Method Statement for Installation by Welding an Additional

8mm thick Steel Plate to the Main Steel Beam (IPE 360
and IPE 270) That will Connect Kalzip Roof on the Hajj
Terminal Building
1.Scope

This Method statement is prepared to describe the procedure for installing by welding an
additional 8mm thick galvanized steel plate strips to the main steel beam (IPE 360 & IPE 270) that
will connect Kalzip roof of Hajj Terminal building.
This method upon approval will be applicable for all similar works in future

2.Reference document
- Drawing detail SF # 3031

4.Man power
 SBG Site engineer (1)
 SBG Foreman (1)
 welder (2)
 Helper (2)

5.EQUIPMENT
 Welding machine (Big- heavy duty w/ complete accessories)
 Electrical Grinder with grinding discs.
 Cutter ( acytelane and oxygen w/ complete accessories)
 Generator
 Welding mask

6. MATERIAL
 Welding rod
 Steel brush
 Approved Epoxy/Galvanized spray paint
7. PROCEDURE FOR REPAIR
Steps :
1. Installed Bracket to be cut according to Erection Shop drawing.

2. Start cutting using acytelane cutter and cover steel structure w/ protection board not to
damage the paint by grinder dust.
3. Weld the 8mm galvanized plates on the location conforming to Shop drawing to the IPE or as

per site requirement.

4. 5cm Welding 5mm thick strips shall be at 50cm intervals on both sides of the plate

5. Clean the welding surface with steel brush and apply approved spray galvanized/epoxy paint.

8. Quality control

 Review / approval of methodology


 Monitor the on-going rectification
 Submit RFIA for inspection and approval of completed works

9. Safety

 All labors to wear their PPE


 Safety application
 Safety tools