Project Brief
- Project scope
Project Capacity: 2 x 55MW
Power block (include steam turbine), BOP and transmission line
95km to be connected with nearest substation Pekalongan - Kepahiang
- Land status : the Bengkulu Provincial Government Land Procurement Preparation
Team through Announcement Number: 27 / TIM / SET.B4 / 2018 dated January 2, 2019
land covering an area of approximately 15Ha
Project Finance Loan from JICA, project value: USD. 204Mill (base on Blue Book Mid. term planning 2020 – 2024)
Project Period Power Plant : 38 month, Transmission line : 22 month
10 months (included in power plant delivery
27 months after
Competitor
1) Sumitomo + IKPT
2) Toshiba + Rekin + HEC +Itochu (Rekind still not
Remarks
Project Purpose :
Additional power supply to the electrical sub-system Bengkulu region and contribute to the
fulfillment of renewable energy supply to the Sumatra island system
Technical issue:
- Existing JICA Loan for Engineering Services Hululais Geothermal Power Plant (Loan Agreement
Sign December 2015) of USD 6 million
- The results of the steam exploration have met the requirement of 112.8 MW, doing by
PT.Pertamina Geothermal Energy (PGE)
Financial issue :
- EIRR : 14,95%
- FIRR : 18,93% ( case without carbon credit ), 18,97% ( with carbon credit )
*Source data FS E/S Hululais (Nov. ’18)
Project Milestone
PQ issued : Jan. ‘21
PQ submission : March ‘21
ITB issue : Apr. ‘21
Proposal submit : July ’21
---END