Calculation of Multiplying Factor for Price Adjustment

RA-1 (July 2020)


Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 307 En = 75.10 Dn = 75.87
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (307/288) + 0.38 X (75.1/77.1) + 0.25 X (75.87/68.72)
= 1.027
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 307 Sn = 105.60 Cn = 121.90
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.10 Dn = 75.87 On = 121.00
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (307/288) + 0.3 X (105.6/110.1) + 0.22 X (121.9/117.3)
+ 0.07 X (75.1/77.1) + 0.04 X (75.87/68.72) + 0.02 X (121/119.9)
= 1.009
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 307 Sn = 105.60 En = 75.10 Dn = 75.87
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (307/288) +0.73 X (105.6/110.1) + 0.02 X (75.1/77.1)
+ 0.02 X (75.87/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-1 (July 2020)
= 0.974
Calculation of Multiplying Factor for Price Adjustment
RA-1 (July 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 307 Dn = 75.87 On = 121.00
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.14 X (75.87/68.72) + 0.49 X (121/119.9)
= 1.030
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 307 En = 75.10 Dn = 75.87 On = 121.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.06 X (75.1/77.1) + 0.04 X (75.87/68.72)
+ 0.53 X (121/119.9)
= 1.019
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 307 En = 75.10 Dn = 75.87 On = 121.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.12 X (75.1/77.1) + 0.06 X (75.87/68.72)
+ 0.45 X (121/119.9)
= 1.018
Calculation of Multiplying Factor for Price Adjustment
RA-2 (August 2020)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 309 En = 75.60 Dn = 77.31
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (309/288) + 0.38 X (75.6/77.1) + 0.25 X (77.31/68.72)
= 1.036
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 309 Sn = 104.80 Cn = 121.50
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.60 Dn = 77.31 On = 122.00
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (309/288) + 0.3 X (104.8/110.1) + 0.22 X (121.5/117.3)
+ 0.07 X (75.6/77.1) + 0.04 X (77.31/68.72) + 0.02 X (122/119.9)
= 1.008
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 309 Sn = 104.80 En = 75.60 Dn = 77.31
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (309/288) +0.73 X (104.8/110.1) + 0.02 X (75.6/77.1)
+ 0.02 X (77.31/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-2 (August 2020)
= 0.969
Calculation of Multiplying Factor for Price Adjustment
RA-2 (August 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 309 Dn = 77.31 On = 122.00
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (309/288) +0.14 X (77.31/68.72) + 0.49 X (122/119.9)
= 1.038
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 309 En = 75.60 Dn = 77.31 On = 122.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (309/288) +0.06 X (75.6/77.1) + 0.04 X (77.31/68.72)
+ 0.53 X (122/119.9)
= 1.026
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 309 En = 75.60 Dn = 77.31 On = 122.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (309/288) +0.12 X (75.6/77.1) + 0.06 X (77.31/68.72)
+ 0.45 X (122/119.9)
= 1.025
Calculation of Multiplying Factor for Price Adjustment
RA-3 (September 2020)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 311 En = 75.30 Dn = 77.31
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (311/288) + 0.38 X (75.3/77.1) + 0.25 X (77.31/68.72)
= 1.036
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 311 Sn = 102.80 Cn = 120.30
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.30 Dn = 77.31 On = 122.90
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (311/288) + 0.3 X (102.8/110.1) + 0.22 X (120.3/117.3)
+ 0.07 X (75.3/77.1) + 0.04 X (77.31/68.72) + 0.02 X (122.9/119.9)
= 1.002
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 311 Sn = 102.80 En = 75.30 Dn = 77.31
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (311/288) +0.73 X (102.8/110.1) + 0.02 X (75.3/77.1)
+ 0.02 X (77.31/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-3 (September 2020)
= 0.956
Calculation of Multiplying Factor for Price Adjustment
RA-3 (September 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 311 Dn = 77.31 On = 122.90
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.14 X (77.31/68.72) + 0.49 X (122.9/119.9)
= 1.043
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 311 En = 75.30 Dn = 77.31 On = 122.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.06 X (75.3/77.1) + 0.04 X (77.31/68.72)
+ 0.53 X (122.9/119.9)
= 1.030
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 311 En = 75.30 Dn = 77.31 On = 122.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.12 X (75.3/77.1) + 0.06 X (77.31/68.72)
+ 0.45 X (122.9/119.9)
= 1.030
Calculation of Multiplying Factor for Price Adjustment
RA-4 (October 2020)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 316 En = 75.30 Dn = 74.31
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (316/288) + 0.38 X (75.3/77.1) + 0.25 X (74.31/68.72)
= 1.028
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 316 Sn = 104.50 Cn = 119.60
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.30 Dn = 74.31 On = 123.60
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (316/288) + 0.3 X (104.5/110.1) + 0.22 X (119.6/117.3)
+ 0.07 X (75.3/77.1) + 0.04 X (74.31/68.72) + 0.02 X (123.6/119.9)
= 1.006
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 316 Sn = 104.50 En = 75.30 Dn = 74.31
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (316/288) +0.73 X (104.5/110.1) + 0.02 X (75.3/77.1)
+ 0.02 X (74.31/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-4 (October 2020)
= 0.967
Calculation of Multiplying Factor for Price Adjustment
RA-4 (October 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 316 Dn = 74.31 On = 123.60
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (316/288) +0.14 X (74.31/68.72) + 0.49 X (123.6/119.9)
= 1.043
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 316 En = 75.30 Dn = 74.31 On = 123.60
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (316/288) +0.06 X (75.3/77.1) + 0.04 X (74.31/68.72)
+ 0.53 X (123.6/119.9)
= 1.035
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 316 En = 75.30 Dn = 74.31 On = 123.60
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (316/288) +0.12 X (75.3/77.1) + 0.06 X (74.31/68.72)
+ 0.45 X (123.6/119.9)
= 1.032
Calculation of Multiplying Factor for Price Adjustment
RA-5 (November 2020)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 318 En = 75.60 Dn = 74.25
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (318/288) + 0.38 X (75.6/77.1) + 0.25 X (74.25/68.72)
= 1.030
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 318 Sn = 106.30 Cn = 119.40
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.60 Dn = 74.25 On = 125.10
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (318/288) + 0.3 X (106.3/110.1) + 0.22 X (119.4/117.3)
+ 0.07 X (75.6/77.1) + 0.04 X (74.25/68.72) + 0.02 X (125.1/119.9)
= 1.012
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 318 Sn = 106.30 En = 75.60 Dn = 74.25
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (318/288) +0.73 X (106.3/110.1) + 0.02 X (75.6/77.1)
+ 0.02 X (74.25/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-5 (November 2020)
= 0.979
Calculation of Multiplying Factor for Price Adjustment
RA-5 (November 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 318 Dn = 74.25 On = 125.10
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.14 X (74.25/68.72) + 0.49 X (125.1/119.9)
= 1.050
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 318 En = 75.60 Dn = 74.25 On = 125.10
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.06 X (75.6/77.1) + 0.04 X (74.25/68.72)
+ 0.53 X (125.1/119.9)
= 1.043
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 318 En = 75.60 Dn = 74.25 On = 125.10
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.12 X (75.6/77.1) + 0.06 X (74.25/68.72)
+ 0.45 X (125.1/119.9)
= 1.040
Calculation of Multiplying Factor for Price Adjustment
RA-6 (December 2020)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 314 En = 75.80 Dn = 76.27
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (314/288) + 0.38 X (75.8/77.1) + 0.25 X (76.27/68.72)
= 1.036
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 314 Sn = 108.00 Cn = 119.10
L0 = 288 S0 = 110.10 C0 = 117.30
En = 75.80 Dn = 76.27 On = 125.40
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (314/288) + 0.3 X (108/110.1) + 0.22 X (119.1/117.3)
+ 0.07 X (75.8/77.1) + 0.04 X (76.27/68.72) + 0.02 X (125.4/119.9)
= 1.015
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 314 Sn = 108.00 En = 75.80 Dn = 76.27
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (314/288) +0.73 X (108/110.1) + 0.02 X (75.8/77.1)
+ 0.02 X (76.27/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-6 (December 2020)
= 0.991
Calculation of Multiplying Factor for Price Adjustment
RA-6 (December 2020)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 314 Dn = 76.27 On = 125.40
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (314/288) +0.14 X (76.27/68.72) + 0.49 X (125.4/119.9)
= 1.053
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 314 En = 75.80 Dn = 76.27 On = 125.40
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (314/288) +0.06 X (75.8/77.1) + 0.04 X (76.27/68.72)
+ 0.53 X (125.4/119.9)
= 1.043
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 314 En = 75.80 Dn = 76.27 On = 125.40
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (314/288) +0.12 X (75.8/77.1) + 0.06 X (76.27/68.72)
+ 0.45 X (125.4/119.9)
= 1.041
Calculation of Multiplying Factor for Price Adjustment
RA-7 (January 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 307 En = 76.60 Dn = 77.72
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (307/288) + 0.38 X (76.6/77.1) + 0.25 X (77.72/68.72)
= 1.041
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 307 Sn = 112.80 Cn = 119.70
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.60 Dn = 77.72 On = 126.50
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (307/288) + 0.3 X (112.8/110.1) + 0.22 X (119.7/117.3)
+ 0.07 X (76.6/77.1) + 0.04 X (77.72/68.72) + 0.02 X (126.5/119.9)
= 1.028
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 307 Sn = 112.80 En = 76.60 Dn = 77.72
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (307/288) +0.73 X (112.8/110.1) + 0.02 X (76.6/77.1)
+ 0.02 X (77.72/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-7 (January 2021)
= 1.022
Calculation of Multiplying Factor for Price Adjustment
RA-7 (January 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 307 Dn = 77.72 On = 126.50
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.14 X (77.72/68.72) + 0.49 X (126.5/119.9)
= 1.057
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 307 En = 76.60 Dn = 77.72 On = 126.50
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.06 X (76.6/77.1) + 0.04 X (77.72/68.72)
+ 0.53 X (126.5/119.9)
= 1.045
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 307 En = 76.60 Dn = 77.72 On = 126.50
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.12 X (76.6/77.1) + 0.06 X (77.72/68.72)
+ 0.45 X (126.5/119.9)
= 1.043
Calculation of Multiplying Factor for Price Adjustment
RA-8 (February 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 302 En = 76.60 Dn = 80.35
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (302/288) + 0.38 X (76.6/77.1) + 0.25 X (80.35/68.72)
= 1.048
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 302 Sn = 118.20 Cn = 119.00
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.60 Dn = 80.35 On = 128.10
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (302/288) + 0.3 X (118.2/110.1) + 0.22 X (119/117.3)
+ 0.07 X (76.6/77.1) + 0.04 X (80.35/68.72) + 0.02 X (128.1/119.9)
= 1.040
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 302 Sn = 118.20 En = 76.60 Dn = 80.35
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (302/288) +0.73 X (118.2/110.1) + 0.02 X (76.6/77.1)
+ 0.02 X (80.35/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-8 (February 2021)
= 1.058
Calculation of Multiplying Factor for Price Adjustment
RA-8 (February 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 302 Dn = 80.35 On = 128.10
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (302/288) +0.14 X (80.35/68.72) + 0.49 X (128.1/119.9)
= 1.065
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 302 En = 76.60 Dn = 80.35 On = 128.10
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (302/288) +0.06 X (76.6/77.1) + 0.04 X (80.35/68.72)
+ 0.53 X (128.1/119.9)
= 1.051
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 302 En = 76.60 Dn = 80.35 On = 128.10
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (302/288) +0.12 X (76.6/77.1) + 0.06 X (80.35/68.72)
+ 0.45 X (128.1/119.9)
= 1.048
Calculation of Multiplying Factor for Price Adjustment
RA-9 (1st March - 15th March, 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 305 En = 76.60 Dn = 84.60
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (305/288) + 0.38 X (76.6/77.1) + 0.25 X (84.6/68.72)
= 1.065
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 305 Sn = 125.60 Cn = 119.80
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.60 Dn = 84.60 On = 129.90
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (305/288) + 0.3 X (125.6/110.1) + 0.22 X (119.8/117.3)
+ 0.07 X (76.6/77.1) + 0.04 X (84.6/68.72) + 0.02 X (129.9/119.9)
= 1.066
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 305 Sn = 125.60 En = 76.60 Dn = 84.60
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (305/288) +0.73 X (125.6/110.1) + 0.02 X (76.6/77.1)
+ 0.02 X (84.6/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-9 (1st March - 15th March, 2021)
= 1.109
Calculation of Multiplying Factor for Price Adjustment
RA-9 (1st March - 15th March, 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 305 Dn = 84.60 On = 129.90
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.14 X (84.6/68.72) + 0.49 X (129.9/119.9)
= 1.083
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 305 En = 76.60 Dn = 84.60 On = 129.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.06 X (76.6/77.1) + 0.04 X (84.6/68.72)
+ 0.53 X (129.9/119.9)
= 1.063
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 305 En = 76.60 Dn = 84.60 On = 129.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.12 X (76.6/77.1) + 0.06 X (84.6/68.72)
+ 0.45 X (129.9/119.9)
= 1.061
Calculation of Multiplying Factor for Price Adjustment
RA-10 (16th March - 31st March, 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 305 En = 76.60 Dn = 84.60
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (305/288) + 0.38 X (76.6/77.1) + 0.25 X (84.6/68.72)
= 1.065
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 305 Sn = 125.60 Cn = 119.80
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.60 Dn = 84.60 On = 129.90
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (305/288) + 0.3 X (125.6/110.1) + 0.22 X (119.8/117.3)
+ 0.07 X (76.6/77.1) + 0.04 X (84.6/68.72) + 0.02 X (129.9/119.9)
= 1.066
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 305 Sn = 125.60 En = 76.60 Dn = 84.60
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (305/288) +0.73 X (125.6/110.1) + 0.02 X (76.6/77.1)
+ 0.02 X (84.6/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-10 (16th March - 31st March, 2021)
= 1.109
Calculation of Multiplying Factor for Price Adjustment
RA-10 (16th March - 31st March, 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 305 Dn = 84.60 On = 129.90
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.14 X (84.6/68.72) + 0.49 X (129.9/119.9)
= 1.083
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 305 En = 76.60 Dn = 84.60 On = 129.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.06 X (76.6/77.1) + 0.04 X (84.6/68.72)
+ 0.53 X (129.9/119.9)
= 1.063
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 305 En = 76.60 Dn = 84.60 On = 129.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (305/288) +0.12 X (76.6/77.1) + 0.06 X (84.6/68.72)
+ 0.45 X (129.9/119.9)
= 1.061
Calculation of Multiplying Factor for Price Adjustment
RA-11 (April 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 306 En = 76.80 Dn = 84.00
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (306/288) + 0.38 X (76.8/77.1) + 0.25 X (84/68.72)
= 1.065
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 306 Sn = 124.70 Cn = 123.60
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.80 Dn = 84.00 On = 132.00
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (306/288) + 0.3 X (124.7/110.1) + 0.22 X (123.6/117.3)
+ 0.07 X (76.8/77.1) + 0.04 X (84/68.72) + 0.02 X (132/119.9)
= 1.072
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 306 Sn = 124.70 En = 76.80 Dn = 84.00
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (306/288) +0.73 X (124.7/110.1) + 0.02 X (76.8/77.1)
+ 0.02 X (84/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-11 (April 2021)
= 1.103
Calculation of Multiplying Factor for Price Adjustment
RA-11 (April 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 306 Dn = 84.00 On = 132.00
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.14 X (84/68.72) + 0.49 X (132/119.9)
= 1.091
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 306 En = 76.80 Dn = 84.00 On = 132.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.06 X (76.8/77.1) + 0.04 X (84/68.72)
+ 0.53 X (132/119.9)
= 1.073
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 306 En = 76.80 Dn = 84.00 On = 132.00
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.12 X (76.8/77.1) + 0.06 X (84/68.72)
+ 0.45 X (132/119.9)
= 1.069
Calculation of Multiplying Factor for Price Adjustment
RA-12 (May 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 306 En = 77.00 Dn = 83.86
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (306/288) + 0.38 X (77/77.1) + 0.25 X (83.86/68.72)
= 1.065
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 306 Sn = 124.60 Cn = 124.70
L0 = 288 S0 = 110.10 C0 = 117.30
En = 77.00 Dn = 83.86 On = 132.90
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (306/288) + 0.3 X (124.6/110.1) + 0.22 X (124.7/117.3)
+ 0.07 X (77/77.1) + 0.04 X (83.86/68.72) + 0.02 X (132.9/119.9)
= 1.074
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 306 Sn = 124.60 En = 77.00 Dn = 83.86
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (306/288) +0.73 X (124.6/110.1) + 0.02 X (77/77.1)
+ 0.02 X (83.86/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-12 (May 2021)
= 1.102
Calculation of Multiplying Factor for Price Adjustment
RA-12 (May 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 306 Dn = 83.86 On = 132.90
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.14 X (83.86/68.72) + 0.49 X (132.9/119.9)
= 1.095
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 306 En = 77.00 Dn = 83.86 On = 132.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.06 X (77/77.1) + 0.04 X (83.86/68.72)
+ 0.53 X (132.9/119.9)
= 1.077
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 306 En = 77.00 Dn = 83.86 On = 132.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (306/288) +0.12 X (77/77.1) + 0.06 X (83.86/68.72)
+ 0.45 X (132.9/119.9)
= 1.072
Calculation of Multiplying Factor for Price Adjustment
RA-13 (June 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 307 En = 76.80 Dn = 88.51
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (307/288) + 0.38 X (76.8/77.1) + 0.25 X (88.51/68.72)
= 1.082
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 307 Sn = 127.60 Cn = 124.00
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.80 Dn = 88.51 On = 133.70
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (307/288) + 0.3 X (127.6/110.1) + 0.22 X (124/117.3)
+ 0.07 X (76.8/77.1) + 0.04 X (88.51/68.72) + 0.02 X (133.7/119.9)
= 1.084
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 307 Sn = 127.60 En = 76.80 Dn = 88.51
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (307/288) +0.73 X (127.6/110.1) + 0.02 X (76.8/77.1)
+ 0.02 X (88.51/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-13 (June 2021)
= 1.124
Calculation of Multiplying Factor for Price Adjustment
RA-13 (June 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 307 Dn = 88.51 On = 133.70
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.14 X (88.51/68.72) + 0.49 X (133.7/119.9)
= 1.108
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 307 En = 76.80 Dn = 88.51 On = 133.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.06 X (76.8/77.1) + 0.04 X (88.51/68.72)
+ 0.53 X (133.7/119.9)
= 1.084
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 307 En = 76.80 Dn = 88.51 On = 133.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307/288) +0.12 X (76.8/77.1) + 0.06 X (88.51/68.72)
+ 0.45 X (133.7/119.9)
= 1.080
Calculation of Multiplying Factor for Price Adjustment
RA-14 (July 2021)
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 307.254 En = 76.40 Dn = 92.31
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (307.254/288) + 0.38 X (76.4/77.1) + 0.25 X (92.31/68.72)
= 1.094
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 307.25 Sn = 130.90 Cn = 124.50
L0 = 288 S0 = 110.10 C0 = 117.30
En = 76.40 Dn = 92.31 On = 134.50
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (307.254/288) + 0.3 X (130.9/110.1) + 0.22 X (124.5/117.3)
+ 0.07 X (76.4/77.1) + 0.04 X (92.31/68.72) + 0.02 X (134.5/119.9)
= 1.096
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 307.254 Sn = 130.90 En = 76.40 Dn = 92.31
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (307.254/288) +0.73 X (130.9/110.1) + 0.02 X (76.4/77.1)
+ 0.02 X (92.31/68.72)
= 1.147
Calculation of Multiplying Factor for Price Adjustment
RA-14 (July 2021)
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 307.25 Dn = 92.31 On = 134.50
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307.254/288) +0.14 X (92.31/68.72) + 0.49 X (134.5/119.9)
= 1.119
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 307.254 En = 76.40 Dn = 92.31 On = 134.50
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307.254/288) +0.06 X (76.4/77.1) + 0.04 X (92.31/68.72)
+ 0.53 X (134.5/119.9)
= 1.089
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 307.254 En = 76.40 Dn = 92.31 On = 134.50
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (307.254/288) +0.12 X (76.4/77.1) + 0.06 X (92.31/68.72)
+ 0.45 X (134.5/119.9)
= 1.086
Calculation of Multiplying Factor for Price Adjustment
RA-15 (August 2021) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 311 En = 78.40 Dn = 93.30
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (311/288) + 0.38 X (78.4/77.1) + 0.25 X (93.3/68.72)
= 1.109
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 311 Sn = 131.70 Cn = 126.20
L0 = 288 S0 = 110.10 C0 = 117.30
En = 78.40 Dn = 93.30 On = 136.20
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (311/288) + 0.3 X (131.7/110.1) + 0.22 X (126.2/117.3)
+ 0.07 X (78.4/77.1) + 0.04 X (93.3/68.72) + 0.02 X (136.2/119.9)
= 1.106
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 311 Sn = 131.70 En = 78.40 Dn = 93.30
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (311/288) +0.73 X (131.7/110.1) + 0.02 X (78.4/77.1)
+ 0.02 X (93.3/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-15 (August 2021) / Package-I
= 1.153
Calculation of Multiplying Factor for Price Adjustment
RA-15 (August 2021) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 311 Dn = 93.30 On = 136.20
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.14 X (93.3/68.72) + 0.49 X (136.2/119.9)
= 1.130
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 311 En = 78.40 Dn = 93.30 On = 136.20
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.06 X (78.4/77.1) + 0.04 X (93.3/68.72)
+ 0.53 X (136.2/119.9)
= 1.101
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 311 En = 78.40 Dn = 93.30 On = 136.20
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (311/288) +0.12 X (78.4/77.1) + 0.06 X (93.3/68.72)
+ 0.45 X (136.2/119.9)
= 1.098
Calculation of Multiplying Factor for Price Adjustment
RA-16 (September 2021) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 313 En = 77.90 Dn = 92.15
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (313/288) + 0.38 X (77.9/77.1) + 0.25 X (92.15/68.72)
= 1.104
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 313 Sn = 131.40 Cn = 125.50
L0 = 288 S0 = 110.10 C0 = 117.30
En = 77.90 Dn = 92.15 On = 137.40
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (313/288) + 0.3 X (131.4/110.1) + 0.22 X (125.5/117.3)
+ 0.07 X (77.9/77.1) + 0.04 X (92.15/68.72) + 0.02 X (137.4/119.9)
= 1.104
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 313 Sn = 131.40 En = 77.90 Dn = 92.15
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (313/288) +0.73 X (131.4/110.1) + 0.02 X (77.9/77.1)
+ 0.02 X (92.15/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-16 (September 2021) / Package-I
= 1.151
Calculation of Multiplying Factor for Price Adjustment
RA-16 (September 2021) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 313 Dn = 92.15 On = 137.40
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (313/288) +0.14 X (92.15/68.72) + 0.49 X (137.4/119.9)
= 1.134
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 313 En = 77.90 Dn = 92.15 On = 137.40
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (313/288) +0.06 X (77.9/77.1) + 0.04 X (92.15/68.72)
+ 0.53 X (137.4/119.9)
= 1.106
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 313 En = 77.90 Dn = 92.15 On = 137.40
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (313/288) +0.12 X (77.9/77.1) + 0.06 X (92.15/68.72)
+ 0.45 X (137.4/119.9)
= 1.102
Calculation of Multiplying Factor for Price Adjustment
RA-17 (October 2021) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 318 En = 78.30 Dn = 93.58
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (318/288) + 0.38 X (78.3/77.1) + 0.25 X (93.58/68.72)
= 1.114
v
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 318 Sn = 132.90 Cn = 124.50
L0 = 288 S0 = 110.10 C0 = 117.30
En = 78.30 Dn = 93.58 On = 140.70
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (318/288) + 0.3 X (132.9/110.1) + 0.22 X (124.5/117.3)
+ 0.07 X (78.3/77.1) + 0.04 X (93.58/68.72) + 0.02 X (140.7/119.9)
= 1.110
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 318 Sn = 132.90 En = 78.30 Dn = 93.58
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (318/288) +0.73 X (132.9/110.1) + 0.02 X (78.3/77.1)
+ 0.02 X (93.58/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-17 (October 2021) / Package-I
= 1.162
Calculation of Multiplying Factor for Price Adjustment
RA-17 (October 2021) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 318 Dn = 93.58 On = 140.70
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.14 X (93.58/68.72) + 0.49 X (140.7/119.9)
= 1.153
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 318 En = 78.30 Dn = 93.58 On = 140.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.06 X (78.3/77.1) + 0.04 X (93.58/68.72)
+ 0.53 X (140.7/119.9)
= 1.125
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 318 En = 78.30 Dn = 93.58 On = 140.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.12 X (78.3/77.1) + 0.06 X (93.58/68.72)
+ 0.45 X (140.7/119.9)
= 1.119
Calculation of Multiplying Factor for Price Adjustment
RA-18 (November 2021) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 318 En = 78.70 Dn = 101.88
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (318/288) + 0.38 X (78.7/77.1) + 0.25 X (101.88/68.72)
= 1.146
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 318 Sn = 133.50 Cn = 126.50
L0 = 288 S0 = 110.10 C0 = 117.30
En = 78.70 Dn = 101.88 On = 143.70
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (318/288) + 0.3 X (133.5/110.1) + 0.22 X (126.5/117.3)
+ 0.07 X (78.7/77.1) + 0.04 X (101.88/68.72) + 0.02 X (143.7/119.9)
= 1.121
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 318 Sn = 133.50 En = 78.70 Dn = 101.88
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (318/288) +0.73 X (133.5/110.1) + 0.02 X (78.7/77.1)
+ 0.02 X (101.88/68.72)
Calculation of Multiplying Factor for Price Adjustment
RA-18 (November 2021) / Package-I
= 1.168
Calculation of Multiplying Factor for Price Adjustment
RA-18 (November 2021) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 318 Dn = 101.88 On = 143.70
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.14 X (101.88/68.72) + 0.49 X (143.7/119.9)
= 1.183
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 318 En = 78.70 Dn = 101.88 On = 143.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.06 X (78.7/77.1) + 0.04 X (101.88/68.72)
+ 0.53 X (143.7/119.9)
= 1.143
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 318 En = 78.70 Dn = 101.88 On = 143.70
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318/288) +0.12 X (78.7/77.1) + 0.06 X (101.88/68.72)
+ 0.45 X (143.7/119.9)
= 1.138
Calculation of Multiplying Factor for Price Adjustment
RA-19 (December 2021) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 318.08 En = 78.50 Dn = 90.11
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (318.08/288) + 0.38 X (78.5/77.1) + 0.25 X (90.11/68.72)
= 1.102
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 318.08 Sn = 140.80 Cn = 128.90
L0 = 288 S0 = 110.10 C0 = 117.30
En = 78.50 Dn = 90.11 On = 143.30
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (318.08/288) + 0.3 X (140.8/110.1) + 0.22 X (128.9/117.3)
+ 0.07 X (78.5/77.1) + 0.04 X (90.11/68.72) + 0.02 X (143.3/119.9)
= 1.139
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 318.08 Sn = 140.80 En = 78.50 Dn = 90.11
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (318.08/288) +0.73 X (140.8/110.1) + 0.02 X (78.5/77.1)
+ 0.02 X (90.11/68.72)
= 1.213
Calculation of Multiplying Factor for Price Adjustment
RA-19 (December 2021) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 318.08 Dn = 90.11 On = 143.30
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318.08/288) +0.14 X (90.11/68.72) + 0.49 X (143.3/119.9)
= 1.157
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 318.08 En = 78.50 Dn = 90.11 On = 143.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318.08/288) +0.06 X (78.5/77.1) + 0.04 X (90.11/68.72)
+ 0.53 X (143.3/119.9)
= 1.135
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 318.08 En = 78.50 Dn = 90.11 On = 143.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (318.08/288) +0.12 X (78.5/77.1) + 0.06 X (90.11/68.72)
+ 0.45 X (143.3/119.9)
= 1.126
Calculation of Multiplying Factor for Price Adjustment
RA-20 (January 2022) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 322.75 En = 79.40 Dn = 90.11
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (322.75/288) + 0.38 X (79.4/77.1) + 0.25 X (90.11/68.72)
= 1.110
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 322.75 Sn = 140.40 Cn = 127.10
L0 = 288 S0 = 110.10 C0 = 117.30
En = 79.40 Dn = 90.11 On = 143.80
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (322.75/288) + 0.3 X (140.4/110.1) + 0.22 X (127.1/117.3)
+ 0.07 X (79.4/77.1) + 0.04 X (90.11/68.72) + 0.02 X (143.8/119.9)
= 1.138
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 322.75 Sn = 140.40 En = 79.40 Dn = 90.11
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (322.75/288) +0.73 X (140.4/110.1) + 0.02 X (79.4/77.1)
+ 0.02 X (90.11/68.72)
= 1.211
Calculation of Multiplying Factor for Price Adjustment
RA-20 (January 2022) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 322.75 Dn = 90.11 On = 143.80
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (322.75/288) +0.14 X (90.11/68.72) + 0.49 X (143.8/119.9)
= 1.162
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 322.75 En = 79.40 Dn = 90.11 On = 143.80
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (322.75/288) +0.06 X (79.4/77.1) + 0.04 X (90.11/68.72)
+ 0.53 X (143.8/119.9)
= 1.140
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 322.75 En = 79.40 Dn = 90.11 On = 143.80
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (322.75/288) +0.12 X (79.4/77.1) + 0.06 X (90.11/68.72)
+ 0.45 X (143.8/119.9)
= 1.132
Calculation of Multiplying Factor for Price Adjustment
RA-21 (February 2022) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 325.70 En = 79.40 Dn = 90.11
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (325.7/288) + 0.38 X (79.4/77.1) + 0.25 X (90.11/68.72)
= 1.111
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 325.70 Sn = 139.00 Cn = 127.00
L0 = 288 S0 = 110.10 C0 = 117.30
En = 79.40 Dn = 90.11 On = 145.30
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (325.7/288) + 0.3 X (139/110.1) + 0.22 X (127/117.3)
+ 0.07 X (79.4/77.1) + 0.04 X (90.11/68.72) + 0.02 X (145.3/119.9)
= 1.135
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 325.70 Sn = 139.00 En = 79.40 Dn = 90.11
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (325.7/288) +0.73 X (139/110.1) + 0.02 X (79.4/77.1)
+ 0.02 X (90.11/68.72)
= 1.202
Calculation of Multiplying Factor for Price Adjustment
RA-21 (February 2022) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 325.70 Dn = 90.11 On = 145.30
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (325.7/288) +0.14 X (90.11/68.72) + 0.49 X (145.3/119.9)
= 1.170
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 325.70 En = 79.40 Dn = 90.11 On = 145.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (325.7/288) +0.06 X (79.4/77.1) + 0.04 X (90.11/68.72)
+ 0.53 X (145.3/119.9)
= 1.149
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 325.70 En = 79.40 Dn = 90.11 On = 145.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (325.7/288) +0.12 X (79.4/77.1) + 0.06 X (90.11/68.72)
+ 0.45 X (145.3/119.9)
= 1.140
Calculation of Multiplying Factor for Price Adjustment
RA-22 & 23 (March 2022) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 329.64 En = 80.00 Dn = 90.11
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (329.64/288) + 0.38 X (80/77.1) + 0.25 X (90.11/68.72)
= 1.117
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 329.64 Sn = 139.90 Cn = 128.40
L0 = 288 S0 = 110.10 C0 = 117.30
En = 80.00 Dn = 90.11 On = 148.90
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (329.64/288) + 0.3 X (139.9/110.1) + 0.22 X (128.4/117.3)
+ 0.07 X (80/77.1) + 0.04 X (90.11/68.72) + 0.02 X (148.9/119.9)
= 1.144
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 329.64 Sn = 139.90 En = 80.00 Dn = 90.11
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (329.64/288) +0.73 X (139.9/110.1) + 0.02 X (80/77.1)
+ 0.02 X (90.11/68.72)
= 1.209
Calculation of Multiplying Factor for Price Adjustment
RA-22 & 23 (March 2022) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 329.64 Dn = 90.11 On = 148.90
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (329.64/288) +0.14 X (90.11/68.72) + 0.49 X (148.9/119.9)
= 1.187
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 329.64 En = 80.00 Dn = 90.11 On = 148.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (329.64/288) +0.06 X (80/77.1) + 0.04 X (90.11/68.72)
+ 0.53 X (148.9/119.9)
= 1.167
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 329.64 En = 80.00 Dn = 90.11 On = 148.90
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (329.64/288) +0.12 X (80/77.1) + 0.06 X (90.11/68.72)
+ 0.45 X (148.9/119.9)
= 1.157
Calculation of Multiplying Factor for Price Adjustment
RA-24 (April 2022) / Package-I
Earthwork (S1)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 e = 0.38
b = 0.17 f = 0.25
Ln = 337.76 En = 80.30 Dn = 96.53
L0 = 288 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.17 X (337.76/288) + 0.38 X (80.3/77.1) + 0.25 X (96.53/68.72)
= 1.146
Controlled Cement Concrete M20 and Above (S2)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑑 𝐶𝑛/𝐶0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 c = 0.30 e = 0.07 O = 0.02
b = 0.15 d = 0.22 f = 0.04
Ln = 337.76 Sn = 144.80 Cn = 129.80
L0 = 288 S0 = 110.10 C0 = 117.30
En = 80.30 Dn = 96.53 On = 152.30
E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.15 X (337.76/288) + 0.3 X (144.8/110.1) + 0.22 X (129.8/117.3)
+ 0.07 X (80.3/77.1) + 0.04 X (96.53/68.72) + 0.02 X (152.3/119.9)
= 1.168
Sheet Pile (S3)
𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑐 𝑆𝑛/𝑆0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0

Where,
a = 0.20 c = 0.73 f = 0.02
b = 0.03 e = 0.02
Ln = 337.76 Sn = 144.80 En = 80.30 Dn = 96.53
L0 = 288 S0 = 110.10 E0 = 77.10 D0 = 68.72
So,
Pn = 0.2 + 0.03 X (337.76/288) +0.73 X (144.8/110.1) + 0.02 X (80.3/77.1)
+ 0.02 X (96.53/68.72)
= 1.244
Calculation of Multiplying Factor for Price Adjustment
RA-24 (April 2022) / Package-I
Boulder Pitching (S4)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 f = 0.14
b = 0.17 O = 0.49
Ln = 337.76 Dn = 96.53 On = 152.30
L0 = 288 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (337.76/288) +0.14 X (96.53/68.72) + 0.49 X (152.3/119.9)
= 1.218
Road Works (S5)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.06 O = 0.53
b = 0.17 f = 0.04
Ln = 337.76 En = 80.30 Dn = 96.53 On = 152.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (337.76/288) +0.06 X (80.3/77.1) + 0.04 X (96.53/68.72)
+ 0.53 X (152.3/119.9)
= 1.191
Miscellaneous Works (S6)

𝑃𝑛=𝑎+𝑏 𝐿𝑛/𝐿0+𝑒 𝐸𝑛/𝐸0+𝑓 𝐷𝑛/𝐷0+𝑂 𝑂𝑛/𝑂0

Where,
a = 0.20 e = 0.12 O = 0.45
b = 0.17 f = 0.06
Ln = 337.76 En = 80.30 Dn = 96.53 On = 152.30
L0 = 288 E0 = 77.10 D0 = 68.72 O0 = 119.90
So,
Pn = 0.2 + 0.17 X (337.76/288) +0.12 X (80.3/77.1) + 0.06 X (96.53/68.72)
+ 0.45 X (152.3/119.9)
= 1.180
Calculation Sheet : Price Adjustment of RAB - 22 & RAB - 23 (March - 2022)
Multiplying RAB-22 (1st March to 12th March 2022) RAB-22 (13th March to 31st March 2022)
BOQ Net Payable Amount of
Sl. Description Unit Rate Factor
Item Schedule Amount including Amount without Net Payable Amount including Amount without Net Payable Price Adjustment Bill
No. of Item No. (March Quantity Quantity of RAB-22 & RAB-23
No. 2022) Price Adjustment Price Adjustment Amount Price Adjustment Price Adjustment Amount

1 Bullah Supply 1 m ₹ 323.00 S6 1.157 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 2175.780 ₹ 813,112.92 ₹ 702,776.94 ₹ 110,335.98 ₹ 110,335.98

2 Bullah Driving 2 m ₹ 130.00 S6 1.157 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 1928.310 ₹ 290,037.11 ₹ 250,680.30 ₹ 39,356.81 ₹ 39,356.81

3 Half Split 3 m ₹ 125.00 S6 1.157 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 487.200 ₹ 70,461.30 ₹ 60,900.00 ₹ 9,561.30 ₹ 9,561.30

4 Earthwork in 4 cum ₹ 140.00 S1 1.117 1261.470 ₹ 197,268.68 ₹ 176,605.80 ₹ 20,662.88 3072.605 ₹ 480,493.97 ₹ 430,164.70 ₹ 50,329.27 ₹ 70,992.15
Excavation

5 Earthwork in 5 cum ₹ 96.00 S1 1.117 1376.230 ₹ 147,575.90 ₹ 132,118.08 ₹ 15,457.82 2750.575 ₹ 294,949.66 ₹ 264,055.20 ₹ 30,894.46 ₹ 46,352.28
Filling

6 Transported Earth 6.04 cum ₹ 339.00 S1 1.117 710.781 ₹ 269,146.47 ₹ 240,954.76 ₹ 28,191.71 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 28,191.71
(3-4km)

7 Transported Earth 6.05 cum ₹ 361.00 S1 1.117 2386.927 ₹ 962,497.28 ₹ 861,680.65 ₹ 100,816.63 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 100,816.63
(4-5km)

8 Polythene Sheet 7 cum ₹ 30.00 S6 1.157 1019.075 ₹ 35,372.09 ₹ 30,572.25 ₹ 4,799.84 2386.500 ₹ 82,835.42 ₹ 71,595.00 ₹ 11,240.42 ₹ 16,040.26

9 Single Brick Flat 8 sqm ₹ 415.00 S6 1.157 795.125 ₹ 381,783.24 ₹ 329,976.88 ₹ 51,806.36 1833.250 ₹ 880,244.15 ₹ 760,798.75 ₹ 119,445.40 ₹ 171,251.76
Soling

10 Compacting 9 cum ₹ 1,042.00 S5 1.167 73.824 ₹ 89,771.02 ₹ 76,924.61 ₹ 12,846.41 187.929 ₹ 228,524.30 ₹ 195,822.02 ₹ 32,702.28 ₹ 45,548.69
sand

11 Cement 10 cum ₹ 9,486.00 S2 1.144 536.470 ₹ 5,821,763.86 ₹ 5,088,954.42 ₹ 732,809.44 1386.690 ₹ 15,048,337.69 ₹ 13,154,141.34 ₹ 1,894,196.35 ₹ 2,627,005.79
Concrete (M20)

12 Cement 11 cum ₹ 10,344.00 S2 1.144 320.575 ₹ 3,793,535.80 ₹ 3,316,027.80 ₹ 477,508.00 424.775 ₹ 5,026,590.25 ₹ 4,393,872.60 ₹ 632,717.65 ₹ 1,110,225.65
Concrete (M25)

13 Reinforcement 12 MT ₹ 76,680.00 S2 1.144 30.132 ₹ 2,643,236.89 ₹ 2,310,521.76 ₹ 332,715.13 58.226 ₹ 5,107,696.51 ₹ 4,464,769.68 ₹ 642,926.83 ₹ 975,641.96

14 MS Sheet Pile 13 sqm ₹ 13,765.00 S3 1.209 34.500 ₹ 574,145.03 ₹ 474,892.50 ₹ 99,252.53 319.500 ₹ 5,317,082.26 ₹ 4,397,917.50 ₹ 919,164.76 ₹ 1,018,417.29

15 Sausage Cage 14.01 m ₹ 421.00 S4 1.187 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 891.280 ₹ 445,396.68 ₹ 375,228.88 ₹ 70,167.80 ₹ 70,167.80
(0.75m X 0.45m)

16 Labour for 16 cum ₹ 584.00 S4 1.187 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 3455.539 ₹ 2,395,407.28 ₹ 2,018,034.78 ₹ 377,372.50 ₹ 377,372.50
Boulder Pitching

17 Labour for 18 cum ₹ 39.00 S4 1.187 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 3758.750 ₹ 174,003.81 ₹ 146,591.25 ₹ 27,412.56 ₹ 27,412.56
Boulder Stacking

18 Geo-textile 19 sqm ₹ 301.00 S4 1.187 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 13637.746 ₹ 4,872,589.36 ₹ 4,104,961.55 ₹ 767,627.81 ₹ 767,627.81
filter

19 Jungle 20 sqm ₹ 6.00 S6 1.157 9572.500 ₹ 66,452.30 ₹ 57,435.00 ₹ 9,017.30 15534.250 ₹ 107,838.76 ₹ 93,205.50 ₹ 14,633.26 ₹ 23,650.56
Clearence

20 Nylon Cage 23 Nos. ₹ 136.00 S6 1.157 112 ₹ 17,623.42 ₹ 15,232.00 ₹ 2,391.42 0 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 2,391.42

21 HDPE Bag 24 Nos. ₹ 27.00 S6 1.157 2352 ₹ 73,474.13 ₹ 63,504.00 ₹ 9,970.13 0 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 9,970.13

22 Coal Tarring 33 sqm ₹ 39.00 S6 1.157 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 1415.917 ₹ 63,890.42 ₹ 55,220.76 ₹ 8,669.66 ₹ 8,669.66

23 Suuply of empty 39 Nos. ₹ 3.00 S6 1.157 161445 ₹ 560,375.60 ₹ 484,335.00 ₹ 76,040.60 0 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 76,040.60
Poly bag

24 Filling of empty 40 Nos. ₹ 3.00 S6 1.157 161445 ₹ 560,375.60 ₹ 484,335.00 ₹ 76,040.60 0 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 76,040.60
Poly bag

25 Dumping of empty 41 Nos. ₹ 3.00 S6 1.157 161445 ₹ 560,375.60 ₹ 484,335.00 ₹ 76,040.60 0 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 76,040.60
Poly bag

26 Silver Sand Add-1 cum ₹ 1,626.67 S4 1.117 5416.409 ₹ 9,841,563.10 ₹ 8,810,710.03 ₹ 1,030,853.07 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 ₹ 1,030,853.07

27 Stone Boulder Add-2 cum ₹ 6,382.02 S1 1.144 0.000 ₹ 0.00 ₹ 0.00 ₹ 0.00 3758.748 ₹ 27,442,735.22 ₹ 23,988,404.91 ₹ 3,454,330.31 ₹ 3,454,330.31
Multiplying RAB-22 (1st March to 12th March 2022) RAB-22 (13th March to 31st March 2022)
BOQ Net Payable Amount of
Sl. Description Unit Rate Factor
No. of Item Item Schedule (March Amount including Amount without Net Payable Amount including Amount without Net Payable Price Adjustment Bill
No. Quantity Quantity of RAB-22 & RAB-23
No. 2022) Price Adjustment Price Adjustment Amount Price Adjustment Price Adjustment Amount

Total ₹ 26,596,336.01 ₹ 23,439,115.54 ₹ 3,157,220.47 Total ₹ 69,142,227.07 ₹ 59,929,141.66 ₹ 9,213,085.41 ₹ 12,370,305.88