PROPOSAL FOR
SMART JB
January 5, 2022
2
Index
1. Backgrounds
2. Product Information
3. Cabling Concept
4. Pros. and Cons. of Smart JB
5. Key Design Aspects
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 3 of 18)
3
1. Backgrounds
Conventional JB design
2 FARs are expected. (rough estimate)
Full set of infrastructure required (HVAC/FAP etc.) regardless
FAR size
Home run cable tradition design, multi pair/core cable
15 to 20% of construction MH is for homerun cable related
work (PF2 base)
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 4 of 18)
4
1. Backgrounds
Smart JB design
Without FAR
Reduced home run cable (FOC only)
Construction BQ reduction (10%< expected)
Auto loop check / commissioning optimization
Minimum CAPEX
Work hours reduction, achieve project short delivery
Reduce the risk of construction delay by upstream delay
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 5 of 18)
5
1. Background – Cabling Concept
FARs
Controllers, PLCR
etc. ONLY
Decrease no.
of Cabinets
FO Cable
Decrease no.
of Cables
Configurable
IO modules
Smart JB enabling at Field JB
- Elimination of FARs
- Decrease Construction BQ
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 6 of 18)
1. Backgrounds
Comparison - ZLNG / PF2 / FLNG-B
E&I BLD
Confidential & AFT M/S Train 2 Train 1
Reference Only
ZLNG_Prelimin 212,000
ary only
(ZLNG plot is informal/preliminary)
<256,000> <77,200>
<333,200>
E&I
GTG Train 2 Train 1
LER
<70,800>
<404,000>
AFT M/S FAR-A LQ & FWD M/S
LQ
FLNG-B
FAR-B FAR-C
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 7 of 18)
1. Backgrounds
Comparison - ZLNG / PF2 / FLNG-B
Confidential Topside
FAR (HOLD) Total Weight Reduction by FAR Elimination
E&I room
ZLNG_Preliminary
only FWD Electrical room
Under Check to remove FWD Electrical room
AFT Electrical room
FAR-B
FAR-A FAR-C
FLNG-B
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 8 of 18)
1. Backgrounds - Information 8
related to Cost
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 9 of 18)
9
2. Product Information
Item Yokogawa Emerson
Product N-IO Field Enclosure (DCS/SIS) CTO CHARM Field Enclosure (DCS)
CTO CSLS Field Enclosure (SIS)
I/O number Max. 64 ch. Max. 96 ch.
Size (mm) 835(W) x 1330(H) x 380(D) 915(W) x 1220(H) x 475(D)
Weight (kg) 120 175
Ambientes -40 ~ 55 ºC, 5 ~ 100 %RH -40 ~ 55 ºC, 5 ~ 100 %RH
EMC directive EN 61000-6-2, -3-2, -3-3 IEC61326-1
Hazardous area Suitable for Zone 2 – IEC Ex certified Suitable for Zone 2 – IEC Ex certified
protection
Ingress Protection IP66 IP66
10
2. Product Information
Mfrʼs Experiences of Smart JB in Offshore
Emerson
Smart JB
In Operation
Smart JB
Under Comm/Const.
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 11 of 18)
11
2. Product Information
Mfrʼs Experiences of Smart JB in Offshore
Yokogawa
Smart JB
In Operation
Smart JB
Under Comm/Const.
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 12 of 18)
12
2. Product Information
Sample Photo: Emerson SIS Sample Photo: Yokogawa SIS
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 13 of 18)
13
3. Cabling Concept
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 14 of 18)
14
4. Pros. and Cons. of Smart JB
PROS CONS
Less amount of Main cables N/A
Less Instrument cabinets in I/E room Electronics in Field Smart JB
Bigger JB size
Enabling Loop Check at module yard N/A
- Verification of “field to Smart JB” at module yard
(with laptop connection to Smart JB)
Standard design of Smart JB N/A
- Off-the shelf Item
- Highly modular design for ease of replacement
Max. 96 I/O per Smart JB Loose many signals in case
(Emerson: max. 96 ch., Yokogawa: max. 64 ch.) loss of a Smart JB
Recent Technology (since ≈ 2010) Less experiences
** Sample video for the standard design from Yokogawa: N-IO Field Enclosure | Yokogawa Electric Corporation
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 15 of 18)
15
5. Key Design Aspects
16
5. Key Design Aspects
Smart JB 3 sided shelter concept
(Concept Only, Details to be developed)
Attachment-2: Presenation Material of JSC Proposal of Smart JB (sheet 17 of 18)
17
5. Key Design Aspects
18
5. Key Design Aspects