You are on page 1of 6

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal

(Kemasan Warna Jubin Luaran dan Dalaman)

Pembinaan Bangunan Tambahan Hospital


Projek
Baling Kedah (Reka & Bina)

Tarikh Mesyuarat 3 Oktober 2019 (Khamis)

Waktu Dimulakan 9.00 pagi


Waktu Ditamatkan
Bilik Mesyuarat BRBF Kesihatan 2
Aras 13, Menara Tun Ismail Mohamad Ali
Tempat Mesyuarat
Cawangan Arkitek, IPJKR Malaysia

KEHADIRAN

A KEMENTERIAN KESIHATAN Bahagian Perancangan


Dr Ali Munawar KPPK
A1
012 205 8650

Dr Nikram Subramaniam KPP


A2
012 924 4032
Azlie bin Ismail PPP
A3
010 517 5960

B KEMENTERIAN KESIHATAN Hospital Baling


Hanita bt Mukhtar Ketua Jururawat
B1
013 485 4518
Zainab binti Hamid Penyelia Jururawat
B2
011 3252 6463
Nur Fairuz bt Md Desa Penolong Jurutera
B3
012 501 2327

C JABATAN KERJA RAYA Bahagian Pengurusan Projek 1

C1 Mohd Sany Mohammad


012 221 7851

D JABATAN KERJA RAYA KEDAH Pasukan Projek Persekutuan (Kedah)

D1 Azizan bin Ab Rahman , BCN.,BCK. Jurutera Awam Penguasa Kanan `

D2 Nor Shakila Ibrahim Jurutera Awam


012 585 6774

Wan Mohd Hafiz bin Wan Yusoff Arkitek


D3 019 755 1640 JKR Kedah

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 1 dari 6
E IP JABATAN KERJA RAYA Bahagian Rekabentuk Fasiliti Kesihatan 2,
Mohd Nor Sahrul Md Ali Arkitek
E1
019 735 2372

F AZHAR AHMAD CONSTRUCTION SDN BHD


Khairul Akif b Azahar Pengarah
F1
012 2310 117
Muhd Rodzi bin Kassim Jurukur Bahan
F2
013 453 6016
Danial Diya Sadiq b Sazali Penolong Jurukur Bahan
F2
018 4660 450
En. Mohammad Taufik Bin A. Aziz Arkitek/ Prinsipal
F3
013 3 999 675 Taufik Aziz Architect
Margaret Ooi Pembekal Jubin
F4
017 885 3488 (Guocera)
Lim Lian Peng Pembekal Jubin
F5
012 283 2403 (Guocera)

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 2 dari 6
1.0 UCAPAN PENGERUSI

1.1 En Azizan bin Ab Rahman , BCN.,BCK. selaku Pegawai Penguasa Kanan Makluman
Pasukan Projek Persekutuan (Kedah)mempengerusikan mesyuarat
interaksi bahan untuk hari ke dua ini.

En Mohd Nor Sahrul Md Ali selaku arkitek Bahagian Rekabentuk Fasiliti


Kesihatan 2, memaklumkan yang sesi hari, seperti semalam adalah untuk
pihak pembekal membuat pembentangan akan produk mereka, pematuhan
kepada spesifikasi yang disyaratkan dan juga pembekal jenis waranti yang
diberikan untuk projek ini.

2.0 Pembentangan Pertama – Jubin

Pembekal yang membuat pembentangan adalah Madam Margaret Ooi dan Makluman
Mr Lim Lian Peng.

2.1 Butiran Maklumbalas Guocera


In general, all ceramic tiles Jubin seramik dikategorikan
manufactured locally are using the `dry- atas keupayaannya tidak
pressed’ manufacturing process and the menampung air sepertimana
ceramic tiles are categorized based on MS ISO 13006 dan bukannya
their water absorption rate as defined in MS 1294
the MS 1294 or the International
Standard Organization (ISO) Standards.
a) All ceramic tiles to internal and
external floor for heavy duty areas MS 1294 ialah kod untuk
shall be fully vitrified with water kaedah pemasangan jubin
absorption less than 0.5%
Rujuk kepada penjelasan
[Classification Group BIa] also
diatas.
referred to as heavy duty tiles shall
be vitreous hard wearing non-slip
glazed tiles 300mm x 300mm
complying with MS 1294.

b) All ceramic tiles to internal floor


areas under normal condition shall Jubin dibawah kategori BIIa
be fully vitrified with water absorption dan BIIb tidak keras oleh
more than 0.5% less than 10% sebab ianya menampung air
[Classification Group BIb, BIIa and ldalam julat dari 0.5% - 10%.
BIIb] and shall be vitreous
Hanya kategori BIa sahaja
hardwearing non-slip glazed tiles
kurang dari 0.5%.
300mm x 300mm complying with MS
1294.
c) All ceramic tile skirting shall match Use of cement mortar is not
the flooring tiles and shall be 300mm recommended as specified in
x 100mm laid lengthwise on cement MS1294 tidak mengesyorkan
and sand (1:3) screed as described. mortar simen
All angles to skirting shall be neatly
cut to fit all abutments.

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 3 dari 6
d) All accessories such as skirting (bull Akan dipatuhi
nose or cove base), step tiles, step
nosing, edging strips, angle tiles
(internal and external), etc. shall be
of an approved type from the same
material to match flooring.
All skirting shall be 100mm high,
stair nosing shall be minimum 20mm
wide laid full length of the treads and
of bull nose profile, and edging strips
25mm wide.
e) All ceramic tiles for internal walls Projek ini terpaksa
shall be scuff- resistant glazed menggunakan jubin lantai
vitrified tiles with water absorption untuk pematuhan kepada
more than 0.5% less than 10% syarat ini.
[Classification Group BIb, Blla or
Bllb].
The tiles minimum size shall be of
300mm x 300mm
f) All ceramic tiles for external walls MS 1294 ialah kod untuk
shall be scuff- resistant glazed kaedah pemasangan jubin
vitrified tiles with water absorption
Rujuk kepada penjelasan
less than 0.5% [Classification Group
diatas.
BIa]. The tiles minimum size shall be
of 300mm x 300mm complying with
MS 1294.
g) All ceramic tiles for walls and floors Akan dipatuhi
shall be of Grade A approved
surface finish & texture, colour and
manufacture
h) Ceramic tiles for walls shall be MS 1294 membenarkan
bedded with cement paste or hanya jubin dalam kategori
alternatively with approved tile BIIa, BIIb and BIII dilekatkan
adhesive to the manufacturer’s menggunakan mortar simen.
specification on 20mm thick cement
Piawaian ini juga
and sand (1:3) screed, which has
mensyaratkan jarak jubin
sufficiently hardened.
adalah 3mm.
The surface of the screed shall be
properly roughened to form key to
the tiling. The tiles shall be laid
close-butt and all joints shall be filled
with approved tile adhesive or
coloured cement to match. Exposed
edges of tiling shall be finished with
rounded on edge tiles.
i) The selection and application of Akan dipatuhi oleh Kontraktor
ceramic tile adhesives for internal Utama.
and external tile installations on

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 4 dari 6
walls and floors shall comply with
MS ISO 13007-1. The application of
ceramic tile grouts for internal and
external tile installations on walls
and floors shall comply with MS ISO
13007-3.
j) Staircases solely meant for fire Akan dipatuhi
escape and emergency staircases
purposes shall be finished with non-
slip nosing tiles and shall be
protected to maintain a dry and non-
slippery condition in all weathers.
k) The main entrance, lobby, waiting Akan dipatuhi
area, lift lobby, hospital streets and
revenue collection area shall be
finished with minimum 600x600mm
polished/unpolished fully vitrified
with water absorption less than 0.5%
[Classification Group BIa] with
patterns and that shall be integrated
with I.D work to P.D’s concurrence.
l) Non-slip matt finished fully vitrified Akan dipatuhi
with water absorption less than 0.5%
[Classification Group BIa] with
minimum size of 300x300mm shall
be used for toilets, wet areas, and
external corridor unless otherwise
finishes for toilets in special areas
i.e. V.I.P areas shall be of higher
range of tiles than normal toilet.
m) All tile joints shall be filled with Akan dipatuhi
approved epoxy grout of suitable
width to manufacturer’s details and
shall be levelled evenly to prevent
chipping due to movement of
equipment and trolleys.

Warranty Guocera akan memberi


waranti jikalau pemasangan
mematuhi MS 1294, Part 1 , 2
and 3.

5.0 Lain-lain Hal

5.1 Jadual Pembentangan Bahan Klinikal


Azhar Ahmad Construction membentangkan deraf jadual pembentangan
yang akan bemula pada 4-7hb November 2019 untuk memastikan sebelum
peperiksaan SPM bermula, dan musim cuti sekolah.

Deraf ini akan diperincikan dan diserahkan kepada JKR secara rasmi.

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 5 dari 6
6.0 Penangguhan Mesyuarat
Tiada isu lain dibangkitkan.

Mesyuarat ditangguhkan pada jam 4.30 petang.

Mesyuarat akan datang akan disahkan kelak.

Disediakan dan Disemak Oleh, Disahkan Oleh,


TAUFIK AZIZ ARCHITECT AZHAR AHMAD CONSTRUCTION SDN BHD

…………………………………………………
……………………………………………
En Muhd Rodzi bin Kassim
Mohammad Taufik bin A Aziz
Pengurus Projek
Arkitek / Prinsipal

Minit Mesyuarat Interaksi Kelulusan Bahan Klinikal


(Kemasan Warna Jubin Luaran dan Dalaman)
Mukasurat 6 dari 6