You are on page 1of 18

Journal of Energy Storage 42 (2021) 102975

Contents lists available at ScienceDirect

Journal of Energy Storage


journal homepage: www.elsevier.com/locate/est

Impact of the deployment of solar photovoltaic and electrical vehicle on the


low voltage unbalanced networks and the role of battery energy
storage systems
Ahmed A. Raouf Mohamed a, *, Robert J. Best a, D. John Morrow a, Andrew Cupples b, Ian Bailie b
a
EPIC Research Cluster, School of Electronics, Electrical Engineering and Computer Science, Queen’s University Belfast, Belfast, UK
b
Northern Ireland Electricity Networks, Belfast, UK

A R T I C L E I N F O A B S T R A C T

Keywords: The deployment of low carbon technologies (LCTs) such as solar photovoltaics (PVs) and electric vehicles (EVs) is
Electric vehicles increasing due to their various benefits. However, their rapid integration in the residential networks imposes
Solar PV critical technical issues to the network operators. In this paper, a sensitivity analysis is conducted to investigate
Unbalanced LV networks
the impact of these technologies on low voltage unbalanced residential networks located in Northern Ireland.
Battery energy storage systems
Low Carbon Technologies
Different penetrations are investigated, and the results are assessed using various technical indices. The simu­
lations are performed using actual load measurements in a 10-minute resolution obtained from the network
operator of Northern Ireland. The impact of LCTs on the phase imbalance is considered by analyzing the voltage
unbalance and neutral losses. The results suggest that monitoring each feeder and phase separately and consider
the voltage unbalance in the assessment as it can be violated without a voltage magnitude violation occurring, in
addition, the farthest nodes from the transformer bus were found to be very sensitive to violations. The solution-
based community battery energy storage systems (BESS) is investigated by introducing sizing and scheduling
algorithms to solve the network issues and enhance the network performance using black-box optimization. The
results proved the wide capability of the community BESS in providing the network with different services. The
main purpose of this study is to provide a full understanding of the future challenges posed by the deployment of
LCTs and the role of BESS in accelerating the transition towards a low carbon future by supporting the network
operation.

1. Introduction levels. The main issue with the LVRN is the lack of measurement devices
and monitoring. In Northern Ireland, there is as of yet no policy decision
Distribution system operators (DSOs) are facing major challenges for smart meter rollout, which contributes to the lack of visibility of the
arising from the rapid deployment of low carbon technologies (LCTs) on LV network. Hence, it is very difficult for the DSO to take the proper
the low voltage residential network (LVRN). The two main contributing actions at the right time to avoid curtailing power delivery. Further­
technologies are solar photovoltaics (PVs) and electric vehicles (EVs). more, regulations are enforced by the ESQCR to protect the network
Their deployment is increasing rapidly due to their economic and security and power quality such as the G98 connection recommendation
environmental benefits, in addition to the vast decrease in their cost and that limits the PV feed-in power for single-phase connections to 3.68 kW
the maturity level they have reached. In the UK and Northern Ireland, [3], which restrict prosumers to export their excess generation and
the integration of LCTs is increasing to fulfil the zero-emission target by hence it is considered as wasted energy. The technical challenges behind
2050 [1]. This commitment has forced several regulations to be intro­ the use of LCTs are voltage violations beyond the allowable limits,
duced in order to encourage customers to own these technologies by thermal overloading on the transformers and cables, and high power
offering subsidies, including tax deduction, feed-in tariff and micro­ losses in both phase lines and neutral. Severe voltage unbalance (VU)
generation export programs [2]. can also occur due to the rapid deployment of these unmanaged
The impact of LCTs is widespread as they can affect different network technologies.

* Corresponding author.
E-mail address: amohamed06@qub.ac.uk (A.A. Raouf Mohamed).

https://doi.org/10.1016/j.est.2021.102975
Received 21 October 2020; Received in revised form 31 May 2021; Accepted 21 July 2021
Available online 31 July 2021
2352-152X/© 2021 Elsevier Ltd. All rights reserved.
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

There are different conventional and smart solutions that can be there are differences in the results in the literature related to this topic.
applied to maintain the safe operation of the LVRN. Battery energy Furthermore, the assessment methodology applied in addition to the
storage systems (BESS) have been considered recently as a powerful adopted assumptions also affect the results. When analyzing the impact
option due to their different environmental, economic, and technical of LCTs, it is important to consider three-phase unbalanced power flow
benefits, especially their crucial role in facilitating the safe integration of calculations and define properly the technical indices used in the
more LCTs to support the energy evolution towards low carbon future. assessment. In addition, the LVRN headroom should not be defined by a
The BESS can be utilized to achieve different technical goals and solve specific value unless the network has only one feeder. For the LVRN with
various challenges in the LVRN. In the LVRN, the BESS can be installed multiple feeders, the hosting capacity should be determined for each
along the feeders, at the transformer bus, or at the properties behind the feeder independently besides the transformer headroom.
meter. According to current regulations, DSOs cannot operate, manage, The integration of BESS to support the LVRN against the LCTs
or own energy storages [4]. Hence, DSOs aim to utilize the storage units challenges has proved to be an attractive option as demonstrated by
owned by third parties and individuals to provide the network with the recent projects and reported in the literature. As a part of low carbon
needed support in return for agreed payments. network fund projects in the UK, Scottish and Southern Electricity
In Northern Ireland, the DSO (NIE Networks) is facing some network Networks has investigated the application of small-scale BESS (25 kWh /
challenges due to the rapid deployment of LCTs at the low voltage level. 25 kW) in assisting the LVRN operation and performance [14]. The
These challenges affect the power stability, quality, and security of project deployed three single-phase units of the same size at street level
different network levels. Hence, NIE Networks is investigating different and utilized the BESS inverter active and reactive power in peak
conventional and innovative smart solutions to mitigate these chal­ shaving, and voltage regulation as well as improving the phase imbal­
lenges. One of these solutions is the Facilitation of Energy Storage Ser­ ance and power quality. The BESS proved its capability in regulating the
vices (FESS) project [5]. This project will provide a framework to voltage by ±7V and reducing the network peak by a maximum of 100
integrate third-party customers/aggregators energy storage systems Amps over the day in addition to improving the network power quality.
(ESS) to enhance the performance of Northern Ireland distribution The use of BESS for peak shaving in the LVRN has been addressed in
networks. [15], where a probabilistic method was adopted to assess the capability
The aim of this paper is to analyze the impact of LCTs on Northern of behind the meter BESS in peak shaving. The study considered the
Ireland LVRNs as well as investigating the role of community BESS in impact of residential PV and heat pumps. The size of community BESS at
mitigating the LCTs challenges. LVRN was determined to solve the voltage and feeder largest problems
in [16] using rule-based approach. While the BESS was controlled using
1.1. Literature review linearized optimal power flow (OPF) to maintain the voltage and line
flow within the acceptable limits. Yet, the previous studies modelled the
In the literature, there are many studies investigating the impact of LVRN as balanced network and ignored the LVRN unbalanced nature.
LCTs on LVRNs. In [6], probabilistic assessments using Monte Carlo The phase balancing using BESS was addressed in [17], where the
simulations are conducted for different LVRNs located in the UK to capability of BESS in optimizing the VU was proved in addition to
evaluate the impact of LCTs on the network constraints. The results enhancing the operation of the LVRN. The study investigated different
showed that 50% of the test networks faced some violations in node locations for the BESS, and the results suggest that the BESS should be
voltages or thermal ratings. In [7], the impact of EV charging on the installed at the feeder’s end node.
LVRN is assessed for a network located in Ireland. The study showed that In [18], an approach is introduced to allocate, size and dispatch
with 20-40% penetration of EV, the network limitations will be violated. behind the meter BESS optimally on the LVRN. Mixed-integer linear
However, both studies have not considered the VU factor/rate in the programming was employed for the BESS allocation, while linear pro­
analysis based on specific standards. The phase VU rate (PVUR) defined gramming was used to settle the BESS active and reactive power
by IEEE [8] was considered in [9], where the LCTs impacts are assessed dispatch through three-phase OPF by linearizing the constraints to
in terms of energy losses and voltage problems. However, the definition minimize the total cost of system installation as well as managing the
of PVUR is not accurate enough and may lead to inexact results as it does violations. Yet, the study did not consider the phase imbalance in their
not consider the line voltage and the phase angle. Furthermore, the analysis. Another residential BESS control approach based on
study [9] did not consider the impact of LCTs on thermal overloads of multi-objective optimization using particle swarm has been introduced
the feeders and transformer. in [19] to optimize the VU, voltage deviation, power losses and PV
The impact of the high PV penetration on the LVRN in the UK was curtailment. The formulation adopted OPF using penalty factors to
studied in [10]. The study concluded that the LVRN safe PV penetration consider the network and BESS constraints. However, the BESS sizing
limit is around 75%. However, the study focused only on the impact of based on the LCTs potential impacts has not considered. In addition, the
PV on the network voltage and did not consider the thermal overloading previous studies considered only the impact of PV and did not consider
and the unbalanced nature of the LVRN. The impact of EV charging on other evolving LCTs such as the EVs.
LVRN located in Budapest is addressed in [11], where the voltage sta­ The community BESS sizing and sitting in unbalanced LV networks
bility and transformer loading were only considered. The impact of EV was introduced in [20] to minimize the BESS installation costs as well as
on LVRN located in the UK is presented in [12]. The study employed maintaining the network constraints within the allowable limits. The
deterministic and probabilistic approaches, and the results revealed that study considered the network constraints represented in node voltages,
the violations occurred to node voltages and main feeder with 33% EV VU, and line flows which were formulated as hard constraints in the OPF
penetration, while the distribution transformer was found to be over­ problem. However, OPF is NP-hard problem due to the nonconvexity
loaded for all the EV uptake scenarios. However, the VU was not associated with the equations and constraints which may result in
considered which is a crucial factor that should be considered in eval­ convergence to a local point of infeasibility [21], hence, other methods
uating the impact of LCTs. The EV charging drawbacks on LVRN located should be considered in formulating the nonlinear constraints to reduce
in Malaysia are analyzed in [13], the results showed that the LVRN can the complexity through linearization, convex relaxation, or by using soft
accommodate up to 10% of EV without exceeding the network constraints [22]. The BESS control to mitigate VU in the LVRN has been
constraints. addressed in [23]. However, the study did not consider other network
The impact of LCTs on the LVRN varies from one network to another constraints such as node voltage and line flow.
as it depends on the location, type, and specifications of the network. Few studies have addressed the integration of BESS in Northern
Additionally, the regulations and standards define the network con­ Ireland distribution networks. In [24], an investigation of system ser­
straints, thus, affecting the network hosting capacity. As a consequence, vices that can be delivered by the BESS has been addressed through a

2
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

case study on an actual distribution network located in Northern Ireland. 2. LCTs assessment modelling
The study investigated the active/reactive power capability of the BESS
in supporting the network operation and performance. In [25], BESS In this section, the models used in this paper are explained which are
allocation, sizing, and scheduling approach is introduced for congestion related to the test networks, EV charging profiles, PV generation pro­
management, the study investigated different installation scenarios to files, and the future LCTs uptake scenario of 2030 for Northern Ireland.
solve the anticipated high LCTs uptake in Northern Ireland. The
look-ahead scheduling and real-time operation of BESS to provide the 2.1. LVRN models
distribution networks of Northern Ireland with many ancillary services
including grid power levelling, reactive power support, power quality Three test LVRN are being used to evaluate the impact of LCTs on the
improvements have been addressed in [26,27]. Another study in [28] network constraints. These networks are located in Northern Ireland, UK
addressed the integration of BESS in Northern Ireland distribution net­ and connected to the 11 kV network through 11 kV / 400 V transformers
works to maximize self-consumption of wind energy and maximize the with different ratings. The transformers do not have on-load tap
returned BESS revenues. However, none of these studies addressed the changing capability and the sending voltage at the transformer bus is set
impact of LCTs or the integration of BESS on the LVRN of Northern at +3.75% of nominal (i.e., 415 V). Each transformer feeds a number of
Ireland. households through underground three-phase/four-wire feeders of
different sizes. Details on the number of households and feeders for each
1.2. Contributions network are given in Table 1. The feeders are labelled as units (i.e., from
U2 to U6 for LVRN_1), the simplified schematics for the test LVRNs are
This paper complements the previous studies by providing an given in Fig. 1.
assessment methodology to analyze the impact of LCTs in the LVRN as The network details and aggregated measurements are provided by
well as investigating the sizing and scheduling of a community BESS to the DSO of Northern Ireland (NIE Networks). As mentioned in the
solve the LCTs challenges and enhance the network performance and introduction, there is a lack of monitoring devices on LV networks in
operation. The main contributions of the paper are as follows: Northern Ireland, hence, three-phase measurements for a specific period
in August 2019 for each feeder of each LVRN were only provided by the
1) Investigating the impact of LCTs on LVRNs located in Northern DSO in 10-minute resolution. To illustrate an example of these mea­
Ireland. Unlike the studies mentioned in the literature review that surements, the transformer power of LVRN_1 for the 23rd of August 2019
focus on specific indices or specific technology, the proposed is illustrated in Fig. 2.
assessment methodology covers most of the network technical
indices as well as studying the impact of PV and EV on the network in
2.2. EV modelling
addition to considering the unbalanced nature of LVRN to provide a
complete picture on the LCTs impacts and the network hosting ca­
The EV charging is random as it depends on people’s behaviour.
pacity. Three LVRN located in Northern Ireland are adopted and the
Hence, probabilistic methods are being used to generate different pat­
assessment include observing the VU, phase voltage, feeder and
terns. Three parameters should be defined to generate the EV charging
transformer loadings, phase line losses, and neutral losses.
patterns; 1) start time; 2) EV battery state of charge (SoC), and 3)
2) Introducing a sizing algorithm for the community BESS to overcome
charging power.
the potential congestion caused by the future penetrations of LCTs.
The objective of this sizing algorithm is to find the minimal BESS size
1) Start time: the start time of the EV charging cycle can be arbitrarily
to reduce the investment cost that solves network violations repre­
assigned. However, to mimic the real starting time, one-year data of
sented in node voltage violations, VU, and feeder’s overloads.
actual residential EV charging measurements obtained from the
3) Proposing a look-ahead scheduling algorithm for the community
dataset of the Low Carbon London (LCL) project by UK Power Net­
BESS that aim to optimize the VU and reduce the energy losses in
works [29] was used. For each day, the first hour (cycle start time Ts )
neutral and phases as well as maintaining the LVRN technical con­
of the EV charging cycle is obtained. Afterwards, the daily values for
straints within the acceptable limits.
one year are treated as a normal distribution function with (μ =
4) Evaluating the proposed BESS sizing and scheduling algorithms on an
12.9478, σ = 8.4437) and the cumulative distribution function
actual LVRN located in Northern Ireland with the LCTs uptake scenario
(CDF) can be then illustrated in Fig.. 3, calculated as:
of 2030. In addition, the impact of the BESS scheduling algorithm on the
[ ]
BESS degradation is evaluated using a semi-empirical Li-ion ageing 1 1 Ts − μ
F(Ts | μ, σ ) = + erf √̅̅̅ (1)
model. 2 2 2σ

It is worth mentioning that the assessment methodology introduced Where μ is the mean, and σ is the standard deviation. From Fig. 3,
in this paper considers analyzing the impact of LCTs on the neutral various start times of EV charging cycles can be obtained randomly
losses. Furthermore, the proposed scheduling and sizing algorithms are conditioned by this CDF.
introduced for three-phase community BESS which considers the 2) EV battery SoC: the end time of the EV charging cycle can be deter­
complexity of three-phase model and network in addition to formulating mined using the battery SoC and the charging power. The EV battery
the OPF problem as black-box optimization and modelling the con­ SoC can be simulated as a CDF of the daily travel distance assuming
straints in the objective function as a feasibility problem, which reduces that the daily travel distance of an EV is identical to the conventional
the complexity of the formulation as well as the computation time.
Moreover, the proposed BESS scheduling algorithm aims to reduce the Table 1
neutral losses as one of its objectives. To the best of authors’ knowledge, Test LVRNs details.
these aspects have not been addressed previously in the literature. Network Number of Number Feeders’ Transformer Typical
The paper is organized as follows: Section 2 presents the modelling of ID Households of labels rating[kVA] day max
networks and LCTs, Section 3 presents the impact assessment method­ feeders/ demand
units [kVA]
ology, the impact assessment results are given in Section 4, the BESS
model, sizing, and scheduling algorithms are presented in Section 5, the LVRN_1 92 5 U2 – U6 250 66.77
BESS case study and simulation results are given in Section 6, finally the LVRN_2 95 4 U3 – U6 300 72.59
LVRN_3 103 4 U3 – U6 350 73.11
conclusion is given in Section 7.

3
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

11kV / 400V
U3 250 kVA
19 Houses
20 Houses
18 Houses U2

10 Houses 17 Houses
U6
U6 11kV / 400V
U6 U5
300 kVA
U3 394 m
16 Houses 11kV / 400V
U4 350 kVA

U5
U3
26 Houses

U4
16 Houses 14 Houses
29 Houses U6
U4 45 Houses
29 Houses 31 Houses
U5

(a) (b) (c)


Fig. 1. Test LVRN schematics used in the analysis: (a) LVRN_1, (b) LVRN_2, and (c) LVRN_3.

vehicle as done in previous studies [30,31]. The daily travel dis­


tances of conventional vehicles can be obtained from national sur­
veys such as [32]. In this paper, the EV battery SoC model utilizes the
same approach, where the lognormal is used to define the daily travel
distance probability using the UK daily travel data from [32] with
(μ = 3.2125, σ = 0.6537), sequentially, the EV battery SoC as a CDF
of the daily travel distance can be shown in Fig. 4, calculated as:
[ ]
1 1 ln(1 − SoC) + ln(dr) − μ
F(SoC| μ, σ) = + erf √̅̅̅ (2)
2 2 2σ

Where dr is the maximum range of the EV. The dr is taken as 150 km


as an average value according to the EV battery. In this work, an
average EV battery size of 45 kWh is adopted based on the popular
EV available in the market [33]. By obtaining the EV battery SoC, the
residual capacity to be charged for an EV charging cycle can be
identified. More details on the EV battery SoC modelling can be
found in [30].
3) Charging power: the charging power is determined according to the
available residential EV chargers. Typical single-phase residential EV
chargers’ ratings vary from 3 kW (slow/standard) to 7 kW (fast)
Fig. 2. LVRN_1 Transformer power for the 23rd of August 2019. [33–35].

Fig. 3. CDF of EV charging start time.


Fig. 4. CDF of EV battery SoC.

4
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

After determining the start time, and the residual EV battery capacity For the unbalanced assessment, in addition to the previous indices,
to be charged, the end time can be settled according to the charging the following two indices are also considered:
power. For specific EV charger rating, several EV charging patterns can
be randomly generated conditioned to the CDF in Figs. 3 and 4 which • Voltage Unbalance (VU):
were obtained using real data.
VU is a factor representing the voltage deviation of each line voltage to
the average line voltage. In this work, the approximated factor [45] of
2.3. PV modelling
the true definition of voltage unbalance [46] is adopted. The approxi­
mated factor is adopted to ease the process of determination as it does
The PV generation pattern depends mainly on the weather condition.
not require the negative sequence components and to avoid the use of
In order to generate PV patterns, three parameters need to be settled; 1)
complex algebra while providing more accurate results compared to the
start time; 2) end time; 3) generated power. The start and end times can
IEEE PVUR [45], expressed as:
be settled based on the geographical location, and season. While the
√̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅
generated power is affected by many factors like irradiance, clouds ( ) 2 ( 2 ) (2 )
movement and module status (module efficiency, quality, and clean­ vab
82 × av + vbc av + vca av
t,u − vt,u t,u − vt,u t,u − vt,u
VUt,u = (3)
ness). Different models can be applied to generate generation patterns of vuav,t
residential PV [36]. In this work, real measurements are obtained from
[37] for two PV sizes, 4 kWp and 6.5 kWp due to their popularity in vab bc ca
t,u + vt,u + vt,u
Northern Ireland and the UK. It should be noted that for the impact vav
t,u = (4)
3
assessment and BESS sizing case study, ideal PV generation are adopted
to simulate the worst-case scenario [38], while for the BESS scheduling Where the subscripts u represents the unit/feeder, t is the time index,
case study, actual PV measurements are used adopted from [37]. and the superscript av denotes average voltage, and the other super­
scripts are related to line-to-line voltage. In the UK, the maximum
allowable limit of VU is considered as 2% according to the Engineering
2.4. 2030 Scenario
Recommendation P29 [47].
The deployment of renewable generation and LCTs is expected to
• Daily Neutral Losses: The daily energy loss in the neutral of each
increase massively in Northern Ireland by 2030 [39,40] due to the
feeder is considered in each case.
net-zero carbon target. In this paper, the anticipated penetrations of EVs
and PVs are determined based on 2030 projections to analyze the impact
The previous indices are determined by performing time-series
of these penetrations on the LVRNs. Projections by the transmission
power flow calculations. In this work, the backward/forward method
system operator (SONI) suggest that the number of electric vehicles in
for three-phase unbalanced power flow calculation [48,49] is used due
Northern Ireland may reach 250,000 by 2030 [39]. According to the
to its effectiveness in the calculations and convergence for the unbal­
Northern Ireland Statistics & Research Agency, the population in
anced LVRN. The adopted algorithm is validated using the power system
Northern Ireland will reach 1.95 million by 2030 [40]. The average size
software (NEPLAN) [50].
of a household in Northern Ireland is 2.5 ~ 3 persons on average [41].
In this paper, a deterministic approach is applied to assess the LCTs
Thus, 0.4 EV/household is projected in Northern Ireland by 2030. Ac­
impact on the LVRN by applying various penetrations of LCTs on the
cording to the available data on the Zap-map for the residential chargers
network using typical day load measurements. The worst-case scenario
in Northern Ireland [42], the deployment percentage of each EV charger
is concerned, hence for the EV start time, it is assumed that all the EVs
(3 kW and 7 kW) is 50%, hence 0.2 EV/household for each charger
are starting to charge at the same time (18:00 hr). The probability of this
rating is projected by 2030. For PV deployment, according to recent data
is currently very low, however, in the carbon-free future when the ma­
provided by NIE Networks, the number of PV with microgeneration
jority of vehicles are EVs, this case will likely be normal. For the PV,
connection represents 3% of the households in Northern Ireland. Ac­
ideal PV generation profiles for the UK in August are adopted for the two
cording to future projections by the national grid, the number of solar
adopted PV sizes [38].
rooftop PV will represent 20% of the households by 2030 [43].

4. LCTs impact assessment results


3. LCTs impact assessment methodology
To evaluate the LCTs impact on the LVRNs, detailed analysis are
In this paper, the proposed methodology in assessing the impact of
provided for the first network (LVRN_1) as it has more feeders compared
LCTs is divided into two parts; the first part is to simulate different
to the other two networks, while the results summary for the other two
penetration scenarios assuming that the LCT penetration is divided
networks are given.
equally across the three phases, the second part is to simulate the LCTs
penetration on a single-phase to assess their impact on the voltage un­
balance. The following indices are recorded to analyze the impact 4.1. Balanced distribution
properly.
The LCTs penetration is distributed equally on the three phases. The
• Feeder Voltage: For the EV assessment, the minimum phase voltage in simulations are conducted for various penetrations of PVs / EVs as a
the day is recorded as per-unit, while for the PV, the maximum percentage of households, for the first network (LVRN_1), the LCTs
voltage is recorded. The phase voltage allowable limits in this work distributions are as follows: a) 20 EVs / PVs = 21.7% of the households,
are taken as 230V +10% / -6% (216.2V – 253V) in agreement with b) 40 EVs / PVs = 43.4% of the households, c) 60 EVs / PVs = 65.2% of
the UK ESQCR [44]. the households, and d) 80 EVs / PVs = 86.9% of the households. The
• Cable Loading: Maximum line flow in the day for each feeder is simulations are conducted for 50% EVs of 3 kW, 50% EVs of 7 kW, 50%
considered as a percentage of maximum current carrying capacity. PVs of 4 kWp and 50% PVs of 6.5 kWp. The number of the LCTs/unit for
• Transformer Loading: Maximum transformer loading in the day is each case is distributed according to the number of households in each
recorded. unit as given in Table 2 for the first network (LVRN_1). The results of the
• Daily Line Losses: The total daily loss in energy of each feeder is LCTs impact assessment for different penetrations of LCTs are shown in
considered in each case. Figs. 5, 6, and 7.

5
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Table 2 given in Fig. 8.


Number of EVs/PVs per unit for each case (LVRN_1). As shown in Fig. 8, the LCT hosting capacity varies from one feeder to
Number of LCTs another in each network according to the feeders’ parameters. These
values represent the maximum allowable LCT hosting capacity before
Total U2 U3 U4 U5 U6
20 4 4 4 6 2 network violation occurs (voltage violation and cable overloads). Note
40 8 8 8 12 4 that, the previous analysis was conducted for the worst-case scenario,
60 12 12 12 18 6 where all the EVs are assumed to start charging at the same time, while
80 16 16 16 24 8 ideal PV generation profiles were used. Additionally, typical demand
measurements were used. However, for other assumptions, these values
As shown in Figs. 5–7, the high penetrations of EVs and PVs will lead may be subject to change. It can be concluded that the LCTs impact on
to severe violations. These figures show the violated units only. It can be low voltage networks differs according to the network specifications (i.
noticed that the farthest nodes from the transformer bus (U5) had the e., feeder parameters, transformers, number of households in each
most severe violations in terms of voltage. Furthermore, the impact of feeder) as well as the analysis assumptions. Hence, for each feeder in a
EVs on cables overloading for both the transformer and cables is higher network, an impact assessment should be conducted with regard to the
than the impact of the PVs, while, the PVs have a higher impact on the DSO’s data and assumptions.
feeder overvoltage. The violations occur mainly after 43.4% of LCTs
uptake. Below this percentage, cable overloading occurred only for
4.2. Unbalanced distribution
Phase B of U2. This is because Phase B of U2 is already heavily loaded by
normal demand. Regarding the network losses, the LVRN with high
In this part, another sensitivity analysis is conducted to estimate the
penetration of PVs will have a higher energy loss compared to the EVs.
impact of LCTs with varying penetration on the phase imbalance. The
This is because PVs generate power during long periods in the summer.
impacts of this variation are examined for two units of the first network
Moreover, for higher LCTs penetrations, the losses tend to increase
(LVRN_1) selected based on the feeders’ lengths with respect to the
exponentially. The total network daily loss in energy for different cases
transformer bus; the nearest (U2) and the farthest (U5). For each unit,
is given in Table 3.
the LCTs penetration is varied for only one phase (Phase A) which
The units are affected based on their electrical distance from the
represents the worst-case scenario. It is assumed that the number of
transformer and the number of households in each unit in addition to
households of each unit is divided equally on the three phases (6 houses/
their feeder specifications. Noteworthy, in the previous simulations, the
phase for U2 and 10 houses/phase for U5). The simulations are con­
LCTs were divided equally (50% EVs of 3 kW, 50% EVs of 7 kW, 50% PVs
ducted for the 3 kW and 7 kW EV chargers and the 4 kWp and 6.5 kWp
of 4 kWp and 50% PVs of 6.5 kWp). On the other hand, the number of
PV sizes, the penetration is varied with an increment of 2 LCTs per step
LCTs/unit in the previous analysis was determined based on each unit’s
until the number of households per phase is reached for each unit
number of households. However, in reality, the LCTs power and their
separately. The summarized results are shown in Figs. 9–11, and Fig. 12.
numbers can vary randomly across the LVRN. Hence, the power flow
The previous results show the impact of LCTs on phase imbalance.
simulations were repeated with varying the number of LCTs for each
For the same LCT power, it can be observed that the farthest units from
unit to determine the maximum allowable number of EVs charging at
the transformer bus are very sensitive to violations as the VU and node
the same time for each unit, and the maximum number of PVs that each
undervoltage values are significant for U5 with respect to U2. The
unit can accommodate without violating the technical constraints. The
impact of LCTs on the voltage unbalance can be averaged as +0.025% /
results are summarized in Table 4. The numbers of LCTs per unit in
kW for U2 and +0.061%/kW for U5. Furthermore, the EV charging had a
Table 4 represent the maximum allowable number of LCTs in order not
higher impact on the voltage unbalance which can be averaged as
to violate the cable ratings or voltage at each unit which depends mainly
+0.05%/kW compared with the PV with +0.037%/kW, while, the PV
on the length, and specifications of each feeder.
had a higher impact on the voltage limit violation. U2 can safely
The previous analysis was conducted for the other two networks
accommodate only 33.3% EVs (7 kW) of households/phase, 75% EVs (3
(LVRN_2 and LVRN_3) and the results summary for the three networks is
kW), 66.6% PVs (6.5 kWp), and 100% PVs (4 kWp). The main violation

Fig. 5. Feeder voltage for different number of LCTs (LVRN_1).

6
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

120
Phase A - U2 (PV) Phase B - U2 (PV) Phase C - U2 (PV) Phase A - U3 (PV)
110 Phase B - U3 (PV) Phase C - U3 (PV) Phase A - U5 (PV) Phase B - U5 (PV)
Phase C - U5 (PV) Limit
100

90

Cable Loading [%]


80

70

60

50

40

30

20
0 20 40 60 80
Number of PVs

(a)

200
Phase A - U2 (EV) Phase B - U2 (EV) Phase C - U2 (EV) Phase A - U3 (EV)

180 Phase B - U3 (EV) Phase C - U3 (EV) Phase A - U5 (EV) Phase B - U5 (EV)


Phase C - U5 (EV) Limit
160

140
Cable Loading [%]

120

100

80

60

40

20
0 20 40 60 80
Number of EVs

(b)
Fig. 6. Maximum cable loading for different number of LCTs: (a).

concerned with U2 is cable overloading. While U5 can accommodate of unmanaged LCTs on the LVRN operation. The high uptake scenarios
30% EVs (7 kW), 60% EVs (3 kW), 40% PVs (6.5 kWp), and 55% PVs (4 of LCTs may lead to critical violations which need to be considered
kWp). All types of violations have been observed for U5. earlier by DSOs to avoid any future problems. As shown in the results,
For the losses, the line losses tend to be linear with the increase of with 2030 LCTs projections (20% PV and 40% EV), the network stability
LCTs power, however, the neutral loss increases exponentially. The may be threatened as the anticipated increase in LCTs deployment will
impact of phase imbalance on the neutral losses is significant as the lead to technical violations. Additionally, the high reverse power flow
losses increase proportionally to the increase of LCTs. While, if the LCTs from PV introduces additional technical issues to the protection equip­
are balanced distributed, the neutral losses should be fixed. It can be ment that should be considered in future planning. In the previous
concluded that the impact of LCTs on the voltage unbalance is critical analysis, the voltage limit was constrained at +10%, -6%, however,
and need to be monitored especially for the farthest loaded units as a some DSOs prefer to set tighter limits based on working practice to
small number of LCTs operating at the same time on the same phase will ensure the stability and security of the network which should be
result in severe violations that may lead to curtailing the power supply considered in the impact assessment and determining the hosting
by the DSO. capacity.
It is highly advised to consider monitoring each phase separately and
consider the voltage unbalance in the assessment as the VU limit can be
4.3. Impact assessment discussion violated without a voltage magnitude violation occurring. The snapshots
presented in the previous results represent the most severe conditions of
The sensitivity analysis proposed in this paper emphasizes the impact

7
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 7. Maximum transformer loading for different number of LCTs.

may cause severe issues to the network operation. Furthermore, with


Table 3
high LCTs penetrations, phase imbalance will likely occur frequently
Daily losses for different LCTs penetration levels (LVRN_1).
due to increasing the probability of multiple LCTs operation on a sole
Number of LCTs Daily Network Losses [kWh] phase.
With EVs With PVs
DSOs should monitor the LVRN carefully as the challenges raised
0 5.59 5.59 from this level affects the upper network levels in addition to other
20 11.32 3.48
physical damages that may occur to the low voltage network elements.
40 23.85 26.87
60 44.19 61.98
The technical issues that occur from the high deployment of LCTs in the
80 73.67 111.57 LVRN can be summarized as: 1) Transformer and cables overloading; 2)
Node voltage violations; 3) Severe voltage unbalance; 4) High power
losses, and 5) Other power quality issues. All the previous issues can be
Table 4
solved using conventional solutions such as upgrading a transformer or
Maximum allowable number of LCTs per unit (LVRN_1). underground cables; using reactive power compensators to mitigate the
voltage issues, voltage unbalance and enhance the power quality; and
Unit Maximum Number of LCTs
EVs(3 kW) EVs(7 kW) PVs(4 kWp) PVs(6.5 kWp)
reconfiguring the network to mitigate the unbalance impact and losses.
All these traditional solutions require high capital expenditure and no
U2 12 5 19 11
one solution can address all the aforementioned technical issues. The
U3 16 7 16 10
U4 50 22 50 30 most effective smart solutions that can be applied are BESS and demand
U5 22 10 19 11 side management programs. BESS have attractive potential in solving
U6 16 7 18 11 network challenges. However, the planning and operation of BESS
should be properly defined. In the upcoming section, the planning and
operation of a community BESS to relive network congestion imposed
the day. However, the time-series simulations show that these violations
from the high penetrations of LCTs will be investigated.
may occur for a longer timespan with a lower level of severity. It was
assumed that all the EVs are starting to charge at the same time.
5. The role of battery energy storage systems
Nowadays, multiple EVs may charge at the same time. However, with
high EVs penetration (e.g., by 2030), the overlapping in EVs charging
In this section, a solution to the LCTs challenges is introduced based

(a) (b) (c)


Fig. 8. Impact assessment summary of balanced LCTs distribution for three LVRNs: (a) LVRN_1, (b) LVRN_2, (c) LVRN_3.

8
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 9. Voltage unbalance of Phase A for different number of LCTs.

Fig. 10. Phase A voltage for different number of LCTs.

on BESS. As discussed previously, conventional reinforcements have phase individually. This section introduces the adopted BESS model as
limited applications and high capital expenditures. However, BESS have well as the proposed BESS sizing and scheduling algorithms
the capability to solve all the LVRN violations. The location of the BESS
is crucial to achieve maximum utilization. In the LVRN, the BESS can be 5.1. BESS system model
installed at the transformer bus to mitigate the transformer overloading
as well as the VU at the transformer bus. Yet, other issues such as cable Various models can be used to identify the BESS operational con­
overloading, node voltage magnitude imbalance violations, and high straints. In this paper, a detailed generic model is adopted that can be
energy losses will still exist. While the BESS could be installed on the used for any type of BESS technologies considering realistic parameters
feeder of each congested unit to solve all the LVRN problems, more which explained as follows:
beneficially it should be located at the end of the feeder for maximum
performance [17]. In addition, the connection configuration of BESS 1) BESS Power Rating: The discharged power Pdis chr
t,b or charged power Pt,b
should also be identified as the BESS can be connected as follows: 1) to from the BESS b at any time-point t must not exceed the BESS pre­
the congested phases only; 2) to the three phases using three-phase defined rating.
power conversion system (PCS), and 3) to the three phases using { }
single-phase PCS with/without a phase selector. In this paper, it is PBESS
t,b ≤ Pmax
b ; PBESS
t,b ∈ Pdis chr
t,b , Pt,b (5)
assumed that the BESS can inject and absorb power to/from the three
phases, this can be done by connecting a single BESS to the three phases
through a three-phase PCS or by connecting three separate BESS to each

9
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 11. Cable loading of Phase A for different number of LCTs.

Fig. 12. Total line and neutral losses for different number of LCTs.

2) BESS System efficiency: The power imported Pch di


t,b or exported Pt,b
Where τ is the interval period such that τ = 24
np , np is the number of
from/to the gird by BESS b at any time is affected by input/output points which is determined based on the data resolution (24 for hour, 48
efficiencies of the BESS ηBESS
b and the power conversion system (PCS) for 30-minute, and 144 for 10-minute), ECap
b is the BESS nameplate ca­
ηPCS
b . pacity, and Eus
b is the BESS usable capacity.
√̅̅̅̅̅̅̅
ηb = ηBESS
b × ηPCS
b ; ηBESS
b = ηrte
b (6) 1) PCS Rating: At any time-point, the apparent power handled by the
PCS should not exceed its rating.
Pchr
(7)
t,b
Pdi dis ch
t,b = Pt,b ηb ; Pt,b =
ηb
PCS
St,b ≤ Sbmax (10)
√̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅̅
( )2 ( )2̅
Where ηrte
b is the BESS round-trip efficiency.
PCS
St,b = PPCS
t,b + Q PCS
t,b (11)
3) State of Charge (SoC): SoC is the percentage measurement that in­
dicates the available capacity still in the BESS. The SoC must be
maintained within the pre-defined limits to maintain the BESS ca­
pacity over longer periods.
5.2. BESS sizing
SoCbmin ≤ SoCt,b ≤ SoCbmax (8)
The BESS size should be determined wisely to avoid under/over
Pch
t,b ηb τ Pdi
t,b τ sizing. Additionally, the BESS size should be determined based on the
SoCt,b = SoCt− + − (9)
delivered applications and should consider the future projections of the
1,b
EbCap EbCap ηb
LCTs and demand for a network. These projections should be identified
by the network operators based on their forecasting for each network. In

10
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

this paper, the objective of the BESS is to maintain the network con­ results are then used to evaluate the objective function Eq. (12) as black-
straints (VU, node voltage, and line flow) within the acceptable limits box. In case of no violation observed, the value of objective function Eq.
and the 2030 LCTs uptake scenario is adopted in determining the BESS (12) is zero. After the optimization horizon ends, the solver updates the
size in the case study. Determining the BESS size requires OPF calcula­ decision variables to optimally obtain the minimal needed power to be
tions to obtain the BESS size subject to the network technical con­ distributed over the charging/discharging horizons to satisfy the
straints. Different approaches have been introduced to tackle the OPF objective function. The lower bounds of these variables are set to zero,
problem through linearization, convex relaxation, or by converting the while the upper bounds should not be limited as the aim of this method
OPF constraints into soft constraints using penalty functions [22]. In this to find the BESS size and rating. However, a specific value can be set
paper, the OPF problem is treated as a black-box optimization [51], based on the available BESS ratings or based on the DSO’ preference to
where the network technical constraints (VU, node voltage and line reduce the computation time by decreasing the search space.
flow) are modelled in the objective function as a feasibility problem, After the optimizer converges, the daily power dispatch values are
which avoids the use of hard constraints and reduces the computation used to determine the daily BESS usable capacity Eusb needed during both
time of solving the OPF problem. The goal of this black-box optimization modes (charging/discharging) considering the BESS system efficiency
is to solve all network violations using minimum BESS capacity which is Eq. (7) based on the consecutive period with highest energy dispatch
mathematically formulated as a multi-objective function using the using Eq. (16), afterwards the BESS nameplate capacity ECap is deter­
b
weighted sum method and normalized into a mono-objective function mined in each day based on the SoC pre-defined limits using Eq. (18),
using the consequent upper-bound approach [52], expressed for a BESS whilst the maximum power dispatched within all the day is considered
installed at a specific feeder/unit (u) ∀ t ∈ To as: as the BESS power rating using Eq. (17).
( ) ( )
w1 F1 (x) w2 F2 (x) w3 F3 (x) w4 F4 (x)
min + + + (12) Td ∑
∑ 3
τ ∑Tc ∑
3
x F1max
F2max
F3max
F4max us
Eb = max xt,u,∅ , xt,u,∅ ηb τ (16)
t=1 ∅=1
ηb t=1 ∅=1


To
[ ] ⎛ ⎞
F1 (x) = cvu
t,u VUt,u > 2 (13)
t=1 ⎜∑ ⎟
⎜ 3 xt,u,∅ ∑ 3 ⎟
Pmax
b = max⎜
⎜ , xt,u,∅ ηb ⎟
⎟ (17)

To ∑
3
[ ] ⎝ ∅=1 ηb ⎠
F2 (x) = cvn
t,u,∅ Vt,u,∅ < 0.94 ∨ Vt,u,∅ > 1.1 (14) ∅=1
t∈Td t∈Tc
t=1 ∅=1

Ebus
∑ (18)
To ∑
3
[ ] EbCap = ( )
F3 (x) = ccab
t,u,∅ It,u,∅ > Imu (15) SoCmax
b − SoCmin
b
t=1 ∅=1
Finally, after determining the daily values of BESS capacity and
To ∑
∑ 3
rating, the highest values amongst all the simulation days are considered
F4 (x) = xt,u,∅ τ (16)
t=1 ∅=1
as the BESS specification (capacity in kWh and rating in kW). Note that,
the proposed BESS sizing algorithm considers only the BESS active
Note that [] in Eqs. (13), (14) are Iverson brackets (the Iverson power, and it is assumed that the BESS PCS is operating on unity power
bracket is equal to 1 when the logical condition enclosed is true and factor in agreement with the DSO of Northern Ireland regulations [53]
0 otherwise). ∅ represent the phase such that ∅ ∈ {1, 2, 3} The multi- due to the impact of reactive power on rising the feeder voltage. The
objective function in Eq. (12) consists of four weighted sub-functions. proposed BESS sizing algorithm flowchart is illustrated in Fig. 13, and
F1 (x) represents the VU function. F2 (x) represents the voltage viola­ the algorithm requires the following inputs:
tions, where Vt,u,∅ is the phase voltage. F3 (x) represents the cable
loading, where It,u,∅ is the phase current and Imu is the feeder maximum • Time-series data of demand and LCT (for single or multiple days
carrying capacity. F4 (x) represents the total used BESS capacity over the according to the available data).
dispatch horizon (charging/discharging). The weights were varied, and • Pre-defined dispatch horizons for each day (i.e., from 12:00 hr to
the optimal results were obtained using the following weights: (w1 = 17:00 hr for charging, and from 18:00 hr to 23:00 hr for discharging).
w2 = w3 ), (w1 +w2 +w3 = 4.61w4 ) and (w1 + w2 + w3 + w4 = 1). The • BESS location, DoD/SoC limits, and efficiency.
constraints functions F1 (x), F2 (x), and F3 (x) are given higher weights
compared to the BESS size as they must be maintained within the In the power flow calculations, the BESS decision variable at the
acceptable limits. cvut,u , ct,u,∅ , and ct,u,∅ are penalty factors represent vio­
vn cab
BESS node is treated as a negative load during the discharging mode and
lations of VU, node voltage, and cable rating respectively. To is the as a positive load during the charging mode. As the network constraints
optimization horizon such that To ∈ {Td ,Tc }, where Td is the discharging are modelled in the objective function in Eq. (12), hence the proposed
horizon and Tc is the charging horizon. Fmmax represents the maximum BESS sizing algorithm is unconstrained optimization which can be
value of objective-m for the normalization purpose such that m ∈ {1,2,3, solved easily using many available off-the-shelf optimization solvers.
4}. The VU is considered as a violation if the VU is larger than 2, the
node voltage violation is considered when the node voltage exceeds 230
5.3. BESS scheduling
+10 / -6 % (0.94 pu – 1.1 pu), and the cable loading is considered as a
violation when the line flow exceeds the cable ampacity. The optimal
In order to evaluate the impact of BESS in different operating con­
values of F1 (x), F2 (x), and F3 (x) are zero which represents no violations.
ditions. A scheduling algorithm is introduced. As the BESS size and
The aim of this BESS sizing formulation is to find the minimum BESS
rating have been settled from the previous sizing algorithm, the sched­
size that solves the network violations. The optimization solver initial­
uling algorithm considers all the constraints of the BESS model
izes a set of decision variables x representing the BESS power PBESS t,u,∅,b for described previously in Section 5.1. The aim of this algorithm is to
each phase during each mode (charging/discharging) at each time-point minimize the VU, and the energy loss in neutral (n), and phases (p) while
of the day such that xu,∅ = (xt,u,∅ , xt+1,u,∅ ….xTo ,u,∅ ). Within each mode, satisfying the technical constraints. The BESS scheduling is formulated
the decision variables are adjusted to consider the BESS system effi­ also as black-box optimization where the network constraints are
ciency using Eq. (7). Afterwards, these variables are entered into a time- modelled in the objective function as done in the BESS sizing in addition
series unbalanced three-phase power flow routine. The power flow to adding another three sub-objectives related to the VU, phase losses,

11
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

phase. The proposed scheduling algorithm aims to distribute the BESS


power optimally over the three phases during the daily dispatch hori­
zons by initializing a set of decision variables subject to the BESS system
efficiency Eq. (7) and the BESS power rating Eq. (5), however, because
the BESS is connected to three phases, Eq. (5) is adjusted to the following
Eq. (23).

3
xt,u,∅ ≤ Pmax BESS
b ; xt,u,∅ = Pt,u,∅,b (23)
∅=1

Eq. (23) and the BESS SoC Eq. (8) are formulated as hard constraints.
The optimization solver evaluates the objective function Eq. (19) subject
to these constraints. The proposed BESS scheduling algorithm follows
the steps illustrated in Fig. 14 and requires the same inputs of the BESS
sizing algorithm in addition to the BESS capacity and power rating.

6. BESS case study

To evaluate the proposed BESS sizing and scheduling algorithms,


only the first network (LVRN_1) is considered. Only one feeder of the
LVRN_1 is considered for the BESS installation. Based on the impact
assessment analysis, the farthest nodes from the transformer are the
most sensitive locations to violations. Hence, the BESS is assumed to be
located at the end node of U5, lithium-ion BESS technology is consid­
ered. The BESS SoC limits are taken as SoCmin
b = 10% and SoCmaxb = 80%
which is equivalent to a depth of discharge (DoD) of 70%, these values

Fig. 13. Proposed BESS sizing algorithm.

and neutral losses, which is formulated as a multi-objective function


using the weighted sum method and normalized into a mono-objective
function using the consequent upper-bound approach [52], expressed
for a BESS installed at specific feeder/unit (u) as:
⎛ w F (x) w2 F2 (x) w3 F3 (x) ⎞
1 1
+ +
⎜ F1max F2max F3max ⎟
⎜ ⎟
min⎜ ⎟ (19)
x ⎝
w4 FF4 (x) w5 F5 (x) w6 F6 (x) ⎠
+ + +
FF4max F5max F6max


To
FF4 (x) = VUt,u (20)
t=1


To
F5 (x) = n 2 n
|It,u | Ru τ (21)
t=1

To ∑
∑ 3
F6 (x) = |It,u,∅ |2 Rpu,∅ τ (22)
t=1 ∅=1

The weights are determined according to the importance of the


objective: w1 = w2 = w3 = 30 7
, w4 = 15, and w5 = w6 = 20 1
. The network
constraints are given higher weights and the voltage unbalance is given
higher importance compared to the neutral and phase losses. F1 (x),
F2 (x), and F3 (x) represent the LVRN technical constraints described in
Eq. (13) – Eq. (14). The fourth function FF4 (x) is related to minimizing
the VU and has been written in this way to differentiate between this
function and the fourth function F4 (x) of the BESS sizing algorithm.
F5 (x) aims to reduce the neutral losses, where Rnu represents the feeder/
unit neutral resistance and It,u
n
is the neutral current. F6 (x) aims to reduce
the phase losses, where Rpu,∅ is the feeder/unit phase resistance for each Fig. 14. Proposed BESS scheduling algorithm.

12
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

were selected to preserve the BESS degradation over operation [54,55]. needed due to their impact on threatening the LVRN technical con­
While the PCS efficiency ηPCS b is considered as 95% and the BESS straints. The highest BESS size achieved is 140 kWh / 29 kW. However,
round-trip efficiency ηrte this represents the case with the highest violations which unlikely to
b is assumed as 90% which were imported from
an actual project [56]. In addition, the 2030 uptake scenarios of LCTs happen regularly because the EV charging was constrained to specified
given in Section 2.4 are adopted (20% PV penetration and 40% EV times to simulate violations during the peak. However, in reality, EV
penetration). charging varies across the day. In addition, the distribution of LCTs over
The proposed BESS sizing and scheduling algorithms are formulated phases was pre-settled, however, it may differ in practice. The selection
as black-box optimization, which requires a derivative-free optimizer of BESS specification amongst the results is left to DSOs based on their
[51]. Some derivative-free solvers were tested, and the best results were projections and assumptions. However, it is recommended to simulate a
obtained using the Genetic algorithm (GA) for the BESS sizing and the long period based on DSO assumptions to determine accurately the BESS
NOMAD solver [57] for the BESS scheduling. size using the proposed sizing algorithm. From the previous results, an
NOMAD is a derivative-free global optimization solver that imple­ average BESS specification can be determined as 47kWh / 19kW.
ments the MADS (Mesh Adaptive Direct Search) algorithm [58], which is
a development of the Generalized Pattern Search (GPS) algorithm. 6.2. BESS scheduling results
NOMAD is a direct search, iterative method that has three processes in
each iteration: poll, search, and update. It evaluates the objective To evaluate the effectiveness of the proposed BESS scheduling al­
function by generating trail points lying on a mesh using the poll and gorithm, the following assumptions are adopted. One week of demand
search. The results of these evaluations are then examined and used to measurements are used from 23/8/2019 to 29/8/2019. For the LCTs
generate new trial points using the update process. A variable neigh­ profiles, two actual PV profiles for the following sizes (4 kWp and 6.5
borhood search algorithm is integrated into NOMAD to prevent the al­ kWp) are adopted from [37] for the same week. While different EV
gorithm from being trapped in local optima [59]. NOMAD has been charging patterns were generated from the pre-explained model in
adopted in this work due to its effectiveness in providing optimum so­ Section 2.2. BESS specification of 47 kWh / 19 kW has been used as an
lutions to the BESS scheduling optimization problem in a reasonable average of the BESS sizing results. To simulate random LCTs distribution
processing time. In addition, it has proven its effectiveness in different over phases, the loading of LCTs over the three phases of U5 were
optimization problems for commercial and non-commercial applications distributed randomly for each day as:
[57].

3
For the BESS sizing, different GA generations were tested, and it was r∅ = rand [0, 1]; γ ∅ = ∑3
r∅
; γ∅ = 1 (24)
observed that the objective function does not change significantly after ∅=1 r∅ ∅=1
80 generations. For the BESS scheduling, the following NOMAD pa­
Where r∅ is a random number generated between 0 and 1 for each
rameters are assigned: starting points of zeros, and stopping criteria of
phase, and γ∅ is the LCTs loading fraction for each phase such that the
max execution time of 1000 seconds, and relative/absolute convergence
summation of all loading fractions equals 1. The results of the one-week
tolerances of 1e-7. The GA was utilized using the optimization toolbox of
simulations before and after the BESS scheduling are illustrated in
MATLAB and the NOMAD was implemented in MATLAB through OPTI
Figs. 16 and 17, while the improvements summary is given in Table 5.
Toolbox [60].
As shown in Figs. 16–17, and Table 5, during the peak, the BESS
managed to shave the peaks and solve all the violations represented in
6.1. BESS sizing results VU, undervoltage, and cable overloading. During PV generation, the
BESS reduced the reverse power flow by increasing the feeder self
The proposed BESS sizing algorithm is designed to simulate a period consumption in addition to reducing the overvoltage and the voltage
of time (few days to years) and to determine the optimal BESS size unbalance. For the days with no violations, the BESS optimized the
amongst the simulated days. As shown in the LCTs impact assessment, network performance by regulating the VU and phase voltage as well as
the violations vary according to the LCTs penetrations and assumption reducing the stress on the feeders and minimizing the phase and neutral
used in analysis such as the distribution of LCTs across the phases, and losses. To summarize the average improvements over one-week, the
the LCTs patterns. In this paper, a case study is presented based on a set daily loss in energy was reduced by 12% for phases, and 27.4% for
of assumptions to evaluate the BESS sizing algorithm. As there is a neutral, the VU was optimized by 21%, the voltage was regulated by
paucity in the available measurements for the test network, demand 13%, and the cable loading during peak was regulated by 12%.
measurements of a single day (23/8/2019) in 10-minute resolution are
selected for the BESS sizing which represents the date with maximum 6.3. BESS degradation
demand among the available measurements. For the LCTs, ideal PV
generation profiles are used, while different EV patterns are generated The proposed approach preserves the BESS lifetime by using only
probabilistically using the EV charging pattern model described in 70% of the BESS actual capacity that represent the DoD, which has been
Section 2.2. However, to tighten the EV charging during peak time to shown to maintain the number of BESS cycles defined by the manufac­
consider the severe violations, the start time of EV charging is con­ turers [54,55]. However, in order to evaluate the detailed impact of the
strained between 16:00 hr to 22:00 hr conditioned by the CDF in Fig. 3. proposed BESS scheduling on the degradation, the semi-empirical Li-ion
Furthermore, to consider the unbalanced impact, the LCTs are assumed degradation model in [54] has been adopted to quantify the BESS state
to be distributed on U5 phases as follows (60% of the LCTs on Phase A of health (SoH) at the end of lifetime. The BESS SoC profile was obtained
and 40% on the other phases equally). from the one-week simulation in Fig. 17 and repeated for one-year.
The pre-defined scheduling horizons are assigned as; from 12:00 hr Afterwards, the rainflow counting algorithm [61] has been used to
to 17:00 hr for charging (Tc ) which represents the mid-day period with analyze the SoC profile and extract the data required for the degradation
high PV generation and from 18:00 hr to 23:00 hr for the discharging model. The BESS ageing throughout one-year is illustrated in Fig. 18.
(Td ) which represents the evening peak with high EV charging. Proba­ The results from the ageing model show that the BESS capacity de­
bilistic simulations were implemented by varying the EV patterns 20 grades by 3.05%/year with 365 full cycles. By scaling for 10 years of
times and the BESS sizing summary results are shown in Fig. 15. operation which is the warrantied lifespan of Li-Ion BESS [62], the BESS
As shown in Fig. 15, as the PV and demand profiles are fixed, the is assumed to reach an SoH value of 69.51%. This value represents the
BESS specifications (capacity/power) vary based on the EV charging SoH (residual capacity) at the end of 10 years of operation which is
patterns. The more the EV charging overlaps, the higher BESS capacity adequate as the BESS considered to reach the end of life when the

13
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 15. BESS sizing results for 20 simulations.

Fig. 16. U5 total power before and after the BESS scheduling.

residual capacity reaches 60% – 80% [54,63]. The SoH of 69.51% proves inject reactive power and they are operated on unity or leading power
the effectiveness of the proposed scheduling algorithm in preserving the factor [53]. Equipping the BESS with a proper PCS/inverter will allow
BESS capacity through its warrantied lifetime. Note that, in the previous for absorbing/injecting reactive power which will be beneficial in the
assumption, the degradation was calculated assuming that the BESS case of over/under voltage in addition to enhancing the power factor
operates all the year according to the simulated one-week case study. and quality. However, managing the reactive power should be coordi­
However, in practice, the BESS may not be required to be used nated with the DSO to avoid affecting the network constraints and
completely in daily basis. Thus, the expected BESS SoH at the end of a supply security.
lifetime might be higher in reality. In the previous results, one BESS (47 kWh / 19 kW) was installed at
the end of the U5 feeder, this BESS can be replaced with three BESS of
7. Discussion (16 kWh / 7 kW). Each one of these BESS should be connected to a phase
selector to be able to inject and absorb from the three phases. On the
The previous results show the effectiveness of the BESS and the other hand, these units can be replaced by behind the meter units, by
proposed scheduling algorithm in solving all the technical violations in equipping only 25% of the households in U5 with a BESS with 7 kWh / 3
addition to optimizing the operation of the LVRN. The use of BESS in the kW. However, in this case, the connections should be balanced across
LVRN has proven to be very attractive due to their wide applications. In the phases and the DSO should have full management of these units. An
addition, in the previous simulations, it was assumed that the BESS PCS agreement can be settled between the DSO and customers in which the
is operating on a unity power factor, this is due to the reactive power DSO can have full access to these BESS by incentivizing the customers
effect on raising the system voltage, the majority of distributed gener­ through offering a single payment as a part of the capital cost or fixed
ation and microgeneration units in Northern Ireland are not permitted to small yearly/monthly payments. Recent findings from the Distributed

14
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 17. Summarized results before and after the BESS incorporation (a) voltage unbalance; (b) phase voltage for critical phases; (c) cable loading for critical phases;
(d) power loss; (e) BESS power and SoC.

Table 5
Average improvements for the one-week case study.
Day VU Voltage regulation Voltage regulation Voltage regulation Cable loading Cable loading Cable loading Phase energy Neutral
[%] (Phase A) [%] (Phase B) [%] (Phase C) [%] (Phase A) [%] (Phase B) [%] (Phase C) [%] losses [%] energy losses
[%]

1 24.945 14.791 24.850 0.280 15.043 25.307 -2.862 10.663 14.635


2 25.542 8.159 14.242 13.117 1.882 14.013 12.513 7.189 22.969
3 19.925 21.521 3.067 0.337 19.012 1.258 0.311 13.902 37.990
4 10.535 -0.426 20.553 12.079 0.587 20.529 9.946 13.897 35.493
5 25.511 -1.301 6.826 11.155 -10.522 2.386 12.082 2.505 22.542
6 19.995 25.817 14.341 1.141 23.065 19.333 1.970 21.815 34.391
7 18.857 17.259 17.504 8.629 14.922 15.551 14.20 14.395 23.332

Storage & Solar Study by Northern Powergrid [64], have shown the hence, it can be used for short/long term planning. In this paper, the
effectiveness of residential BESS in shaving the peak demand averagely scheduling results were determined assuming perfect foresight in order
as well as reducing the impact of residential solar PV export power. to evaluate the proposed scheduling algorithm. However, proper fore­
It is worth mentioning that the proposed BESS scheduling algorithm casting model should be used in practice. Moreover, real-time operation
should be implemented on a look-ahead basis using forecasted data, and methodologies should be investigated to overcome the uncertainties

15
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Fig. 18. BESS degradation throughout one year of operation using the proposed BESS scheduling algorithm.

associated with forecasting, which can be considered an extension of this in mitigating the LCTs technical problems. This can be achieved by of­
work. Examples of applicable BESS real-time methods have been intro­ fering incentives to pre-defined customers according to their locations in
duced in [26,27]. return for their assistance in supporting the LVRN operation by
reducing/increasing their demand at specific times according to signals
8. Conclusion from the DSOs. Additionally, bespoke time of use tariff structures can
also indirectly enforce customers to reduce their consumption during
This paper investigated the impact of LCTs such as EVs and PVs on the peak and increase their consumption during the PV generation. This
the low voltage unbalanced residential networks. Different LCTs pene­ will help in mitigating the demand peak and reverse power flow.
trations were tested on real LV residential networks located in Northern However, other issues may be introduced such as voltage unbalance.
Ireland for balanced and unbalanced distribution of LCTs over the three Hence, dynamic tariff structures can be considered as a good option. The
phases. The assessment was conducted by evaluating various critical tariff structure can also be varied over the households in the LVRN to
technical indices including voltage unbalance, phase voltage, line flow, achieve a balance in the consumption across the day.
and phase/neutral losses. The results show that with high penetration of
unmanaged LCTs, the network security and power quality will be Author statement
threatened. A flexible solution based on the community BESS was
introduced by proposing a sizing algorithm to determine the proper Ahmed A.Raouf Mohamed: Conceptualization, Methodology, Soft­
BESS size with minimum investment to be installed at the feeder’s end ware, Validation, Formal analysis, Investigation, Writing - Original
node that supports the network during congestion. The scheduling of Draft, Writing - Review & Editing, Visualization, Data Curation
BESS was also introduced via a scheduling algorithm to solve the Robert J. Best: Conceptualization, Supervision, Validation, Writing -
network violations in addition to improving the network power quality. Review & Editing, Formal analysis, Investigation
The community BESS proved its capability in enhancing the network D. John Morrow: Conceptualization, Supervision, Project adminis­
performance and flexibility which supports the secure integration of tration, Funding acquisition, Writing - Review & Editing
further LCTs. Andrew Cupples: Writing - Review & Editing, Validation, Resources
The payments that should be received by the BESS owners are not yet Ian Bailie: Writing - Review & Editing, Resources
established by the DSO in Northern Ireland. The BESS payments should
be profitable to encourage the BESS investors to participate in sup­ CRediT authorship contribution statement
porting the LVRN. Usually, these payments will be structured according
to the type of the service as well as the availability and utilization. DSOs Ahmed A. Raouf Mohamed: Conceptualization, Methodology,
should introduce profitable commercial contracts to attract and Software, Validation, Formal analysis, Investigation, Writing – original
encourage energy investors to participate in the BESS to accelerate the draft, Writing – review & editing, Visualization, Data curation. Robert
transition towards the net-zero target and low carbon communities. The J. Best: Conceptualization, Supervision, Validation, Writing – review &
main goal of this paper is to assess the technical impacts of high LCTs editing, Formal analysis, Investigation. D. John Morrow: Conceptuali­
penetration and the role of community BESS in providing different zation, Supervision, Project administration, Formal analysis, Writing –
services to support the network operation. However, further in­ review & editing. Andrew Cupples: Writing – review & editing, Vali­
vestigations are required to determine the specific payment of each dation, Resources. Ian Bailie: Writing – review & editing, Resources.
service (e.g., voltage unbalance, voltage regulations, peak shaving, …
etc.) and the BESS stacked revenues in the low voltage networks, which
Declaration of Competing Interest
is considered as future research.
Behind the meter units can be considered as a very attractive option,
The authors declare that they have no known competing financial
however, these units require appropriate monitoring and management.
interests or personal relationships that could have appeared to influence
Unmanaged residential BESS can act as additional demand during
the work reported in this paper.
charging and as a generation during discharging and so can introduce
the same technical issues to the LVRN operation discussed previously in
Acknowledgements
this paper. Hence, proper coordination and management frameworks
should be introduced to achieve maximum utilization of these resources
The authors would like to thank NIE Networks for their valuable
by the DSOs and assuring the profitability of customers, which is
support and providing the data used in this paper. This research is part of
considered as future research. Demand side management can also assist
SPIRE 2 project (Grant No: IVA5038) supported by the European

16
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

Union’s INTERREG VA Programme, managed by the Special EU Pro­ Network Operation, in: 9th IET International Conference on Renewable Power
Generation, Dublin, Ireland, 2021, p. 6.
grammes Body (SEUPB). The views and opinions expressed in this
[28] O.O. Ademulegun, P. Keatley, M.Bani Mustafa, N.J. Hewitt, Energy Storage on a
document do not necessarily reflect those of the European Commission Distribution Network for Self-Consumption of Wind Energy and Market Value,
or the SEUPB. Energies 13 (11) (2020) 2688.
[29] UK Power Networks, ‘Low Carbon London Electric Vehicle Load Profiles - London
Datastore’, 2014-2013. [Online]. Available: https://rb.gy/d8eouq. [Accessed: 17-
References Jul- 2020].
[30] P. Zhang, K. Qian, C. Zhou, B.G. Stewart, D.M. Hepburn, A Methodology for
[1] A.A.R. Mohamed, D.J. Morrow, R. Best, The Deployment of Low Carbon Optimization of Power Systems Demand Due to Electric Vehicle Charging Load,
Technologies in Modern Distribution Networks’, in: presented at the 2019 IEEE PES IEEE Trans. Power Syst. 27 (3) (Aug. 2012) 1628–1636, https://doi.org/10.1109/
Innovative Smart Grid Technologies Europe (ISGT-Europe), Bucharest, Romania, TPWRS.2012.2186595.
2019, pp. 1–5. [31] B. Zhou, D. Yang, S. Bu, G. Du, T. Littler, The impact of electric vehicle
[2] Ofgem, Smart Export Guarantee (SEG), Ofgem (2020), 16-Sep-2019[Online]. uncertainties on load levelling in the UK, in: 2017 IEEE Power & Energy Society
Available: https://rb.gy/3kqiyi [Accessed: 18-Jul-]. General Meeting, Chicago, IL, 2017, pp. 1–5, https://doi.org/10.1109/
[3] Energy Networks, ‘Engineering Recommendation G98’, 2018 [Online]. Available: PESGM.2017.8274727.
https://rb.gy/vawbzm. [Accessed: 20-Aug-2020]. [32] Department for Transport, ‘National Travel Survey’, 2019. [Online]. Available:
[4] S. Bradbury, A. Price, Storage business models in the UK market, Report. Pöyry https://www.gov.uk/government/collections/national-travel-survey-statistics.
Management Consulting, UK (2014). [Accessed: 17-Jul-2020].
[5] Northern Ireland Electricity Network, ‘FESS’, 2020. [Online]. Available: https://bit [33] J. Dixon, K. Bell, Electric vehicles: battery capacity, charger power, access to
.ly/3bELisY. charging and the impacts on distribution networks, ETransportation 4 (2020),
[6] A. Navarro-Espinosa, L.F. Ochoa, Probabilistic Impact Assessment of Low Carbon 100059.
Technologies in LV Distribution Systems, IEEE Trans. Power Syst. 31 (3) (May [34] C. Lilly, EV Charging connectors - Electric car charging speeds, Zap-Map (2021)
2016) 2192–2203, https://doi.org/10.1109/TPWRS.2015.2448663. [Online]. Available: https://www.zap-map.com/charge-points/connectors-speeds/
[7] P. Richardson, D. Flynn, A. Keane, Impact assessment of varying penetrations of [Accessed: 17-May-].
electric vehicles on low voltage distribution systems, in: IEEE PES General Meeting, [35] UK GOV, ‘Electric vehicle charging in residential and non-residential buildings’,
Minneapolis, MN, 2010, pp. 1–6, https://doi.org/10.1109/PES.2010.5589940. 2019.
[8] ‘IEEE Std 112- 2004, IEEE Standard Test Procedure for Polyphase Induction Motors [36] T. Niimura, K. Ozawa, D. Yamashita, K. Yoshimi, M. Osawa, Profiling residential
and Generators’, p. 87. PV output based on weekly weather forecast for home energy management system,
[9] A. Rodriguez-Calvo, R. Cossent, P. Frías, Integration of PV and EVs in unbalanced in: 2012 IEEE Power and Energy Society General Meeting, 2012, pp. 1–5.
residential LV networks and implications for the smart grid and advanced metering [37] PVOutput, ‘PV output data’, 2019. [Online]. Available: https://pvoutput.org/.
infrastructure deployment, Int. J. Electr. Power Energy Syst. 91 (Oct. 2017) [38] M.B. Ndawula, I. Hernando-Gil, S. Djokic, Impact of the stochastic behaviour of
121–134, https://doi.org/10.1016/j.ijepes.2017.03.008. distributed energy resources on MV/LV network reliability, in: 2018 IEEE
[10] S. Ali, N. Pearsall, G. Putrus, Impact of High Penetration Level of Grid-Connected International Conference on Environment and Electrical Engineering and 2018
Photovoltaic Systems on the UK Low Voltage Distribution Network, REPQJ (Apr. IEEE Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Europe),
2012) 519–522, https://doi.org/10.24084/repqj10.368. 2018, pp. 1–6.
[11] Y. Zou, J. Zhao, X. Gao, Y. Chen, A. Tohidi, Experimental results of electric vehicles [39] SONI, ‘Tomorrow’s Energy Scenarios Northern Ireland 2019 Consultation’, 2019
effects on low voltage grids, J. Cleaner Prod. 255 (2020), 120270. [Online]. Available: http://www.soni.ltd.uk/media/documents/TES-NI-2019-Cons
[12] P. Papadopoulos, S. Skarvelis-Kazakos, I. Grau, L.M. Cipcigan, N. Jenkins, Electric ultation.pdf.
vehicles’ impact on British distribution networks, IET Electr. Syst. Transp. 2 (3) [40] Northern Ireland Statistics and Research Agency, 2018-based Population
(2012) 91, https://doi.org/10.1049/iet-est.2011.0023. Projections for Northern Ireland, Northern Ireland Statistics and Research Agency
[13] C.H. Tie, C.K. Gan, K.A. Ibrahim, The impact of electric vehicle charging on a (2019), 23-Aug-[Online]. Available: https://www.nisra.gov.uk/publications/2
residential low voltage distribution network in Malaysia, in: 2014 IEEE Innovative 018-based-population-projections-northern-ireland [Accessed: 17-Jul-2020].
Smart Grid Technologies - Asia (ISGT ASIA), Kuala Lumpur, Malaysia, 2014, [41] Statista Research Department, Household size in Northern Ireland 2008-2018,
pp. 272–277, https://doi.org/10.1109/ISGT-Asia.2014.6873802. Statista (2020) [Online]. Available: https://www.statista.com/statistics/524942/
[14] SSE, ‘Low Voltage (LV) Network Connected Energy Storage’, UK, Jan. 2012 average-household-size-in-northern-ireland/ [Accessed: 17-Jul-2020].
[Online]. Available: https://www.smarternetworks.org/project/sset1008. [42] Zap-Map, Map of charging points for electric car drivers in UK, Zap-Map (2020)
[15] A.J. Pimm, T.T. Cockerill, P.G. Taylor, The potential for peak shaving on low [Online]. Available, https://www.zap-map.com/live/ [Accessed: 17-Jul-2020].
voltage distribution networks using electricity storage, Journal of Energy Storage [43] nationalgridESO, ‘Future Energy Scenarios’, 2019 [Online]. Available: https
16 (2018) 231–242. ://www.nationalgrideso.com/sites/eso/files/documents/fes-2019.pdf.
[16] W. van Westering, H. Hellendoorn, Low voltage power grid congestion reduction [44] A. REGULATIONS, The electricity safety, quality and continuity regulations 2002,
using a community battery: Design principles, control and experimental validation, Crown Copyr (2002).
Int. J. Electr. Power Energy Syst. 114 (2020), 105349. [45] P. Pillay, M. Manyage, Definitions of Voltage Unbalance, IEEE Power Engineering
[17] M. U. Hashmi, J. Horta, L. Pereira, Z. Lee, A. Bušić, and D. Kofman, ‘Towards Phase Review (2) (2001).
Balancing using Energy Storage’, arXiv:2002.04177 [cs, eess, math], Feb. 2020 [46] R.C. Dugan, M.F. McGranaghan, H.W. Beaty, Electrical Power Systems Quality,
[Online]. Available: http://arxiv.org/abs/2002.04177. [Accessed: 16-Jul-2020]. Second Edition, McGraw-Hill, New York, 2004.
[18] R.C. Johnson, M. Mayfield, S.B.M. Beck, Optimal placement, sizing, and dispatch of [47] E.N. Association, Engineering recommendation p29: Planning limits for voltage
multiple BES systems on UK low voltage residential networks, Journal of Energy unbalance in the united kingdom, Energy Networks Association, London, 1990.
Storage 17 (2018) 272–286. [48] D. Shirmohammadi, H.W. Hong, A. Semlyen, G.X. Luo, A compensation-based
[19] F.M. Camilo, R. Castro, M.E. Almeida, V. Fernão Pires, Energy management in power flow method for weakly meshed distribution and transmission networks,
unbalanced low voltage distribution networks with microgeneration and storage IEEE Trans. Power Syst. 3 (2) (1988) 753–762.
by using a multi-objective optimization algorithm, Journal of Energy Storage 33 [49] N.K. Meena, J. Yang, P. Singh, Backward/Forward Method for Three-phase Power
(Jan. 2021), 102100, https://doi.org/10.1016/j.est.2020.102100. Flow Calculation in Low Voltage Distribution Networks with EV Charging Points,
[20] G. Carpinelli, F. Mottola, D. Proto, A. Russo, P. Varilone, A hybrid method for in: 2018 8th IEEE India International Conference on Power Electronics (IICPE),
optimal siting and sizing of battery energy storage systems in unbalanced low JAIPUR, India, 2018, pp. 1–6, https://doi.org/10.1109/IICPE.2018.8709560.
voltage microgrids, Applied Sciences 8 (3) (2018) 455. [50] B. C. P. Switzerland, NEPLAN® Power System Analysis and Engineering.
[21] S.H. Low, Convex relaxation of optimal power flow—Part I: Formulations and [51] C. Audet and W. Hare, ‘Derivative-free and blackbox optimization’, 2017.
equivalence, IEEE Transactions on Control of Network Systems 1 (1) (2014) 15–27. [52] R.T. Marler, J.S. Arora, Function-transformation methods for multi-objective
[22] H. Glavitsch, R. Bacher, Optimal power flow algorithms, Analysis and control optimization, Eng. Optim. 37 (6) (2005) 551–570.
system techniques for electric power systems 41 (1991) 135–206. [53] J. Pollock, D. Hill, L. Smyth, D. McGuckin, Development of NIE networks’ nodal
[23] A.M. Nour, A.A. Helal, M.M. El-Saadawi, A.Y. Hatata, A control scheme for voltage controller project to deliver reactive power support to the wider electricity system,
unbalance mitigation in distribution network with rooftop PV systems based on The Journal of Engineering 2019 (18) (2019) 4794–4798.
distributed batteries, Int. J. Electr. Power Energy Syst. 124 (2021), 106375. [54] B. Xu, A. Oudalov, A. Ulbig, G. Andersson, D.S. Kirschen, Modeling of lithium-ion
[24] A. Bagchi, R. Best, D.J. Morrow, J. Pollock, I. Bailie, A. Cupples, System Service battery degradation for cell life assessment, IEEE Trans. Smart Grid 9 (2) (2016)
Provision Capabilities of Storage Devices Connected to a MV Distribution Network: 1131–1140.
A Northern Ireland Case Study, in: presented at the 2020 IEEE Power & Energy [55] S. You, J. Hu, A.B. Pedersen, P.B. Andersen, C.N. Rasmussen, S. Cha, Numerical
Society Innovative Smart Grid Technologies Conference (ISGT), 2020, pp. 1–5. comparison of optimal charging schemes for electric vehicles’, in: presented at the
[25] A.A.R. Mohamed, D.J. Morrow, R.J. Best, I. Bailie, A. Cupples, J. Pollock, Battery 2012 IEEE power and energy society general meeting, 2012, pp. 1–6.
Energy Storage Systems Allocation Considering Distribution Network Congestion, [56] D. Greenwood, N. Wade, P. Papadopolous, N. Heyward, P. Mehtah, P. Taylor,
in: presented at the 2020 IEEE PES Innovative Smart Grid Technologies Europe Scheduling power and energy resources in the smarter network storage project, in:
(ISGT-Europe), 2020, p. 5. presented at the CIRED 23rd Int. Conf. and Exhibition on Electricity Distribution,
[26] A.A.R. Mohamed, D.J. Morrow, R.J. Best, A. Cupples, I. Bailie, J. Pollock, Lyon, France, 2015, pp. 1–5.
Distributed Battery Energy Storage Systems Operation Framework for Grid Power [57] M. A. Abramson, C. Audet, G. Couture, J. E. Dennis Jr, S. Le Digabel, and C. Tribes,
Levelling in the Distribution Networks, IET Smart Grid (2021) 12. The NOMAD project. Technical report, 2011.
[27] A.A.R. Mohamed, D.J. Morrow, R.J. Best, Real-time Model Predictive Control of
Battery Energy Storage Active and Reactive Power to Support the Distribution

17
A.A. Raouf Mohamed et al. Journal of Energy Storage 42 (2021) 102975

[58] S. Le Digabel, Algorithm 909: NOMAD: Nonlinear optimization with the MADS [62] K. Mongird, et al., Energy storage technology and cost characterization report,
algorithm, ACM Transactions on Mathematical Software (TOMS) 37 (4) (2011) Pacific Northwest National Lab.(PNNL) (2019). Richland, WA (United States).
1–15. [63] U.G.K. Mulleriyawage, W.X. Shen, Optimally sizing of battery energy storage
[59] N. Mladenović, P. Hansen, Variable neighborhood search, Computers & operations capacity by operational optimization of residential PV-Battery systems: An
research 24 (11) (1997) 1097–1100. Australian household case study, Renewable Energy (2020) 13.
[60] J. Currie, D.I. Wilson, N. Sahinidis, J. Pinto, OPTI: Lowering the barrier between [64] Northern Powergrid, ‘Distributed Storage & Solar Study (NIA_NPG_011)’, 2020.
open source optimizers and the industrial MATLAB user, Found. of computer-aided [Online]. Available: https://www.northernpowergrid.com/innovation/projects/di
process operations 24 (2012) 32. stributed-storage-solar-study-nia-npg-011. [Accessed: 18-Jul-2020].
[61] E08 Committee, Practices for Cycle Counting in Fatigue Analysis, ASTM
International [Online], 2020. Available: http://www.astm.org/cgi-bin/resolver.cgi
?E1049-85R17 [Accessed: 11-Dec-].

18

You might also like