You are on page 1of 3

May 11, 2022

MEMORANDUM

FOR : THE GENERAL MANAGER

THRU : THE REGIONAL MANAGER


Regional Office XI

SUBJECT : Request for Approval of the Contract Time Extension No. 1


for the Project Kapyaan Heights Located at Brgy. Balabag,
Digos City, Davao del Sur

We are respectfully submitting for consideration and approval of the General


Manager the Time Extension No. 1 for the contract: Kapyaan Heights Located at
Brgy. Balabag, Digos City, Davao del Sur

Hereunder are pertinent data and information, to wit:

I. Contractual Data:

Project Title : Kapyaan Heights


Contractor : Rotaflex Construction and Development
Corporation
Original Contract Cost : Php 1,451,140,608.00
Original Contract Duration : 720 Calendar Days
Board Resolution and Date : NHA BR-6658, February 28, 2020
Notice of Award : February 19, 2021
Start-Up Date : August 17, 2021
Original Completion Date : August 06, 2023
Work Suspension Order No. 1 : August 17, 2021
Work Resumption Order No. 1 : November 15, 2021

II. Justification

The contractor requested for Contract Time Extension No. 1 due to unworkable days
caused by the inclement weather condition on site and the issuance of Work
Suspension Order No. 1 by reason of inability to secure the following permits and
clearances of the project, to wit:

1. Land Reclassification and DAR conversion clearance certificate;


2. Preliminary Approval and Locational Clearance (PALC); and
3. Development Permit (DP).

Regional Office XI • region11@nha.gov.ph.


3rd Floor, Villa Oro Building 2, Quimpo Blvd cor. Escandor Rd., Brgy. Matina, Davao City
Request for Approval of the Contract Time Extension
No. 1 for the Project Kapyaan Heights Located at
Brgy. Balabag, Digos City, Davao del Sur

Page 2 of 3

III. Revision on Contract

a. Summary/Breakdown of Approved Contract Time Extension:

CTE Duratio Revised Contract Revised Reason for granting


No. n of Duration Completion Date CTE
CTE
(Original Contract (Original
Duration) Completion Date)
720 c.d. August 06, 2023
Due to unworkable
days caused by
inclement weather
1 129 c.d. 849 c.d. December 13,
condition on site and
2023
Work Suspension
Order No. 1

E. Recommendation

In view of the foregoing, we are recommending for the approval of Contract Time
Extension No. 1 due to the above-cited reasons, thereby adjusting the contract
duration from Seven Hundred Twenty (720) Calendar Days to Eight Hundred Forty-
Nine (849) and revising target completion date from August 17, 2021 to December
13, 2023.

Prepared by:

ENGR. ROMY C. CASANILLO


Senior Engineer A
GEHP Regional Office XI

Reviewed by:

ENGR. JAYVEE D. BOISER


Principal Engineer A
Program Coordinator – GEHP RO XI
Request for Approval of the Contract Time Extension
No. 1 for the Project Kapyaan Heights Located at
Brgy. Balabag, Digos City, Davao del Sur

Page 3 of 3

Checked by:

ALPER JOHN G. ALCARAZ


Officer-In-Charge
Davao City/Digos City/IS Garden Samal/
Davao del Sur/Davao del Norte District Office

Recommending Approval:

ENGR. CLEMENTE A. DAYOT


Regional Manager
Regional Office XI

Approved by:

MARCELINO P. ESCALADA, JR.


General Manager

You might also like