Professional Documents
Culture Documents
( floor to floor)
G+2 considered for frame anaylisis and
Structural configeration foundation
At this stagedesign
G+1 considered for
construction
Option 1 Option 2
Conventional RCC framed structure with
beams and slab Flat slab Design
Breif
30 Days .Generally venders will take 15 20 days.Due to the flat shuttering only for the slab
Time frame for each floor readiness with +15 days ( if total area concrete pour soffit and column cap the repetition and better
1 shuttering planned in two segments) speed can be achived
Posibility of increase column free Area in
2 internal Layout . Moderate High
3 Grade of concrete M 20 /M 25 M25 /M 30 . Crn to comment
6 Venders capacity / knowledge Normally all venders used to do it Normally all venders used to do it
Fully in situ shuttering beam shuttering
7 Quandum in situ shuttering work takes the time comparitvely lesser and relatively faster
Recommendations
Fire protection Good fire resistance capacity Good fire resistance capacity
Ease of future vertical extension and Ease of future vertical extension and connection to
Vertical extension connection to existing buildings. existing buildings.
Ranking I IV
Option 3 0ption 4 Option 5
Flat slab with Post tentioning Rcc column with steel joist and rcc slab with shuttering RCC column with steel joist and Deck sheeting
similer to Asian Paint sriperumpudur
steel joist can be Solid web or open web
Relatively high due to the scale of work crn to give input Crn to give input
CRN to give input CRN to give input CRN to give input
Available Available Available
Small value of works, is not likely to To enable future extension of column to upper floors, the To enable future extension of column to upper
attract, required attention or response. steel beam have been seated on RC bracket from RC column. floors, the steel beam have been seated on RC
In situ welding of steel beam to insert plates on column face bracket from RC column. In situ welding of steel
With only two upper floors, reduction not recommended. beam to insert plates on column face not
load compared to Optoin -2 will be less. recommended.
Therefore column and foundation will be subjected to
Costlier then - Option - 2 excessive bending moment. Therefore column and foundation will be subjected
to excessive bending moment.
Good fire resistance capacity Acceptable fire resistance behaviour Acceptable fire resistance behaviour
Vertical extension more difficult Vertical extension more difficult Vertical extension more difficult
Only limited number of builders Many builders available Many builders available
available
V II III