic Sea - Offshore Croatia 2008 E-I-T

PETROBEL/PMS Semman Offshore Oil Field: Deck and Flare Installation Mediterranean Sea - Offshore Egypt 2007 E-I

ENI SpA Tea Platform Deck and Helideck Installation Adriatic Sea - Offshore Croatia 2007 E-I

EDISON Alba Marina FPSO 8” Flexible Hose Sub Sea Replacement Adriatic Sea - Offshore Italy 2007 E-I

Cavendish Gas Field: Installation Platform and subsea pipeline 10” + 3” 45 km (including Sub North Sea
RWE 2007 E-P-C-I
Sea Spools & Mattress) Southern Sector

Didon ptf. Offshore installation of the production jacket, topside drilling and production
MP ZARAT Tunisian Offshore 2006 E-P-I
platform, inst. & hook up

INAgip d.o.o Katarina Jacket/Deck Installation Adriatic Sea - Offshore Croatia 2006 E-I

EDISON Installation of 2 new conductors and work-over activities on RSM-A ptf. Italian Offshore 2006 E-I

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

APISOI SERVICE Single mooring buoyancy tank Adriatic Sea - Offshore Italy 2005 E-P-C-I-D-T

MADISON OIL TURKEY Guardian sleeve installation Black Sea 2005 E-I

Mediterranean Development Projects:


PETROBEL Hook up activities, PLEM and Closing Spools Installation on Akhen, Temsah 4 and Barboni Mediterranean Sea - Offshore Egypt 2005 E-I
Platforms

INAgip d.o.o Marica and Barbara T2 ptf. SSIV sub sea Installation and spools installation Adriatic Sea - Offshore Croatia 2004 E-P-I

INAgip d.o.o Marica ptf. deck, helideck and cold vent installation Adriatic Sea - Offshore Croatia 2004 E-P-I

INAgip d.o.o IDA C monopod jacket installation Adriatic Sea - Offshore Croatia 2004 E-P-I

Marica ptf. jacket installation:


INAgip d.o.o Adriatic Sea - Offshore Croatia 2004 E-P-I
Conductor pipes - foundation piles boat landing - transition module

BECHTEL (BG TUNISIA) Miskar ptf. shutdown (preparatory to the installation of the Compression Module) Tunisian Offshore 2003 E-C-I-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

POSIDONIA Lifting and installation of cages for fish farming - Ortona Adriatic Sea - Offshore Italy 2002 E- I

HARRIS CO. - U.S.A. Ocean Net Buoy – 2 risers repair Mediterranean Sea - Offshore Italy 2002 E-C

Clamps and J-tube installation on Vega A ptf.; clamps and risers installation on SPM, Vega
EDISON Mediterranean Sea - Offshore Italy 2002 E-I
Oil tank; flexible pipe laying between Vega A ptf. and Vega Oil tank

AGIP GAS BV LIBYAN BRANCH Installation of pre-drilling Template Mediterranean Sea - Offshore Libya 2002 E-I

Installation of Davide 7 ptf


NAVALMARE (ENI-AGIP) Adriatic Sea - Offshore Italy 2002 E-I
Hiring of personnel during hook-up phases on Davide ptf. and Davide 7 ptf

ENI SpA Mechanical modifications on Barbara F platform after work-over Adriatic Sea - Offshore Italy 2001 E-I

HARRIS CO. - U.S.A. Communication system positioning at 2.175 m water depth Mediterranean Sea - Offshore Italy 2001 E-I

SAIPEM Deck and Helideck installation on Naomi-Pandora platform Adriatic Sea - Offshore Italy 2001 E-I

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

ENI SpA Rigging activities on Barbara F platform to receive FMWR system Adriatic Sea - Offshore Italy 2000 E-I

ENI SpA Sub Sea Recovery activities of protection structures on Lavinia 3 underwater well Ionian Sea - Offshore Italy 2000 E-I

ENI SpA Hook-up of Calpurnia-Clara Est platforms Adriatic Sea - Offshore Italy 2000 H

Offshore spread hiring (DLB M30 and AHT “Pineto”) for Ivana Field Offshore Installation
SAIPEM Croatian OffShore 2000 E-I
Project – Phase II

ENI SpA Hook-up, electrical and instrumental works on Annalisa and Brenda platforms Adriatic Sea - Offshore Italy 2000 E-I

ENI SpA Recovery activities on Garibaldi C platform structures after work-over Adriatic Sea - Offshore Italy 2000 E-I

ENI SpA Maintenance, improvement and mechanical modification on-offshore structures Adriatic Sea - Offshore Italy 2000 E-C-I

ENI SpA Dismantling, recovery and removal of no.18 platforms Adriatic Sea - Offshore Italy 1999 D-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

INAgip d.o.o Jacket and Deck Installation on Ivana platform Adriatic Sea - Offshore Croatia 1999 E-I

ENI SpA Construction and Installation of Fabrizia platform Adriatic Sea - Offshore Italy 1998 E-P-C-I-T

SAIPEM Platform Installation Adriatic Sea - Offshore Italy 1997 E-I

AGIP Dismantling of Offshore Structures Adriatic Sea - Offshore Italy 1996 D

AGIP Cranes Removal and Installation on board Offshore Structures Adriatic Sea - Offshore Italy 1996 E-I

ELF IDROCARBURI ITALIANA SPA Coil Tubing Offshore Platform Adriatic Sea - Offshore Italy 1995 E-I

POSIDONIA Installation of a 700 tons jacket and 300 tons deck Adriatic Sea - Offshore Italy 1995 E-I-T

AGIP Removal of PCWA - PCWB - RMA - PC25 platforms Adriatic Sea - Offshore Italy 1995 E-D-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

MOLINO ALIMONTI Removal and transportation to quay of a 250 tons steel structure Adriatic Sea - Offshore Italy 1995 E-D-T

ELF IDROCARBURI ITALIANA SPA Offshore Heavy Lifting Adriatic Sea - Offshore Italy 1994 E-I

SUCOR Transportation and installation of FA Platform and piles engineering and fabrication South Africa 1991 E-C-I-T

SONANGOL Transportation and installation of Impala Platform Angola 1990 E-I-T

CONOCO PHILLIPS Engineering, transportation and installation of Jolliet Platform Gulf of Mexico 1989 E-I-T

SHELL Campos Basin – Engineering, transportation and installation of Merlouza Platform Campos Basin – Brasil 1989 E-I-T

Polo North East


PETROBRAS Polo Nord Este – Transportation and installation of no. 7 platforms 1988 E-P-C-I -T
Campos Basin – Brasil

Oseberg 2 topside:
NORSK HYDRO Engineering, transport and installation of M 10 - L 00 - M 20 - COB - M 30 - M40 - M50 - M North Sea - Offshore Norway 1987 E-I-T
60 - FOO modules

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV


MICOPERI
Client Project Description Location Completed Services

Togi Troll East installation:


NORSK HYDRO North Sea - Offshore Norway 1987 E-I-T
54 x 35 x 13 mts. template 1,250 M.T. weight. N. 4 48” dia. piles 72 mts long

Veslerfrikk platform:
Four legged jacket 9.800 MT weight
STATOIL North Sea - Offshore Norway 1987 E-P-C-I
185 mts height 60x60 mts base
20 x 20 mts top

PETROBRAS Campos Basin – Transportation and installation of Cherne II Platform Campos Basin – Brasil 1982 E-P-C-I-T

PETROBRAS Campos Basin – Transportation and installation of Garoupa Platform Campos Basin – Brasil 1980 E-P-C-I-T

PETROBRAS Campos Basin – Transportation and installation of Enchova Platform Campos Basin – Brasil 1979 E-P-C-I-T

E = Engineering - P = Procurement - C= Fabrication - I= Installation - H= Hook-Up - D= Decommissioning - T= Transportation - DO=Diving - RO=ROV