Technical Proposal for Preparation of Detailed Master Plan of Hospital

FORM TECH 5: WORK PLAN

Months
Total
SN Deliverables 1 2 3 4 Months
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
D-1 Inception Report 0.5
1 Signing of the agreement, Mobilization &
Orientation of the Project Team and Office
Set up 0.1
2 Preparatory Meeting with the Client 0.1
3 Secondary Data Collection and review 0.2
4 Meeting with the Stakeholders and Site
Visit 0.2
5 Detailed Topographical survey 0.25
6 Preparation and Submission of the
Inception Report(with work plan) 0.25
D-2 Interim Report 1
1 Engineering Details (Field Survey) 0.5
2 Detailed Geotechnical Investigation 0.5
3 Preparation of Conceptual Master
Planning 0.5
4 Detailed Assessment Works 0.5
5 Visual survey and identification 0.5
6 Preparation and Submission of the Interim
Report
D-3 Draft Report 1.5
1 Preparation of Master Plan and Detailed
Engineering Design of Physical
Facilities(including 3D model) 1
2 Environmental and Social Consideration 0.25

Shrestha-GRID-DCON JV
Technical Proposal for Preparation of Detailed Master Plan of Hospital
Months
Total
SN Deliverables 1 2 3 4 Months
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
3 Cost Estimate, Rate Analysis and BOQ
(including tentative estimate for
demolition building) 0.75
4 Preparation of Construction Drawings 0.75
5 Preparation of Specifications/ Bid
documents 0.25
6 Preparation and submission of the Draft
Report 0.75
7 Presentation of the Draft Report

Shrestha-GRID-DCON JV
Technical Proposal for Preparation of Detailed Master Plan of Hospital
Months
Total
SN Deliverables 1 2 3 4 Months
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
D-3 Final Report 1
1 Capacity Building 0.5
2 Feedback meeting with Client on report
after incorporating comments & suggestion
from Client. 0.5
3 Approval of entire documents from
concerned authories and agencies 0.5
4 Preparation of Final Report 0.75
5 Presentation of Final Report
6 Submission of the Final Report
Note:
1. Different Phases of project
2. Task to be carried out by Client
3. Task to be carried out by Consultant
4. Preparation of report
5. Due Submission Date