A. EARTHWORKS
Clearing and Grubbing sq.m 36 0 \
Structural Excavation cu.m 32
Gravel Bedding cu.m 2.5 750 1875
Backfill & Compaction cu.m 10
SUB TOTAL
B. CONCRETE WORKS
Column Footing cu.m
16mm Ø RSBx6.0m pcs 96 545 52320
Portland cement bags 27 250 6750
Gravel G1 cu.m 3 950 2850
Albay sand cu.m 1.5 650 975
Tie Wire kl 2.5 90 225
Canopy cu.m
12mm Ø RSBx6.0m pcs 36 310 11160
10mm Ø RSBx6.0m pcs 14 218 3052
Portland cement bags 21 250 5250
Gravel 3/4" cu.m 3 1200 3600
Albay sand cu.m 1.5 650 975
Tie Wire kl 4.5 90 405
SUB TOTAL
C. MASONRY WORKS
CHB Laying
CHB 5" pcs 1099 15 16485
CHB 4" pcs 509 13 6617
10mm Ø RSBx6.0m pcs 107 218 23326
Mortar
Portland cement bags 158 250 39500
Albay sand cu.m 10 650 6500
Plastering (Column) sq.m
Portland Cement bags 31 250 7750
Albay Sand cu.m 2 650 1300
SUB TOTAL
D. ELECTRICAL WORKS
uPvc Pipe 3/4"Ø pcs 22 125 2750
uPvc Pipe 1/2"Ø pcs 33 95 3135
Circuit Breaker 70A set 1 550 550
Circuit Breaker 30A set 3 340 1020
Circuit Breaker 20A set 1 340 340
Circuit Breaker 15A set 4 340 1360
THNN Wire Stranded 2.0mm2 box 3 0
Single switch set 1 125 125
2-Gang Switch set 2 150 300
3-Gang Switch set 1 150 150
2-Gang C.O. set 3 135 405
Led Bulb pcs 4 0
Utility Box pcs 15 38 570
Junction Box pcs 12 35 420
SUB TOTAL
E. PLUMBING WORKS
Water Line
G.I Pipe 1/2"Ø pcs 8 1 8
G.I Coupling pcs 4 65 260
G.I Tee pcs 4 130 520
G.I Elbow pcs 6 55 330
Teflon Tape pcs 5 90 450
Sewer
PVC Sanitary Pipe 4"Ø pcs 6 130 780
PVC Sanitary Pipe 2"Ø pcs 3 105 315
PVC Elbow 4"X45˚ pcs 7 95 665
PVC Elbow 4"X90˚ pcs 3 50 150
PVC Wye 4"x4" pcs 4 130 520
PVC Wye 4"x2" pcs 1 120 120
Floor Drain 4"x4" pcs 1 55 55
PVC Clean Out 4" w/ Plug pcs 1 55 55
Water Closet set 1 6000 6000
Lavatory set set 1 5000 5000
Kitchen Sink set 1 3000 3000
SUB TOTAL
SUB TOTAL
G. Tile Works
30 x 30 Floor Tiles pcs 27 65 1755
30 x 30 Wall Tiles pcs 20 65 1300
40 x 40 Floor Tiles pcs 85 75 6375
20 x 60 Wall Tiles pcs 134 80 10720
Tile grout pcs 3 70 210
Tile Adhesive pcs 5 230 1150
Tile Trim pcs 3 50 150
Portland Cement bags 3 230 690
Albay Sand cu.m 0.5 650 325
SUB TOTAL
SUB TOTAL
TOTAL COST
Prepared by:
percentage of labor
0.35