Professional Documents
Culture Documents
net/publication/340165813
CITATIONS READS
0 6,933
1 author:
Ibrahim Arabi
Ain Shams University
1 PUBLICATION 0 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Ibrahim Arabi on 25 March 2020.
A THESIS
Submitted in partial fulfillment of the requirements for
Concrete project in the Bachelor of Engineering
Submitted By:
Ibrahim Arabi Ahmed Samir
Ehab Mostafa Ahmed Mohamed
Mohamed Mostafa
Supervised By
Associate Prof. OSAMA EL NESR
Associate Professor of RC Structures Faculty of Engineering Ain Shams , Egypt
2020
i
CERTIFICATE OF APPROVAL
Prof. Dr ___________________
Prof. of RC Structures
i
ACKNOWLEDGMENT
First of all, we would like to express all our thanks to GOD for his great help in completing
this report.
Also, we would like to express our sincere thanks to our supervisor Dr. Osama Mohamed Saad
Ahmed ELNESR for his guidance throughout the development of this report.
i
ABSTRACT
The aim of this study is to cover the purpose of why we, as designers, turn to using prestressed
steel for reinforcement instead of reinforcing with steel bars.
Firstly, we tell the reader how the prestressing process was developed and how it reached
Egypt; then we discuss in details the design process, manually and then using computer
programs. Secondly, we explain in details and illustrations how the construction process is
done and what machines nowadays are used.
Finally, we introduce three case studies that we find intriguing to a designer that summarize
the idea of what was introduced in the whole study.
i
Table of Contents
TABLE OF CONTENTS
Table of Contents
ACKNOWLEDGMENT ............................................................................................... i
Abstract ......................................................................................................................... i
__________________________________________________________________________________
ii
Table of Contents
__________________________________________________________________________________
ii
Table of Contents
3.7.1.1 Slabs........................................................................................................ 34
__________________________________________________________________________________
ii
Table of Contents
Chapter IV Construction.................................................................................... 52
Reference ............................................................................................................... 61
__________________________________________________________________________________
ii
List of Figures
LIST OF FIGURES
List of Figures
Figure 1 Cross section and dimensions of 7-wires unbonded tendon ...................... 1
Figure 2 bonded system tendons detail for beams and slabs ................................... 2
Figure 5 Reinforcement details for fully and partial prestressed beams .................. 6
__________________________________________________________________________
x
List of Figures
Figure 33 cable pass according to the desien drawings and pointing location....... 56
__________________________________________________________________________
x
List of Tables
LIST OF TABLES
List of Tables
Table 2.3.1.1 Experimental program for beams .......................................................... 7
Table 2.3.3.1 Experimental results .............................................................................. 8
Table 2.4.1 Specimens details .................................................................................... 11
Table 2.4.2.1 Experimental results ........................................................................... 13
Table 2.4.2.2 Cracking results ................................................................................... 13
Table 2.5.1.1 Details of specimens ........................................................................... 17
Table 2.6 comparetive of experiments results ........................................................... 21
Table 3.4.2.1 Approximate prestress losses ............................................................... 32
Table 3.7.1.1.a Suggested thickness requirements for concrete slabs for
fire endurance…………………………… …………………………………………34
Table 3.7.1.1.b Suggested minimum cover for slabs prestressed .............................. 34
Table 3.7.1.2 Suggested cover thickness for beams prestressed................................ 35
Table 18.1 Minimum area of bonded reinforcement ................................................. 38
Table 17 Concrete cover ............................................................................................ 39
Table 10-3 Allowble stresses in prestressing steel .................................................... 41
Table 10-2 Allowble stresses in concrete .................................................................. 42
Table 10-6 Minimum thickness of concrete cover .................................................... 44
Table 2-14-b Minimum concrete dimensions for fire resistance
for prestressed concrete.............................................................................................. 45
Table 10-7 Minimum concrete cover for cables with curved ducts ........................... 47
Table 10-8 Minimum spacing between the ducts axes in the plan of
the curved ducts ......................................................................................................... 48
Table 10-9 Minimum inside dimensions and minimum allowable
thickness for ducts...................................................................................................... 49
Table 721.2.2.1 Minimum slab thickness .................................................................. 50
Table 721.2.3(2) Cover thickness for prestressed concret for roof slabs................... 50
Table 720.1(1) Avarage tendon cover ....................................................................... 51
Table 3-14 conclusion ................................................................................................ 51
xx
Notations and Definitions
a
Notations and Definitions
* Notations
Fps = stress in prestressing reinforcement at nominal flexural strength, psi (MPa)
Fps = stress in post-tensioned tendons at nominal strength at high temperatures, psi (MPa)
Fpu = specified tensile strength of prestressing reinforcement, psi (MPa)
Fpu = tensile strength of tendons at high temperatures, psi(MPa)
Fse = effective stress in prestressing reinforcement, after allowance for all prestress losses, psi
(MPa)
fy = specified yield stress of reinforcement, psi (MPa)
h = slab thickness, in. (mm)
L = span length of beam or one-way slab; clear projection of cantilever, in. (mm)
l = length of tendon, in. (mm)
M = total applied static moment (unfactored), lb-in. (kN-m)
+
M tq = retained midspan moment, lb-in. (kN-m)
b
Notations and Definitions
c
Chapter I Introduction
__________________________________________________________________________________
1- INTRODUCTION
1.1-Scope
The post-tensioning systems commonly used in building and bridge Construction are grouped
into two principal categories. These are the unbonded and the bonded systems.
The distinguishing characteristic of an unbonded tendon is that, by design, it does not form a
bond along is length with the concrete Unbonded tendons are generally made of single strand
high strength Steel, covered with a corrosion inhibiting coating and encased in a plastic
sheathing (Figure1). The force in the stressed tendon is transferred to the concrete primarily by
the anchors provided at its ends. Variations in force along the tendon is effected by the friction
between the strand and the tendon profile in the concrete member. Since the force in an
unbonded tendon transferred primarily by the anchors at its ends, the long-term integrity of
anchors throughout the Service lite of an unbonded Tendon become crucial
the function of the plastic sheathing is, (i) to act as a bond breaker, (ii) to provide protection
against damage by mechanical handling, and (iii) to form a barrier against intrusion of moisture
and chemicals. The strand coating, commonly referred to as grease, (i) reduces friction between
the strand and the plastic sheathing, and (ii) provides The added protection against corrosion .
Unbonded tendons are typically employed as mono-strands, with each tendon having its
dedicated end anchors. Also, tendons are stressed individually. Recently however, unbonded
tendons consisting of groups of two, or more strands, each wrapped individually, but encased
in a tough group sheathing have been introduced into the market in Europe and overseas. Mono-
strand unbonded tendons have been in use in the United States since the late 1950s. Their
application has been primarily in building construction. A short history of development of
unbonded tendons is given in [Aalami 1990b]. In some literature, the unbonded tendons are
referred to as debonded tendons.
_________________________________________________________________________________
1
Chapter I Introduction
__________________________________________________________________________________
The characteristic feature of a bonded tendon is that, by design, the tendon forms a continuous
bond along its length with the concrete sur rounding it. The bond is achieved through a
cementitious matrix which surrounds the strands, commonly referred to as grout. It acts with
the duct which is encased in the concrete member to complete the bond path between the
prestressing strands and the concrete member. After stressing of a tendon, the grout is injected
into the void of the tendon duct which houses the prestressing strands (Figure 2)
materials of choice. Use of the flat plastic corrugated duct is more common in the US. whereas
elsewhere. flat metal ducts are more widely used. The larger round ducts are for application in
beams and deep members. the strands in these are stressed and locked off simultaneously using
a specially designed multistrand stressing jack .
In this system, the function of the grout is; (i) to provide a continuous bond between the strand
and the duct, (ii) to increase protection against corrosion by acting as a physical barrier to
moisture penetration, and (iii) through its alkalinity, provide an environment non-conductive
for corrosion. The function of the duct is: (i) to maintain avoided path for the strands in the
concrete member during construction, (ii) to transfer the bond between the grout within the
duct and the concrete surrounding, and (iii) to act as additional protection against penetration
of moisture and chemicals into the interior of the duct. The principal function of the anchor
assemblies at the ends is to hold the forces generated in the tendon at stressing, until the grout
is introduced, hardened and cured. Bonded tendons are generally multi-strands. Tendons of up
to 50 strands in one duct are not uncommon Traditionally, the principal application of bonded
tendons has been in bridge construction
In recent years, there has been a growing tendency in the use of external tendons in new bridge
construction, as well as in the retrofit of buildings. Many designers and investigators regard
external tendons as a form of unbonded tendon construction. While admitting their likeness
This Technical Note does not address their application. The focus of this Technical Note is on
tendons which are used in building construction, and which are contained within the body of
the structural member they pre-stress.
In its infancy and throughout later development, due to lack of Knowledge, absence or
inadequacy of relevant specifications and Codes, and possibly short sightedness or aggressive
entrepreneur ship, unbonded post-tensioning systems, which today are viewed as systems with
inherent flaws in their durability performance, were used. These problems are now well
recognized and have been effectively addressed. Today, through a full understanding of the
structural behavior, availability of strong analytical tools, matured specifications and codes
(PTI 1993, ACI 1992, 1989), refined construction techniques (PTI 1994), improved materials
and hardware, owners and engineers can fully realise the advantages of prestressing in their
building projects. This Technical Note examines the features and performance of the unbonded
and the bonded systems as they are available today. It provides a comparative review of the
merits the two Systems.
Let it be clear at the outset both systems if designed detailed and Constructed according to
Current specifications and good practice will provide durable structures meeting code intended
serviceability and strength requirements. Or, If need be, both systems are capable to reach
beyond the minimums stipulated in codes and produce a user-defined level of performance, in
particular With respect to durability. The merits of each, and the selection of a system depends
on the technology. the skilled labor and hardware readily available to the supplier, as well as
the economies of Construction in the local market . None is blessed to be categorically superior
to the other. The following review concludes with a numerical design example, giving the
material quantities which are needed for a frame of a typical parking structure
_________________________________________________________________________________
3
Chapter II State of The Art
__________________________________________________________________________________
-They use
• Rectangular beam with 10-20m span.
• Extra reinforcement in both system.
• Deflection, Bending Moment, Top-Bottom stress, Shear force,
• Manual calculation base on IS-1343:1980,ACI-318 code including all parameter.
2.2.1-Tendons:
Unbonded tendons typically consist of single (mono) strands or threaded bars that remain
unbonded to the surrounding concrete . The strands in unbonded mono-strand systems are
coated with specially formulated grease with an outer layer of seamless plastic extruded in
one continuous operation to provide protection against corrosion, For bonded systems the
pre-stressing steel is encased in a corrugated metal or plastic duct. After the tendon is stressed,
cementitious grout is injected into the duct to bond it to the surrounding concrete. In addition,
the grout creates an alkaline environment which provides corrosion protection for the pre-
stressing steel.
_________________________________________________________________________________
4
Chapter II State of The Art
__________________________________________________________________________________
2.2.2-Design:
The complete analysis and design done in structural analysis tool ADAPT-PT- BUILDER
and also ETABS 2016 Design of Post-Tensioning and RCC Structural Systems, also data
give bending moment, shear force, deflection, mid top stress, mid bottom stress. Size of beam
consider 600mmx750mm,this size and must prefer for both system. Also apply dead load, self
weight live load consider 5kN/m2 ,with standard, column size 500mmx500mm, All losses are
included by span,In beam up to 7 tendon use, Analysis result give total service load
(D.L+L.L+PT)and sustained load(D.L+0.3L.L+P.T) combination.
D.L+L.L+PT
_________________________________________________________________________________
5
Chapter II State of The Art
__________________________________________________________________________________
The main reinforcement of the specimens changed according to the pre stressing index (Ip),
which was defined as the ratio of the yield strength of the pre stressing reinforcement to the
sum of the yield strength of the pre stressing and non-pre stressing reinforcement, as given by
the following equation [9]:
Eq ( 9 )
The prestressing steel strand diameter 15.24-mm had a profile similar to the bending moment
induced from the concentrated loads, as shown in Figs. 5a and 5b
_________________________________________________________________________________
6
Chapter II State of The Art
__________________________________________________________________________________
2.3.1-Test specimens
The variables considered in this study, were concrete compressive strength (43, 72 and 97
MPa), bonded and unbonded tendons and pre stressing index (0%, 70% and 100%), as given
in Table 2.3.1.1 The details of the tested specimens are as follows:
Table 2.3.1.1 (Experimental program for beams)
2.3.2-Test set-up
The beams were subjected to a cyclic loading up to failure using a hydraulic machine of 300
kN capacity. The load was measured using a load cell of 1000 kN capacity . Two concentrated
loads at 1000 mm from mid span were applied on the beam using a stroke control system. The
longitudinal and transverse strains of the specimens were measured by two different methods;
linear variable differential transducers, (LVDT), and electric strain gauges. The strains of non-
pre stressed steel reinforcement were measured in the longitudinal direction. Deflection was
measured at the mid-span and under the concentrated loads. Figure. 8 shows location of the
different instrumentations.
_________________________________________________________________________________
7
Chapter II State of The Art
__________________________________________________________________________________
2.3.3-Experimental Results:
Table 2.3.3.1 summarizes the experimental results: the cracking load P cr at the mid span and
the corresponding vertical deflection Dcr, the maximum load P max and the corresponding
vertical deflection D, the yielding load and the corresponding vertical deflection Dy and the
vertical deflection at failure Du. The table also shows the initial stiffness, which represented
by the slope of load deflection curve before cracking, post cracking stiffness, which represented
by the slope of load deflection curve after cracking up to yielding of reinforcement and the
modes of failure for the tested beams as shown at figure ( 9 )
** According to the pervious observations the non-pre stressed steel improves serviceability of the
beams, because it decreases the crack width and distributes it along the beam length. In addition, the
small crack width produces lower stress concentration at the location of cracks. These results are
complying with those given in the literature for the pre stressed beams with different pre stressing
indices.
_________________________________________________________________________________
8
Chapter II State of The Art
__________________________________________________________________________________
2.3.4-Failure Modes :
_________________________________________________________________________________
9
Chapter II State of The Art
__________________________________________________________________________________
_________________________________________________________________________________
10
Chapter II State of The Art
__________________________________________________________________________________
_________________________________________________________________________________
11
Chapter II State of The Art
__________________________________________________________________________________
2.4.1-Test Set-up :
All specimens were loaded in four-point bending using two symmetrical monotonic
concentrated static loads applied at one-third of the span length as shown in Fig. 12.
Specimens were subjected to a monotonically increasing load up to failure using a load
control test. All measurements, such as beam deflections, strains in steel strands, strains
in steel bars and strains in concrete were recorded twice, immediately after the application
of the load and after (10) minutes later.
Deflection was measured at midspan using dial gage of (0.01) mm accuracy. Electrical
strain gauges were used to measure the strains in prestressing steel, non-prestressing steel
and concrete. Cracks were monitored along the span of the beams. Maximum crack width,
number of cracks and average crack spacing were measured sequentially during loading.
_________________________________________________________________________________
12
Chapter II State of The Art
__________________________________________________________________________________
2.4.2-Experimental results :
• Cracking behavior :
Flexural cracks in all specimens were initiated at the location of pure moment zone
perpendicularly to the longitudinal axis of the specimen and extended up to the
location of the tensile nonprestressed reinforcement. Table 2.4.2 illustrates
experimental and theoretical cracking load as well as experimental and theoretical
deflection at this loading stage as shown at Figure 13 .
From Table 2.4.2.1, it was observed that the presence of prestressing steel has good
contribution to delay the cracking appearance and increase the cracking load.
Crack width, number of cracks and average crack spacing at failure were measured
and recorded throughout the test as shown in Table 2.4.2.2.
Table-2.4.2.2-(Cracking results)
• Load-Deflection response :
The load deflection curves for the tested specimens are shown in Fig.14. It can be
seen that for specimens of (FR) and (PP) groups with tension-controlled and
transition-controlled concrete sections, three distinctive points could be observed.
These points are characterized cracking, yielding and ultimate loads.
_________________________________________________________________________________
13
Chapter II State of The Art
__________________________________________________________________________________
The strain in prestressing strands has been measured using two electrical strain gauges
per each strand which were fixed at midspan section. Accordingly, the stress was
determined by using the actual stress-strain curve of the strand. This stress was
compared with the stress determined according to the mentioned below empirical
equations, which adopted by the ACI-318-2011.
** The magnitude of ultimate load capacity was varied depending on the value of the
reinforcement index. Almost experimental ultimate load results were greater than the
theoretical values. The reason of this can be interpreted that the calculated stress in
prestressing steel, according to equations (4) or (5), was smaller than the experimental
values. In general, comparison of these results indicates good agreement between the
experimental and theoretical results for all the specimens except the compression-
controlled specimens.
2.5-Exp "4":
They use :
• Two prestressed SRC (PSRC) frame beam specimens, which were denoted as UPSRC
(unbonded) and BPSRC (bonded).
• The span between two column centerlines is 8200mm and the clear height of column is
1610 mm.
• The width and the depth of frame beam section were respectively 210mm and 490 mm
.
• The column section were 300mm and 430 mm .
• The two specimens were cast with C40 concrete
• The prestress strength ratio (λ = Ap fpy /(Ap fpy + As fy + Asf fsy )) of the specimens
was about 0.5.
• The average measured effective stress of the tendons at two ends was about 1312 MPa
in UPSRC and 1100 MPa in BPSRC .
_________________________________________________________________________________
15
Chapter II State of The Art
__________________________________________________________________________________
_________________________________________________________________________________
16
Chapter II State of The Art
__________________________________________________________________________________
2.5.2-Measurement :
The strains of longitudinal rebar and steel flange were measured, as shown in
Fig. 16(a). The concrete strain at top and bottom of the frame beams were also
measured, as shown in Fig. 16(b). In addition, displacement transducers were
arranged to measure the vertical deflection of the frame beams (Fig. 16(b)). Fig. 17
shows the pressure sensors and acquisition instruments at two ends of the frame
beam to measure the forces in tendons.
(b)
Figure (16) Test measurement for exp.4
_________________________________________________________________________________
17
Chapter II State of The Art
__________________________________________________________________________________
_________________________________________________________________________________
18
Chapter II State of The Art
__________________________________________________________________________________
2.5.4-Failure mode :
The failure of both frame beams was dominated by flexure effects and three plastic hinges
were developed at beam ends and mid-span. During displacement control stage, as the
displacement increased, longitudinal rebar and steel flange at beam ends and mid-span
yielded in turns firstly. Then, the compression cover concrete crushed and the spall of
concrete was serious. Finally, the compression rebar at midspan and beam ends buckled.
In addition, local concrete split destruction happened at the top of beam-column joint. It
could be resulted from the local compress action caused by tendons, which may cause
initial longitudinal cracks or defects in concrete. The cracks developed during the loading
period and resulted in the split destruction when load and deformation increased. Fig. 19
showed the failure mode of UPSRC and BPSRC frame beams.
Figure 19- the failure mode of UPSRC and BPSRC frame beams.
_________________________________________________________________________________
19
Chapter II State of The Art
__________________________________________________________________________________
2.5.5-Test discussion :
Ductility: A widely accepted indicator used to evaluate the ductility of structure is called
ductilitycoefficient, μ, which is expressed by μ = Δu/Δy (1)
where Δu is ultimate displacement, Δy is yield displacement, as shown in Fig. 20.
The values of μ of UPSRC and BPSRC were listed in Table 4. The ductility coefficients
of UPSRC and BPSRC were 2.91 and 2.84, implying that the prestress tendon form
(unbonded/bonded) seemed to exhibit little influence on the ductility of PSRC frame beam
_________________________________________________________________________________
20
Chapter II State of The Art
__________________________________________________________________________________
_________________________________________________________________________________
21
Chapter III CODES AND STANDERDS REQUIREMENTS
_________________________________________________________________________________
3-MEMBER DESIGN
3.1—One-Way Systems
One-way slabs are addressed in ACI 318-14 Chapter 7. The chapter organization provides
design limits, required strength, required design strength, reinforcement limits, and reinforcing
detailing. Prestressed members are grouped into three design categories: uncracked (U),
transition (T), and cracked (C). Each category is defined according to the maximum calculated
flexural tensile stress under service load conditions. For C members, there is no upper limit on
calculated flexural tensile stresses under service loads, and any combination of stressed and
unstressed reinforcement is permitted. Serviceability requirements related to C and T members
are given in ACI 318
One-way post-tensioned beams and slabs with unbonded tendons are waived from the 1.2Mcr
requirement of ACI 318-14,7.6.2.1, because the undesirable behavior due to sudden transfer of
tensile force from concrete to prestressing reinforcement at first cracking in lightly reinforced
sections does not occur in members with unbonded tendons
22
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
3.1.2 Tendon spacing— The minimum bonded reinforcement requirements for one-way
slabs under ACI 318-14, 7.6.2.3, typically result in the use of No.4 (No.13) bars at 21 in. (500
mm) centers for both positive and negative moments for a 4-1/2 in. (115 mm) thick slab. For
an 8 in. (200 mm) thick one-way slab, No.4 (No.13) bars are required at approximately 12 in.
(300 mm) centers , larger bars can be used at somewhat wider spacing. In consideration of
this amount and spacing of bonded reinforcement,
a maximum tendon spacing of eight times the slab thickness but not more than 5 ft (1.5 m)
is recommended for one-way slabs with normal live loads and uniformly distributed loads
(refer also to 3.3.5). Tendon spacing may need to be adjusted for slabs with concentrated loads,
based on the size, configuration and magnitude of the load concentration. ACI 318 contains
no requirement for maximum tendon spacing or minimum axial compressive stress in one-way
prestressed slabs. It is common practice to use an average minimum effective axial
precompression stress of 125 psi (0.86 MPa) at every cross section tributary to the tendon,
which can be further reduced to 100 psi (0.69 MPa) for short spans with little or no tension
stresses. In certain cases, such as external tendon retrofits, tendon spacing greater than eight
times the slab thickness or 5ft (1.5 m) may be applicable. In such cases, these limits may be
exceeded, provided it can be shown by analysis that the slab system can adequately carry the
design loads.
in accordance with ACI 318-14, 7.7.6. At least one tendon is required in the slab between the
faces of adjacent beams or walls.
Tendons used for shrinkage and temperature reinforcement should be positioned parallel to the
beams and vertically as close as practicable to the center of the slab. Where shrinkage and
temperature tendons support or conflict with the principal slab tendons, variation from the slab
centroid is permissible, but the resultant eccentricity of the total shrinkage and temperature
tendons within the slab should not extend outside the kern limits of the slab cross section.
Figure 21 illustrates details for the use of unbonded tendons as shrinkage and temperature
reinforcement in one-way beam and slab construction.
Figure 21 -Details for use of unbonded tendons as shrinkage and temperature reinforcement
in one-way beam and slab construction. ( Note:1in.= 25.4 mm ).
_________________________________________________________________________________
24
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
3.2—Two-way systems
Two-way slabs are addressed in ACI 318-14 Chapter 8.The chapter organization provides
design limits, design strength, required resistance, reinforcement limits, and reinforcing
detailing.
3.2.1-Analysis-Slab systems prestressed in more than one direction for flexure should be
analyzed in accordance with the provisions of equivalent frame or by more precise methods,
including finite element techniques or classical elastic theory. The equivalent frame method of
analysis has been shown by tests of large structural models to satisfactorily predict factored
moments and shears in prestressed slab systems (Post-Tensioning Institute 1977; Burns and
Hemakom 1977; Scordelis et al. 1959; Cleland et al. 1979). The referenced research also shows
that the yield-line theory accurately predicts the flexural strength of two-way post-tensioned
slabs. Analysis using prismatic sections or other approximations of stiffness, which differ
substantially from the equivalent frame method, may provide erroneous and unsafe results.
Moment redistribution for prestressed slabs is covered in ACI 31 8-14, 6.6.5. ACI 31 8-14,
8.11.6.5, does not apply to two-way prestressed slabs. ACI 318-14, 8.11.6.6, is excluded
because the distribution of moments between column strips and middle strips is based on
tests of reinforced concrete slabs and the concept of column strips and middle strips is virtually
never used in prestressed slabs, almost all of which use a banded tendon distribution (Fig. 3.3.I).
Further, simplified methods of analysis using average coefficients do not apply to prestressed
concrete slab systems. All other provisions of ACI 318-14, 8.11, specifically including the
arrangement of live loads specified in ACI 318-14, 6.4.3, are applicable for the analysis of
post-tensioned slabs. ACI 318 requires that two-way prestressed slab systems be designed as
Class U, with a maximum permissible concrete flexural tensile stress of under service loads.
The lateral load stiffness should be assessed considering the effects of slab cracking (ACI 318-
14, 8.11; Kang and Wallace 2008b; Han et al. 2006). For lateral load analysis, the cracked
section bending stiffness should be used and the torsional stiffness taken as 1/10 of the
torsional member when using the equivalent frame method of analysis and where there is the
potential for extensive cracking; where slabs have highly irregular shapes; where there are long
pour lengths between construction, expansion joints, or both; or where slabs have unfavorable
locations of walls. The cracked section bending stiffness should always be used for the
computation of drift under seismic loads. Strength under lateral loads should be evaluated using
the load factor combinations given in ACI 318-14, 5.3, in conjunction with the provisions of
ACI 318-14, 8.4.1.Evaluation of strength requirements under lateral loads may disclose the
need for reinforcement to resist moment reversals (Han et al.2006). Such reinforcement should
be located within a distance of 1.5h outside opposite faces of the column, where h is the slab
thickness.
3.2.2 Limits for Reinforcement— Two-way post-tensioned slabs with unbonded tendons
are waived from the 1.2Mcr. requirement of ACI 318-14, 8.6.2.2, because the undesirable
behavior due to the sudden transfer of tensile force from concrete to prestressing reinforcement
at first cracking in lightly reinforced slabs does not occur in members with unbonded tendons.
Only at load levels beyond the factored design load is the additional cracking extensive
enough to cause an abrupt change in the load-deflection pattern. Tests have also shown
that it is not possible to rupture, or even yield, unbonded post-tensioning tendons in two-
way slabs before a punching shear failure (Post-Tensioning Institute 1977; Bums and
Hemakom 1977; Hemakom 1975; Kosut et al. 1985; Scordelis et al. 1959; Gerber and Burns
_________________________________________________________________________________
25
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
1971; Smith and Burns 1974; Kosut 1977). The use of unbonded tendons in combination with
the minimum bonded reinforcement requirements of ACI 318-14, 8.6.2.3 and 8.7.5, has been
shown to ensure post-cracking ductility and that a brittle failure mode will not develop at first
cracking
This amount of bonded reinforcement is required within a slab width between lines that are
1.5h outside opposite faces of the column support. Tests on square panel specimens have
shown a steel area of 0.00075 Ac to be adequate to assure sufficient punching shear strength,
where Ac is the tributary cross-sectional area of the slab between panel centerlines
perpendicular to the bonded reinforcement.4-6,34-36 This value was expressed in the code as
0.00075hl, where l is the span in the direction of the reinforcement, to generalize the expression
for rectangular panels, placing more bars in the direction of the longer span. The use of hl as
opposed to Ac is appropriate to determine bonded reinforcement requirements at the interior
columns and reinforcement perpendicular to the slab edge at exterior columns. Tests4-6,34-36
show that it is appropriate to provide bonded reinforcement parallel to the slab edge at exterior
columns on the basis of 0.00075 Ac where Ac is the tributary cross-sectional area of the slab
perpendicular to the direction of the bonded reinforcement between the center of the exterior
span and the slab edge. At exterior columns of flat plates with square panels and no projection
of the slab beyond the exterior column face, the bonded reinforcement parallel to the slab edge
should be 50 percent of the bonded reinforcement perpendicular to the slab edge. Bonded
reinforcement in positive moment areas of two-way flat plates is required where the computed
tensile stress in the concrete at service load exceeds MPa)
The amount of positive moment bonded reinforcement, when required, is specified by Eq.
(18-7) of ACI 318 (18-7)
where the specified yield strength of non-prestressed reinforcement fy shall not exceed 60,000
psi (400 MPa), and Nc is the tensile force in concrete due to unfactored dead load plus live load
D + L. Details of placement for the reinforcement provided in this section are included in
Section 3.3.5. Slab reinforcement spacing requirements specified in Section 7.6.5 of ACI 318
are not applicable to bonded reinforcement in unbonded post-tensioned slabs.
3.2.4 Tendon and Bonded Reinforcement Distribution and Spacing -For uniform
loading, ACI 31 8-14, 8.7.2.3, specifies that the maximum spacing of single tendons or groups
of tendons in one direction shall not exceed eight times the slab thickness, with a maximum
spacing of 8h or 5 ft (1.5 m). In addition, tendons are spaced to provide a minimum average
prestress of 125 psi (0.9 MPa) on the local slab section tributary to the tendon or tendon group,
the section being one-half of the spacing on either side of the center of the tendon or tendon
group. The spacing of individual single-strand tendons is usually governed by the minimum
average prestress requirements. For groups of two or more tendons, the 8h criterion usually
controls maximum tendon spacing. Tendon spacing may need to be adjusted to accommodate
concentrated loads. Horizontal curvature of bundled single-strand tendons should be avoided.
_________________________________________________________________________________
26
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
If this is not possible, additional transverse reinforcement, such as hairpins, and other
accessories may be required at points of horizontal curvature to maintain the horizontal plane
of tendon bundles during stressing. Bundles should be limited to a maximum of four tendons
where significant horizontal curvature is required. Transverse reinforcement may also be
required to control horizontal splitting cracking that can occur due to in-plane forces from
horizontally-curved banded tendons, particularly those curved to avoid openings.
3.2.4.1-Recommended Details of Reinforcement for Banded Tendon Distribution-
The predominant and recommended method of placing tendons in two-way slab systems is the
banded distribution illustrated in ( Figure. 22 ) The use of a banded tendon distribution greatly
simplifies the process of placing tendons, and therefore provides a significant reduction in field
labor cost. The number of tendons required in the design strip-that is, the center-to-center of
adjacent panels-may be banded close to the column line in one direction and distributed in the
other direction. At least two tendons are required by ACI 318-14,8.7.5.6, to be through the
region bounded by the longitudinal reinforcement of the columns in each direction. For lift-
slab construction, the same general details of tendon distribution apply and provisions should
be made for tendons to pass through or over the lifting heads. Even though no tendons are
provided in one direction between bands, the maximum spacing of tendons normal to bands
ensures one-way reinforcement for this part of the slab. Except for small triangular sections
adjacent to the slab edge and closure strips, the area between bands is also prestressed in both
directions. For widely spaced tendons, consideration should be given to placing reinforcement
similar to ACI 318 (Figure 23) in these triangular regions Recommended details for non-
prestressed reinforcement are.
a) Minimum bonded slab reinforcement As,min at columns is As,min =0.00075 Acf ; given in
Table 8.6.2.3 of ACI 31 8-14, where Acf is the larger of cross-sectional areas of the slab-beam
strips of the two orthogonal equivalent frames intersecting at the column (refer to 3.3.3). At
least four No.5 (No.16) bars should be provided in each direction in negative moment areas at
columns. The minimum area of bonded reinforcement parallel to the slab edge at exterior
columns should be based on0.00075Ac', where Ac' is the cross- sectional area of the slab,
perpendicular to the slab edge, between the center of the exterior span and the slab edge.
b) Bonded reinforcement should be placed within a slab width between lines that are 1.5h outside
opposite faces of columns (ACI 31 8-14, 8.7.5.6.3). Maximum spacing of these bars is 12 in.
(300 mm).
c) The minimum length for negative moment bars is one- sixth the clear span on each side of
support. Refer to Item (f) for development considerations.
d) Where service load positive moment produces stress exceeding
minimum bonded reinforcement is given by Eq. (3.3.5.1) of this document or ACI 318-14
Table 8.6.2.3b As,min = Nj0.5/y (3.3.5.1) as discussed in 3.3.3
e) The minimum reinforcement for pos1t1ve moment, when required, should have a length at
least one-third the clear span, with the bars centered in the positive moment area. Refer to Item
(f) for development considerations.
f) Where bonded reinforcement is required along with unbonded tendons to satisfy strength
requirements, in addition to minimum As,min this reinforcement is to be developed in
conformance with ACI 318-14 Chapter 25.
g) Some licensed design professionals provide a continuous bottom mat of non-prestressed
reinforcement in two-way slabs regardless of the bottom tensile stress to mitigate cracking.
This reinforcement can be used to satisfy serviceability and strength requirements and for
tendon supports in one direction
_________________________________________________________________________________
27
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Figure 23 Plan view at slab edge showing added shrinkage and temperature reinforcement
(ACI318-14, Fig. R 7. 7. 6. 3.2)
3.3-ANCHORAGE ZONES
3.3.1-Anchorage Zone Reinforcement -Anchorage zone reinforcement should be
designed in accordance with ACI 31 8-14, 25 .9. This section considers the anchorage zone to
be divided into two zones, as seen in Figure 24.
a) The local zone is the rectangular prism, or equivalent rectangular prism for circular or
oval anchorages, of concrete immediately surrounding the anchorage device and any
associated confining reinforcement.
_________________________________________________________________________________
28
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
b) The general zone in post-tensioned members is the portion of the member through
which the concentrated prestress force is transferred to the concrete and distributed
more uniformly across the section. For intermediate anchorage devices, the anchorage
zone includes the disturbed regions ahead of and behind the anchorage devices. The
general zone includes the local zone
For the local zone, bearing plates are defined as either basic or special anchorage devices. Basic
anchorage devices are typically large, stiff, bearing plates that develop bearing stresses less
than 0.4fc` and can function adequately with no confining reinforcement. The requirements for
basic devices are specified in 5.10.9.7.2 of AASHTO (2014). Special anchorage devices are
typically smaller bearing plates with more complex geometries, multiple bearing planes,
integral wedge plates, and stiffening ribs, which develop high bearing stresses and require
confining reinforcement to function properly. Special devices are required to pass acceptance
tests outlined in 10.3.2 of AASHTO (20 15). For single-strand anchors, ACI 318 allows
anchorage devices that meet the bearing strength requirements of ACI-423.7. Anchorage
dimensions should be such that average bearing stresses on concrete should not exceed
permissible concrete compressive stress at transfer,
given as (4. l a)
and at service (4. lb)
where fcP is permissible concrete compressive stress; fci` is strength of concrete at time of
initial prestress; fc' is specified concrete compressive strength , Ab' is maximum area of the
portion of the concrete anchorage surface that is geometrically similar to and concentric with
the area of the anchorage; and Ab is net bearing plate area. The average bearing stress P/Ab
in the concrete is calculated by dividing the force of the prestressing steel by the net bearing
area between concrete and bearing plate or other structural element of the anchorage that has
the function of transferring force into the concrete. Tests have shown that to function
properly at this stress level, with an acceptable factor of safety against failure, backup bars
are required as described in ACI 31 8-14, (Sanders et a!. 1987; Falconer and Wilson 1988).
An acceptable detail is illustrated in Figure 24 The two No.4 (No.13) horizontal bars are
usually adequate for single- strand anchors. For more complex general zones, ACI 318 allows
the following methods for analysis and design:
a) Equilibrium-based plasticity models; for example, strut-and-tie models
b) Linear stress analysis including finite element analysis or equivalent
Simplified equations where applicable For design, ACI 31 8-14, 25.9.2.1, stipulates a load
factor of 1.2 be used on the maximum tendon jacking force. The strength reduction factor
for post-tensioning anchorage zones for normal weight concrete is 0.85 (ACI 318-14
Table 21.2. 1). Additional guidance for anchorage zone design can be found in Sanders
et al. (1987), Breen et al. (1994), and Post-Tensioning Institute (2000a). Anchorage zone
reinforcement can be spirals, stirrups, orthogonal reinforcement, headed shear stud
reinforcement, or combinations of these. Groups of anchorages should be restrained with
reinforcement in a direction perpendicular to tendons and extending through the entire
group of anchorages. All orthogonal reinforcement should be mechanically anchored
around reinforcement running parallel to the tendons. Spirals, stirrups, or orthogonal
reinforcement should be fully developed. The clear distance between bars or pitch of
_________________________________________________________________________________
29
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
spirals used as anchorage zone reinforcement should be not less than the maximum size of
the aggregate plus 1/2 in. ( 13 mm) or 1-1 /2 in. (40 mm).
Figure 25-Anchorage zone reinforcement for groups of 112 in. (13 mm) diameter
2 70k (1860 MPa) single-strand tendon anchorages in slabs (ACI 318-14, R25. 9. 4.4. 6).
(Note: 1 in. = 25. 4 mm.)
3.4-Design Considerations
3.4.1—Tendon Stress at factored load
Equation (6.3a) or Table 20.3.2.4. 1 of ACI 318-14 was developed primarily from test results
of beams and is limited to members with span-depth ratios of 35or less (Mattock et al. 1971 )
Where;
_________________________________________________________________________________
30
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
fps is the stress in prestressed reinforcement at nominal strength; fse is the effective stress in
prestressed reinforcement after allowance for all prestress losses; pp is the ratio of prestressed
reinforcement Aps/bdp; and fpy is the specified yield strength of prestressing reinforcement,
psi (MPa). In all cases fps should not exceed fpy.
Tests have shown that Eq. (6.3a) overestimates the amount of stress increase in unbonded
tendons in one-way slabs, two-way flat plates, and flat slabs with higher span-depth ratios
(Mojtahedi and Gamble 1978). For members with span-depth ratios greater than 35,fps is
calculated using Eq. (6.3b) or ACI 31 8-14 Table 20.3.2.4. 1 for design stress in unbonded
tendons
ACI 318 eliminated the requirement that the tendon stress after transfer be less than 0.82fpy
for less than 0.74fpu Whereas this condition could theoretically exist in the interior of a beam
away from anchor locations, it was not observed to result in any field performance issues.
3.4.2—Prestress losses
Prestress losses, considering the factors noted in Section 18.6 of ACI 318, should be
calculated by the design engineer and stated on the design drawings. Articles have been
published that make it possible to calculate reasonably accurate values for the various
code-defined sources of loss without excessive effort.45 For typical applications, the
values of pre-stress loss given in Table 3.4.2.1 may be used in lieu of more de-tailed
loss calculations. The loss values in Table 3.4.2.1 are based on use of normal weight
concrete and on average values of concrete strength, prestress level, and exposure
conditions.
Prestress losses may vary significantly above or below the values in Table 3.1 in cases
where the concrete is stressed at low strengths, where concrete is highly prestressed, or
in very dry or very wet exposure conditions. The loss values in Table 3.1 do not include
losses due to friction or anchor seating losses. Design calculations should consider
friction losses in accordance with Section 18.6.2 of ACI 318. Some portion of the
friction loss can usually be offset by use of temporary initial tendon stresses in excess
of 0.70 fpu . Special consideration should be given to friction losses whenever tendons
in excess of 100 ft (30 m) long are stressed from only one end.
For calculation of friction losses for greased unbonded strand tendons in plastic sheathing using
the formulas in Section 18.6.2 of ACI 318, the friction factor , usually ranging from 0.05 to
0.25, and the wobble factor K, usually ranging from )5 to 15 x 10-4/ft (15 to 50 x 10-4/m) may
be used for design calculations. It may be necessary to obtain more precise values for the
friction-factor and wobble-factor coefficients to calculate tendon elongations during stressing
to conform with the 7-percent tolerance specified in Section 18.18.1 of ACI 318 for comparing
tendon force as measured by gage pressure and tendon elongation.
_________________________________________________________________________________
31
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
3.5—Average Prestress
3.5.1-Minimum Average prestress—The average prestress is defined as the total
prestress force (after losses) divided by the total area of concrete. There has been much
satisfactory experience in recent years in one-way slabs and flat plates with an average
prestress of about 125 psi (0.9 MPa). Lower values have also been used successfully for
short span applications. These short span applications can be characterized as having flexural
stresses substantially below 6 f c psi (0.5 f c MPa), minimal volume-change effects, and
vertical element stiffness such that restraint to shortening is minimized. It should be noted
that the125 psi (0.9 MPa) minimum average compressive stress for two-way slabs in ACI
318-14, 8.6.2. 1, was based on punching shear criteria (Bums and Hemakom 1977) and not
flexural behavior. ACI 3 1 8- 1 4, 8.6.2.1 , clarified that the 125 psi (0.9 MPa) minimum
prestress must apply at all slab sections along the tendon group.
carrying capacity. Reinforcement required by ACI 318-14, 7 .6.2, is not required to satisfy
Chapter 25 of ACI 318-14; the top and bottom reinforcement is not even required to overlap.
In ACI 31 8-14,7.7.4.4, positive moment bars need only be L/3 in length, centered in the span,
and negative moment bars need only extend one-sixth the clear span on each side of the
support. Restraint-to-shortening cracking has been observed in the space between the ends
of the top and bottom bars detailed in accordance with ACI 31 8-14, 7.7.4.4. Some licensed
design professionals extend at least one-third of the bottom reinforcement in single-span slabs
or one-fourth of the reinforcement in continuous span slabs to the full span length as an
added element for structural integrity. In accordance with ACI 318-14, 7.7.4.2 or 7.7.4.3,
bonded reinforcement required for strength in both beams and slabs is required to be detailed
in accordance with the provisions of ACI 31 8-14 Chapter 25, with sufficient development
length for the positive and negative moment bars, to ensure that the bonded reinforcement will
function as an independent load-carrying system
3.7 - Fire resistance -Fire resistance ratings can be determined in accordance with the heat
transmission and dimensional provisions of PCI MNL-124-11,6.9.1, or by the rational design
procedures for determining fire endurance discussed in PCI MNL-124-11, 6.9.2. Additional
references are found in Post- Tensioning Institute (2000b), ACI 216.1,and ASTM E119. ASTM
E 119 includes a guide for classifying construction as restrained or unrestrained. A restrained
member may develop considerable axial forces due to the lateral stiffness of the supporting
elements. This allows the member to arch and may improve its ability to support load.
Similarly, rotational end restraint may assist load-carrying capacity. If the supporting
members are too flexible and cannot restrain the expansion of the member, or are incapable
of resisting the axial forces caused by the expansion of the member, the member should be
treated as unrestrained
temperature is 800°F (430°C). restrained slabs, there are no steel temperature limitations, but
the heat transmission end-point temperature limitation (250°F [140°C]) is the same as for
unrestrained slabs. Fire tests of axially restrained slabs indicate that slabs with unbonded post-
tensioned reinforcement behave approximately the same during a fire as reinforced concrete
slabs of the same dimensions. Accordingly, the required cover for post-tensioning tendons in
axially restrained slabs could be essentially the same as the cover specified by the International
Building Code (International Code Council 2015) for mild reinforcement in slabs. Applying
these criteria to post- tensioned slabs, the suggested slab thickness is provided in Table
3.7.1.1a and cover is as recommended in Table 3.7.l .l b (ACI 2 1 6.1; Bailey and Ellobody
2009).
Table 3.7.1.1a-Suggested thickness requirements for concrete slabs for fire endurance (From
ACI216.1-14 Table 4.2)
_________________________________________________________________________________
34
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
_________________________________________________________________________________
35
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
3.8-Materials
3.8.1-Tendons
ACI 423 .7 specifies the testing protocols for tendons and anchorages. Key elements of the
specification are summarized in the following sections.
3.8.1.2-Anchorage Devices-ACI 423.7 and ACI 318-14, 25.8. 1, require the anchorage
devices for unbonded tendons to develop 95 percent of the specified strength fpu The actual
breaking strength of a length of prestressing reinforcement is an unknown quantity, known
after the fact, only for the sample tested. For a discussion of actual-versus-specified strength in
this context, refer to Bondy (2008). In either case, this is much higher than the maximum
permissible design stress for unbonded tendons fps. discussed in section 3.4
movement of the tendon. All coupler components should be completely encapsulated before
final encasement in concrete. Anchorages and couplers in aggressive environments should be
encapsulated.
3.9-Protection Materials
3.9.1-Post-tensioning Coating-Unbonded single-strand tendons should use a corrosion-
inhibiting coating in conformance with ACI 423 .7.
3.10-Concrete cover
Specification of concrete cover for unbonded tendons should consider the placement tolerances
specified in ACI 31 8-14, 26.6.2.1 a, and the exposure conditions. The use of high-quality
concrete, adequate cover, good construction practices, and a limit on the amount of water-
soluble chloride ions in the concrete (ACI 318-14,19.3) are all necessary to ensure long-term
durability, particularly in aggressive environments. At the minimum, the use of at least the
additional cover specified in ACI 31 8-14, 20.6.1, and consideration of a somewhat higher
average prestress level, is recommended for applications exposed to deicing chemicals or for
locations in the immediate vicinity of coastal regions. What is considered as the immediate
vicinity is left to the judgment of the licensed design professional. Some guidance is given in
ACI 362. 1R. Extra cover cannot be a substitute for good quality concrete. At angled slab edges,
minimum concrete covers should be maintained to all parts of the anchorage. Angled pocket
formers or angled block-outs should be such so that the anchors and anchorage cavity areas
have adequate cover for protection against of corrosion and fire.
_________________________________________________________________________________
37
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table 18.1 Minimum area of bonded reinforcement(See Clauses 18.8.1, 18.8.2, and 18.9.2.)
_________________________________________________________________________________
38
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
*This refers only to concrete that will be continually dry within the conditioned space, i.e.,
members entirely within the vapour barrier of the building envelope.
†The cover for a bundle of bars shall be the same as that for a single bar with an equivalent
area.
‡The specified cover from screeded surfaces shall be at least 1.5 times the nominal maximum
aggregate size to reduce
interference between aggregate and reinforcement where variations in bar placement result in
a cover smaller than specified.
Notes:
(1) Greater cover or protective coatings may be required for exposure to industrial chemicals,
food processing, and other corrosive materials. See PCA IS001.08T.
(2) For information on the additional protective measures and requirements for parking
structures, see CAN/CSA-S413.
(3) For information on the additional protective measures and requirements for bridges, see
CAN/CSA-S6.
_________________________________________________________________________________
39
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
(b) where the depth of a flexural member, the thickness of a wall, or the smallest dimension of
a column is
(i) 200 mm or less: ±8 mm;
(ii) larger than 200 mm but less than 600 mm: ±12 mm; and
(iii) 600 mm or larger: ±20 mm;
(c) lateral spacing of bars: ±30 mm;
(d) longitudinal location of bends and ends of bars: ±50 mm; and
(e) longitudinal location of bends and ends of bars at discontinuous ends of
members:±20 mm.
Note: Where reinforcement is added to help provide a more rigid reinforcing mat or cage, as
for instance in prefabricated reinforcing cages, such additional reinforcement is not subject to
the tolerances of this Clause, except for the minimum cover requirements.
18.6.2 In lieu of a more accurate determination of fpr based on strain compatibility, the
following approximate values of fpr may be used:
(a) for members with bonded tendons, provided that c /dp is not greater than 0.5 and fpe is not
less than0.6fpy
where kp = 2(1.04 – fpy /fpu ) and c shall be determined assuming a stress of fpr in the tendons;
Note: Further information can be found in the Cement Association of Canada’s Concrete
design handbook
(b) for members with unbonded tendons:
_________________________________________________________________________________
40
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
10-3-1-4 Relationship between ultimate stress (fpu) and yield stress in tension (fpy) for
prestressing steel shall be taken based on steel type and according to the following
relationships:
fpy / fpu = 0.80 for deformed bars (10-1)
fpy / fpu = 0.85 for normal relaxation stress – relieved strands, wires and smooth bars (10-2 )
fpy / fpu = 0.90 for low relaxation stress-relieved strands and wires (10-3)
_________________________________________________________________________________
41
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
_________________________________________________________________________________
42
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
10-3-3-1-5-b For prestressed members with unbonded prestressing tendons where the span
to effective depth ratio shall not exceed 35, stress in pre stressing steel at ultimate limit moment
of the section Mu shall be calculated from the following equation (10-8)
fps Shall not exceed fpy or ( fpe +420) whichever is less; stress is in N/mm2
10-3-3-1-5-c For prestressed members with unbonded prestressing tendons where span to
effective depth ratio is greater than 35, stress in prestressing steel at ultimate limit moment
shall be calculated from the following equation ( 10-9)
fps Shall not exceed fpy or ( fpe +200) whichever is less; stress is in N/mm2
10-3-3-1-7-b For two-way slabs and flat slabs with constant depth, the minimum bounded
non-prestressed steel is as follows:
1 -In positive moment area, minimum bonded non-prestressed steel in section shall satisfy the
following equation
_________________________________________________________________________________
43
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
10-3-4-Prestress losses
10-3-4-1-1 Loss of prestress affects the behavior of prestress
members under service loads. The loss of prestress is divided into two
groups.
a. Immediate loss of prestress due to: b. Time dependant losses due to:
1. Anchorage slip at transfer 1. Shrinkage of concrete
2. Elastic shortening of concrete 2. Creep of concrete
3. Friction 3.Relaxation of prestressing steel stress.
10-4-3-6-Slab reinforcement details
• For distributed and normal live loads, the distance between tendons or tendon groups in one
direction shall not exceed six times slab thickness or 1.5 m or the larger dimension of duct (for
non circular ducts)
• Tendons are located such that minimum average stress of prestressing forces in one tendon
after all prestress loss shall be higher than 0.9 N/mm2 for slab section attributed to one tendon
or group of tendons
• Number of tendons in shear section over column shall not be less than two in each direction
10-5-3-1-Bonded tendons
10-5-3-1-2- Concrete cover for rust protection- The concrete cover for rust protection
shall be determined based on: the environmental conditions specified in table (4-11), and mix
design and constituents as shown in table (10-6). Recommendations concerning concrete
materials and mixtures detailed in chapter two of this code shall be applied on data of table
(10-6) and requirements of prestressed concrete in section (10-2). The cement content in the
mix shall not be less than 350 kg per cubic meter of concrete in addition to satisfying
requirements of table (2-13).
_________________________________________________________________________________
44
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table (2-14-b) Minimum concrete dimensions in (mm) for fire resistance of pre-stressed
concrete
Concrete cover measured from external of ducts shall not be less than 50 mm or concrete cover
specified in section (10-5-3-1) and tables (10-6) and (2- 14-b) plus diameter of stirrup, or those
shown in figures (27) and (28), whichever is greater and with due consideration to use concrete
cover made of dense concrete. As for curved cables the requirements of section (10-5-5) shall
be observed.
_________________________________________________________________________________
45
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Figure. ( 29) Minimum concrete cover and the distances between cable ducts for post-
tensioning systems ( Bundled Cables)
10-5-5-2-Concrete cover To avoid the breakage of the concrete cover perpendicular to the
plane of curvature of the cables and in their plane, the cover thickness shall be chosen according
to Table (10-7). In this case, the movement of the ducts that may result in radial forces
perpendicular to the visible concrete surface shall be prevented using stirrups fixed inside the
structural element.
10-5-7-1-Duct Sizes
The inside duct diameter shall exceed that of the cable diameter by at least 6- mm when using
a single cable inside the duct. The area of the duct void shall not be less than twice the cross-
sectional area of a group of cables inside the duct (preferably 2.5 times). Table (10-9) shows
the minimum allowable inner dimensions and thickness for the ducts. For the ducts used in
post-tensioning cables, a minimum straight distance of 50 cm shall exist before the curvature
starts inside the duct.
_________________________________________________________________________________
46
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table (10-7) Minimum concrete cover for cables with curved ducts measured from the side of
curvature center
_________________________________________________________________________________
47
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table (10-8) Minimum Spacing Between The Ducts Axes In The Plane Of The Curved Ducts
_________________________________________________________________________________
48
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table (10-9) Minimum inside dimensions and minimum allowable thickness for ducts*
_________________________________________________________________________________
49
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
3.13-IBC-2009
721.2.2-Concrete floor and roof slabs. Reinforced and prestressed floors and roofs shall
comply with Section721.2.2.1.
721.2.2.1- Reinforced and prestressed floors and roofs. The minimum thicknesses of
reinforced and prestressed concrete floor or roof slabs for fire-resistance ratings of 1 hour to 4
hours are shown in Table 721.2.2. 1.
TABLE 721.2.2.1 Minimum Slab Thickness (inches)
721.2.3.1-Slab cover. The minimum thickness of concrete cover to the positive moment
reinforcement shall comply with Table 721.2.3(2) for prestressed concrete. The table is
applicable for solid or hollow-core one-way or two-way slabs with flat undersurfaces. This
table is applicable to slabs that are either cast in place or precast. For precast prestressed
concrete not covered elsewhere, the procedures contained in PCI MNL 124 shall be acceptable.
TABLE 721.2.3(2) Cover Thickness For Prestressed Cconcrete Floor Or Roof Slabs (inches)
_________________________________________________________________________________
50
Chapter III CODES AND STANDERDS REQUIREMENTS
__________________________________________________________________________________
Table 3 – 14 - Conclusion
Parameters Bonded P-T System Unbonded P-T System
Eccentricity Less available due to duct size and minimum passage More due to its compact
required for grouting top as pass through arrangement
Friction More due to the friction between corrugations of duct Grease reduces friction between
Losses and cable while stressing cable and smooth sheathing
Load Lesse due to less “e” and more Friction More due to more “e” and less
Balancing Friction
Serviceabilit Less control on; More control on;
y Aspects 1.TensileStresses 1.TensileStresses
2.Long-termDeflection 2.Long-termDeflection
4- CONSTRUCTION
4.1-Construction Scope
• In slab-on-ground construction, unbonded tendons are typically prefabricated at a plant
and delivered to the construction site, ready to install
• The tendons are laid out in the forms in accordance with installation drawings that as
shown in Figure (30).
• After the concrete is placed and has reached its required strength, usually between 3000
and 3500 psi (“pounds per square inch”), the tendons are stressed and anchored.
• The tendons, like rubber bands, want to return to their original length but are prevented
from doing so by the anchorages
• The fact the tendons are kept in a permanently stressed (elongated) state causes a
compressive force to act on the concrete.
• The compression that results from the post-tensioning counteracts the tensile forces
created by subsequent applied loading (cars, people, the weight of the beam itself when
the shoring is removed).
• This significantly increases the load-carrying capacity of the concrete.
• Since post-tensioned concrete is cast in place at the job site, there is almost no limit to
the shapes that can be formed.
➢ Limitations of Prestressing
The limitations of prestressed concrete are few and really depend only upon the imagination of
the designer and the terms of his brief. The only real limitation where prestressing is a possible
solution may be the cost of providing moulds for runs of limited quantity of small numbers of
non-standard units.
_________________________________________________________________________________
52
Chapter IV Construction
_________________________________________________________________________________
_________________________________________________________________________________
53
Chapter IV Construction
_________________________________________________________________________________
process of loading the coil inside the container, people should stay away from those who are
experienced.
6- Seal the bowl on the coil and tighten the provisions and make sure that.
7- The coil is loosened and the crown on which the weight and number of the coil is written is
retained.
8- Ensure that the cutting area is clean.
9- We begin the process of cutting by preparing the electrical connections necessary to operate
the cutting rocket according to the required voltage.
10- In the case of a sample request for the test preferably get rid of the first 5 m and take the
sample after that and the sample is within 1.5 meters and is encapsulated And maintain with
the writing of all its data from the number and weight.
11- The cutting process begins according to the table shown where we increase 40 cm more
than the length in the design tables in the case of live Screwing them.
12- Is made onion form of the dead hand, which is not tensile .
13- The onion is made by means of a special machine, where the cable is placed inside the
frame and the grip is held according to the cable size - 13 or 15 mm It is driven by a hydraulic
jack and thus is obtained by this shape.
14- Cable cutting process need from 5 to 6 people) 1 for cable pulling, 2 for size, 1 for cutting
and 2 for onion
15-.Cables are coiled in order to facilitate their transfer.
16- Cables should be covered and placed on wooden veins so as to keep them from dust and
dust that affect negatively in the coefficients Friction.
Figure (31) Mark the path of strands Figure (32) opening and clicking of tendon place
_________________________________________________________________________________
54
Chapter IV Construction
_________________________________________________________________________________
_________________________________________________________________________________
55
Chapter IV Construction
_________________________________________________________________________________
Second : All the links between the pipes and some of them or pipes and anchor are blocked by
duct tape and is also at the area of Where the cables appear last one and a quarter meters pipes
are blocked using adhesive. Roll on each cable at the end of the pipe (denzo tape) or fill The
end of the duct (hand pipe) in terms of dead end silicon
Thirdly : PVC pipes are placed as inputs and injections. Pipe diameter 10 mm. One is placed
at the anchor and the other At the end of the pipe taking into account the good packaging around
with adhesive or silicon. The distance between these pipes, which are placed in a vertical
position does not increase About 15 m .
Fourth : After placing all these accessories, make sure that the cable paths do not have any
deviations and according to the design drawings and point locations High and low oil as shown
in Figure (33).
Fifth : Make sure the iron of the cables conform to the design drawings.
Sixth : Ensure that the number of cables in accordance with the plans. The distances between
them are according to the drawings and thus the ceiling is adopted for casting.
This process requires 9 individuals :
-Distribute the chairs
-one For mounting with stapler
-two to connect it to the pipe containing cables
-two to put the sticker
-two To place the injection pipes...
Figure (33) cable pass according to the desien drawings and pointing location
_________________________________________________________________________________
56
Chapter IV Construction
_________________________________________________________________________________
_________________________________________________________________________________
57
Chapter IV Construction
_________________________________________________________________________________
_________________________________________________________________________________
58
Chapter IV Construction
_________________________________________________________________________________
with injection material, including vertical pipes, due to the shrinkage of the mortar after a
period and it is advisable to use additives that reduce Shrinkage of cement mortar
-After completion of the kit the marking of the spray is marked as carried out and the marking
of the painting is carried out.
-In case of blockage of any path is made a light hole in the middle of the distance between the
open and closed part and so on until it is determined by - Use constant air pressure during the
light hole operation until it does not reach the cables
-After the completion of the injection process must be cleaned places of descent mortar and
collect the excess and cut cables in the process of tightening and assembled in boxes .
-As a scrap and cut vertical pipes and protruding for safety and safety.
-Upon the completion of the injection process, the work of the slabs after the tensile will be
completed on site .
_________________________________________________________________________________
59
Chapter IV Construction
_________________________________________________________________________________
_________________________________________________________________________________
60
Reference
________________________________________________________________________________________
Reference
Chap.I - Aalami, B.O. 1994b. Unbonded and Bonded Post-Tensioning Systems in Building
Construction, PTI Technical Notes Issue 5. Post-Tensioning Institute, Phoenix, AZ.
Exp 1 - Behavior of bonded and unbounded prestressed normal and high strength concrete
beams: accepted 21 June 2012
Exp 2 - Experimental and numerical studies on seismic behavior of bonded and unbonded
prestressed steel reinforced concrete frame beam: accepted 7 April 2018
Exp 3 - Cracking and deformability of bonded and unbonded prestressed concrete beams under
monotonic static loading :13 November 2017
Exp 4 - International Journal of Advance Engineering and Research Development Volume 4,
Issue 4, April -2017- Comparative Study Of Bonded & Unbonded Post-Tensioning For Long
Span Beam In Building
Chap.III - ACI Committee 318. 2008. Building Code Requirements for Structural Concrete
and Commentary, ACI318-08. American Concrete Institute, Farmington Hills, MI, 465 pp
Chap.III - ACI 423.3R-17 Recommendations for Concrete Members Prestressed with Single-
Strand Unbonded Tendons Reported by Joint ACI-ASCE Committee 423
Chap.III - CSA A23.3-04 Design of concrete structures
Chap.III - ECP-203 -2007 - 2018
Chap.III - IBC-2009
Presentation on prezi
https://prezi.com/view/R4JcEGsMh5STCI20MHL7/
_________________________________________________________________________________
61