SM CENTER SAN PEDRO

Brgy. San Vicente, San Pedro Laguna


BAR BENDING SCHEDULE

1,427.69 1,427.69
125,662.30 130,223.80 -3.63%
127,089.98 131,651.49
CUT WEIGHT / Total Comm.
LOCATION a QTY BAR Ø CUT WEIGHT Final Qty Comm.L Total Cut Wt Wastage
sets LENGTH METER Wt
/ ITEM
(m) (pcs) (m) (mm) (kg) (kg)

- - x - - - -
- - x - - - -
- - x - - - -
- - x - - - -
- - x - - - -
- - x - - - -
PROJECT: SM CENTER SAN PEDRO
LOCATION: Brgy. United Bayanihan San Pedro, Laguna
SUBJECT: R.O.L # - 13
DATE 26-Aug-22
SUPPLIER : Steel Asia

STP AND NON-POTABLE TANK


QTY. BAR Ø LENGTH GRADE kg/m KGS.
15.00 75 7.99 -
87.00 13.50 75 7.99 9,385.43
- 12.00 75 7.99 -
- 36mm 10.50 75 7.99 -
87.00 9.00 75 7.99 6,256.95
- 7.50 75 7.99 -
- 6.00 75 7.99 -
15.00 75 4.83 -
13.50 75 4.83 -
134.00 12.00 75 4.83 7,771.46
153.00 28mm 10.50 75 4.83 7,764.21
93.00 9.00 75 4.83 4,045.22
86.00 7.50 75 4.83 3,117.29
20.00 6.00 75 4.83 579.96
15.00 75 3.8540 -
13.50 75 3.8540 -
95.00 12.00 75 3.8540 4,393.56
67.00 25mm 10.50 75 3.8540 2,711.29
57.00 9.00 75 3.8540 1,977.10
10.00 7.50 75 3.8540 289.05
15.00 6.00 75 3.8540 346.86
15.00 75 2.4660 -
13.50 75 2.4660 -
21.00 12.00 75 2.4660 621.43
6.00 20mm 10.50 75 2.4660 155.36
10.00 9.00 75 2.4660 221.94
11.00 7.50 75 2.4660 203.45
- 6.00 75 2.4660 -
15.00 75 1.5790 -
13.50 75 1.5790 -
68.00 12.00 75 1.5790 1,288.46
5.00 16mm 10.50 75 1.5790 82.90
- 9.00 75 1.5790 -
5.00 7.50 75 1.5790 59.21
- 6.00 75 1.5790 -
15.00 75 0.8880 -
13.50 75 0.8880 -
293.00 12.00 75 0.8880 3,122.21
12mm
1,470.00 12mm 10.50 75 0.8880 13,706.28
467.00 9.00 75 0.8880 3,732.26
312.00 7.50 75 0.8880 2,077.92
231.00 6.00 75 0.8880 1,230.77
15.00 75 0.62 -
13.50 75 0.62 -
228.00 12.00 75 0.62 1,685.38
202.00 10mm 10.50 75 0.62 1,306.54
77.00 9.00 75 0.62 426.89
51.00 7.50 75 0.62 235.62
- 6.00 75 0.62 -
TOTAL = 78,795.00
Prepared by Noted by

Engr. Ricky Calara Engr. Marvin Isidro


Project Engineer Project Manager

Checked by

Engr. Lester Gene Gasita


Project-In-Charge