Professional Documents
Culture Documents
Chapter 13
Demolition
165
Code of Constructions Safety Practice
Introduction:
Demolition is considered one of the most dangerous operations in the Building/Construction industry.
Demolition operations varies between different types such as using explosives, mechanical demoli-
tion as well as manual demolition.
This chapter covers the measures and safe methods to be taken prior to any demolition operation to
carry out such operations safely and to protect workers from all potential hazards.
There are many demolition techniques such as:
- Manual Demolition.
- Demolition using equipment (Mechanical Demolition).
- Overturning/Wire Rope Pulling
- Demolition using Explosives.
13 -1 Demolition Hazards:
13-1-1 Health Hazards:
13-1-1-1 Exposure to Lead:
Lead as a toxic dust or fumes arises from cutting and burning steelwork covered with lead based
paint, therefore it is essential before carrying out any demolition operations to identify the presence
of any lead based paint or lead-containing materials and in case it is available and it is possible that
the workers could be exposed to high concentration of lead exceeding the permissible exposure lim-
its (50 μg/m3), the contractor must provide his workers with the suitable personal protective equip-
ment (Respiratory Protection equipment). (fig. 1)
Fig. 1
166
Code of Constructions Safety Practice
Asbestos insulation or coating must be removed by specialist contractors only and before any de-
molition work is started, also all precaution safety measures should be followed including the use of
suitable and adequate respiratory protection equipment.(Masks with high efficiency particulate air
filters – HEPA Filters).
It is important to identify equipment PCB’s before carrying out any demolition work, and take all pre-
cautionary measures to get rid of it and use adequate personal protective equipment before starting
demolition work.
Each contractor shall prepare a study about the effect of noise resulting from demolition works on the
adjacent buildings particularly hospitals, schools, ….etc. and determine the best methods and tech-
niques he will follow to reduce the exposure noise levels at such buildings, taking into consideration
the possibility of scheduling the work in coordination with the adjacent sites.
(Refer to section # 2 regarding noise hazards).
167
Code of Constructions Safety Practice
the white fingers disease. These hazards can be reduced by using anti-vibration gloves, and se-
lecting tools and equipment which produce less vibration levels as well as scheduling work so that
exposure to vibration hazards is reduced.
2- Collapse Hazards:
Employees are exposed to the hazard of collapse of buildings or part of the buildings during demoli-
tion works the matter which might lead to death or serious injuries, therefore each contractor shall
ensure that all structures are properly supported to protect his employees from the hazard of col-
lapse of such buildings in particular at the buildings which was exposed to fire or partially supported
buildings.
13 -2 General requirements:
1. No demolition work shall be commenced unless a demolition permit is issued from
the concerned department at Dubai Municipality according to the rules and regulations
followed in this regard.
2. Demolition work shall not be started unless all safety and security measured are
provided at the demolition site and in the equipment which will be used during the
demolition work.
3. Any contractor before undertaking a demolition work shall obtain a no objection
certificates (NOC’s) from the appropriate authorities (electricity, water, roads, sewer,
traffic,etc.) and he shall ensure that the drawings and actual utilities are identical, and
he shall stop working immediately and refers to the concerned party in case there is a
deference.
4. Before starting any demolition work, the contractor shall conduct an engineering survey
(by a registered professional engineer) of the structure to determine the structure layout,
the condition of the framing, floors, walls, the possibility of unplanned collapse of any
portion of the structure and the existence of other potential or real demolition hazards.
Also surveying the adjacent structures including historical buildings and accordingly
plan his demolition method, equipment to be used, and all necessary precautionary
measures.
5. Prior to the commencement of any demolition job, the contractor shall conduct a
survey for asbestos, to determine the presence, quantity, and condition of substances
168
Code of Constructions Safety Practice
169
Code of Constructions Safety Practice
170
Code of Constructions Safety Practice
Fig. 2
Fig. 3
171
Code of Constructions Safety Practice
8. The contractor shall provide a protection barrier not less than the building to be
demolished high to the adjacent buildings, and he has to consider the safety of
pedestrians and adjacent building and includes that in the demolition methods.
9. The contractor shall follow adequate safe systems of work, and he must inform the
concerned department in case there are any obstacles to report this case before the
commencement of demolition operations.
10. When employees are required to work within a structure to be demolished, adequate
shoring or bracing shall be used to prevent accidental collapse of building. This is
essential for structures damaged by fire, explosion or other cause.
11. The contractor shall close the demolition site at the end of working hours to ensure
that unauthorised persons are not entered or damage the machinery and equipment.
12. The contractor shall provide security services at the demolition site 24 hours a day.
172
Code of Constructions Safety Practice
Fig. 4
8. At the end of working hours, the demolition work shall be stopped at a stage with a safe
and stable structure to avoid the fall of any structure.
9. Employees entrances to multi-story structure being demolished shall be completely
protected by side-walk sheds or canopies or both. Protection shall be provided from the
face of the building for a minimum of 2.4 m (8 feet).
10. All such canopies shall be at least 0.6 m (2 feet) wider than the building entrances or
openings and shall be capable of sustaining any loads or materials which might fall
on it.
11. Masonry walls or other sections of masonry shall not be permitted to fall upon the floors
of the multi-story buildings in such masses as to exceed the safe carrying capacities of
the floor.
12. Mechanical equipment shall not be used on floors or working surfaces unless such
floors or surfaces are of sufficient strength to support the imposed load.
13. Except for cutting holes in floors for chutes, holes through which to drop materials,
preparation of storage space, and similar preparatory work, the demolition of floors and
exterior walls shall begin at the top of the structure and proceed downward.
14. Only those stairways, passageways, and ladders designated as means of access to the
structure shall be used during the demolition operations as follows:
14-1 The designated means of access shall be indicated on the demolition plan,
other access ways shall be indicated as not safe for access and closed at
all times.
14-2 The stairwell shall be covered at a point no less than two floors below the
floor on which work is being performed.
14-3 Access to a floor where work is in progress shall be through a separate lighted,
protected passageway.
15. The contractor shall coordinate with historical buildings department to provide
additional protection measures to protect such historical buildings from any damages
173
Code of Constructions Safety Practice
174
Code of Constructions Safety Practice
Fig. 5
2. When debris is dropped through openings in the floors without chutes, the openings
and the area onto which the material is dropped shall be enclosed with barricades not
less than 1.05 m (42 inches) in high and not less than 1.8 m (6 feet) back from the
projected edge of the opening above.
3. Any openings cut in a floor for the disposal of materials shall be not longer in size than
25% of the aggregate of the total floor area to avoid the effect on the stability of the
whole floor.
4. Signs warning of the hazard of falling materials shall be posted at each side of the
debris opening at each floor.
5. Debris removal shall not be permitted in lower areas until debris handling ceases on
the floors above.
6. The storage of waste and debris on any floor shall not exceed the allowable floor loads.
7. All openings at all floors below the top floor when not in use, shall be kept closed.
8. A substantial gate shall be installed in each chute at or near the discharge end.
A competent employee shall be assigned to control operation of the gate and the
backing and loading of trucks.
Fig.6
175
Code of Constructions Safety Practice
9. Chutes shall be designed and constructed of such strength as to eliminate failure due
to impact of materials or debris loaded therein.
10. Where materials is dumped from mechanical equipment or wheelbarrows, a toe board
or bumper, not less than 10 cm (4 inches) thick and 15 cm (6 inches) high, shall be
attached at each chute opening.
13 -6 Wall Removal:
1. Masonry walls, or sections of masonry, shall not be permitted to fall upon the floors of
the building in such masses as to exceed the safe carrying capacities of the floors.
2. All wall sections must be supported until all the adjacent waste materials which are
restricting its demolition have been removed.
3. Structural or load-supporting members on any floor shall not be cut or removed until
all stories above such a floor have been demolished and removed.
4. Employees shall not be permitted to work on the top of a wall when weather (winds,
rains, .etc.) constitutes a hazard.
5. Walls that serves as retaining walls to support earth or adjoining structures shall not
be demolished until such earth has been braced or adjoining structures have been
underpinned.
6. Walls shall not be used to retain debris unless capable of safely supporting the
imposed load.
7. Floor openings within 3 m (10 feet) of any wall being completely demolished shall
be planked using thick wooden boards. (See fig. # 7).
Fig. 7
13 -7 Floor Removal:
1. Openings cut in a floor shall extend the full span of the arch between supports.
2. Before demolishing any floor arch, debris and other material shall be removed from
such arch and other adjacent floor area.
3. Planks not less than 5 cm x 25 cm (2 in x 10 in) in cross section, full sized undressed
shall be provided for and shall be used by employees to stand on while breaking down
floor arches between beams. Such planks shall be so located as to provide a safe
support for personnel should the arch between the beams collapse, taking into
consideration that the straddle space between planks shall not exceed 40 cm (16 in).
4. Safe walkways, not less than 45 cm (18 in) wide, formed of wood planks not less 5 cm
176
Code of Constructions Safety Practice
(2 in) thick or of equivalent strength, shall be provided and used by personnel when
necessary to enable them to reach any point without walking upon exposed beams.
5. Planks shall be laid together over solid bearings with the ends overlapped at least
30 cm (1 foot).
6. When floor arches are being removed, employees shall not be allowed in the area
directly underneath. The area shall be barricaded to prevent access and signed to
warn of the hazard.
7. Opposite Removal: in case of suspended ceilings, they shall be removed from bottom to
top and all the precautionary measures mentioned in this section must be considered.
177
Code of Constructions Safety Practice
3. Before starting the demolition operations, it shall be well planed and this will be in the re
verse order to the erection of the building and the sequence of demolition will start from
the upper floor then the other below floors and so on.
4. Where demolition operations are carried out at upper open floors, the proper protection
to the open sided edges shall be provided (proper guardrails) or employees shall
use proper harness to protect them from fall hazards.
5. Each main structural member, shall be supported by a crane or temporary props
whilst the ends are unbolted or cut. Structural members and trusses shall be carefully
lowered to ground level.
6. The free fall of debris on the ground inside or outside the building is permitted only
when the horizontal distance between the point where the debris will fall and the main
road is more than 6 m, or more than half the drop height (whichever is the greater). In
other cases the debris will be removed using the normal means such as chutes.
7. Steel structural members shall be demolished and lowered gradually to the ground or
being cut to a suitable lengths of suitable size and weight before lowering it. Cranes
shall be used to support joists and beams during cutting and lowering them to the
ground. Same methods shall be used to untie joints during the demolition of pre-cast
structural buildings or steel buildings.
8. When it is needed to demolish a part of a building, the demolition line shall be
determined to be at a safe structural areas.
Fig. 8
178
Code of Constructions Safety Practice
Fig. 9
Fig. 10
179
Code of Constructions Safety Practice
Fig. 11
180
Code of Constructions Safety Practice
181