Professional Documents
Culture Documents
FORM From
من
Alharthyh ltd co
Discipline التخصص □ Civil/Str. إنشائي/مدني □ Architectural معماري □ Electrical كهرباء □ Mechanical ميكانيكا
Consultant’s
Comments
مالحظات
الستشاري □ Approved □ Approved with Comments □ Revise and Resubmit □ Rejected □ Received for Information
موافقة موافقة مع مالحظات مراجعة وإعادة تقديم مرفوض نسخة منقحة للمعلومية
Approved by Consultant’s Discipline Engineer Approved by Project Manager
يعتمد من مهندس القسم لالستشاري يعتمد من مدير المشروع لالستشاري
Distribution Copy to نسخة إلى □ Contractor المقاول □ ZATCA EPMO Representative ممثل إدارة المشاريع بالجمارك السعودية
Note: These documents have been reviewed for general conformity with Contract terms & هذه.تمت مراجعة هذه المستندات للتوافق العام مع شروط وأحكام العقد والمواصفات وجداول الكميات :مالحظة
conditions, the specifications and bill of quantities. Such review doesn’t relieve the المراجعة ال تعفي المقاول من مسؤولياته التعاقدية بموجب شروط العقد وال تعتبر موافقة على أي
Contractor of his responsibilities under the terms of the Contract and shall not be deemed
as approval for any further compensation or permission to carry out additional works. .تعويض إضافي أو إذن لتنفيذ أعمال إضافية
Revision Section /
Revision Date Description and reason for amendment
No Page
00
01
02
03
04
05
06
Controlled Documents
All document control records for the OHS Construction Management Plan shall
be maintained by OHS Department in compliance with Al-Harthyh Document
Control: and will be made available for auditing purposes at all times.
Approved revisions of this document shall be distributed to all concerned and
shall beinducted or briefed to project employees as a confirmation of
understanding. SiteInduction Records shall dully be signed or filled up,
1. INTRODUCTION .................................................................................................................................................... 8
2. PURPOSE ............................................................................................................................................................... 8
3. SCOPE ..................................................................................................................................................................... 8
7. DEFINITIONS ....................................................................................................................................................... 12
INITIAL ACTIONS........................................................................................................................................................ 36
2. Purpose
The purpose of the Al-Harthyh Project OHS Construction Management Plan
(OHS-CMP) is to provide a system and strategy that enables its Occupational
Health and Safety policies and objectives to be achieved via successfully
performing the project work in compliance with ZATCA requirements and the legal
requirements of the Kingdom Of Saudi Arabia.
This OHS-CMP defines the execution strategy and methodologies for
implementation of the aforementioned requirements. It is designed to
complement the Project execution Plan and Schedule and provide a disciplinary
framework for management of aspects of OHS for the project.
This is a "live document "and shall be updated periodically as the Project
progress further.
3. Scope
This Program outlines the Health and Safety activities to be performed by Al-
Harthyh within the scope of the ZATCA works for the Contract “Durrah LP
Infrastructure Development & Improvement”.
The main objective of this plan is to drive OHS improvement throughout the
contract in all Serious Services locations in a consistent manner and to ensure that
the OHS performance targets set out in this plan are achieved through action items
planned.
Achieve continuous improvement of OHS culture
Attain improvement in Safety through the agreed action items from
workshop and meetings with client and Sub-contractors.
Manage sub-contractors/vendors more effectively for the minimization of
incidents through hazard elimination and control measures.
Training to ensure competent workforce.
Meeting the Key Performance Indicators (KPI) targets.
4. Project description
Project Title
Contractor’s Details
Company : Al-Harthyh
Telephone : 0598552135
00 20/07/2022
5.1. Location:
The land port is about 5 km from the town of Haql
and it is implemented in a narrow platform between
the Red Sea and the steep elevations along the
cost. To the North, Aqaba’s phosphate terminal
located in Jordan is the most important industrial
activity in the region.
Coordinates:
689790.91 m E , 3247865.18 m N
00 20/07/2022
00 20/07/2022
Ramadan
During the Ramadan period working hours will be sapecified according the memorandam
that will issued between ZATCA and Al-Harthyh. Eating food in the public areas is strictly
prohibited.
00 20/07/2022
7. DEFINITIONS:
00 20/07/2022
The air, land or water within the vicinity of the Project that may
07 Environment be exposed and vulnerable to adverse impacts potentially
arising from non-compliant environmental emissions.
Any one-time treatment and any follow-up visit for the
purpose of observation of minor scratches, cuts, burns,
splinter and so forth, which do not ordinarily require medical
08 First Aid Case
care. Such a one-time treatment and the follow-up visit for
the purpose of observation are considered first aid although
provided by a physician or registered medical professional.
The inherent property or ability of something to cause harm:
The potential to interrupt or interfere with a process or person,
09 Hazard
which is or may be casually related to an incident by itself or
with other variables.
Overall HEALTH AND SAFETY goal, arising from the H&S
10 H&S Objectives Policy, that the project sets itself to achieve, and which is
quantified where practicable.
11 H&S Performance Measurable results of the H&S Management System.
Statement by the company of its intentions and principles in
relation to its overall H&S performance which provides a
12 H&S Policy
framework for action and for the setting of H&S objectives and
targets.
Detailed performance requirement, quantified where
practicable, applicable to the project’s parts thereof, that
13 H&S Targets
arises from the H&S objectives and that needs to be set and
met in order to achieve those objectives.
Use of open flame, other heat sources and/or spark
14 Hot Work producing devices where there is a potential for explosion or
fire.
An unplanned, undesired event that can result in physical
harm and/or property damage, usually resulting from contact
15 Incident
with a source of energy above the ability of the body or
structure to withstand it or be a near miss or error.
A before-the-loss program designed to identify and correct
16 Loss Prevention potential causes of incidents before they result in actual
injuries or financial loss.
A lost time injury (LTI) is an injury sustained by an employee
17 Lost Time Incident that will ultimately lead to the loss of productive work time in
the form of worker delays or absenteeism. An injury is
considered a lost time injury only when the worker is unable
00 20/07/2022
to perform the regular duties of the job, takes time off for
recovery, or is assigned modified work duties for the recovery
period.(Any absence from the work-related
fatalities,permanent total disabilities, permanent partial
disabilities and lost work day cases)
The total number of calendar days on which the injured
18 Lost Workdays person was temporarily unable to work as a result of a lost
time incident.
Works that is essential to the safe operation of the project or
19 Major Work location, and works that would be necessary to control any
threat to the project, location, or personnel.
Is an occupational injury/illness which is not classified as a
lost time injury, but which results in loss of consciousness or
medical treatment other than first aid. Example, Loss of
Medical Treatment
20 consciousness due to lack of oxygen/heat
Case
induced/electrocution/head injury, penetrating eye injury,
chemical or hot burns, fracture not resulting from lost time
injury, etc.
Safety Data Sheet Identifies the hazards, proper procedures and emergency
21
(SDS) treatment for a particular chemical.
Near Miss/Near Hit Incidents with no injury, property damage, but having the
22
potential to cause it. This could include an unsafe act.
A failure to satisfy a requirement specified in the OHS-CMP,
23 Non-Conformance
or applicable regulation or procedures.
A job that is performed once or less time per month or a job
24 Non-Routine Job
whereby the job hazards significantly change with its location.
Individuals who are employees, contractors, customers,
25 Personnel
and/or vendors of Al-Harthyh .
A rule, ordinance, law, legal regulation or device by which
26 Regulation
conduct or performance is controlled.
A hazard identification tool comprising of a document
27 Risk Assessment containing a list of basic job steps, hazards identified with the
job steps and the mitigating measures.
The probability that a hazard will result in injury or loss, with
28 Risk
definable consequences.
Freedom from unacceptable risk or harm (or a judgment as
29 Safety
to the acceptability and tolerability of risk).
00 20/07/2022
00 20/07/2022
Safety Awards
00 20/07/2022
00 20/07/2022
00 20/07/2022
PROJECT Manager'PM'
The Project Manager has overall OHS responsibility for the project,
ensuring that all aspects of the OHS-CMP are implemented and
adhered to. He shall ensure that all possible measures are taken to
protect and promote the health, safety and welfare of the workforce
and to protect the environment. Specifically, the Project Manager shall
be responsible towards OHS for:
a. The application of applicable laws, regulations and procedures
related to:
Site safety and security
Fire prevention
Health and hygiene
Housekeeping
OHS implementation and enforcement
b) Allocating sufficient resources for all OHS requirements.
d) Ensuring that an induction program covering all Project activities,
adequate and all staff received induction training.
f) Ensure that all incidents are investigated, reported,
recorded and closed out.
g) Ensure that all persons under his control have OHS awareness,
implement it and are equipped with appropriate PPE relevant to
the tasks being performed.
00 20/07/2022
00 20/07/2022
Safety Supervisor/Foreman
Reports to the Project OHS Engineer and project Manager
Roles &Responsibilities:
Participate in the OHS activities including auditing, sampling and
inspection.
Inspect the respective construction areas daily to make sure that
the work carried out are in compliance with Project OHS
Procedures and other applicable documents and report inspection
result to OHS Engineer and PM.
To be responsible for the training of new hires and all levels of
personnel on OHS matters, with a specific attention to particularly
hazardous tasks.
To actively participate in the investigation of all incidents, accidents
and near misses
Attend JSA meetings for jobs pertaining to their assigned areas
Take action and report immediately to the Project Manager in case
of dangerous actions and/orsituations.
To be of constant advisor on the field for any problem related to
OHS for all the personnel.
To actively participate in the weekly toolbox meetings and support
superintendent/supervisor during this activity
To verify on daily basis the correct use of PPE by all the personnel
To participate in the required Safety meetings
To inspect the Fire Fighting and Safety equipment regularly
Carry out and record regular site safety Inspection and audit of site
activities.
00 20/07/2022
Ensure site security, fire security, fire, First Aid and welfare facilities
and procedures appropriate to the works are provided and properly
and maintained
Ensure all agreed safety standards and applicable regulations are
observed.
Investigate all incidents, dangerous occurrences and follow up
near-miss/incidents corrective actions.
Ensure all plant and equipment is fit for purpose, adequately
maintained and possess valid test certificate.
Assist Site Superintendent, Supervisors and foremen in promoting
a Safety prevention spirit withintheir respective work groups,
according to the approved safety programs.
Conduct OHS Monthly OHS Training according to approved
training plan from OHS Engineer.
Conduct TBT to workers and supervisors / Foreman before starting
any new construction activity.
00 20/07/2022
WORKERS/OPERATIVES
All the workmen are responsible for their work also responsible to:
Follow company OHS policy, plan, project OHS and security rules
and regulations, risk assessment controls / work instructions and
procedures without any deviations.
Must undergo site OHS orientations before start of the work.
Follow the OHS instruction given by the supervisor / foreman or
safety officer while working in the hazardous area.
Maintain their work area, dress, and accommodation neat and clean
within acceptable hygienic condition at all the time.
Report all incidents / near misses on time to their supervisors for
corrective action.
Attend tool box talk, special briefings regularly and co-operate in
OHS related issues with their co-workers.
Shall not do any work without work instruction from the concerned
supervisor.
Protecting and minimizing the risk of damage to assets at his work
place.
00 20/07/2022
Al-Harthyh RESPONSIBILITY
Al-Harthyh shall ensure that its Subcontractors are fully aware of
the Project OHS requirements and all OHS procedures during the
execution of the work and shall beresponsible for the OHS
performance of its Subcontractors.
Al-Harthyh shall also set up, maintain and remove, when directed
by the ENGINEER, throughout the course of the contract, Safety
Notice Boards (Safety Signs and Emergency Contact information)
in prominent places on the site for the labor force.
International Standards:
The list of parties likely to be influenced by our scope and nature of project and other stake
holders are provided below.
00 20/07/2022
When a need arises for the engagement of a Sub contractor, the Company shall evaluate their
safety standards, either based on their previous work with the company or from reports available
from elsewhere. The following procedures for selection of a contractor are necessary and should
be established:
1. Specify the work including the technical content, quality, safety conditions and any other
requirements.
2. Prepare a list of contractors who were pre-qualified and are potentially able to fulfill the
conditions.
3. All subcontractors’ workers/staff must first undergo competency test by the project manager
and or the concerned section head.
Then a safety Induction meeting on Project office, Then the Al-Harthyh Safety Officer will
carryout also safety compliance evaluation accordance the Sub-Contractor work in the site.
4. It is imperative that all subcontractor workers abide by Al-Harthyh safety rules and regulations.
5. Any Subcontractor failure to comply with Al-Harthyh Safety procedures/plan will receive heavy
penalties or immediate expulsion from the work site.
6. Select the particular contractor who best fits the Company’s requirements.
7. The contractor’s site performance including Safety & Health requirements will be under
constant surveillance by the Site Manager and Al-Harthyh Safety officer. The detailed
performance will be recorded to PM and OHS Manager weekly based and should also be
observed and discussed by the Project Manager and Workplace Safety & Health Officer.
8. Carry out regular reviews of the contractor’s performance, including safety inspections of
their work and compliance with the Company’s rules & regulations, safe work practices &
procedures etc.
9. Al-Hathyh will keep a register of the contractors, which will include a record of safety
incidentsinvolving contractors in the worksite.
10. All non-compliance with the Safety and Health Regulations or codes of practices will be
recorded with the subcontractor for immediate corrective measures. Failure to comply with
these instructions will result in the subcontractor being removed from the site and being deleted
from the ‘Approved Subcontractor’ listing.
00 20/07/2022
Once the subcontractor has been selected, a contractual agreement between Al-Harthyh and
the subcontractor selected will be prepared and signed by both parties. The agreement will
includea clear scope of works and projects specific requirements for OHS management.
The Projects Manager will hold a contractual agreement meeting where the outline details of the
contract will be discussed and agreed.
Al-Harthyh and the selected subcontractor will be agreeing on the methods of coordination of
subcontractor’s activities, with clear arrangements for communicating OHS information and
requirements to Al-Harthyh and all relevant parties.
All approved subcontractors to carry out works on Al-Harthyh projects will be required to meet
therequirements of the Al-Harthyh OHSMS. They will also comply with the Project OHS-CMP set
by Al-Harthyh, as the Principal Contractor.
00 20/07/2022
12.1. INTRODUCTION
12.2. SCOPE
This procedure is applicable to all OHS hazards arising from the activities,
products and services of Al-Harthyh in conformance to its OHS
Management System based on the requirements of Contract between Al-
Harthyh and its Client (ZATCA).
12.3. OBJECTIVE
00 20/07/2022
12.5. DEFINITIONS
HAZARD INDENTIFICATION
00 20/07/2022
Each operation should identify all OHS hazards within each respective
area together with evidence to show that risks and consequences are
clearly understood.
The hazards shall be reviewed whenever major changes should apply.
All hazards identified shall be fully investigated and evaluated by a
management team, controlled by supervisor of relevant department.
Input from field personnel should be encouraged during identification
evaluation.
CONSULTATION
00 20/07/2022
Final Risk (R2) shall be reduced to a level within the green or yellow zone ≤ 9 for approval and
acceptance of the risk.
A ‘Risk Control Plan’ is an action plans that sets out how the OHS
risks identified in the Risk Assessment will be eliminated and
controlled. Risk Control Plans are developed from risk assessments.
Risk Control Plans may include:
Hazards identified;
Risks associated with the hazards identified;
Existing risk controls;
Proposed short-term controls (including proposed completion
dates);
Proposed medium-term controls (including proposed completion
dates);
Proposed long-term controls (including proposed completion
dates);
00 20/07/2022
A risk register that summarizes their risk assessments and can act as
a management tool for the monitoring and updating of risk
assessment.
The risk register should include all the basic details of the risk
assessment.
Risk assessment reference / number;
Activity;
Control measure;
Timescale;
Action owner; and
Review dates.
The OHS Management Representative shall maintain the OHS Risk Registers (Aspects,
Impacts, and Hazards & Risk) to ensure that any changes to the identified hazards, the level of
risks or risk controls, which was previously establish through risk assessments are included and
updated.
00 20/07/2022
Al-Harthyh shall introduce an Induction Course and shall ensure the participation of all
employees and those of its Subcontractors also the visitors.
The Induction Course shall be specific to personnel and their trade. Shall include, but may
not be limited to:
Toolbox Talk
The Toolbox Talks should be conducted by the Foreman & witnessed by OHS Officer. It
should be held in the morning before work commences. The Toolbox Talk Meetings will
discuss matters on safety issues that are related to the workers and worksite. The workers
will be briefed on related AHA’s and the likely hazards that will be involved in their work.
00 20/07/2022
Records of the Toolbox Meeting will be documented. These will be completed weekly,
however may be more frequent depending on the risk exposure.
Al-Harthyh Project OHS Engineer will ensure that all personnel are aware and trained in their
responsibilities.
Fire Training:
Selected Al-Harthyh employees shall participate in a Basic Fire Training Course, the
contentof which shall be as shown in the Safe Work Practices.
Al-Harthyh Employees and those of its Subcontractors shall participate in a First Aid
Training Course. The ratio of employees participating in first aid training shall be, at
minimum, 1 in 50.
OHS Competence
Jobs like working in confined space, safe lifting and slinging operatives will be given training
to make the aware of risk involved and control measures needed. So after having training
and working for sufficient time onsite the operators will become competent as he will be able
to identify the defects or weakness in work practices and will perform job more safely.
Training Records
The entire training which is conducting at work site shall be recorded. All training records are
being uploaded onto a corporate structure both hard and soft copy for easy access for all
senior managers.
A: In house training;
00 20/07/2022
The investigation shall discuss what went wrong and ways in which work practices can be
improved to avoid such an incident in future, in a blame free atmosphere. For all major incidents
Al-Hrthyh's OHS Safety Engineer/Officer shall be present in the investigation. A full detailed
written report of the investigation findings and proposals for remedial action is to be provided to
Supervision consultant and Project Manager.
Detailed investigations shall be carried out for all serious and major incidents and any minor
incident or near-miss with a high potential of being a major incident.
In the event of any employee being referred to a doctor for further treatment, a brief summary of
that treatment will be obtained from the doctor stating whether,
00 20/07/2022
Investigation team of the incident will involve expertise departmental heads particularly, plant
manager, construction manager, OHS Managers to derive all possible causes and conclude on
its corrective and preventive measures. External specialized third party would be engaged in
investigation works, if the case demands.
Al-Harthyh Project Manager will ensure that all incidents are reported to the OHS team and GM.
OHS Department will review and monitor all incidents reported by subcontractor/s and others
and identify area/s of potential hazards/risks that shall be focussed and problem solved.
Incase of accidents related to Vehicles ,then traffic department must informed to attend to the
site and carry out investigation report that must be submited directly to the Cost Control engineer
in the Al-Harthyh Head office to claim the accident cost to inssurance company.
The investigation team shall be comprising the PM, Safety officer, activity supervisor and their roles and
responsibilities are:
Any safety and health incident occurring at site shall be reported to Al-Harthyh OHS Safety
Officer/Foreman immediately. Al-Harthyh OHS Safety Officer/Foreman shall report OHS
Engineer and Project Manager. Following this a short report shall be prepared by OHS officer
and issued to OHS Engineer and Project Manager, as required report to the appropriate
governmental agencies and authorities’ in line with their requirements.
00 20/07/2022
Al-Harthyh shall issue an Initial Notification Report for the incident within 24 hours
Al-Harthyh shall be issuing report to General Organization For Social Insurance within 72
hoursin case of work related injury occurred.
In the event of a serious incident, Al-Harthyh OHS Safety Officer/Foreman shall conduct a joint
thorough investigation with Al-Harthyh and forward findings and recommendations OHS
Engineer and Project Manager within forty eight hours of the incident.
Initial Actions
a) Questioning the injured person: when an incident happens and someone is injured, the first
priority shall be treatment of the injured person. Sometimes the victim’s condition is such
that immediate questioning shall be avoided to allow the doctor or first aider to make him
comfortable, treat him for shock and attend to the injury.
b) Witnesses and conditions: in any case Al-Harthyh Safety Team/ OHS Engineer shall go
to the scene of the incident and get a fairly complete story from the conditions they find on
arrival.
C) Avoid transferring the Victim’s by Al-Harthyh car to the hospital to avoid any
Complicationsof injury and the victim’s must be transferred by ambulance to governmental
hospital only.
Al-Harthyh employees/staff shall issue a written report per occurrence, for each of the following
Health and safety–related events but not limited to:
a) Any incident/near miss where oil spillage or chemical product/service was released into
the environment.
b) Any incident that may causing a loss of Al-Harthyh or Subcontractor’s asset or
constructionequipment “An event or chain of events that may inflicted physical harm
upon any asset”.
c) Any incident/near miss with the potential to cause an injury or health harm.
The written report shall include the potential consequences on people and the environment in
addition to the real consequences of incidents, near miss and unsafe situations.
We recognize that open, two-way communication between management and staff on health
and safety issues is essential to an injury free, productive workplace. The following system of
communication is designed to facilitate a continuous flow of safety and health information
between management and staff in a form that is readily understandable and consists of one or
more of the following checked items:
00 20/07/2022
New worker inductions will be completed and will consist of safety and health policies and
procedures. This will also include the minimum PPE Requirements.
Review of our safety plan and safety program.
Workplace safety and health training programs.
All related Method Statements & revisions made time to time.
Regular safety meetings.
Effective communication of safety and health concerns between workers and supervisors,
including translation where appropriate.
Posted or distributed information.
OHS Alerts, Notices and Best Practice documents will be developed with photographs
and displayed in Safety Notice boards, used as Toolbox Talks and laminated for use in
welfare areas.
Contractors of Al-Harthyh will be given all Alerts for their internal communication and will
be invited to meet the project team on a regular basis to discuss performance.
A system for workers to anonymously inform management about workplace hazards.
00 20/07/2022
The opportunity will be given to the workforce to raise health and safety issues which may
be of concern via the Subcontractors’ Toolbox Talks, both formal and informal.
ACTION RESPONSIBILITY
Safety Alerts and OHS Best practice & lesson learned OHS Engineer/Deputy
Manager/Officer/Foreman
ACTION RESPONSIBILITY
All accidents and incidents shall be reported immediately. Project Manager/OHS Engineer officer/
Foreman/& all staff.
All OHS plans non-compliance shall be reported according to
OHS Engineer/Officer/ Foreman
the requirements.
Prepare the Monthly Occupational Health performance report
OHS Engineer
and will be submit to GM.
00 20/07/2022
Toolbox Talks will be used as an opportunity for the workforce to be consulted on health and safety
issues as a means of complying with the "Health and Safety Regulations. At all Toolbox Talks,
induction meetings, and training sessions, it will be a requirement that those present are asked to
report any issues related to health and safety that may be of concern.
All high-risk activities will be discussed with concerned personnel before the commencement of
work and the management will record it and action as appropriate.
The objective of group meeting is to assemble persons with particular responsibilities for safety so that
they can formally address issues and take appropriate actions towards the achievement of the objectives
of the Workplace Safety & Health Management System.
The followings are the group meeting by which safety issues are raised for discussion and communication
made to the personnel affected by them. Meetings will be held as per the necessity or as mutually agreed
in the conference room of the Contractors site office.
Workplace Safety, Health & Environment Committee Meeting (Project)
Tool Box Meetings.
As per as request from client OHS meeting with the client or his representative will be held to discuss
progress, issues in relation to safety and health in the work site and all findings or problems in the project.
The agenda shall contain particularly the following:
Introduction.
Confirmation of Minutes of previous meeting.
Review of Minutes of previous meeting.
Progress on actions from the previous meeting.
Findings from Joint Safety Inspection.
Incident record and statistics.
Hazards identified / Risk Assessment.
Any other safety matters, e.g. Public Safety.
Internal communication will be either through Memos, Emails and/or Notice Boards within the Company.
00 20/07/2022
00 20/07/2022
When products, materials, equipment or work practices are identified as not complying with OHS
requirements, they will be brought to the attention of the Construction Manager/Section Manager who
will rectify the issue. Where rectification is not straightforward, it will be resolved by the Project Manager.
While unsafe condition report shall be issued for implementation of corrective action, prevention of
recurrence and record
An Observation Report (Non Conformance Report: NCR) or similar to be filled by Safety Person and
get the signature from the Supervisor responsible for the violation with a time schedule for correction.
One copy shall be handed over to Supervisor and he shall return the same on completion to Safety
Supervisor. The events shall be categorized as follows:
00 20/07/2022
Checking and monitoring movements of plant, equipment and materials entering and leaving the
construction site.
Enforcing traffic and parking regulations within and outside the entrances of the construction site.
All Sites at the night and holidays must be watchmen by assigned watchman by Al-Harthyh if need it.
The system that allows central control and ongoing monitoring of high-risk activities to ensure that
activities are:
Authorized.
Carried out by qualified personnel using safety precautions; and
Those activities with potentially hazardous interactions do not take place at the same time.
00 20/07/2022
Confined spaces.
Excavation and trenching).
Work At height.
Lifting more than 10 ton.
Hot work.
19.3. RESPONSIBILITIES
The Project Construction Management Team has the overall responsibilities for ensuring
that provisions are made for the implementation of safe systems of work. The implementation
of the “Permit to Work” scheme shall be the responsibility of the Site Engineer.
19.4. PROCEDURE
Application
Applications shall be made by the Al-Harthyh construction team who shall supply information
relevant to the scope of works.
Personnel Awareness
Personnel such as the permit receiver and permit issuers shall be sign to the permit depending
on the nature of the work to be carried out and the impact such work may have on adjacent
activities.
Confined Spaces
Minimum requirements are that adequate measures shall be in place and responses to
emergencies that cover all personnel involved in the operations.
The minimum requirements for confined space are outlined in the confine space procedure.
Entries will only take place after the area has been checked by the Safety Representative on
site.
Gas Test
Gas tests shall be decided by the permit issuer to carry our gas testing. Results of the gas test
will be entered prior to issuing the permit. The requirement for ongoing testing is specified on
the permit form.
Records
00 20/07/2022
Completed Permits will be kept in a master file to maintain history of work carried out. These
documents in some cases can be used in Litigation and should be treated as Legal documents.
Safety practices are an effective means of preventing accidents. All personnel, subcontractor
personnel and visitors are obliged to comply with the following safe practices. This basic safety
00 20/07/2022
rules shall be displayed on the site notice boards as instructions for Al-Harthyh employees, Sub-
Contractors, Visitors and other stakeholder.
00 20/07/2022
Manual lifting injuries and incidents are the most predominant within the materials handling
and lifting operations. However careful planning, learning and following the basic manual
handling rules are the effective means of manual handling incidents prevention. Al-Harthyh
shall ensure:
Manual handling should be avoided primarily, if it is not possible take mechanical aid
Labourers shall be provided with the suitable hand gloves for the material to be
handled.
Employee shall not be asked to carry more than 25 kg.
Assistance to lift unbalanced, awkward or heavy items.
The line of travel is free from obstacles and tripping hazards.
Where possible mechanical lifting equipment shall be used.
Provide toolbox talk/training session on the Lift Using the Five Stage Method prior to a
manual lifting activity.
Long objects must be handled by two workers.
Assessment
The level of risk to the person(s) involved with the task should be assessed where the level of
risk is moderate or higher, and then risk reduction measures are required. The Manual
Handling Risk Assessment Form will assist you in completing and documenting the
assessment. The risk or a musculoskeletal disorder affecting an employee must be
eliminated, or if not reasonably practicable, reduced as far as reasonably practicable using
the manual handling hierarchy of control.
Particular attention should be given to posture, layout, conditions, and the task, and object
involved.
00 20/07/2022
The task must be reassessed before alteration is made to the objects being handled, or a
change to the workplace location. If additional information about a manual handling task
becomes available, it should also be incorporated into the assessment.
Control
Provision of information, training or instruction in manual handling techniques must NOT be
used as the sole or primary means of controlling risk unless the following ways of controlling
risk are not practicable-
Altering the workplace,
Altering the environmental conditions, including heat, cold and vibration, where the
task involving manual handling is carried out,
Altering the systems of work used to carry out the task involving manual handling;
Changing the objects used in the task involving manual handling;
Using mechanical aids. These controls must also be assessed for their short, medium
or long term viability.
Training
The health and safety department can provide training in manual handling and ergonomic
workstation design.
00 20/07/2022
Al-Harthyh shall ensure that guardrail system and fall arrest system are provided when
workingat height to prevent fall of person or materials.
Guardrails shall be provided a minimum of 950 mm the walking/working flat form level
where there is a risk of falling 2 meters or more
Toe boards or toe board shall be provided at least 150mm high and run continuously
along the edge of the guardrail
Mid-rail shall be fitted to all edges, shall be installed to all edges so the gap between
guardrail and mid-rail/toe board does not exceed 470mm
It shall be capable of enduring at least 1.25kN point load
When guardrail system shall be used at holes, they shall be erected on all unprotected
sides or edges of the hole.
When used around holes that are used as point of access, they shall be provided with
a gate or be offset so that a person cannot walk directly into the hole.
Inspection &Maintenance
Periodic inspection must be carried out for the fall arrester system and to be recorded.
Adequate color-coding practice shall be followed. Ensure that fall protection systems provided
are adequate and that regular routine maintenance schedule are being followed. The
damaged equipment and materials shall discard from the site.
00 20/07/2022
Ensure system is designed with due consideration of its purpose, external influences,
compatibility of equipment and maintainability of equipment used.
Al-Harthyh shall appoint, competent person who shall be responsible for the
installation,its use and modification during the construction phase of the contract.
Al-Harthyh will ensure appropriate "Electrical and first aid" signs are displayed, and
alsocarry out equipment inspection and colour coding.
All bar wires must covered by isolating electrical tape.
The sheath of wire must enter the socket and plug.
Only industrial plugs is allowed to be used with suitable ampere.
All wires from distrbution panels must be either buried underground or to pass overhead
by cable support.
All distribution panels must be connected to the ground.
The DB must be inspected by competent electrician joinyl with safety officer.
All circuit beakers must be in good condition and proper calculation by electrical
engineer provided to be sure that it will work safely.
All live wires must not be the steel structure or scaffolding and to be fare with the
distance according to OSHA standard.
Power tools must be inspected prior to use and must be of 110 volts whereas 240 volts
is forbidden.
All power tools must be double insulated with a trade mark of CE.
All power tools must be inspected by electrician/ electrical department prior to use.
Should any occasion arise where 240 volts has to be used such tools will be double
insulated.
Equipment casing will be intact with no loose fittings or exposed cables.
Color Code certifying good condition and safe for use will be pasted after the monthly
inspection.
Plugs fitted will be of an approved industrial type.
Condition will be good and the tool will be subject to the preventative maintenance
routine.
00 20/07/2022
Electrical safety is a subject requiring utmost care in all industrial operations. To prevent shock,
burns, fire and explosion the safe practices detailed below should be observed strictly:
Al-Harthyh shall maintain a planning and scheduling system for all maintenance, inspection and
testing activities.
Al-Harthyh shall ensure that only trained & competent person to carry out the work. Training
shallbe provided to comply with Al-Harthyh -EHS- Training & Competency Procedure.
00 20/07/2022
Al-Harthyh shall ensure that no person will be engaged in any work activity on or so near any live
conductor (other than one suitably covered with insulating material so as to prevent danger) that
danger may arise unless:
It is not reasonable practicable in all the circumstances for it to be dead;
It is reasonable practicable in all the circumstances for the employee to be at work on or
near it while it is live;
Appropriate control measures (including where necessary the provision of appropriate
protective equipment) are taken to prevent injury.
00 20/07/2022
All equipment must inspected by thrid party and the certtificate must be issued and
renewed.
All moving equipment or vehicle must not work without the precent of the banksman, but
if there will be a risk of getting crashed by moving vehicles then no one will be on the
ground between moving equipment and one way system will be enforced.
Guarding of Machinery
Through its management line, maintenance, operating, inspection and auditing Procedures,
Al-Harthyh shall ensure that:
Moving parts of machinery such as V belts, chains, drive shafts .etc. are effectively
guarded at all times
Guards are designed so that they cannot easily be removed
No guard, fence or other safety device is removed from machinery or otherwise
rendered inoperative.
Power operated tools such as grinders, cutters etc.shall have a guard fitted, which as
a minimum shall protect half of the diameter of the grinding or cutting wheel.
00 20/07/2022
Al-Harthyh shall have in place a procedure, which incorporates, but may not be limited
to, the following:
Visual pre-use inspection by users of hand tools and the safe tool will be
marked by green color tape and unsafe one will be marked by red color
tape and to be withdrawn and kept in store.
Instructions and identification for defective, damaged and worn tools.
Monthly inspection by the applicable supervisor
Instructions for the correct and proper use of the respective tools.
Sanctions with regard to miss-use of hand tools.
Prohibition of the use of non-patent hand tools.
Record keeping.
Check for any sign of damage to the tool itself, damage to wires or cables. If there is
any damage, report immediately and do not use the tool.
Management should arrange for defective equipment be kept where it cannot be used
until repaired.
110V supply or RCCB protection provided on all plugs/sockets should always be used
on temporary wiring installations.
Make sure that all tools are properly earthed and have the correct fuses.
All connections to socket outlets or wire – to – wire must be made by proper electrical
plugs – NOT by bare cable ends.
Do not allow cables or wires to come into contact with moisture.
Do not carry or drag a tool by its cable.
Disconnect tools from mains when they are not in use and before changing blades,
discs and drill bits.
Regular maintenance of electrically operated tools is essential. It must be done by
someone who is properly trained. Temporary repairs by amateurs can be very
dangerous.
00 20/07/2022
Manufacturer's safe operating pressure for hoses and attachments should never be
exceeded.
All hoses exceeding 12mm inside diameter shall have a safety device at the source to
reduce pressure in case of hose failure.
Air supply lines to be protected from damage by vehicles and materials by use of
channels or ramps.
Al-Harthyh shall ensure that people who are required to use air operated equipment have
been instructed in its use by a competent person, and operate in compliance with the safety
rules given below to avoid incidents to both the operator and others:
Quite low pressures of compressed air have been known to cause serious injuries or
fatalities. (Treat it with respect)
Before starting work, check that hoses and pipes have no leaks.
Keep hoses short as possible and keep traffic away from them, if necessary by
barriers or ramps.
Do not bend or restrict hoses in any way to reduce power. The extra pressure on
couplings can make the hose whip and twist at high speed.
Never direct the air jet at yourself or another person. Compressed air in the
bloodstream, eyes, ears or nose can be fatal
Do not use an open line for blowing out shutters, etc. A restrictor to the air flow or
lance must be used.
Do not blow dust, dwarf etc. off your clothing with an air line.
Never try to change tools without turning off the air supply. Tools must be
disconnected from the air supply for inspection and cleaning/maintenance or when
not in use.
Ear protection, goggles, gloves and/or safety footwear must be worn when using air
operated tools.
In case of Jack Hammering tool, operator shall be replaced at a maximum interval of
two hours and take a rest of minimum half an hour to resume jack-hammering work.
Al-Hathyh shall ensure that all operators are properly trained in their safe use
andmaintenance.
All external switching devices, protection devices, plugs and sockets are weather proof
IP 55 minimum.
All individual circuits shall have their own residual current circuit breaker (RCCB).
00 20/07/2022
That individual employee shall be responsible for keeping their own workareas and
using the waste bins provided to collect waste from site.
That a housekeeping crew is designated for keeping work areas clean and tidy. The
numbers involved in this crew shall be dependent upon the number of personnel
employed in the areas to be cleaned.
That storage of waste can be in a designated area with levelledwaste bin/yard
Those hazardous wastes are kept properly contained, identified and segregated from
non-hazardous waste.
That combustible waste is properly disposed. Burning of waste at site is not permitted.
All lifting operations shall be under the direct control of an experienced slingers.
All lifting equipment shall be tested and examined by a competent person and a
certificate obtained by third party.
All lifting gear shall be clearly marked with their safe working load )SWL (and this should
never be exceeded.
All lifting equipment shall be of good construction, sound material, adequate strength,
suitable quality and free from patent defects.
Inspection and certification of lifting accessories.
Lifting procedure
00 20/07/2022
Incidents involving the failure and damage of lifting equipment are frequent on construction
sites and usually very severe when they do occur.
Riggers
Banks-men/riggers shall be trained and be competent for the task, specifically they will:
Be trained and experienced
Be able to determine the weight, centre of gravity and characteristics of a load
Inspect and determine whether a wire rope sling or other piece of lifting equipment is
damaged or not fit for purpose
Be familiar with the different and correct slinging techniques.
Know the correct hand signals
Be authorized by Al-Harthyh EHS Department to carry out the work
Ensure that tag lines are used on all loads.
00 20/07/2022
The Lifting Appointed Person have to ensure the following lifting operations requirements:
Assessment and planning of lifts with regard to the selection of cranes, lifting gear,
equipment, instruction and supervision.
Ensure that the equipment selected has been adequately inspected and maintained
An effective procedure is in place for reporting defects, taking into account remedial
actions.
Organised and controled of lifting operations.
Stopping any unsafe operation and reporting any incidents.
Monitoring and provide performance evaluation report on the project lifting operations.
Ground Stability
When planning a lift consideration must be given to the ground conditions
Outrigger and track loading should be established before sitting the crane, taking into
account the added weight when lifting operations take place
When setting a crane in live operational areas and on concrete ground, the safe load
limits should be identified against the specification of the concrete, foundations etc. of
the area involved. For other areas the density and compaction qualities should be
assessed
00 20/07/2022
Note: The outriggers must be extended on both sides when performing a lifting operation and
contracted to its original position before moving the crane even for a short distance.
Personnel Carrying
Personnel may only be carried on a crane, with the use of a man-cage and they shall be tied
off above the hook assembly, this practice shall be followed when the use of a hoist, cherry
picker and scaffolding are impractical.
The crane used must be fitted with dead-mans controls, and incapable of free fall
operations
Personnel may only be carried in a bosun’s chair, man cage or other suitable and
tested/certified container which shall display the safe working load
Rigging of any man carrying container shall be on a single point suspension at the hook
end, and configured to prevent any spin
Personnel working from a man cage shall be tied off above the hook assembly by safety
harness and lifelines
The inspection for the crane if will be used for manbasket will be each 6 month by the
third party.
When wind velocities are above 32 km/h (20 mph), the rated load and boom lengths shall be
reduced according to manufactures specifications. Wind forces are greater at height by as
much as 35% or more. All lifts above ground level, must account for wind force i.e., side
loads, down drafts, etc., as applied to the load and the boom.
Cranes shall cease operation when the wind speed exceeds the safe operating level
recommended in the crane manufacturer's specification.
Safety marking
All warning signs shall be posted in English and Arabic and Urdu
All mobile cranes shall have a conspicuously posted sign stating the length or lengths
of the boom which may be fitted, safe working load capacities at the appropriate radius
and recommended operating conditions. Such instruction plaques shall be
00 20/07/2022
permanently affixed to the cab of the crane in a location readily visible to the operator
while he is seated in his control station
Being sworn at
Someone threatening to hurt you
Someone insulting you
Pushing, shoving, punching or kicking
Racial abuse
00 20/07/2022
Erection of safe working platforms 'Scaffolds' by Al-Harthyh shall be supported by scaffold for
any work from 2m height by qualified and experienced scaffolders. Scaffold design following
(ANSI CoP.), must ensure:
Mobile Scaffolds
Al-Harthyh shall use, and cause their Subcontractor’s to use, proper material, and erection
and maintenance of MobileScaffolds on Site.
00 20/07/2022
Scaffolding erection / dismantling shall be performed by trained labours and under the
supervision of competent certified scaffolder, who shall be inspecting the scaffold on
daily and weekly basis.
Formal visual scaffolding inspection shall be performed by the safety personnel before
work on it and during working.
Shall only be used on firm level ground.
Wheels shall be locked before climbing tower.
Tower shall not to be moved if there are persons or materials on the working platform.
Maximum height of free standing tower should not be more than 3½ times the width
of the shortest base .If height to base ratio has to be exceeded, outriggers shall be
used.
Adequate means of access to the working platform should be provided by means of
internal ladders.
Ladders
Al-Harthyh shall use, and cause their Subcontractor’s to use, proprietyladders on Site. Site
assembled ladders of nailed timber or scrap metal shall not bepermitted.
All ladders used on site by Al-Harthyh and its Subcontractors shall be free fromdefects, i.e.
broken rungs, split stiles, and shall not be painted.
Al-Harthyh shall ensure that ladders erected for use by itself, or its Subcontractor's, are:
In good condition, free from obvious defects, inspected.
Properly secured near the top, or if this is not practicable, secured near the bottom,
weighted or footed.
Set at correct angle, 1 m out for every 4m height.
Rise at least 1.05m above the landing point.
When handling and using ladders no overhead power lines are in the vicinity
The No Objection Certificate must be obtained, and approval granted before any
excavation work is carried out.
The exact location of all installations such sewer, power cables, telephone lines, water
and gas services etc. shall be identified before excavation begins. Relevant authorities
shall be referred to obtain a Permit-To-Work Entry, as required by the Authority.
00 20/07/2022
The above must be marked on the ground of the excavation area before
commencement of work.
Permit to Work for excavation shall be issued; initiated by the construction team
supervisor.
In order to prevent damage to installation, precautionary measures shall be taken.
For example, where excavator could reach but may damage electrical cables, the
excavation machine shall not be used; hand or manual excavation technique shall be
exercised.
Excavation near any underground facilities shall be carried out manually using hand
tools.
Trail holes may be hand dug to a depth exposing the underground obstacles or to the
depth of the planned excavation.
No excavation shall be done within 2 meters of the existing live electric cable unless
the Al-Harthyh supervisory personnel are present
Cables, piping, etc, that are exposed during excavation work, must be sufficiently
supported to avoid breaking under their own weight (Max. 2 meters distance).
Banks man shall wear a color coded (Class II ) and fitted vest and be station next to
the excavation area to ensure no unauthorized person(s) enter the excavation and
proper clear instructions are given to the excavator operator.
Special precautions, like de-energizing of electrical cables, removing of boulders,
working at edges which might exposed hazards as a result of excavation; shall be
carried out whenever necessary.
All excavations > 1.2 m shall be subject to preparation and approval of Method
Statements, AHA’s, RA’s and EIA’s before the work starts.
A cable detector shall be used to locate actual location / line of existing utilities, as
needed.
All excavation must be barricaded by plastic barricades which will be filled by sand and
the 6 meter pipes will be used between two barricade also the barricaded area will be
covered by orange mesh.
All personnel who involved in excavation works shall be trained and ensured that they
understand the risk associated with the excavation work.
Proper training program will be provided to ensure that all persons involved in
excavation work acquire the understanding, knowledge, and skills necessary for the
safe performance of all excavation activities.
00 20/07/2022
Battered sides or benches will generally provide temporary stability if the slopes are:
Note:
That safe means of getting into and climbing out of an excavation shall be provided;
Ladders shall securely fixed and appropriately maintained, and shall permit quick and
easy escape in case of flooding or fall of materials; and
Using the walings &struts (if available) for access and egress purposes shall be
prohibited.
The workplace is appropriately lit, particularly at access points & openings, &
whenever lifting operations take place.
Ventilation
Site Lighting
Al-Harthyh shall ensure that the workplace is properly lit, in particular at access points and
openings, & whenever lifting operations take place.
All excavation opening will be barricaded by plastic barriers and proper signage will be
provided to communicate the excavation hazards.
00 20/07/2022
Where there is any doubt as to the stability of structure adjoining or over areas to be
excavated, the structure shall be supported where necessary by shoring/shielding, bracing
or other means made or erected according to the design of a Professional Engineer
(Geotechnical Engineer).
If any person in an excavation is exposed to the hazard of falling or sliding materials from
any bank or side more than 2 meters high above his footing, adequate shoring and bracing
shall be provided against the bank or side to eliminate such hazard(s) in accordance with
design / drawing of a professional engineer.
A designated person shall regularly check the excavation site to ensure dangerous
occurrences are curbed during and after a rainstorm or any other hazardous occurrence.
Be placed at least 2m away from the edge of open excavations and trenches; and
Be so piled or retained that no part thereof can fall into the excavation, cause the banks
to slip or cause the upheaval of the excavation bed.
Adequate concrete barricades shall be placed on any excavation to protect public car and
public members to fall inside trenches.
For excavations exceeding 1 meter in depth shall be provided by proper access and
egress such as ladders, stairways or ramps shall be provided to furnish safe access to
and egress from such excavation.
It is the responsibility for site engineer to be sure that all cavitation in the trench is removed
before allowing any employee to access to the trench.
Inspection
Al-Harthyh shall take approval from all interested parties that may the Al-Harthyh work
will affect their own work or effect the utilization under their authorities, and that all
partieswill be specified from Haql municipality to Al-Harthyh before starting any work
in the project.
00 20/07/2022
Identify all required confined space entries in live lines and comply with the
recommendations contained in "Safe Working in Sewers and at Sewage Works"
published by the National Joint and Safety Committee for Water Services, UK, in
respect of all wok in operational sewers and sewage works.
Light fittings and associated switching devices shall be classified as explosion proof.
Major part of this project consist of Deep excavations, Manholes & chembers and tanks.
Those are considered as Confined spaces.
Training
The Al-Harthyh and Subcontractor shall provide training so that all employees, whose
work is regulated by Permit Required Confined Space Entry Program, obtain the
understanding, knowledge, and skills necessary for the safe performance of the
responsibilities assigned under this section.
Training shall be provided to each employee before the employee is assigned
responsibilities. If there is a change in assigned duties employees must undergo
additional raining or orientation. If there is a change in permit required confined space
operations that present a hazard which concerns employee who has not previously been
trained in that area, he must be given training concerning the proper operations and the
required procedures.
The training shall establish employee competence in the responsibilities required by this
section and shall present new or revised operations, as necessary, for compliance with
these programs.
Al-Harthyh shall document and certify that the training for these procedures has been
accomplished.
BEFORE ENTRY
All members of the team that have been designated to undertake the work must undergo
training before commencement of work.
This training must include the following:
The Hazards
Emergency Procedures
Understanding the permit to work
A record of those attending the training will be kept by the Safety Department no person who
has not undergone the training will be allowed into the confined space.
SUITABILITY OF PERSONNEL
It should be taken into account the following factors when considering the team.
00 20/07/2022
That none of the personnel suffer from claustrophobia (fear of enclosed space)
They do not suffer from any medical condition that may be brought on by extreme
conditions.
PERMIT TO WORK
Before anybody enters the confined space the following must have been carried out and
signed off.
EMERGENCY PROCEDURES
Firstly the hot permit work have to be issued before starting any hot work.
When electrode holders are to be left unattended, the electrodes shall be removed and
the holder shall be placed or protected.
00 20/07/2022
When the arc welder or cutter has occasion to leave his work or to stop work for any
appreciable length of time, or when the arc welding or cutting machine is to be moved,
the power supply shall be switched off.
All arc welding and cutting operations shall be shielded by non-combustible or flame-
proof screens, which will protect employees and other persons working in the vicinity
from the direct rays of the arc.
Adequate mechanical fume extraction and forced ventilation shall be arranged
whenever work does not take place in opening air.
Employees performing any type of welding, cutting shall be protected by suitable eye,
face, hand, body, foot and respiratory protective equipment.
Gas Welding
Al-harthyh and its Subcontractors shall ensure:
Safe system of work; a DCP fire-extinguisher located nearly and readily accessible,
area free from combustible material, First Aid box and Fire-Blanket made available at
the time of work.
All welding operators are competent and properly trained in the safe use and
maintenance of gas welding equipment.
Regulators always fitted to cylinders to adjust the gas pressure to the blowpipe.
Correct colour coding of cylinders and always transported and kept in an upright
position.
To keep and use cylinders fixed upright in purpose made trolleys.
Protection against the effects of noise exposure shall be provided when the sound
levels exceed those shown below in Table B-1 when measured on A-Scale of a
Standard Sound Level Mete.
When employees are subjected to sound levels exceeding those listed in the table
above, feasible administrative or engineering controls shall be utilized. If such controls
fail to reduce sound levels within the levels of the Table B-1, personal protective
equipment shall be provided.
In all cases where the sound levels exceed the values shown, a continuing effective
hearing conservation program shall be administered.
When the daily noise exposure is composed of two or more periods of noise exposure
of different levels, their combined effect should be considered rather than the individual
effect of each. Exposure to different levels for various periods of time shall be
computed.
Exposure to impulsive or impact noise should not exceed 140 dB peak sound pressure
level.
Monitoring shall take place throughout the operation to ensure compliance.
All practicable methods should be used to reduce noise levels, but where these remain
excessive and harmful, ear protectors ‘Plugs or Muffs’ shall be worn.
Average Noise Level dB (A) at the ear Maximum exposure in one working day
85 8 hours
90 4 hours
95 2 hours
100 1 hour
105 30 min
Permissible maximum sound power limits for equipment for use outdoors
Kingdom of Saudi Arabia National Environmental Standard for Environmental Noise for 01/05/1433H, have
specified the noise limits and exposure based on sound level dB (A) for the equipment. These limits are
shown on the following Table
Rev. No. Rev. Date
Project Specific Occupational Health and Safety
Construction Management Plan (OHS-CMP) 00 20/07/2022
Occupational Vibration
Health Effects;
Exposure to vibration may result in a range of health effects, collectively known as hand-arm
vibration syndrome (HAVS). The most well-known health effect is vibration white finger
(VWF). Symptoms resulting from damage to either the vascular or the neurological systems
in the hands include:
Chronic:
- numbness and blanching of the fingers;
- swollen painful joints;
- reduction in manual dexterity;
- Reduction in the sensation of touch; and ulceration and gangrene in extreme cases.
In Europe, for example, a limit on hand-arm vibration exposure is set. The 8-hour daily
exposures limit value A(8) is 5m/s2 and if exceeded an employer should:
reduce exposure;
identify the reason for exceeding the limit; and
Modify the control measures to ensure it is not exceeded again.
A hand-arm vibration daily exposure action value of 2.5 5m/s2 A(8) is set, whereby an
employer should introduce health surveillance for employees.
Control Measures
Other factors:
- reducing the time workers are exposed;
- introducing health surveillance / health promotion Programme;
- wearing warm weatherproof clothing in cold or wet areas;
- wearing gloves and / or using heating pads to keep hand warm; and
- Information and training on the nature and risks and early indications of the injury and
the methods of reporting signs of the injury.
Be aware of heat exhaustion and heat stroke and know that the treatment of the two
conditions differs.
Assess all workers health and abilities and locate workers accordingly during summer
months (June – to – September)
In accordance with ministry of labor requirements, adjust the working hours to avoid
working in the heat of the day .All physically intensive work is required to start early in the
day with a break for no less than 3 hours during the hottest part of the day.
Provide shade over the task area if practicable and ensure shade is set up at work
locations.
In extreme temperatures, each worker may need 5-10 Ltrs. of water per day.
Provide proper cooled resting facilities during afternoon breaks.
Provide labourers in the field with light,cotton and loose coveralls
Ensure proper nutrition and use of water with electrolyte against dehydration.
Al-Harthyh Emergency Response Procedure shall be activated in case of emergency
ofHeat Stress / Stroke.
Al-Harthyh shall be insuring that workplaces are adequately ventilated. Fresh air drawn from a
source outside the workplace, uncontaminated by discharges from flues, chimneys or any
other process outlets and be circulated through the workrooms.
Confined space workplace shall be equipped with a draft ventilation to remove and dilute heat,
humid air and provide air movement that gives a sense of freshness without causing a draught
that shall be regularly monitored, inspected and maintained.
We shall also ensure that there is adequate ventilation around the IT equipment, A/Cs and
refrigerator
Wherever necessary clean or service water spray shall be applied especially at the
vehicles moving areas/route/access roads to suppress airborne dust.
Use vaccume cleaning when this will be applicable.
Control driving speed at the site.
All equipment operators has to operate the equipment while the cabin is closed.
43. COVID-19
Eating not allowed at the site.
For the workers who is doing too must effort it is recommended from CDC to not to wear
mask for long time as this can cause CO2 toxicity effect.
The temprature must be measured daily for the workerd.
Any worker have the COVID- symptoms have to refered to the hospital and isolated.
All workers must be vaccinated.
Training and awarness posters must be provided.