Planned Cumulative
Balance Achvd till Previous Planned for Sep-22 Planned for Oct-22 Planned for Nov-22 Achieved This Cummulative %
Sr. No Item Description Unit Total Scope This Month Achieved Today Achieved as on Remarks
Scope Month (July-22) Month Aug-22 Achieved
(Aug-22) W1 W2 W3 W4 T W1 W2 W3 W4 T W1 W2 W3 W4 T date
A ELEVATED VIADUCT WORK
1 Piling Nos 88 28 60 4 2 2 2 2 8 3 3 3 3 12 3 3 3 3 12 60 68% P17-P20 utility trenching doen
3 Pier Nos 21 21
C ELEVATED RAMP
1 Excavation Rmt 309 277 32 500 500 1000 500 500 1000 32 10% Ramp area dewatering wip
E UG STATION WORK
1 Secant Pile Nos 615 415 146 100 100 110 110 54 200 33% SP-275, 268, 338, 214, 224 concrete done
a Hard Pile Nos 308 231 56 65 15 20 15 15 65 20 10 20 20 70 20 10 20 20 70 21 2 77 25% HP-340, 319 concrete done
b Soft Pile Nos 307 184 90 35 10 5 10 10 35 10 10 10 10 40 10 10 10 10 40 33 5 123 40% Capping beam reinforcement WIP
c Excavation cum 35000 32986 2014 1000 2000 1000 2000 6000 1000 2000 1000 2000 6000 1000 2000 1000 2000 6000 2014 6%
G UG STATION (LS+SB)
1 Secant Pile Nos 852 415 368 100 110 110 69 437 51%
H CASTING ELEMENTS
Tunnel Ring segments Nos 2935 2914 1 50 20 20 20 20 80 25 25 25 25 100 30 30 30 30 120 20 5 21 1%
I Critical Isue