Professional Documents
Culture Documents
Au Yeung-Review of Past Failures of Trench Excavations
Au Yeung-Review of Past Failures of Trench Excavations
Sheetpile Failure at Yun Ping Road Sheetpile Failure at Yun Ping Road
Failure occurred
in October 1990
1
Sheetpile Failure at Yun Ping Road Sheetpile Failure at Yun Ping Road
10m
10m long Fence wall and
pavement
ground floor slab of
subsided
adjacent building
collapsed
However !
2
Trench Study
The GEO Study • A total of 17 cases have been reviewed
• Review of records which could be
Review of known past failure cases
occurred between 1986 and 2000, retrieved from newspapers, file
plus a very serious fatal incident in records, LD’s incident reports,etc
1966
• Review of Landslide Investigations
Types of Failues
• Collapses of Slopes Adjacent to Consequence :
Closure of Pokfulam
Trenches Road, resulting in
serious traffic
• Collapses of Trenches disruption
“Cause of failure
Consequence
identified by :LI
One injured;
Study:
closure of amount
large of roads & of
damage of
buildings
surface runoff
entering the trench”
Kennedy Road near Hau Fung Lane (August 1999) Kennedy Road near HK Park (August 2000)
3
Cause of failure
identified by LI :
Consequence
major :
loss of soil
Closuredue
material of school
to
water ingress into
the trench
22.2.1987
A broken concrete
Cause of failure identified by Professor Lumb : pavement slab fell
“ the collapse of the wall was due to the inside the trench
excavation at the foot of the wall………..Failure
might not have been occurred if there had been
no trench excavated ……..” 1 killed
4
16.1.1991 26.2.1993
1 killed, 1 injured
1 killed
5.11.1999
Trench side
collapsed
1 killed 1 injured
5
Recommendations
Objective Scope
• Enhance construction site safety
• Planning
• Construction
• Supervision
6
Construction Stage
.
Design Considerations
• Installation of support
• Loading – for depth > 1.2m (CS(S)R (Cap.59I))
– traffic load, lateral force
•Drainage provisions
•Drainage - trench cover, seal voids, upstand,
- surface runoff, infiltration sump pumping, full-time workman
•Backfilling of trench
•Vibration
- in layers, compacted to 95%
- pneumatic hammer
•Other Considerations