KUKUM DRYER (7-BAY)

Capacity: 21,000 Split Nuts


Capacity per Bay: 3000 Split Nuts
Number of Bay: 7-Bay
Area/Bay: 8.45 sq.mtr
Bill of Materials:
➢ Material cost: Php 767,417.00
➢ Labor cost: Php 80,000.00
➢ Utility cost: Php 50,000.00
TOTAL COST: Php 897,417.00*
*Costing based on 2018 prices

Figure 1. FLOOR PLAN OF KUKUM DRYER (7-BAY)


Figure 2. FRONT VIEW OF THE KUKUM DRYER (7-BAY)

Figure 3. LEFT VIEW OF THE KUKUM DRYER (7-BAY)


Figure 4. ISOMETRIC VIEW OF THE KUKUM DRYER (7-BAY)

Figure 5. ISOMETRIC VIEW OF THE KUKUM DRYER (7-BAY)


Figure 6. ISOMETRIC VIEW OF THE KUKUM DRYER’S BAY
KUKUM DRYER ESTIMATES (7-BAY)

Item Qty Unit price (Php) Total (Php)


4”x4”x8’ coconut wood 20 pcs 192 3840
2”x4”x6’ coconut wood 30 pcs 72 2160
2”x4”x12’ coconut 28 pcs 144 4032
wood
2”x3”x6’ coconut wood 60 pcs 54 3240
1”x12”x12’ coconut 30 pcs 216 6480
wood
1”x12”x6’ coconut 28 pcs 108 3024
wood
4” diam. Bamboo 20 pcs 200 4000
4” diam. Bamboo 25 pcs 200 5000
4” diam x 4’ coconut 30 pcs 150 4500
wood
2”x3”x16’ coconut 6 pc 144 864
wood
2”x4”x12’ coconut 45 pcs 144 6480
wood
G.I. plainsheet, #26 20 pcs 850 17000
B.I. sheet, 3/8” (heat 47 pcs 10500 493500
exchanger)
Cement 90 bags 265 23850
CHB 1000 pcs 28 28000
Common nail, 4” 12 kg 36 432
Common nail, 3” 12 kg 18 216
Common nail, 2” 7 kg 47 329
Common nail, 11/2” 12 kg 45 540
1”x10”x12’ coconut 18 pcs 180 3240
wood
Welding rod, #12 15 kg 180 2700
Rivet, 3/16 5 box 450 2250
Sand 8m3 1800 14400
Def.bar, 16mm 100 pcs 385 38500
8” dia.x12’ coconut 35 pcs 450 15750
wood
2”x4”x16’ coconut 15 pcs 192 2880
wood
G.I. corr. Sheet, #26 80 pcs 790 63200
2”x3”x12’ coconut 45 pcs 108 4860
wood
2”x3”x10’ coconut 35 pcs 90 3150
wood
2”x2”x10’ coconut 150 pcs 60 9000
wood
Labor cost 80000
Utility cost 50000
TOTAL 897,417