In Assignment 2
In Assignment 2
22. PB/209/2018 10th The Office of Larson and In a site visit it has been
august Deputy Toubro seen that the work has
2018 Engineer, some demerits like the
National pot holes has not been
Highway filled properly and
division, approach slab work has
Satara not been done properly.
23. PB/1928/2018 19th July The Executive Larson and The contractor has been
2018 Engineer, Toubro requested to construct a
National new bridge after
Highway examination of the old
Division, bridge and plan the
Kolhapur details accordingly.
24. PB/292/2018 22nd Oct The Office of Larson and In the site visit it has
2018 Deputy Toubro been noticed that there
Engineer, are many faults in the
National site.
Highway
division,
Satara
25. PB/295/2018 26th Oct The Office of Larson and It was instructed to fill
2018 Deputy Toubro the pot holes and
Engineer, prepare programme for
National Sub Grade, GSB, DLC &
Highway PQC for dust control.
division,
Satara
26. LT/TIIC/KHRP/PL/AE/174 2nd Jan Larson and The team The contractor informed
2018 Toubro leader, that the road repair and
Highway pot filling work had been
Engineering carried out thoroughly.
Consultants,
Karad.
27. NHPKG2-GEN-HEC-LT- 4th Jan The team Larson and It was informed to the
TN/0278 2019 leader, Toubro contractor that after
Highway repeated letters the pot
Engineering hole management was
Consultants, not done thus it would
Karad. now be done by the
internal department and
the double the cost
would be cut from there
account.
th
28. NHPKG2-GEN-HEC-LT- 8 Jan The team Larson and It is again reminded to
TN/0284 2019 leader, Toubro the contractor about the
Highway pot holes and if they fail
Engineering to complete it then the
Consultants, department would take
Karad. the actions as it
mentioned previously.
29. NHPKG2-GEN-HEC-LT- 27th June The team Larson and It is brought to notice to
TN/348 2019 leader, Toubro the contractor of how
Highway many faulty work is going
Engineering on within the project
Consultants, with no rectification of
Karad. pot holes and no proper
weep holes, etc.
30. PB/1782/2019 13th Aug The Executive Larson and It was instructed to fill
2019 Engineer, Toubro the pot holes with
National emulsion or WMN during
Highway the monsoon period and
Division, afterwards with bitumen.
Kolhapur
31. NHPKG2-GEN-HEC-LT- 16th Aug The team Larson and The contractor is
TN/0383 2019 leader, Toubro reminded of the
Highway obligations of Art. 3 Sub
Engineering Clause 3.1.4, Art. 16 Sub
Consultants, Clause 16.1.1 and 16.1.2
Karad.
32. NHPKG2-GEN-HEC-LT- 27th Aug The team Larson and The contractor is
TN/0390 2019 leader, Toubro reminded of the pot
Highway holes filling work and
Engineering referred to previous
Consultants, letters about it. If it is not
Karad. complied with then the
department would take
necessary actions.
33. PB/2172/2019 24th Sept. The Executive Larson and It is instructed to fill the
2019 Engineer, Toubro pot holes and if there is
National any mishaps due to it
Highway then the contractor
Division, would be soley
Kolhapur responsible.
34. PB/366/2019 16th Nov. The Office of Larson and During site inspection
2019 Deputy Toubro many irregularities were
Engineer, seen and a list of
National problems where sent
Highway including non fixing of
division, pot holes , low quality of
Satara overall work, etc.
35. SE/NHC-Pune/PB-1/ 2460 27th Nov. Government The It was informed in ths
of 2019 2019 Of Executive letter about the
Maharashtra, Engineer, manhandling of the staff
public works National of the contractor and
department Highway they were instructed to
Division, carry out the work with
Kolhapur police protection.
36. PB/2639/2019 5th Dec. The Executive Larson and It was informed to the
2019 Engineer, Toubro contractor that this
National situation of
Highway manhandeling of staff
Division, occurred because they
Kolhapur were not competent
enough in there work
which led to agitated
public and resulted in the
aforementioned problem,
however the office will
provide any necessary
help required by them.
37. LT/TIIC/KHRP/PL/AE/321 15TH July Larson and The The contractor assured
2018 Toubro Executive that the work was done
Engineer, diligently and they would
National update them about daily
Highway maintainence with
Division, pictures.
Kolhapur
38. LT/TIIC/KHRP/PL/AE/988 9th Oct Larson and Chief The Contractor has
2020 Toubro Engineer, notified the achievement
National of the project milestone-
Highway 3.i.e. 60% of the financial
(PW) Navi progress with respect of
Mumbai the contract price in the
month of Aug 2020.