ASSIGNMENT-I

Program : B.ARCH Max. Marks : 15


Course : Project Management Time :
Course code: SAR 1611 Sem : IX
Batch : 2018-2023 Date :2-07-22

1) Expedite your understanding on any one of the following : ( 5 marks)

a)Traditional method of Project Management

( OR)

b) Work break down Levels

2) Attempt any one of the following; (10marks)

a) A construction project consists of 12 activities. The predecessor relationship are


identified by their node numbers as indicated below:

Job Identification Job Identification


A ( 1, 2 ) G ( 4, 6 )
B ( 2, 4 ) H ( 5, 6 )
C ( 2, 3 ) I ( 5, 7 )
D ( 2, 7 ) J ( 7, 8 )
E ( 3, 4 ) K ( 6, 8 )
F ( 3, 5 ) L ( 8, 9 )

Draw the network diagram.

(OR)
b) The maintenance project of a building consists of 10 jobs. The predecessor relationships are
identified by their node numbers as indicated below.

Event Predecessor

1 -

2 1

3 2

4 2

5 2

6 3,5

7 3,4

8 3,7

9 7

10 3,6,8,9

Draw Network diagram for the project.