Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY

HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

Attendance: Firm Name (Position) Contact Email


Representative M/s SP Group Mr Joshua Tay Boon Howe (Snr Engr) 91790529 joshuabh@spgroup.com.sg
Mr Shafie Bin Abu Bakar 98890341 ShafieAbuBakar@spgroup.com.sg
M/s SurbanaJurong Consultants Pte Ltd Mr Cheng ShauChuan (Engr, M&E Engrg, ELEC) 97521930 ShauChuan.Cheng@surbanajurong.com
Mr Murali S/O Jothinathan (RE, ELEC) 90279217 Murali.Jothinathan@surbanajurong.com
Mr Shanmugam Maheshbabu (RTO, ELEC) 90066087 Shanmugam.Maheshbabu@surbanajurong.com
M/s China Construction (South Pacific) Mr Su YanPei (Snr Prj Mgr, M&E ) 91269158 SuYanPei@chinaconstruction.com.sg
Development Co Pte Ltd Mr Adrian Fong Ying Sin (Snr M&E Engr, ELEC) 91386532 FongYingSin@chinaconstruction.com.sg
Mr Kelvin LOH Ping Kwan (Snr M&E Engr, MECH) 97600713 KelvinLoh@chinaconstruction.com.sg
Mr Chen Yi (M&E Engr, ELEC) 81867980 ChenYi@chinaconstruction.com.sg
Mr Ng Yong Siang (M&E Engr, MECH) 90849665 NgYongSiang@chinaconstruction.com.sg
Mr Ye Feng (Snr Mgr, C&S) 90669827 YeFeng@chinaconstruction.com.sg
Mr Chong Kam Seong (Snr Site Engr, ARCH) 91881789 ChongKamSeong@chinaconstruction.com.sg
* Key Contact Person Mr Adrian Fong Ying Sin (Snr M&E Engr, ELEC) 91386532 FongYingSin@chinaconstruction.com.sg

1) Location: Switchgear Room


Comment: Installed isolators serving to equipment, the precise location would be advised upon confirmation by SPPG's Sub-Contractor
Date: Thu 14 Apr 2022 Date: Pending advice from SPPG
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Pending advice from SPPG


(if any) (if any)

Page 1 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

2) Location: Switchgear Room


Comment: Installed metal clad switch socket outlets (SSO), the height to be 1.5 m taking reference between FFL and the bottom of receptacle
Date: Thu 14 Apr 2022 Date: Mon 18 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

3) Location: Switchgear Room


Comment: Installed smoke detectors, along the center above the HT Switchgear Board, to the shifted away from the critical zone that will affect the Switchgear maintenance
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 2 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

4) Location: Switchgear Room


Comment: To make provision with angle bar with spacer to protect the shoot bolt-housing/dust cover of the main doors
Date: Thu 14 Apr 2022 Date: Mon 30 May 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

5) Location: Switchgear Room


Comment: Vertically run Trunking offset to be at 90 degrees butt to the floor
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 3 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

6) Location: Switchgear Room


Comment: Public Address (PA) speakers to be removed
Date: Thu 14 Apr 2022 Date: Tue 19 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

7) Location: Switchgear Room


Comment: Additional Nuts or trimming of the sharp edges bolts of the cat ladder
Date: Thu 14 Apr 2022 Date: Thu 21 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 4 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

8) Location: Switchgear Room


Comment: To provide 2 holes on the frame of aluminium trap door to allow the door catch able to penetrates through
Date: Thu 14 Apr 2022 Date: Thu 21 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

9) Location: Switchgear Room


Comment: The 1st rung of Cat Ladder to make provision with 200 mm space between the wall and the rung
Date: Thu 14 Apr 2022 Date: Sat 02 Jul 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 5 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

10) Location: Switchgear Room


Comment: Suspended mounted lights to be higher than the perimeter wall trunking routing
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

11) Location: Switchgear Room


Comment: Trap door to be flushed on the floor
Date: Thu 14 Apr 2022 Date: Thu 21 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 6 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

12) Location: Switchgear Room


Comment: "Hard Hat Area" and "No Smoking" signage to be situated above the catch of trap door
Date: Thu 14 Apr 2022 Date: Tue 05 Jul 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

13) Location: Switchgear Room


Comment: Circuit Labels in DB to be engraved type
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 7 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

14) Location: Switchgear Room


Comment: Engraved label to be added to the side of the isolator
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

15) Location: Switchgear Room


Comment: To make provision with minimum of 100 mm clearance between the penetration and the wall
Date: Thu 14 Apr 2022 Date: Mon 25 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 8 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

16) Location: Switchgear Room


Comment: Vertically run Conduit from the Soffit to the FFL and downwards to the cable chamber to have no offsets
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

17) Location: Switchgear Room


Comment: Door hook to be provided serving to the switchgear doors
Date: Thu 14 Apr 2022 Date: Thu 21 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 9 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

18) Location: Switchgear Room


Comment: To ensure the RCCB is bypass the circuitries of Isolators serving to Equipment of Battery Charger, RTU, Marshalling Box, Pilot Box, IDS, RTU, etc.
Date: Thu 14 Apr 2022 Date: Thu 14 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: No amendment required as the RCCB has already bypass


(if any) (if any) the circuitries of Isolators

19) Location: Cable Chamber


Comment: The verge between cable ramp and floor of cable chamber to be chamferred
Date: Thu 14 Apr 2022 Date: Mon 25 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 10 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

20) Location: Cable Chamber


Comment: Conduits to avoid routing under the beam along the accessible area
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

21) Location: Cable Chamber


Comment: Public Address (PA) speakers to be removed
Date: Thu 14 Apr 2022 Date: Tue 19 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 11 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

22) Location: Cable Chamber


Comment: "Hard Hat Area" and "No Smoking" signage to be situated near entrance door
Date: Thu 14 Apr 2022 Date:
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

23) Location: Cable Chamber


Comment: Opening for SPPG Earthing Cable on grating of cable trench to be situated at the side corner area near the wall
Date: Thu 14 Apr 2022 Date: Mon 30 May 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 12 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

24) Location: Cable Chamber


Comment: LT cable & trunking from DB box to route along the wall to the designated LT Opening with excess 2m length of cable c/w flexible conduit
Date: Thu 14 Apr 2022 Date: Wed 20 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

25) Location: Cable Chamber


Comment: The distance clearance and gradient of Cable Ramp and Entry Pipes to be based on the SPPG Handbook
Date: Thu 14 Apr 2022 Date: Mon 25 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 13 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

26) Location: Cable Chamber


Comment: Aluminium handle at external of the Cable Chamber Exit Door to be removed
Date: Thu 14 Apr 2022 Date: Thu 21 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 14 of 15
Subject: Project: SGH - H9A : APPLICATION NUMBER 1210029638 : HIGH TENSION ELECTRICITY
HANDOVER INSPECTION OF SPPG SUBSTATION CONNECTION TO HOSPITAL DEVELOPMENT SITUATED AT NO. 1 HOSPITAL
BOULEVARD, SINGAPORE 168581

27) Location: Cable Chamber


Comment: To provide door floor steel pipe section for door steel bolt serving to exit doors (typical to Switchgear and Cable Chamber Exit Door)
Date: Thu 14 Apr 2022 Date: Mon 25 Apr 2022
Before (Pictures, diagrams, etc.) After (Pictures, diagrams, etc.)

Remark: Remark: Completed


(if any) (if any)

Page 15 of 15