Scope: To supply material, labour, tools and equipment to fabricate Vessel as per attachment specification
Delivery: Ex-Work
Date of Delivery: 16 weeks upon purchase order, down payment and AFC drawing received.
Validity: 7 days from date hereof.
Term of payment: 35% Down Payment,
55% Upon Hydro-Test completed,
10% 30days after delivery
Shell Head Design Qty Unit Price Total Amount
Item Description Material OD CS-CS Thk Thk
*JE *JE Pressure Temp. (unit) RM RM
(mm) (mm) (mm) (mm)
1 Surge Vessel 1000L BSEN S275Jr 915 1524 9 0.7 9 0.85 10 Barg 60oC 1 17,650.00 17,650.00
*JE: Joint Efficiency
1 Total Amount : 17,650.00
Note:-
1- That inspection and certification of the above vessel dimensional and surface treatment such as the painting and etc shall be carried out at our
Factory or painting yard as final inspection of goods completed in good order and condition.
2- No Limitation on Material's Country of Origin
Brian Lim.
To Alpha Primax Sdn, Bhd From Brian Lim
Attention Mr. Edmund Date 13/9/2021
Email / Fax alphaprimax@gmail.com Our ref TP/ALP-21-213
INCLUDE:
▪ Design Calculation as per ASME & Fabrication drawing
▪ DOSH Approval & JKJ127
EXCLUDE:
▪ 3rd party inspection.
▪ Internal piping & External frontal piping.
▪ Ladder Cage, Handrail & Platform
▪ Other NDT testing.
▪ Re-qualified of PQR, WPS & WPQ.
▪ Production Test Coupon & Testing
▪ Spare Part, Anchor Bolts & Nuts.
▪ Packing for transportation & shipment.
▪ All others, apart from the above scope of works.