JENIS PEKERJAAN Qty Sat Harga Material

A. Preliminieries
1. Setting out & Cleaning Area 1.00 ls
2. Safety, Insurance & Others 1.00 ls
3. Site Office, Labour Camp, Store & Others 1.00 ls
4. Eraction Wf 300x150 & Gording CNP125 1.00 ls

B. Pekerjaan Pondasi
Pondasi Pilecap
1. Pembobokan beton 1.02 m³
2. Galian tanah 5.12 m³
3. Urugan pasir (t = 100 mm) 0.51 m³
4. Lean concrete (t = 50 mm) 0.26 m³
5. Rebar D16 mm 616.77 kg Rp 15,000
6. Rebar D10 mm 121.75 kg Rp 15,000
7. Angkur Bolt M32 36.00 pc Rp 135,000
8. Bekisting Plywood 12 mm 41.60 m²
9. Concrette Ready Mix K-350 5.92 m³ Rp 1,350,000
10. Grouting sica 0.16 m³ Rp 1,650,000

C, Pekerjaan Baja
1. WF 300X150X5,5 4527.67 kg
2. Base Plate 12mm 157.33 kg Rp 35,000
3. Gording CNP 125 1409.20 kg Rp 27,000
4. Pemasangan Sagrod M18 214.08 kg Rp 15,000
5. Pemasangan Treker M20 8.00 pcs Rp 15,000
6. Pemasangan Bracing Angin Rebar D10 59.20 kg Rp 15,000
7. Brush Baja 304.18 m2
8. Painting Primer,Skunder & Finish 304.18 m2 Rp 28,000
9. Pemasangan Atap 275.87 m2

10. Installation & Purchase self retracting lifeline safeguard Brand 8.00 UNIT Rp 6,000,000
MSA 12 Ft 400lb

Dibuat Oleh,

PT. ANDALAS METALCON AGUNG Page 1 of 3 2021.07.122/OG-AMA (revisi 2)


( Akmal Hakim )
Site Manager

PT. ANDALAS METALCON AGUNG Page 2 of 3 2021.07.122/OG-AMA (revisi 2)


PT. ANDALAS METALCON AGUNG Page 3 of 3 2021.07.122/OG-AMA (revisi 2)
PT. ANDALAS METALCON AGUNG Page 4 of 3 2021.07.122/OG-AMA (revisi 2)
PT. ANDALAS METALCON AGUNG Page 5 of 3 2021.07.122/OG-AMA (revisi 2)

You might also like