Professional Documents
Culture Documents
Table of Contents
1. PURPOSE 3
2. INTRODUCTION 3
3. PLANNING 5
3.1 Notification Process 5
3.2 Planning thru Work Orders 7
3.3 Standards and specifications 10
4. SCHEDULING 12
4.1 Backlog 12
4.2 Maintenance Master Schedule 15
4.3 Weekly Maintenance Plan 16
4.4 Daily Maintenance Plan 21
4.5 Material Staging and Preparation 21
5. PLANNING AND SCHEDULING EFFICIENCY INDICATORS 22
6. MAJOR SHUTDOWN 22
6.1 The impact of planned shutdowns 23
6.2 How to achieve effective Planned Shutdowns 23
6.3 Performance drivers 24
6.4 Planned shut down process 24
6.5 Shutdown Management with SAP-PS 28
6.6 Conclusion 28
7. MESSAGE 28
8. DEFINITION 30
9. REVISION LOG 31
1. PURPOSE
2. INTRODUCTION
The situation in many plants shows that maintenance is often blindfolded due to
short term cost control measures instead of long-term results. As a result of this, a
reactive maintenance approach takes place, which increases cost and reduces
equipment reliability.
It is therefore of upmost importance that the different tools and techniques that shall
be applied in order to properly plan and schedule the work are clearly understood.
This supports the move from a reactive towards a proactive maintenance approach.
This will not only help increasing reliability, reducing costs and time consuming
reactive work, but is also an important step towards clearly defining the maintenance
needs and optimizing resources (labour and material).
However, both the planning and scheduling function are the center from which all
maintenance activities are coordinated. Both represent the “work preparation” in
maintenance and tackle the following aspect:
Planning is mainly about identifying the problem and determining the proper
solution, manpower, and other resources such as material, time, tools, equipment
and technical data required for a safe, efficient and effective work execution.
Scheduling work is the process when the specific dates are finally defined and
coordinated for the execution of (planned) work for the following week. Maintenance
can not leave the reactive stage without a firm control over the activities to be done.
Therefore also poor backlog management is a hurdle.
Work
Production
requirement
Plan
Notification
Evaluation
Feedback
Work planning
Request for
resources
Resources
Preventive available
Maintenance Work Execution
Work Schedule
3. PLANNING
In order to keep and manage the overall work load, it is necessary to plan work
activities for it to be successfully completed. Planning means preparatory activities
to be done before execution of the actual work.
There are many sources for incoming job requests and the way to manage these
sources is through the notification process.
Example
Sources Example
Occurrence of equipment failures R Motor failed to start
R Belt torn
Feed back from preventive R Oil leakage on a gear box
maintenance activities R Abnormal noise of a bearing
Alert levels from condition R Vibration too high on mill gear box
monitoring activities R Oil temperature too high on air
compressor
Request for all departments R Modification of the lighting in an area
R Request for a modification of installation
for customer trial
Root Cause Failures Analysis R Modification of belt chute to avoid leakage
and belt torn
Safety, environment or quality R Repair of handrail
requirement R Control the air separator turbine of raw
mill due to quality issue
The purpose of the notification process is to create a request when a need for
maintenance has been identified, to record a completed maintenance activity and to
cover a downtime record for process operations. (see figure below)
Notification
Notification Maintenance
Maintenance Order
Order
Request
Request Planning
Planning Schedule
Schedule Execution
Execution Report
Report
Type of Notification Release
HAC code work order
Request/Malfunction Tasks to perform Print work order Material withdrawal
Planner Group Time confirmation
and other papers Planned
Main Work Center Resources Technical
Capacity leveling Unplanned
Basic Dates Components Completion
Availability Check External
Priority Order settlement
Object Part Tools Purchase Procurement
Symptom Codes Requisition
Cause Codes Reserves
Created
Created Created
Created Scheduled
Scheduled Released
Released Completed
Completed
History
History
Figure 2. Work Order flow wherein the notification process is the starting
point of the process
After a notification has been created and approved, it is now converted into a
maintenance order. Maintenance orders show in detail how a particular
maintenance activity has to be executed. This allows the maintenance department
to plan and schedule maintenance activities such as corrective or preventive
maintenance activities (see figure below).
Notification
Notification Maintenance
Maintenance Order
Order
Request
Request Planning
Planning Schedule
Schedule Execution
Execution Report
Report
Type of Notification Release
HAC code work order
Request/Malfunction Tasks to perform Print work order Material withdrawal
Planner Group Time confirmation
and other papers Planned
Main Work Center Resources Technical
Capacity leveling Unplanned
Basic Dates Components Completion
Availability Check External
Priority Order settlement
Object Part Tools Purchase Procurement
Symptom Codes Requisition
Cause Codes Reserves
Created
Created Created
Created Scheduled
Scheduled Released
Released Completed
Completed
History
History
Figure 3. Work Order flow wherein the planning process is the next step thru
work orders
As shown in the figure above, all relevant information concerning “what”, “who”,
“when”, “where” and “how” is clearly shown in the work order.
For each identified job, the planner needs to establish a detailed task list with
“operation”. The level of detail will depend on the skills of the maintenance people.
However, all relevant tasks have to be described, always bear in mind “What do I
need to remember!”
In SAP PM, creating too many operations in the work order will add more
administrative tasks for its confirmation later on. Sub operation and long text of
operation have also to be used in order to address this issue.
Once all prerequisites are completed and the work order is approved, it is now part
of the planned backlog. Before being ready for execution, material’s availability
needs to be checked in a timely manner. However, the work order shall be
integrated into the maintenance master schedule, taking into account planned
delivery times and then cascaded into the weekly maintenance plan and daily
maintenance plan.
SAP-PM provides all capabilities needed for work order planning. Basic data and
data for analysis and control of maintenance are kept in work orders.
In the cement industry most of the performed maintenance jobs, complex or not, are
repetitive with only minor changes. Some are done frequently others less frequently.
Standards and specifications are part of the plant’s library which catalogues all
necessary information to perform the job.
The steps to establish standards and specifications are the same as for planned
work orders as described in the previous chapter.
There are different ways of storing standards and specifications. The easiest is to
write Word or Excel documents including pictures to illustrate. However, it is not
sufficient enough in term of planning as the planner will have to encode all
information in SAP for each job. In order to take advantage of SAP, the standards
and specifications should be stored in SAP using the function “task list”. The task list
function allows the storage for each operation, the spare part requirement and
purchase request as in a work order.
Once the job has been executed, the planner has to get feedback from the shop
floor in order to improve the standards and specifications:
R Was the schedule successfully completed?
R Was the job estimate versus actual accurate?
R Were any of the schedule shortfalls due to incomplete or poor planning?
R What was the problem? Could it be avoided? What can be done differently
next time? What will it take?
The figure below is an example of a standard and specification list which should be
developed for each plant
4. SCHEDULING
After works have been planned, they still need to be performed. In order to reduce
the downtime of equipment they need to be scheduled in accordance with the
customer requirement. Therefore scheduling answers the question WHEN? and
WHO?
Notification
Notification Maintenance
Maintenance Order
Order
Request
Request Planning
Planning Schedule
Schedule Execution
Execution Report
Report
Type of Notification Release
HAC code work order
Request/Malfunction Tasks to perform Print work order Material withdrawal
Planner Group Time confirmation
and other papers Planned
Main Work Center Resources Technical
Capacity leveling Unplanned
Basic Dates Components Completion
Availability Check External
Priority Order settlement
Object Part Tools Purchase Procurement
Symptom Codes Requisition
Cause Codes Reserves
Created
Created Created
Created Scheduled
Scheduled Released
Released Completed
Completed
History
History
Figure 6. Work Order flow wherein the scheduling process is the next step
thru work orders
4.1 Backlog
Ready to Weekly
execute Plan
Resource Work
Planning Coordination Scheduling
available Yes Daily execution
Plan
Work Order status
• Waiting for resources • Waiting for Major Shutdown Work not performed
• Waiting for approval • Waiting for Materials • Ready
• Waiting for completeness
Outstanding Overdue
Backlog
Figure 7. Total backlog and its division in subgroup
The backlog needs to be maintained between proper upper and lower limits:
R Ready (to be scheduled) backlog between 2 and 4 weeks of available hours
R Total backlog between 4 and 8 weeks
4.1.2 Overdue
Overdue refers to the total labor hours required to complete all overdue work orders.
The purpose is to quantify the level of work not completed as per the designated
due date.
Together with the Outstanding Work indicator, the overdue level should be regularly
reviewed to highlight work which can be assigned to people with free allocation
hours or when planning current and future maintenance schedules.
Outstanding work refers to the total labor hours required to complete all outstanding
work orders for the next 13 weeks. The purpose is to quantify the volume (in
estimated work hours) of work to be completed, as an early indication for the coming
work load.
The outstanding work orders should only include those orders which have actually
been generated or released. However, preventive maintenance work orders, which
have not yet been released, should not be included. The coverage for considering
outstanding work should be taken as 13 weeks, which coincides with the
maintenance master schedule.
Aligning with the Overdue indicator, the outstanding work level should be regularly
reviewed to highlight work which can be assigned to crews with free allocation hours
or when planning current and future maintenance schedules.
The maintenance master schedule is a list of all active work orders for a 13 - week
period including estimated man – hours and due dates. The schedule contains both,
planned corrective and preventive maintenance activities.
Production
plan
Budget
MTBF - Classify orders by date & Maintenance
Pareto priority plan
Balancing
WO for the
next 13
This is a continuous process and has to be reviewed weekly for the next 13 weeks.
A weekly plan indicates maintenance requirements for the week. This has to be
broken down into Daily Plans indicating skills needed and hours required. The
proper use of KPI’s such as plan attainment, % unplanned etc is necessary when
completing the weekly plan.
The Maintenance Plan should be linked to the Production Plan to identify the agreed
equipment availability for both maintenance activities and production needs.
In ours and other related industries this is the most structured time frame due to
change in customer requirements and production planning. Anything less than this
gives no preparation time for planning, purchasing and preparation of parts.
It also increases coordination between production and maintenance and helps to
insure completion and effectiveness of the Preventive Maintenance Program.
Finally this is the most convenient time frame allowing maximum utilization of
workers time.
A key component is determining the actual wok force availability. In order to be able
to schedule all available hours of a maintenance team (own labors and
subcontracted labors), it is of utmost importance to understand the concept of
available hours.
In order to determine the available hours, the total hours (Sum of the normal working
time (paid)) will be reduced by the following time:
R Vacation
R Holidays
R Training
R Meetings
R Miscellaneous company matters
The following table is a possibility of layout to determine the available hours for a
maintenance trade. In this example, two additional information (Hours after PM and
routine; Net backlog relief hours) are estimated in order to provide input for the
maintenance plan that will be explained in the next chapters.
Vacation
Holidays
Meeting
Other specific
Daily Planning Daily Planning Daily Planning Daily Planning Daily Planning
Meeting Meeting Meeting Meeting Meeting
Master
schedule Production
plan
Weekly Plan
Preparation
meeting
Weekly Weekly
Weekly
planning planning
Maintenance Commitment
Setup Setup
Review meeting
Meeting (KPI)
The execution of the weekly maintenance plan is usually reviewed in the Weekly
Maintenance Review Meeting. The meeting covers problems and concerns coming
from the previous / next week, notifications, previous action logs, downtime report
and plans for the next week. It should also address all key matters relating to
maintenance performance. It also gives input for the weekly plan preparation
meeting. Before having the commitment of the plant, the weekly plan has to be
prepared regarding what is the expectation of the following week(s). The purpose of
the Weekly Plan Preparation meeting is to go through the backlog and to reassess
the priority of the work order in order to schedule them for next week. It is also to
collect information regarding the production program for the following weeks and to
address maintenance downtime requirement to production.
The plan has to be established by the end of the week in order to be reviewed and
validated in the commitment meeting together with the other involved departments.
The following staff should attend these meetings:
R Planner(s)
R Maintenance Supervisors
R Production Representative
R Environmental Representative
R Project Engineer
R Warehouse/Purchasing Representative
Then after a final negotiation the weekly schedule is published by the planner prior
to start off the week.
First Second
Scheduling
Supervising
Scheduling Cycle:
R Assure ~25% of available time for PM tasks (first slice) taking into account
the preventive maintenance program
R Use another 35% of available time for high priority jobs most of them on
shutdown equipment
R The remaining 40 % have to be split between less critical jobs that may be
postponed
R Use the average emergency hours of the last weeks (see figure 9) in slice 4.
In this slice, it is non-critical work and people are easily found.
Supervising Cycle:
R The workers assigned on job in the fourth slice have to know that they will
be pulled off their job if an emergency occurs. That is why they should be
working on non-critical work and be easily found.
R The workers assigned on job in the third slice have to know that they are the
next line of defense and may get pulled off.
R Things have to go really bad before starting to pull workers off the second
slice, but things must be completely chaos before pulling off the PM group.
The purpose of the daily maintenance plan is to brake down the weekly
maintenance plan into a manageable daily plan. The maintenance supervisor is
responsible of the execution of the daily maintenance plan.
The daily maintenance plan helps maintenance personnel to become more efficient
in planning day to day maintenance activities. It serves also as a form of short
interval control, to capture data on performance against plan for a given day, and to
document daily maintenance activities. The daily plan includes also emergency and
other unplanned activities.
The execution of the daily maintenance plan is usually reviewed in the Daily
Maintenance Planning Meeting. The meeting covers key discussion of an entire
plants maintenance performance during the last twenty four hours. It should include
problems or concerns coming from the shift turn over report of the previous shift or
day, notifications, previous action logs, and plans for the day.
The supervisor, planner and his crew meet every morning to validate the daily
planning and decide the final assignment regarding the events of the last hours.
Safety and quality of job discussions are welcome at that moment of the day, as any
other relevant subject. The available result of the last shift has to be commented as
well.
At the end of the day the supervisor have to assign the job for next day to each
worker after reviewing the process schedule with the planner and the production
representatives. During this informal meeting the supervisor should have an update
of the advancement of the current job.
The planner has to develop communication with the warehouse responsible and ask
for parts to be prepared and staged one to two days in advance for each work order.
In some cases it could be accurate to involve Purchasing and Warehouse in the
weekly planning meetings.
The warehouse needs to have a separate and secure area for staging (see figure
below), with boxes or cartons of various sizes. The work orders should be attached
to the box, with all reserved parts, issued one or two days before based on the daily
planning adjustment. The time frame will depend on the proactive maintenance
situation of the plant.
The staging area must be checked daily and no one is allowed to take parts out of
the staging area without the authorization of the planner or the responsible of the
Work order. If parts are not used when prepared and staged there needs to be a
policy for returning parts.
6. MAJOR SHUTDOWN
Major shutdown uses the same principle of planning and scheduling process. The
planning approach is identical. The scheduling process will be more detailed for
major shutdown and additional tools will be used in order to optimize planned
shutdowns which will help to balance maintenance cost versus equipment
availability. For this purpose SAP-PS has become an important tool, which will help
developing and following the critical path.
A planned shut down in fact is not just a maintenance event but also a plant event.
Planned shutdowns consume a large amount of resources and from a maintenance
point of view they affect not only the KPI's as availability but furthermore also to a
large extend the maintenance cost.
Planned shutdowns impact all departments and put to test the coordination and
communication starting with sales over to production, maintenance and last but not
least purchasing. The dramatically increased amount of activities by internal and
external personnel in combination with long working times increases the probability
of accidents. Therefore more supervision is required to handle the increased
workload. In terms of cost it can be said that 40 to 50% of the annual maintenance
budget is spent in planned shutdowns throughout the Holcim plants.
The shutdown cost, the number of unplanned activities, the lost time and the amount
of people are symptoms to judge whether a shutdown is effective or not.
One of the factors that cannot be influenced directly but which nevertheless has a
great impact on the planning of the shutdown is the market situation.
Factors which certainly directly can be influenced are such as the management of
preventive maintenance, which has to be streamlined with the shutdown objectives,
or the work order system.
As mentioned above the shutdown has to be planned according to the market
scenarios. The two following market scenarios have to be taken into consideration:
In the first case the focus is on reducing the execution time of the activities.
Therefore the optimal balance between costs versus duration of the shutdown has
to be found, or in other words the opportunity cost for a production loss has to be
known. In this whole process the availability of the main equipment is critical.
In the case of low demand, the effort has to be put on reducing the cost, since in this
case time is not an issue. This can be reached by improving the own labour
productivity, as well as the quality of work. On the other hand of course the usage of
third party services has to be optimized. On the equipment side the lifetime of spare
parts has to be balanced against the cost and with this the failure probability versus
the potentially higher cost.
In order to reach an effective shut down, where the optimal balance between
maintenance cost and equipment availability is found the main drivers have to be
identified and act upon. The figure below shows the different factors that either have
an impact on the shutdown cost or on the equipment reliability.
Unplanned Work
Quality control
Spare parts
Wear parts PMR's
- Review of progress
- Active Supervision
- Control of contractors
Execution
- Testing of equipment, re-commissioning
- Coordination Meeting
Analysis
Preparation
6.4.1 Definition
In the definition phase the shut down process is assessed and roles and
responsibilities are properly defined. An effective communication has to be assured
and the objectives of the shutdown have to be defined. Unplanned work has to be
no more than 5% of the total amount of work, which means that 95% of the total
workload has to be determined by inspections and condition monitoring.
6.4.2 Planning
In the second phase, which is the planning phase the key shutdown activities have
to be defined. It has to be assured that the work in the activity list is a result of
PMR's and inspections, which at the same time of course means that all
requirements are documented in SAP-PM through notifications and work orders.
Planning is an ongoing process. Failing to plan means planning to fail at a later
moment.
During this phase it is also very important to address improvement potential, since
the process will not improve by itself. For repetitive activities a feed back system
should be in place in order to improve the activities for the following shutdowns.
Therefore cost drivers must consistently be identified and addressed. The formal
decision of identifying main potential areas is critical.
Like for the planning and scheduling process, the planned works need to be
scheduled. However for major shutdown, the scheduling process has to be detailed
by using additional tools.
The following figure shows how big the impact of one day less or more of shutdown
on the net availability is.
External
Each day reduced from Planned Shutdown increases availability by 0.27%. So,
reducing the shutdown from 30 days to 18 days will increase the net availability by
3.2 %.
6.4.4 Preparation
The preparation phase is the execution phase of planning. Now it has to be assured
that critical items with long lead times or which afford special logistics are followed
up.
In terms of equipment the accessibility has to be guaranteed. Where needed
scaffolding has to be mounted and lifting equipment installed. Additional energy and
compressed air requirements have to be considered.
Specifications and conditions of materials and spare parts delivered on site have to
be verified upon reception.
Last but not least the understanding of the work has to be reinforced constantly.
Objectives and benefits have to be highlighted. This can be reached by constant on
site training, such as work preparation, reporting and feedback on activities.
6.4.5 Execution
In the execution phase, it will become apparent whether the shutdown can be made
a success or not.
Roles and responsibilities that were implemented at an early stage now will help
assuring a strong coordination and communication of the daily events and herby
support taking decisions on time.
To insure the quality of work a close supervision of critical activities executed by
own or / and third party personnel in all shifts has to be guaranteed. In order to
reduce the probability of failures constant safety awareness has to be kept at all
times.
Once a job is finished the equipment has to be checked before it is formally handed
over to production. This means, that e.g. drives are tested without load, or electrical
connections are checked etc.
For the purpose of assuring optimal working conditions and minimize the risk of
accidents the working area has to be cleaned before, during and after a specific job.
The implementation of the start up strategy finally is the last step of the execution
phase.
6.4.6 Analysis
Last but not least the analysis phase is reached. Although one might think that the
shutdown is finished once the machines have been started up again this is not the
case. This is the time to identify strengths and weaknesses. Doing a formal analysis
(After Action Review) session to address opportunities like lost time or unplanned
activities is a must. Of course the results have to be communicated and taken into
consideration when planning the next shutdown in order to reinforce the
commitment.
6.6 Conclusion
Taking an impact on the cost of the shutdown will heavily impact the maintenance
cost. Therefore it is of utmost importance to establish a consistent base line and
consistent targets including KPI's in order to measure success and target higher
performance.
A systematic approach for the planned shutdown realization will support new
initiatives to improve the shutdown performance in the plant. Furthermore it is an
important step to support maintenance strategies at an organization level.
Where the opportunity cost for production loss allow it, cycle time compression is a
technique to minimize the down time by identifying the critical path and herby also
minimize the loss of net availability.
7. MESSAGE
The strategy of doing planning and scheduling is indeed a vital step towards the
direction to a proactive approach in maintenance.
8. DEFINITION
9. REVISION LOG