Technical Standard - Shaft and


Portal Building MWCC and Rail
Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008

Revision Author Date Issued for/Revision details


P01 Mark Gilbey 26/05/17 First formal issue
P02 Mark Gilbey 05/09/18 Mid Stage 1 MWCC delivery (see (see
HS2-HS2-SY-REP-000-000016))
P03 Mark Gilbey 01/05/19 Updated for revised ventilation
strategy, comms room designs and
electrical room sizes
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Contents
1 Purpose 7
2 General 8
2.1 Applicability 8
2.2 Relationship with and between HS2 shaft and portal building standards and specifications 9
3 Responsibilities 10
4 Design coordination 10
5 Room and spatial provisions 12
6 Environmental conditions 14
7 Reliability, Availability, Maintainability and Safety 17
8 CDM & hazards 18
9 Equipment weights and loadings 19
10 Co-ordination and on-site works 19
11 Construction aspects 20
12 Testing and commissioning 20
13 Maintenance 21
14 Interfaces and interface matrix 21
15 Specific responsibilities related to security 22
16 Specific responsibilities related to tunnel ventilation 23
16.1 Employer 23
16.2 MWCC Works 23
16.3 Rail Systems (Tunnel Ventilation) Works 28
17 Handover States 31
18 Temporary Tunnel Ventilation for Rail Systems Works 33
19 Further information 34
19.1 ‘Standard owner’ 34
20 Appendix A – Room Schedule 35
20.1 Part 1 – Chiltern, Euston, Northolt and Bromford Tunnels 35
20.2 Part 2 – Short tunnels 37
21 Appendix B – Room Data Sheet 38
21.1 Part 1 – General rooms 38

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 2 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

21.2 Part 2 – Rooms specific to the portals of short and long tunnels 46
22 Appendix C – MWCC and Rail Systems Interface Matrix 48
22.1 General 48
22.2 Tunnel ventilation for Euston, Northolt, Chiltern and Bromford tunnels 48
22.3 Tunnel ventilation for mechanically ventilated tunnels without shafts 54
22.4 Tunnel E&M Services 55
22.5 Non-traction HV Power 58
22.6 Communications & CCS 61
22.7 Traction Power 63
22.8 Fire systems 66
23 Appendix D – HV Feeding Arrangement and Room Sizes 68
24 Appendix E – Tunnel Pressure Cycles 76
24.1 General 76

List of figures
Figure 1 – Example of pressure cycles 78

List of tables
See appendices

List of acronyms
A/T Auto Transformer
BIM Building Information Model
CAM Chiltern Amersham
CCP Chiltern Chalfont St Peters
CCR Chiltern Chesham Road
CCTV Closed Circuit Television
CLM Chiltern Little Missenden
CCG Chiltern Chalfont St Giles

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 3 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

DAS Deliverable approach statement


DNO District Network Operator
EAR Euston Adelaide Road
ECW Euston Cantebury Works
EMC Electromagnetic Capability
HA Highways Agency
HVAC Heating, Ventilation and Air Conditioning
HS1 High Speed 1 (also see CTRL)
HV High Voltage
LAN Local Area Network
LU London Underground
LV Low Voltage
LWM London West Midlands
MEPH Mechanical, Electrical and Public Health
MWCC Main Works Civil Contractor
MNO Mobile Network Operator
NGW Northolt Greenpark Way
NMA Northolt Mandeville
NWG Northolt Westgate
NSR Northolt South Ruislip
NR Network Rail
OCS Overhead catenary system
OLE Overhead line equipment
OOC Old Oak Common
PRS Project requirement specification
PRM Passenger of Reduced Mobility
QDR Qualitative Design Review
TID Track Isolation Damper
TPSI Traction Power Section Isolation
TV Tunnel Ventilation
TVCR Tunnel Ventilation Control Room
UIC International Union of Railways
UPS Uninterruptible Power Supply

References
Template no.:
HS2-HS2-QY-TEM-000-000008 Page 4 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Title Reference
HS2 Project dictionary HS2-HS2-PM-GDE-000-000002

HS2 Information Paper – E22: Control of noise from the LWM-HS2-HY-PPR-000-000056


operation of stationary systems

Technical Standard – Acoustic System Interfaces HS2 HS2-SY-STD-000-000003

Technical Standard – Acoustic design of stationary systems HS2 HS2-EN-STD-000-000004

Technical Standard – Shaft and Portal Building HVAC HS2-HS2-ME-STD-000-000003

Technical Standard – Shaft and Portal Building Passive and HS2-HS2-FI-STD-000-000001


Active Fire Safety Provisions

Technical Standard – Shaft and Portal Building Electrical HS2-HS2-EL-STD-000-000002


Services

Technical Standard – Shaft and Portal Building HS2-HS2-EL-STD-000-000003


Communications and Building Management Systems

Technical Standard – Tunnel Ventilation HS2-HS2-RV-STD-000-000001

Technical Standard – Non-traction High Voltage Power HS2-HS2-EL-STD-000-000004


System

Technical Standard – Traction Power System HS2-HS2-RE-STD-000-000002

Technical Specification – MWCC MEPH Shaft and Portal HRS08-WSP-ME-SPE-000-000001


Building Materials and Workmanship HVAC Systems

Technical Specification – MWCC MEPH Shaft and Portal HRS08-WSP-ME-SPE-000-000002


Building Materials and Workmanship Passive and Active
Fire Safety Provisions

Technical Specification – MWCC MEPH Shaft and Portal HRS08-WSP-ME-SPE-000-000003


Building Materials and Workmanship Communications and
Building Management Systems

Technical Specification – MWCC MEPH Shaft and Portal HRS08-WSP-ME-SPE-000-000004


Building Materials and Workmanship Electrical Services

Code of Practice for Health and Safety in Tunnelling in the BS 6164:2011


Construction Industry

Fire Safety on Construction Sites, 8th and 9th Editions Fire Protection Association

Tunnel Ventilation Standard Details – Sheet 1 C240-PBR-RV-DDE-000-000001-FD

Tunnel Ventilation Standard Details – Sheet 2 C240-PBR-RV-DDE-000-000002-FD

Tunnel Ventilation Standard Details – Sheet 3 C240-PBR-RV-DDE-000-000003-FD

Tunnel Ventilation Standard Details – Sheet 4 C240-PBR-RV-DDE-000-000004-FD

Industrial fans - Specifications for balance quality and ISO 14694:2003


vibration levels

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 5 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

HRS08 Tunnel Ventilation System Design Statement – HRS08-WSP-RV-DES-SS04-000001


Victoria Road Crossover Box

Testing and Commissioning Procedure HRS01-HS2-ITT-000-000027

Rail Systems Construction Ventilation Requirements HRS08-HS2-RV-STD-000-000001

HS2 Requirements for Operational Utility Connections HS2-HS2-UT-STD-000-000001

Project terminology
The project terminology used within this document can be found in the ‘HS2 Project dictionary’ (HS2-HS2-
PM-GDE-000-000002).

Conventions
Mandatory clauses
The following convention is used to indicate mandatory clauses.

Mandatory clauses are differentiated from the main text of this document by use of a ‘black box’. They
contain the word ‘shall’ to indicate their status as a requirement.

Departures
Any intention to not comply with a mandatory clause is considered to be a departure from this Technical
Standard. It is recommended that the designer discusses any proposed departures with the ‘standard
owner’ at a very early stage.

Guidance
The following convention is used to indicate guidance.

NOTE – Guidance is differentiated from the paragraph to which it relates by use of italic type and use of the
words “should” or “may”.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 6 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

1 Purpose
1.1.1 This Technical Standard defines the design and construction interfaces between the
geographically based Main Works Civil Contracts (MWCC) and Rail Systems for tunnel
ventilation and intervention shafts and intervention only shafts, hereafter referred to as
‘shafts’ and the tunnel portal fire fighting points, hereafter referred to as ‘portal’ buildings.

1.1.2 The principal Railway Systems Contracts for Phase 1 are:

 HRS01 – Track and Overhead Catenary Systems

 HRS02 – Tunnel and Lineside M&E including Ventilation, cross passage doors, cross
passages services and fit out, tunnel lighting, tunnel small power, tunnel emergency
signage, permanent tunnel ventilation, open route small power, open route lighting and
points heating.

 HRS03 – Traction and Non-Traction High Voltage Power;

 HRS04 – Communications; including distribution networks for HS2 and the mobile
network operators.

 HRS05 – Command, Control and Signalling; and

 HRS06 – Washwood Heath Depot and Network Integrated Control Centre, including
the shell and core of the building.

1.1.3 Within this Technical Standard the Rail Systems Contractors will be referred to by the
Contract number, e.g. HRS02, in the case of tunnel and line side M&E.

1.1.4 This Technical Standard provides requirements for design and co-ordination with Rail
Systems and constitutes part of the MWCC’s Works Information. These are in addition to the
requirements provided in the Works Information series of documents.

1.1.5 This Technical Standard standardises the Rail Systems that are common across the different
HS2 tunnels to meet HS2 operation and maintenance requirements and defines the Rail
Systems inputs into the MWCC designs.

1.1.6 This Technical Standard provides details of the required Rail Systems spatial provisions, the
associated coordination requirements and works responsibilities.

1.1.7 This Technical Standard provides references to other Technical Standards that describe
MWCC and Rail Systems interfaces in further detail.

1.1.8 This Technical Standard defines the Rail Systems interfaces to the extent that requirements
specified and assumptions made within it for MWCC design will become constraints on the
Rail Systems Contracts.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 7 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

1.1.9 This document and the referenced standards will be used by both the MWCC and Rail
Systems contracts throughout the life of the delivery phase of HS2 and are part of the Works
Information for the MWCC and all of the Rail Systems Contractors.

1.1.10 The contracting arrangements for Phase 2A are not determined at the last revision of this
standard. In the interim the general principles of interfaces with the Rail Systems should be
adopted on the basis of the principles established for Phase 1. However, this standard may
require updating to suit the specific Phase 2A contracting strategy once it is decided.

2 General
2.1 Applicability
2.1.1 Any proposed departures from this technical standard requires the acceptance of ‘standard
owner’.

2.1.2 This document shall apply to the intervention shafts and combined ventilation and
intervention shafts associated with long (> 5km) tunnels.

2.1.3 This document shall apply to the fire fighting points associated with the long (> 5km) and
short (<5 km) tunnels.

2.1.4 General requirements for the Contractor’s design and delivery of the works shall be as per the
Works Information.

2.1.5 This standard retains the use of the term ‘fire fighting point’ based on the description given in
the COMMISSION REGULATION (EU) No 1303/2014 concerning the technical specification for
interoperability relating to ‘safety in railway tunnels’ of the rail system of the European
Union), (referred to hereafter as the TSI-SRT). In the 2019 of the TSI-SRT this term has been
changed to ‘evacuation and rescue point’. HS2 documents will be progressively updated to
account for the change in TSI but this revision (P03) of this standard retains the terminology of
the 2014 TSI-SRT.

2.1.6 All tunnels greater than 100m long will have at least one fire fighting point located at one of
the portals (which is more than the minimum requirements of the TSI-SRT). All tunnels
greater than 1km long will have fire fighting points at both portals.

2.1.7 Room requirements for Phase 2A tunnels are described in Appendix D of this standard.

2.1.8 General HS2 requirements related to Operation, Maintenance and replacement, Training,
Environment/aesthetics/sustainability/carbon footprint, Health and safety/safety by design,
Design life, Whole-life costs and BIM and asset management considerations shall be as
described in other HS2 standards referenced in the Standards Baseline as part of the Works
Information.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 8 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

2.2 Relationship with and between HS2 shaft and portal building
standards and specifications
2.2.1 This Technical Standard describes key interfaces between Rail Systems and MEPH systems,
plant and materials that the MWCC will install within shafts and portal buildings.

2.2.2 In cases where the interfaces are complex and/or require more detailed description, the
detailed interface requirements have been included in the most relevant HS2 Technical
Standard for the MEPH systems, plant and materials.

2.2.3 HS2 has prepared Technical Standards for key shaft and portal building MEPH systems, plant
and materials in the following documents:

 Technical Standard – Shaft and Portal Building Electrical Services (HS2-HS2-EL-STD-


000-000002)

 Technical Standard – Shaft and Portal Building Communications and Building


Management Systems (HS2-HS2-EL-STD-000-000003)

 Technical Standard – Shaft and Portal Building Passive and Active Fire Safety Provisions
(HS2-HS2-FI-STD-000-000001)

 Technical Standard – Shaft and Portal Building HVAC (HS2-HS2-ME-STD-000-000003)

2.2.4 The preceding Technical Standards primarily cover key functional and performance
requirements for the associated systems, plant and materials.

2.2.5 Technical Specifications – MWCC MEPH Shaft and Portal Building Materials and
Workmanship (HRS08-WSP-ME-SPE-000-000001 to 000004) shall be used as materials and
workmanship requirements associated with this Technical Standard.

2.2.6 It is recognised that the preceding standards do not cover all of the MEPH systems, plant and
materials that the MWCC will provide. HS2 has provided these standards only in cases where
they consider it important for reasons that include: achieving a high degree of consistency
between the facilities provided by different Contractors; where there is operational criticality;
where there are high degrees of freedom in design; where industry common practice can be
variable; where there are significant numbers of interfaces between systems; where lessons
have been learnt from other similar installations; and, for improved asset management.

2.2.7 For MEPH systems, plant and materials that are not covered by HS2 Technical Standards and
Specifications for Shaft and Portal Buildings each MWCC shall develop the required Standards
and Specifications.

2.2.8 In addition to the Technical Standards outlined in Clause 2.2.3Error! Reference source not
found. related to MEPH systems, plant and materials, HS2 will produce Technical Standards
for Rail Systems. In cases where information about those Rail Systems is very important for

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 9 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

the MWCC Works this standard references key Rail Systems standards to which the MWCC
must refer. Key Rail Systems standards that are cited in this Technical Standard are:

 Technical Standard – Tunnel Cross Passages (HS2-HS2-ME-STD-000-000002)

 Technical Standard – Tunnel Ventilation (HS2-HS2-RV-STD-000-000001)

2.2.9 The Technical Standard cited for Tunnel Cross Passages is no longer used by Rail Systems and
is instead replaced by separate standards on tunnel cross passage doors and tunnel cross
passage services. The information is these two new standards, insofar as it relates to MWCC
scope, has not changed from Technical Standard – Tunnel Cross Passages and hence that
standard will remain for sole use by the MWCC.

2.2.10 This interface standard does not cover the interface between the cross passage doors and the
civil works within tunnels. A separate interface control document will be used to describe that
interface.

3 Responsibilities
3.1.1 The MWCC shall be responsible for the provision of power supplies, cable containment,
structural fixings and supports, openings and penetrations, communications and other
provisions as defined in the Works Information and this Technical Standard and other
referenced Technical Standards.

3.1.2 The Rail Systems Contractor(s) shall be responsible for the design and delivery of the Rail
Systems element and working with and providing the information necessary to allow the
MWCC to prepare an integrated Rail Systems/Civil design spatial arrangement.

3.1.3 Prior to the appointment of the Rail Systems Contractor(s) the Rail Systems input shall be
provided by HS2 or their nominated representative.

3.1.4 HS2 will appoint the Rail Systems Contractor(s) to prepare the final design, to install and
commission the Rail Systems.

3.1.5 The integrated design prepared by the MWCC will define the parameters and constraints
within which the Rail Systems Contractors will have to work.

4 Design coordination
4.1.1 The MWCC is responsible for preparing a fully integrated, clash free design that provides
sufficient space for the efficient installation, commissioning, operation, maintenance and
replacement of the Rail Systems.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 10 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

4.1.2 The MWCC shall show on their design drawings and in BIM models the provisions made for
Rail Systems, including cable containment routes and sizes and major equipment sizes, for
example tunnel ventilation fans, dampers, airways, drives, transformers and HV switchgears.

4.1.3 The MWCC shall show on their design drawings and in BIM models the tunnel ventilation
ductwork, dampers, fans and other equipment up until the time that HS2 appoints the Rail
Systems Contractor responsible for the tunnel ventilation system final design (HRS02), after
which that Contractor’s proposals will be adopted in the models.

4.1.4 The MWCC shall coordinate the input of the Rail Systems Contractors and liaise with them
throughout the design and construction of the works.

4.1.5 Notwithstanding the review and assurance requirements in other parts of the Works
Information, the MWCC shall obtain written confirmation from the Rail Systems Contractors
and Others that the design is fully coordinated with the design or works to be delivered by
those parties and accounts for their requirements. An interdisciplinary design certificate shall
be signed by the MWCC and the Rail Systems Contractors and Others to confirm this.

4.1.6 The MWCC shall work with the Rail Systems Contractors, or HS2 representative, in the
preparation of their designs, particularly with respect to layouts, fixing arrangements and
spatial co-ordination as required to achieve the integration of the Rail Systems within the
shafts, tunnels and portal buildings. For example, in the arrangement of the tunnel ventilation
systems airways and equipment.

4.1.7 The MWCC shall be responsible for the coordination and provision of all horizontal and
vertical builders work penetrations for all systems within shafts and portal structures
including, but not limited to Rail Systems that include telecommunications, traction power,
non-traction HV power, tunnel ventilation and the fire main within the tunnel. This
coordination responsibility shall remain with the MWCC up until the point that the Rail
Systems Contractor becomes the Principle Contractor where upon the responsibility for
coordination shall be transferred to the Rail Systems Contractor.

4.1.8 The MWCC shall be responsible for the fire stopping of all their own penetrations within shafts
and portal buildings.

4.1.9 The MWCC shall ensure that Rail Systems penetrations are not oversized to the extent that
more than 200mm of fire stopping in any direction is required of the Rail Systems Contractor.

4.1.10 The MWCC shall identify acceptable and non-acceptable drilling and fixing locations and
maximum support capabilities to allow the Rail Systems Contractors to complete their
designs and installations.

4.1.11 In recognition of the extent of services within shafts, and their potential impact on each other
and the civil works, the scheme design shall include representation of all services with

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 11 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

pipework diameters over 150mm, cable containment widths over 150mm wide, HVAC ducts
with any cross sectional dimension over 150mm and any HV cables services.

4.1.12 The MWCC shall co-ordinate with the Rail Systems Contractor to confirm the ratings of the
supplies.

5 Room and spatial provisions


5.1.1 The shaft and portal structures shall be designed to provide the rooms as indicated in the
Room Schedule Appendix A for Phase 1 and Appendix D for Phase 2A.

5.1.2 The dimensions of the room shall not be less than the minimum dimensions shown in the
Room Data Sheet shown in Appendix B for the Tunnel Ventilation Control Room, HS2
Communications Room, MNO Communications Rooms, Traction Power Section Isolation
Room, Incoming HV rooms A and B, Transformer Rooms A and B, A/T Switchgear Room, A/T
Transformer Room and A/T Auxiliary and Control room.

5.1.3 The dimensions of the HV incoming rooms vary from location to location. Location specific
feeding arrangements are provided in Appendix D along with location specific minimum
rooms sizes. These dimensions shall take precedent over dimensional requirements shown in
Appendix B.

5.1.4 HV transformer rooms shall have a minimum dimension of 5m x 4m but where practicable
shall be 5m x 5m.

5.1.5 The dimensions of the of the HS2 Communications Room and MNO Communications Rooms
shall conform to the minimum dimensions shown in Appendix B but where this is not
practicable the MWCC shall collaborate with HS2 Rail Systems to understand whether
alternative arrangements may be acceptable to HS2.

5.1.6 The dimensions for the tunnel ventilation system airways and fan rooms are affected by the
nature and patterns of the airflows within the airways and hence the MWCC shall collaborate
with HS2 Rail Systems to develop airway arrangements that provide for a tunnel ventilation
design free of excessive hydraulic resistance and performance risks.

5.1.7 The MWCC shall undertake a space proofing exercise to confirm the required dimensions of all
rooms except those described under Clause 5.1.2 and 5.1.6 above.

5.1.8 The MWCC shall then provide rooms of sizes adequate for the operation and maintenance of
the equipment proposed within them.

5.1.9 The usable space within plant and switch rooms either be rectilinear, or when not rectilinear
shall be demonstrated at all design submittals to be able to accommodate all major
equipment with adequate space for access and maintenance and replacement and submitted

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 12 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

to HS2 for acceptance. Room entrances and thresholds shall be free of steps and obstructions
that would prevent the use of trolleys for equipment movement.

5.1.10 With the exception of risers, floors shall be solid. Risers may include for grated floors subject
to any Fire Compartmentation requirements being satisfied.

5.1.11 All plant and switch rooms shall be free of structural columns and other obstructions, which
reduce the usable space.

5.1.12 The doors to each room shall be sized and coordinated to easily move in and out all
mechanical and electrical plants installed within these rooms in single or multiple sections,
without the need for complete disassembly.

5.1.13 All corridor widths and bends shall take into account the need to move in and out all
mechanical and electrical plants installed within rooms accessed through the corridors
without the need for complete disassembly of the plants.

5.1.14 The bending radius of cables and the supporting cable containment systems shall be taken
into account when sizing electrical switch rooms, plant rooms, risers, corridors and horizontal
and vertical cable routes and penetrations. The form of separation of electrical switchboards
shall also be considered.

5.1.15 The locations of the rooms relative to each other shall take account of their functional
relationship required for the operation of the Rail Systems in the shafts. This shall be agreed
with the Rail Systems Contractor(s).

5.1.16 For example, LV Rooms and their associated Battery Rooms should be adjacent to each other,
HV Incoming Rooms and Transformer Rooms should be adjacent to each other and above
ground, Tunnel Ventilation Control Rooms should be near the Tunnel Ventilation Fan Rooms
and Shaft LV Services Rooms should be near the entrance.

5.1.17 Multiple instances of each room type shall be provided based on the design of the MEPH
services. For example, multiple mechanical rooms may be required depending on the location
of the room in relation to the duct routes, spaces served and the function of the rooms.

5.1.18 Service risers shall be provided within shafts and sized based on the services needs and access
requirements.

5.1.19 Service risers shall be physically segregated between traction/non- traction HV power cables,
LV cables, communications cables and wet services/HVAC.

5.1.20 Service risers shall be further physically sub-divided if further design development indicates
that this is necessary for the improved resistance to failure of cables or components from
adjacent cable failures including but not limited to as required by BS8519.

5.1.21 Service riser access shall be provided and shall account for the need to allow future installation
access for the Rail Systems Contractors.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 13 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

5.1.22 HVAC shall be provided to maintain the environmental conditions described in the Room Data
Sheets in Appendix B of this Technical Standard and as described elsewhere in other HS2
Technical Standards and associated HS2 Technical Specifications.

5.1.23 In providing the HVAC and electrical services it shall be recognised that the services must
operate as a system. Services shall be arranged in a manner that accounts for their
interactions and connectivity and provides for efficient and effective operation, maintenance
and replacement.

5.1.24 No water, drainage or services susceptible to condensation build up shall be routed though
the plant rooms, switch rooms and comms rooms with electrical equipment.

5.1.25 Fire engineering and related inputs shown in Appendix A, B, C and D are preliminary. The
MWCC shall be responsible for the design and provision of fire engineering and fire
compliance of facilities associated with the shafts and portal buildings and shall adapt the
shafts and room provisions to suit.

5.1.26 Fire Engineering Requirements are described further in the document HS2 Technical Standard
– Shaft and Portal Building Passive and Active Fire Safety Provisions.

6 Environmental conditions
6.1.1 Outside environmental conditions shall assume a future climate in the 2080s using data
provided by the UK Climate Change Impacts Programme and based on a medium carbon
emissions scenario at 50% modelling uncertainty.

6.1.2 Future summer 1 % and 0.4% exceedance dry bulb temperatures shall be assumed to be 31.59
and 33.1°C respectively. Future extreme temperatures shall be assumed to be 48°C in summer
and -9.3°C in winter.

6.1.3 Summer tunnel environmental conditions for the long tunnels shall be assumed to transition
from approximately outside conditions at the tunnel entry portal to typically 35°C, but may
reach up to 40°C, at the tunnel exit portal. The exit conditions for shorter tunnels shall be
between the bounds of outside temperature and 35°C.

6.1.4 Winter tunnel environmental conditions for the long tunnels shall be assumed to transition
from approximately outside ambient conditions at the tunnel entry portal to 30°C at the
tunnel exit portal. The exit conditions for shorter tunnels will be between the bounds of
outside temperature and 30°C.

6.1.5 Tunnel relative humidity shall be assumed to vary between 30% and 50% during summer at
the cool end of the tunnel and 20% to 30% at the warm end of the tunnel during winter.

6.1.6 Equipment shall operate without failure under the vibration forces including vibration caused
by the movement of rolling stock and the operation of the railway and associated plant..

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 14 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

6.1.7 The railway is subjected to the inherent vibration from the movement of trains. The locality of
the equipment near the railway will experience vibration due to this movement. The various
tracks will cause different vibrations at the shaft.

6.1.8 Equipment at shafts exposed to tunnel airflow or close to the tunnels shall be capable of
operations in the summer and winter tunnel environmental conditions.

6.1.9 Equipment within equipment rooms shall be capable of functioning within the room
environmental conditions described in the Room Data Sheets in Appendix B of this Technical
Standard.

6.1.10 Equipment within the tunnel ventilation airways that are required to allow operation of the
shaft in support of train movements and signalling, communications, tunnel ventilation and
fire fighter intervention or fire safety shall be capable of operating in an environment of 150°C
for three hours.

6.1.11 The tunnel ventilation modelling has indicated that smoke temperatures downstream of the
fire and in the tunnel ventilation airways may reach these temperatures for the given fire heat
release rate. It is stressed that such conditions are not intended to be considered as tenable
for passengers or staff.

6.1.12 Systems, both active and passive, exposed to train aerodynamic forces of passing trains shall
withstand these pressure effects.

6.1.13 Pressure leakage through features such as tunnel ventilation system dampers and doors may
allow partial transmission of train aerodynamic forces to areas beyond the trackway. These
aerodynamic forces and pressures shall be accounted for.

6.1.14 Equipment exposed to tunnel pressures shall withstand the fatigue associated with the tunnel
pressure patterns given in Appendix E for the Service Life of the system and equipment.

6.1.15 A margin of 1 kPA shall be added onto the pressure differentials given in Appendix E to
account for calculation uncertainties and local pressure effects.

6.1.16 The data in Appendix E accounts for rolling stock parameters that are anticipated as being
operated on HS2. However, they do not account for the least aerodynamic rolling stock that is
credible. Neither do they account for pressures arising from higher density air on cooler days
nor modelling uncertainty. For these reasons the following data provides data for ultimate
structural loading purposes and includes a service factor of 1.4 to account for these
considerations.

6.1.17 Elements within tunnels exposed to tunnel to tunnel differential pressures, for example track
isolation dampers and supporting structure, floors/walls between tracks or between tracks
and plenums and cross passage doors shall be rated against fatigue effects for a differential
pressure loading of 13.0 kPA for bored tunnels and 15.4 kPA for cut and cover tunnels.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 15 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

6.1.18 It is clarified that for cross passages at the base of shafts, where the cross passage is
hydraulically shared with a fire fighters lift, the pressure leakage through naturally occurring
gaps around the lift doors is expected to relieve this pressure and result in pressure
fluctuations of less than 100 Pa in these spaces.

6.1.19 Elements connected to tunnels via leakage paths, but that are not subjected to tunnel to
tunnel differential pressures, shall be rated for an ultimate differential pressure loading of 6.6
kPA for bored tunnels and 10 kPA for cut and cover tunnels.

6.1.20 In the above clause it shall be assumed that doors and track isolation dampers are leakage
paths. Such elements shall include fan isolation dampers, tunnel ventilation ductwork, tunnel
ventilation plenum walls and bypass dampers. Such elements shall not include internal riser
walls where they are permanently sealed at interfaces with tunnels and do not include
potential leakage paths such as tunnel-facing doors.

6.1.21 Differential pressure loadings shall be assumed to regularly fluctuate between positive and
negative values, for example from +13.0 kPA to -13 kPA depending on the relative positions of
the trains.

6.1.22 Equipment shall be capable of operating for its design life in the conditions in which it will be
exposed.

6.1.23 Equipment and materials exposed to tunnel air shall be capable of operating for its design life
in a railway environment, including possible contamination from mineral dust particles and
construction products dust particles present during commissioning and pre- tunnel cleaning.
Evidence shall be provided of sustained successful operation under such conditions.

6.1.24 During the initial operation phase in the HS2 tunnels, where higher levels of dust associated
with construction are likely to be present, there may be additional challenges arising from
dust from construction and metal particle dust from rail grinding. The dust concentration shall
be monitored and reported to HS2 and the need for additional temporary filtration and/or
additional cleaning identified.

6.1.25 It is assumed that there is minimal risk of gas ingress into the tunnels and shafts and that the
tunnels and shaft walls will include a high degree of sealing. Accordingly, the Rail Systems
equipment are not specified as being suitable for hazardous environments.

6.1.26 During the construction, testing and commissioning works the tunnel and shaft environment
shall be monitored for the ingress of noxious, explosive or any other gasses that may be
hazardous to health

6.1.27 Any ingress of such gasses, for example carbon dioxide, methane or hydrogen sulphide, shall
be immediately reported to HS2 and the MWCC shall conduct a risk assessment in accordance
with the Dangerous Substances and Explosive Atmosphere Regulations.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 16 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

6.1.28 If the risk assessment determines that mitigation is required the nature of the mitigation shall
be agreed with HS2.

7 Reliability, Availability, Maintainability


and Safety
7.1.1 To the greatest extent practicable, systems shall comprise of line replaceable units (i.e.
modular components that can be replaced at the location) that are common across the entire
railway.

7.1.2 System shall be based on proven equipment that can be demonstrated to have operated in
similar operational environments for a period of not less than five years.

7.1.3 Equipment that has not been proven to operate successfully in a similar environment may
only be proposed when accelerated end of life testing has been carried out to demonstrate to
HS2’s satisfaction that the equipment may be suitable for the operating conditions.

7.1.4 Similar equipment shall be sourced from the same equipment suppliers for all locations within
any contract. For example, all of the UPS systems should be similar equipment from the same
supplier for all shafts and portal buildings.

7.1.5 Equipment shall be sufficiently reliable and available to meet the overall project objectives
and performance.

7.1.6 A failure modes and effects criticality analysis shall be undertaken by the MWCC to identify
and mitigate against failures that may negatively affect the ability to meet any sub system
reliability targets.

7.1.7 An analysis shall be undertaken by the MWCC to evaluate what spare parts provision would be
required to be procured and stored to achieve the required mean times to repair.

7.1.8 The reliability analysis shall identify what testing, maintenance and repair works are specialist
tasks that are not normally within the competence of railway systems maintainers and what
additional service contracts may be required.

7.1.9 To the greatest extent practicable, it shall be possible to carry out planned preventative
maintenance of the systems during traffic hours, including replacement of a tunnel ventilation
fan or drive.

7.1.10 A maintenance analysis shall be carried out to identify which tasks would be undertaken
during traffic hours and which tasks would be undertaken during the hours of 2400 and 0500.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 17 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

8 CDM & hazards


8.1.1 The Principal Designer duties will be held by the HS2 Head of Project Engineering for each
area up to a defined date, when it will switch to the HS2 Head of Project Engineering for
Route Wide Systems.

8.1.2 The client’s representative role will be held by the HS2 Programme Director for each sector up
to a defined date, when it will switch to the HS2 Programme Director for Route Wide
Systems.

8.1.3 The MWCC shall acts as Principle Contractor during their works.

8.1.4 HS2 will provide access to either the Rail Systems Contractors or appointed representatives to
contribute towards hazard identification, review and mitigation activities.

8.1.5 The MWCC shall provide any hazard mitigation measures required insofar as they relate to the
general scope of works attributed to the MWCC.

8.1.6 The MWCC shall take account HS2’s Health and Safety Policy and HS2’s Procedure for health
and safety in design (Document no: HS2-HS2-HS-PRO-000-000004) and follow a safety by
design philosophy.

8.1.7 Health and safety risks shall be identified and where possible eliminated. This applies to
foreseeable risks occurring during construction, operation and maintenance. Where it is not
possible to eliminate risks, the general ‘principles of prevention’ shall be applied as defined by
the CDM Regulations and brought to the attention of the Principal Designer. In doing so, pre-
construction information shall be taken into account, and residual risks shall be clearly
recorded on the design risk register and communicated to HS2 Ltd.

8.1.8 HS2 Ltd has committed to treat the health risks to those constructing, operating, maintaining
the HS2 railway, and those affected by it, on parity with associated safety risks. In fulfilling
the duties of the designer and in applying the ‘principles of prevention’, equal consideration
shall be given to health as to safety risks

8.1.9 The Rail Systems Tunnels M&E Contractor will take over the role of Principal Contractor from
the MWCC following the sectional completion of the MWCC shaft fit-out works at any shaft
location and prior to the commencement of the Rail Systems Tunnels M&E Contractor ‘s shaft
works and throughout the trial operations works.

8.1.10 The Designer shall request from HS2 any existing or prior CDM hazard records and account for
these in the design.

8.1.11 The Designer shall take ownership of any existing hazards and any additional hazards
identified or introduced by the design and shall take measures to eliminate, reduce, inform or
control them.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 18 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

9 Equipment weights and loadings


9.1.1 Rail Systems equipment weights are provided in the Technical Standards for each Rail
Systems discipline. Transformer weights are including in the Room Data Sheets within this
standard.

9.1.2 Prior to completion of the appointment of the tunnel ventilation system detailed designer the
MWCC shall assume the following for determining the weights of the tunnel ventilation
components:

 Each 200 m3/s axial fan has a weight of 11,000 kg.

 Each sound attenuator has a mass of 150 kg/m3 volume

 Each damper has a mass of 80 kg per m2 face area.

 Sheet metal ductwork is 6mm thick steel plus 25% additional weight for
flanges and bracing.

9.1.3 The MWCC shall use the equipment weight information provided for the design of the
structure and shall account for equipment and plant movements during maintenance.

9.1.4 The MWCC shall account for equipment installation, operation (including vibration and
fatigue), removal, maintenance and replacement routes when developing the structural
loading design criteria.

9.1.5 In addition to the equipment specific loads the MWCC shall account for a 10 kPA uniformly
distributed load in rail systems rooms along with a 20 kN point load on a 300 x 300mm square.

10 Co-ordination and on-site works


10.1.1 The MWCC shall ensure that the design, installation, testing and commissioning activities
associated with the MWCC works are fully integrated and compatible with the design,
installation, testing and commissioning works of all others.

10.1.2 The MWCC shall be responsible for the provision of heated, cooled, lit, clean and dust-free
spaces for the Rail Systems Contractor(s) prior to the Rail Systems Contractors setting their
systems to work.

10.1.3 Where the Rail Systems connects to equipment provided by the MWCC, for example low
voltage switch boards, if the MWCC has not yet demobilised from site they shall be in
attendance and inspect the completed works to the extent required to maintain the MWCC’s
warranties on any equipment.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 19 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

10.1.4 The MWCC shall maintain their design to account for changes in Rail Systems requirements.
For example, discrimination studies and circuit breaker settings shall be reviewed and
updated in response to improvements in the confidence of the Rail Systems electrical loads.

10.1.5 If the MWCC has not yet demobilised from site the MWCC shall be in attendance during any
integrated testing, for example integration with Network Integrated Control Centre (NICC),
and shall carry out any remedial works associated with their systems that become apparent.

11 Construction aspects
11.1.1 As a minimum the guidance provided in HSG 168 - Fire Safety in Construction, BS 6164 – Code
of Practice for Health and Safety in Tunnelling in the Construction Industry and JCOP 8th and
9th Editions – Fire Prevention on Construction Sites shall be adopted during the construction
phase.

11.1.2 A construction phase fire strategy and fire safety management plan shall be developed.

11.1.3 The construction phase plans shall be regularly reviewed and updated based on the phase of
the works and the actual situation on site.

11.1.4 Simultaneous construction activities at any location shall only be carried out when under the
control of the Principal Contractor. A fire risk assessment shall be undertaken by the Principal
Contractor and where identified by the risk assessment works shall be separated by fire
resisting partitions or enclosure.

11.1.5 All permanent fire stopping shall be uniquely identified and recorded and be inspected and
signed-off by the Contractor’s Fire Engineer and be available for inspection by HS2 before
being concealed in any void or service riser.

11.1.6 During the works temporary fire stopping shall be employed to limit the risk of fire spread
during construction activities.

11.1.7 The electrical system shall include temporary power supplies to allow testing and
commissioning during any period where incoming supplies from the HV Auxiliary power
supply is not available.

12 Testing and commissioning


12.1.1 Testing and commissioning shall be in accordance with HS2’s Testing and Commissioning
Procedure (HRS01-HS2-PR-ITT-000-000027) and Contract Requirements/Works Information.

12.1.2 The testing and commissioning shall consider the shaft and portal buildings as part of the
‘system’ named ‘Tunnel Systems’ and shall identify elementary systems within this system
type. For example, shaft and portal building HVAC would be a typical elementary system.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 20 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

12.1.3 Testing and Commissioning of systems and equipment provided by the MWCC shall be carried
out in advance of the Rail Systems Testing and Commissioning where the associated sub
system is required to support Rail Systems operation.

12.1.4 For example, HVAC systems shall be Tested and Commissioned prior to the energisation of
the Rail Systems equipment in rooms such that an adequate thermal environment can be
provided for the Rail Systems equipment to operate in.

12.1.5 Testing and Commissioning of the systems and equipment provided by the MWCC shall be
repeated or amended where the subsequent Testing and Commissioning of Rail Systems
equipment may affect the settings or operation of the equipment provided.

12.1.6 For example, protection settings of upstream circuit breakers may require adjustment once
the power demands of the Rail Systems equipment have been verified by on site.

13 Maintenance
13.1.1 The MWCC shall be responsible for the exercising/operating and maintaining their equipment
and systems from installation and commissioning to handover to the Rail Systems Tunnel
M&E Contractor at any site or locations.

13.1.2 A continuous record of all maintenance shall be kept detailing all activities and any corrective
maintenance or replacement parts. Records and logs shall be maintained and be available for
inspection at any time.

13.1.3 Operating and Maintenance Manuals shall be updated to take account of the actions taken
and lessons learnt during the maintenance period prior to handover.

13.1.4 Operating and Maintenance Manuals shall include all statutory and electrical safety
information needed to allow HS2 and subsequent Contractors to safely and efficiently
understand, plan and carry out maintenance activities.

14 Interfaces and interface matrix


14.1.1 The MWCC shall be responsible for providing design management, co-ordination, verification
and validation to ensure that the interface requirements are in accordance with the HS2
requirements.

14.1.2 General responsibilities regarding the MWCC and Rail Systems shall be as per HS2-HS2-SY-
ICD-000-000001 Main Works Civil Contract Railway Systems Contract Interface Definition.

14.1.3 Specific works responsibilities regarding MWCC and Rail Systems works and interfaces shall
be as per the Interface Matrix provided in Appendix C, the supporting Technical Standards

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 21 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

listed in the Interface Matrix and as per other HS2 Technical Standards and Works
Information.

14.1.4 The MWCC shall identify the interfaces and scope boundaries between their works, the Rail
Systems Contract(s) and other works packages.

14.1.5 The MWCC shall review the HS2 Interface Matrix in Appendix C and advise of any missing
interfaces, including with Rail Systems, or any anticipated or actual incompatibility or lack of
integration.

14.1.6 The MWCC shall proactively manage interfaces to achieve the successful integration and
delivery of the works.

14.1.7 The MWCC shall provide information to the Rail Systems Contractor identifying the provisions
that have been made to accommodate their works. This shall include design information, BIM
models and physical labelling of the assets on site.

14.1.8 Design deliverables relevant to each interface and project stage shall be as per Appendix C.
General deliverables and evidence shall be as described in the Works Information.

15 Specific responsibilities related to


security
15.1.1 The MWCC shall design the security systems to the detailed design stage to comply with
HS2’s Technical Standard – Security.

15.1.2 HS2 are developing options for the line wide management of security. Options under
consideration include the MWCC providing and installing the security system, a separate
supplier providing equipment for installation by the MWCC or a separate party supplying and
installing equipment for connection onto the Security LAN. Such options may include another
party further designing the security system subject to the constraints imposed by the detailed
design that was used to determine the Security LAN requirements.

15.1.3 The MWCC shall provide the infrastructure for a local area network (LAN) for Security as
described in Technical Standard – Shaft and Portal Building Communications and Building
Management Systems.

15.1.4 HS2 will instruct the MWCC as to the preferred option for implementation of the Security
systems delivery prior to the agreement of the scope and costs for the Stage 2 works.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 22 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16 Specific responsibilities related to tunnel


ventilation
16.1 Employer
16.1.1 HS2 has divided the works responsibilities for the tunnel ventilation system between HS2’s
system wide ventilation analysis team under contract HRS08, the MWCC and other Rail
Systems works.

16.1.2 HS2 will represent the Rail Systems Contractor (HRS02) until that party is permanently
engaged.

16.1.3 HS2 will retain the services of a system wide tunnel ventilation analysis team responsible for
identifying the ventilation airflow capacities, number of fans required, mode tables, reliability
requirements and tunnel airflow requirements during testing/commissioning for the long
tunnels.

16.2 MWCC Works


General

16.2.1 The MWCC shall design the shafts to account for the tunnel ventilation system arrangements,
sizes, weights, access, access hatches and maintenance provisions as advised by HS2 Rail
Systems.

16.2.2 Within the constraints of the number of fans, airflow rates, air speeds and sound attenuator
lengths, the MWCC may propose different spatial arrangements for the tunnel ventilation
system fan rooms and airways if they consider it will improve the integration of the system
with the design of the shafts and/or reduce whole-life costs or project risks.

16.2.3 The MWCC and HS2 shall collaborate with each other to determine the acceptability of any
MWCC proposed design changes to the tunnel ventilation system.

16.2.4 The MWCC shall respect and act upon the advice provided by HS2 and develop the ventilation
elements of the shaft design based on the outcome accepted by HS2.

16.2.5 The MWCC shall comply with the technical requirements for permanent tunnel ventilation
that are described in the section Civil, Structural and Architectural Requirements for
Permanent Tunnel Ventilation within Technical Standard – Tunnel Ventilation.

16.2.6 The MWCC shall collaborate with HRS02 to optimise the use of cast-in situ or preformed
concrete ducts (rather than sheet metal ducts) for the tunnel ventilation system.

16.2.7 The MWCC shall convert the equipment weights into loadings for use in their calculations.
These loadings shall account for plant movements during maintenance.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 23 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.2.8 The MWCC shall provide openings within the concrete structures of the tunnels, shaft
structure and head house for the tunnel ventilation equipment to the sizes and/or dimensions
shown requested by HS2 for tunnel ventilation system maintenance.

16.2.9 All openings associated with the tunnel ventilation system shall be constructed within a
tolerance of +/- 10 mm.

16.2.10 All shafts associated with tunnel ventilation airways at locations where sound attenuators are
built into the airway shall be constructed within a tolerance of +/- 10 mm.

16.2.11 All other tunnel ventilation airways shall be constructed within a tolerance of +/- 25 mm.

16.2.12 The MWCC shall provide cast-in frames to permit the connection of tunnel ventilation system
components to civil openings and structures without the need for drilling the structure.

16.2.13 Concepts for cast-in frames are provided in drawings C240-PBR-RV-DDE-000-000001-FD,


C240-PBR-RV-DDE-000-000002-FD, C240-PBR-RV-DDE-000-000003-FD and C240-PBR-RV-
DDE-000-000004-FD. The MWCC shall review these concepts and either develop them further
and adopts them or proposes their own designs to suit their preferred construction methods.
HRS02 shall collaborate with the MWCC to agree a design for the cast-in frames.

16.2.14 The MWCC shall design the system to ensure safety in operation and maintenance and submit
their proposals to demonstrate that his design has minimised the residual access risks during
the operation and maintenance of the project.

16.2.15 The MWCC shall coordinate with Others to achieve, where possible, a standardised approach
to the provision of access into the system, to facilitate safe working practices.

16.2.16 The MWCC shall demonstrate adequate access, maintenance and removal of the tunnel
ventilation equipment (e.g. fans/drives/damper modules) and the traction power section
isolation switchgear using 3D BIM modelling to demonstrate the removal path for all major
components.

16.2.17 The MWCC shall demonstrate that the maintenance access is co-ordinated with their
provision of fixed or portable lifting equipment.

16.2.18 The MWCC shall be the primary point of liaison between the local authority and HRS02 in
terms of system noise. The responsibility shall be transferred to HRS02 upon completion of
MWCC works. The interface for the acoustic design shall be compliant to Technical Standard -
Acoustic System Interfaces (document no. HS2-HS2-SY-STD-000-000003).

16.2.19 The MWCC shall calculate the noise levels at nearby receptors, accounting for the ventilation
system noise and transformer noise compliant to Technical Standard – Acoustic design of
stationary systems (document no. HS2 HS2-EN-STD-000-000004), and be the primary party
responsible for determining compliance with the objectives of HS2 Information Paper E22
(document no. LWM-HS2-HY-PPR-000-000056).

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 24 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.2.20 Prior to the appointment of the Rail Systems Contractors MWCC shall assume noise
ventilation system levels as advised by HS2.

16.2.21 The MWCC shall liaise with HS2 to present their calculation results in terms of noise levels to
the local authority and proactively assist in gaining acceptance of the outcome from the HS2
calculations and modelling.

16.2.22 The MWCC shall provide predictions of the noise impacts at receptors for both the collective
operation of the Rail Systems plant and materials and the MWCC plant and materials such
that the acceptability of the installed noise of the MWCC plant and materials can be
ascertained in advance of the Rail Systems Contractor’s commissioning.

Supports and access platforms

16.2.23 The MWCC shall develop the design of the primary and secondary support of the tunnel
ventilation system to the Detailed Design Stage.

16.2.24 The MWCC shall incorporate maintenance and inspection platforms to allow the inspection of
the tunnel ventilation equipment into the design of the secondary support steelwork.

16.2.25 The location of the platforms shall be in accordance with those advised by HS2 during design
development.

16.2.26 The MWCC shall incorporate in the design of the secondary steelwork any ladders required to
access any gantries.

16.2.27 The MWCC shall provide the primary connection points between the civil structure and the
secondary support steelwork of the tunnel ventilation system and indicates clearly within their
design the connection methods and maximum loads.

16.2.28 The HRS02 may either adopt the MWCC’s design for secondary support steelwork or propose
a design of their own subject to the constraints of the primary support attachment.

16.2.29 The HRS02 shall provide the secondary support steelwork and maintenance access gantries
associated with the secondary support steelwork.

16.2.30 The MWCC shall assume that the connections between the secondary support steelwork and
the tunnel ventilation systems and equipment will be as per the standard details shown in
drawings C240-PBR-RV-DDE-000-000001-FD, C240-PBR-RV-DDE-000-000002-FD, C240-
PBR-RV-DDE-000-000003-FD and C240-PBR-RV-DDE-000-000004-FD.

16.2.31 The MWCC shall provide the primary support structure for the fans to mount upon.

16.2.32 The MWCC shall account for a vibration isolation device between the fan and primary support
with an isolation efficiency of not less than 95%.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 25 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.2.33 The MWCC shall undertake and submit for approval a vibration analysis to ensure that
objectionable vibrations shall not be transmitted by or amplified by the primary structure or
result in fatigue failure over the design life of the structure(s).

16.2.34 The MWCC shall account for fans that are balanced to not worse than Grade 6.3 as defined in
ISO Standard 14694.

16.2.35 The MWCC shall undertake an impact test on the as constructed support structure to
determine the natural frequency of the structure and to validate the predictions of the
vibration analysis. In the event of significant differences between the analysis and as
constructed results, the analysis shall be updated and any remedial works carried out to limit
the probability of objectionable vibration transfer.

Tunnel ventilation fan control room (shafts)

16.2.36 The MWCC shall provide space for the variable speed drives, damper power supply auto
changeover switch, damper power distribution board and tunnel ventilation control panel
within the tunnel ventilation fan control room.

16.2.37 The MWCC shall develop the HVAC and associated cable containment design within and
beyond the room, and also co-ordinate this with the equipment within the room.

16.2.38 The MWCC shall amend the equipment arrangement within the room, if required, to suit the
cable containment and HVAC.

16.2.39 The MWCC shall assumes each variable speed drive is 2.45m long x 0.7m deep x 2.4m high.

16.2.40 The MWCC shall assume that the damper power distribution board panel is 1.2m wide x 0.6m
deep and is wall mounted and the ventilation control panel 1.2m wide x o.6m deep and is wall
mounted.

Tunnel ventilation fan control room (portal)

16.2.41 The MWCC shall provide space for the soft starters arranged in MCC, step-up transformer,
damper power supply auto changeover switch, damper power distribution board and tunnel
ventilation control panel within the tunnel ventilation fan control room.

16.2.42 The MWCC shall comply with the Clauses 16.2.37, 16.2.38 and 16.2.40 for these rooms

Tunnel ventilation fan power supplies and cable containment

16.2.43 The MWCC shall provide circuit protection in the Main LV Switchboards to provide power to
the tunnel ventilation fans in the shafts and to the motor control centres serving the jet fans in
the tunnels.

16.2.44 The MWCC shall allow for one shaft fan to be fed from LV Board A, one fan from LV Board B.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 26 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.2.45 The MWCC shall allow for all the jet fans at each portal to be capable of being powered from
either LV Board A and LV Board B, depending on the availability of the power supplies.

16.2.46 The MWCC shall provide circuit protection in the Main LV Switchboards to provide power to
the ventilation damper power distribution board. The damper control panel shall be fed from
both LV Board A and LV Board with a local auto changeover facility (provided by HRS02) to
determine which main LV board to accept power from at any time.

16.2.47 The MWCC shall provide circuit protection from the essential LV supply board to provide
power to the control boards on the tunnel ventilation fan’s variable speed drives and to the
tunnel ventilation control panel.

16.2.48 The MWCC shall provide cable containment between the LV Switch Rooms and the TVCR,
between the TVCR and the tunnel ventilation fan room and between TVCR and the ventilation
dampers.

16.2.49 The MWCC shall provide the cable containment within 3m of the first tunnel ventilation
damper.

16.2.50 The MWCC shall assume power supply requirements, cable containment sizes and anticipated
cable loadings as described in the Technical Standard – Building Low Voltage Electrical
Services.

Tunnel ventilation communications

16.2.51 The MWCC shall provide a communications point of presence within the Tunnel Ventilation
Control Room for the tunnel ventilation control system to communicate with the NICC.

16.2.52 The MWCC shall provide a communications point of presence (dual CAT 6 RJ45 data outlet)
within the upper and lower lobbies at the firefighting point to allow the fire fighter ventilation
mimic panel to communicate with the NICC.

16.2.53 The Communications provisions shall be as described in the Technical Standard – Shaft and
Portal Buildings Communications and Building Management Systems.

Acoustic insulation/absorption

16.2.54 The MWCC shall undertake an acoustic analysis of the noise breakout from the tunnel
ventilation system and the noise transfer between the tunnel ventilation equipment rooms
and other spaces in accordance to Technical Standard – Acoustic design of stationary
systems.

16.2.55 The MWCC shall design the walls between rooms to include such acoustic insulation so as not
exceed the maximum noise levels specified elsewhere in this standard.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 27 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.2.56 The MWCC shall ensure that the noise transfer caused by noise breakout from the tunnel
ventilation system does not exceed the maximum levels at external receptors as required by
HS2 standards.

16.2.57 The MWCC shall account for acoustically insulated flexible connections, but otherwise no
insulation of the fan casing or ductwork and the use of a 6mm thick steel for these
components.

Lifting equipment

16.2.58 The MWCC shall provide lifting provisions suitable for the removal to ground level and
onwards to road transportation of plant materials and equipment.

16.2.59 The MWCC shall engage a manual handling specialist to advise whether it would be
practicable to erect manual handling equipment in lieu of fixed cranes or hoists. The appraisal
includes identification of the mobilisation time to install the temporary lifting equipment and
respects the mean time to repair targets given in the Technical Standard – Tunnel Ventilation.

16.2.60 The MWCC shall provide permanent lifting equipment or hoists only where the combination
of vertical lift and weight of the fans or other major components requiring lifting, or excessive
time to mobilise portable lifting, prevents the practicable use of portable lifting equipment.

16.3 Rail Systems (Tunnel Ventilation) Works


16.3.1 HRS02 shall provide the equipment quantities, fan capacities and mode tables as identified by
HS2 and demonstrates airflow performance during testing and commissioning for all tunnels.

16.3.2 The HRS02 shall provide a ventilation control system for the ventilation equipment in all
tunnels and integrates this with the Engineering Management System at NICC.

16.3.3 The HRS02 shall liaise with the HS2 Operational teams and the Fire and Emergency Services
via the QDR process to develop further and integrate the central control philosophy and
system operational procedures.

16.3.4 The HRS02 shall provide fully functioning tunnel ventilation systems integrated with the
provisions of the MWCC.

16.3.5 The provisions of the HRS02 shall include the following:

a) Power and control cabling between the LV Switchboard A and B and the Tunnel
Ventilation Control Room (TVCR) and drives, between the variable speed drives
(or jet fan motor control centres) and the fans and between the damper control
panel and the dampers.

b) All control wiring and containment within the TVCR and Tunnel Ventilation Fan
Room.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 28 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

c) All control wiring and conduit/containment between the TVCR and tunnel air
velocity sensors.

d) The damper cable containment from the termination point of the MWCC scope
(i.e. from within 3m of the first damper).

e) Auto changeover switches.

f) The motor control centre, starters, step-up transformers, cable containment,


wiring, supports and jet fans associated with the jet fans in both the long and
short tunnels.

g) The control and power circuits to the fire fighter mimic panel.

h) The Ventilation Control System.

16.3.6 The HRS02 shall proactively engage with and interfaces with HS2, the MWCC and Others to
successfully deliver the works.

16.3.7 The HRS02 shall provide a tunnel ventilation system that is both compatible and integrated
with the MWCC civil engineering designs of the shafts and tunnels which are likely to have
been effectively completed prior to commencement of the tunnel ventilation system designs.

16.3.8 The HRS02 shall liaise with the MWCC and provide detailed acoustic calculations
demonstrating their compliance with the Technical Standard – Acoustic System Interface and
Technical Standard – Acoustic design of stationary systems.

16.3.9 If requested, the HRS02 shall jointly with the MWCC present the findings of their works to the
local authority and proactively assist in gaining acceptance of the outcome.

16.3.10 The HRS02 shall accept the MWCC designs as constraints within which the tunnel ventilation
system is to be designed and constructed.

16.3.11 Examples of constraints include general arrangements and civil engineering designs, airway
and aperture sizes, power availability, weight of equipment, access hatch sizes, lifting
provisions and heat emissions from variable speed drives.

16.3.12 The HRS02 shall make themselves familiar with the constraints/interfacing requirements
posed on the MWCC and other disciplines as described in this standard, the Works
Information and as shown on the designs provided by the MWCC.

16.3.13 The HRS02 shall survey and verify on-site all the facilities constructed by the MWCC prior to
finalising the tunnel ventilation designs and prior to installing any system plant and materials
on site.

16.3.14 The HRS02 shall undertake any remedial works associated with failure to identify any on-site
departures from the expected provision or arrangements constructed/provided by the MWCC.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 29 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

16.3.15 The HRS02 shall connect to any cast-in frames, flanges or fixing points provided. Any
additional spool pieces, closure plates or fill-in devices shall be provided by the HRS02.

16.3.16 Where cast-in frames are not provided the HRS02 shall undertake all drilling, bolting or fixing
works required. HRS02 shall liaise with MWCC regarding the region where these works are
feasible without causing damage to the civils works.

16.3.17 The HRS02 shall design and provides the secondary support steel work, ladders and gantries
and shall develop further the MWCC prior designs within the constraints of the primary
support points.

16.3.18 The HRS02 shall provide any special handling tools, for example A-frames used to install the
vertical tunnel ventilation fans and trolleys for moving fans, and refurbishes, load tests and
free-issues them to HS2 for their use in future maintenance.

16.3.19 The HRS02 shall use digital video or time lapse photography during the installation process
and provides the information in the Operating and Maintenance manuals.

16.3.20 The HRS02 shall ensure that Primary equipment suppliers inspect and certify the tunnel
ventilation fans and variable speed drive as installed in a manner suitable for use prior to any
equipment operation.

16.3.21 The HRS02 shall test, commission, integrate and set into full operational use the tunnel
ventilation system.

16.3.22 The HRS02 shall operate and maintain the tunnel ventilation system prior to the system
being accepted for operational use by HS2.

16.3.23 The Rail systems Contractor shall liaise with HS2 operation and maintenance teams to agree
working practices and documentation during this period.

16.3.24 Prior to Stage 4 (Dynamic Testing) the HRS02 shall thoroughly clean the tunnel ventilation
system to remove any visible signs of lose dust or detritus that may become suspended in the
air and to vacuum the splitters of the sound attenuators to remove materials that may
compromise the acoustic performance of the system.

16.3.25 After cleaning the HRS02 shall verify the acoustic and airflow performance of the system as
being like that during initial onsite measurements when the system is clean. In the event of
any loss of performance further cleaning shall be carried out until the performance is
recovered.

16.3.26 The cleaning and validation of acoustic performance shall be repeated prior to Stage 5 (Trial
Running) and prior to Operational Service.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 30 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

17 Handover States
17.1.1 Specific deliverable requirements at each stage of the design shall be as per Appendix C.

17.1.2 General construction handover states between the MWCC and Rail Systems Contactors shall
be as given in this section.

17.1.3 Structures shall be complete, dust-free, clean and dry.

17.1.4 Construction equipment shall be removed.

17.1.5 Cross passage temporary fire doors shall be intact for later removal by Rail Systems.

17.1.6 The MWCC shall account for removal of the temporary tunnel fire main, but shall liaise with
the Rail Systems Contractors to understand the efficacy of leaving it in place. If this is agreed
to by Rail Systems the main shall be left in place for the free use and disposal of by the Rail
Systems Contractors.

17.1.7 Communications for emergency services radio and fireguard shall be left in place for later free
use and disposal of by the Rail Systems Contractor.

17.1.8 Construction stage portable fire extinguishers shall be left in place for the later free use and
disposal of by the Rail Systems Contractors.

17.1.9 Temporary DNO power supplies primary intake switchboards, transformers and breakers shall
be left in place for potential later use by the Rail Systems Contractors.

17.1.10 Tunnel surveys and track bed shall be complete and accepted by HS2.

17.1.11 All cast-in components shall be installed.

17.1.12 Access routes shall be available and clear.

17.1.13 Sumps and sump pumps within shafts shall be fully commissioned and in an operational state.

17.1.14 Remote sumps and pumps within tunnels shall be fully commissioned and in an operational
state complete with a temporary discharge pipe and power supply which will be co-ordinated
with the location of the tunnel services so as not to impede their later installation and then
removed and disposed of by the Rail Systems Contractor upon changeover to the permanent
pipes and power supplies.

17.1.15 Temporary lighting within the structures shall be available.

17.1.16 Earthing bonding systems installed by the MWCC shall be installed, tested and in fit state for
the Rail Systems to safely connect to.

17.1.17 All rooms heated, cooled and lit to the levels given in the Room Data Sheets cited in this
document.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 31 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

17.1.18 All MEPH and fire assets shall be fully operational, tested, commissioned and working under
full and stable automatic control.

17.1.19 Temporary power supplies shall be used for testing and commissioning where permanent
power supplies are not available.

17.1.20 Plinths and primary structural equipment for Rail Systems shall be complete.

17.1.21 Lifts shall be fully operational and left with temporary protective panelling for later removal
by Rail Systems Contractors.

17.1.22 Defects lists reviewed and agreed with the Project Manager and all defects either closed or a
date and mechanism for closure agreed with the Project Manager.

17.1.23 Interfaces to remote monitoring systems shall be tested and proven at the point of interface.

17.1.24 Operating and maintenance manuals should be available and accepted.

17.1.25 HS2 and Rail Systems staff shall be trained in the operation and maintenance of the MEPH
assets installed by the MWCC.

17.1.26 Hatches and permanent lifting equipment installed and load tested.

17.1.27 All walls and fire compartmentation complete, except where a penetration is required to be
left open to accommodate rail systems installation.

17.1.28 All mesh decking and gantries installed within risers and other spaces where needed to
facilitate safe operation and maintenance.

17.1.29 Fire stopping of all penetrations not required by Rail Systems sealed.

17.1.30 Stairs, handrails and balustrades complete.

17.1.31 Safety and operational signage complete insofar as the services installed by the MWCC.

17.1.32 Doors’ locks and hardware installed and complete.

17.1.33 Cable troughs complete, effectively drained and provided with removable lids.

17.1.34 Floor screeds complete and all wet trades complete.

17.1.35 Finishes shall be made good.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 32 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

18 Temporary Tunnel Ventilation for Rail


Systems Works
18.1.1 Tunnel ventilation for Rail Systems construction activities shall be achieved by a combination
of early installation of the permanent ventilation and temporary fans. Rail Systems
requirements for temporary ventilation are described in the document Rail Systems
Construction Ventilation Requirements (HRS08-HS2-RV-STD-000-000001).

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 33 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

18.1.2 The MWCC shall leave in places temporary power supplies for use by Rail Systems for
construction ventilation of the capacities shown in the document Rail Systems Construction
Ventilation Requirements (HRS08-HS2-RV-STD-000-000001) .

19 Further information
19.1 ‘Standard owner’
19.1.1 The ‘standard owner’ shall be consulted in the event of any query about the requirements and
guidance given in this document – refer to the ‘Engineering Standards Owners List’ (HS2-HS2-
EN-LST-000-000004).

19.1.2 Where appropriate, the ‘standard owner’ will then consult relevant colleagues (e.g. other
standards owners where there is a technical interface and/or Railway Operations Directorate
for operational / maintenance aspects) or forward queries to them for answer.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 34 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

20 Appendix A – Room Schedule


20.1 Part 1 – Chiltern, Euston, Northolt and Bromford Tunnels
Room Ref Tunnel/Room Euston tunnel OOC Station Victoria Road Crossover Northolt tunnel Chiltern tunnel Bromford Tunnel
Box (Note 5)

tunnel South

tunnel South
tunnel North

tunnel North

South Ruislip
North Portal
South Portal

South Portal

North Portal

South Portal

North Portal

South Portal

North Portal
Intervention

intervention

(i.e Northolt

West Portal
Park Village

and Escape

Canterbury

(i.e. Euston

Mandeville

Chalfont St

Chalfont St
firefighting

Amersham

Missenden

East Portal
Greenpark
Westgate

Bromford
Chesham
(i.e. OOC

(i.e. OOC
Adelaide
Terrace
Granby

portal)

portal)

portal)

portal)
Works

Peter
point

Shaft
Road

Road
Little
Giles
Way
East
1 Airway(s) - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
2 System side plenum - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
3 Atmosphere side plenum - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
4 Tunnel ventilation fan room - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
5 Tunnel ventilation control room - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
(shafts only)
6 Tunnel ventilation equipment - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
room(s)
7 Mechanical room(s) Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
8 Services riser(s) Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
9 Services route(s) Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
10 Bypass shaft(s) - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
11 Staircase pressurisation fan room Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
12 External area for split A/C outdoor - Y Y Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
units
13 Outside area - 550 m2 - Y Y Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y

16 Sump/ sump room Y Y Y Y Y Y Y Note 1 Y Y Y Y Y Y Y Y Y Y Y Y Y Y Note Y


1
17 Corridor(s) Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
18 Vestibule(s) - - - Y Y - - - - Y Y Y Y - - Y Y Y Y - - - Y -
19 Cross passage(s) - Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
20 Maintenance or escape staircase(s) - Y Y - - Y Y - Y - - - - Y - - - - - - - Y - Y
21 Fire fighter's stair Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
22 Fire fighter's lobby Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
23 Fire fighter's lift Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
24 Fire fighter's trolley room (at track Y Y Y Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
level)
25 Lift machine room - - - - - - - - - - - - - - - - - - - - - - - -
26 Lift pit Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
27 Battery room (A and B) - Y - Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
28 LV switch room (A and B) - Y - Y Y Y Y - Note 2 Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
29 Shaft services LV switch room Y Y Y Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
30 Traction power section isolation - - - Y Y - - - Y Y Y Y Y - - Y Y Y Y Y - - Y -
room
31 Communications room & CCS - - - Y Y - - - - Y Y Y Y - - Y Y Y Y Y - - Y -
(Shafts only)
32 Incoming HV room (A and B). Note - Y - Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
6.
33 Transformer room (A and B). Note - Y - Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
6.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 35 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room Ref Tunnel/Room Euston tunnel OOC Station Victoria Road Crossover Northolt tunnel Chiltern tunnel Bromford Tunnel
Box (Note 5)

tunnel South

tunnel South
tunnel North

tunnel North

South Ruislip
North Portal
South Portal

South Portal

North Portal

South Portal

North Portal

South Portal

North Portal
Intervention

intervention

(i.e Northolt

West Portal
Park Village

and Escape

Canterbury

(i.e. Euston

Mandeville

Chalfont St

Chalfont St
firefighting

Amersham

Missenden

East Portal
Greenpark
Westgate

Bromford
Chesham
(i.e. OOC

(i.e. OOC
Adelaide
Terrace
Granby

portal)

portal)

portal)

portal)
Works

Peter
point

Shaft
Road

Road
Little
Giles
Way
East
34 A/T switchgear room - Y - - Y - - - Y - - - Y - - - Y - Y Y - Note Note -
4 4
35 A/T transformer room - Yx2 - - Y - - - Y - - - Y - - - Y - Y Y - Note Note -
4 4
36 A/T auxiliary and control switch - Y - - Y - - - Y - Y - Y - - - Y - Y Y - Note Note -
room (occasionally integrated in 4 4
the A/T switchgear room).

37 A/T feeder switchgear room - - - - - - - - - - Y - - - - - - - - - - - - -


(unique and not detailed on room
data sheet, see shaft design)
38 A/T feeder transformer compound - - - - - - - - - - Y - - - - - - - - - - - - -
(unique and not detailed on room
data sheet, see shaft design)
39 Toilet - - - Y Y - - - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
40 Fire suppression room - Y - Y Y Y Y - Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y
41 Water storage tank – 100 m3: Note, Y Y Y - - - - - - - - - - - - - - - - - - Y Y Y
assumes reliable mains supply
available. If not available tanks will
be required.
60 Refuge area - Y - - - Y Y - Y - - - - Y - - - - - - - Y Y Y
61 Lift electrical equipment room Y Y Y Y Y Y Y - Y Y Y Y Y Y - Y Y Y Y Y - Y Y Y
103 MNO communications room - Y - - - Y Y - Y - - - - Y Y - - - - - Y Y - Y
(tunnel portals)
104 2 x Communications room & CCS - Y - - - Y Y - Y - - - - Y Y - - - - - Y Y - Y
(tunnel portals)
105 Tunnel ventilation control room - Y - - - Y Y - Y - - - - Y Y - - - - - Y Y - Y
(portals only)

200 Air curtain fan room – Northolt - - - - - - - - Note 3 - - - - - - - - - - - - - - -


tunnel curtain

201 Air curtain fan room – OOC tunnel - - - - - - - Note 3 - - - - - - - - - - - - - - - -


curtain

202 TVCR for air curtains - - - - - - - Note 3 Note 3 - - - - - - - - - - - - - - -

62 Interface Substation7 - - -- - - - Y - - - - - - Y Y - - - - - - Y - -

Notes
1. Need for sump to be determined by MWCC based on vertical alignment.
2. LV Switchroom to also accommodate feeders for the air curtain fan rooms and hence MWCC must account for this in their room sizing.
3. New room type and dimensions to be taken from those shown in HRS08 Tunnel Ventilation System Design Statement – Victoria Road Crossover Box (HRS08-WSP-RV-DES-SS04-000001)
4. An ATS compound is required to be located at the east portal of the short Bromford tunnel. Due to the extension of this tunnel, this ATS compound will be moved to the new east portal. MWCC to liaise with HS2 to confirm latest
design intent
5. The depth below grade of the Bromford tunnel portals is not clear at revision P03 of this document. It has been assumed that the tracks will be at a depth of more than 3m below the fire fighting point and hence a fire fighting core
and escape stair are assumed.
6. See Appendix D for location specific details.
7. See HS2-HS2-UT-STD-000-000001 - Requirements for Operational Utility Connections for further details

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 36 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

20.2 Part 2 – Short tunnels


Room Ref Tunnel/Room Wendover Greatworth Chipping Warden Long Itchington Wood Burton Green Whitmore Madely
South Portal North Portal South Portal North Portal South Portal North Portal South Portal North Portal South Portal North Portal South Portal North Portal South Portal North Portal
105 Tunnel ventilation control room (portals only) Y Y Y Y Y Y Y Y Y - Y Y Y Y

7 Mechanical room(s) Y Y Y Y Y Y Y Y Y - Y Y Y Y
8 Services riser(s) Y Y Y Y Y Y Y Y Y - Y Y Y Y
9 Services route(s) Y Y Y Y Y Y Y Y Y - Y Y Y Y
11 Staircase pressurisation fan room - - - - - - - - Y - - - - -
12 External area for split A/C outdoor units Y Y Y Y Y Y Y Y Y - Y Y Y Y
13 Outside area - 550 m2 Y Y Y Y Y Y Y Y Y Y Y Y Y Y
16 Sump/ sump room - - - - - - - - Y - - - - -
17 Corridor(s) Y Y Y Y Y Y Y Y Y - Y Y Y Y
19 Cross passage(s) Y Y Y Y Y Y Y Y Y Y Y Y Y Y
21 Fire fighter's stair - - - - - - - - Y Y - - - -
22 Fire fighter's lobby - - - - - - - - Y - - - - -
23 Fire fighter's lift - - - - - - - - Y - - - - -
24 Fire fighter's trolley room Y Y Y Y Y Y Y Y Y Y Y Y Y Y
25 Lift machine room - - - - - - - - - - - - - -
26 Lift pit - - - - - - - - Y - - - - -
107 Battery room (A and B) portals Y Y Y Y Y Y Y Y Y - Y Y Y Y
28 LV switch room (A and B) Y Y Y Y Y Y Y Y Y - Y Y Y Y
104 2 x Communications rooms & CCS (tunnel portals) Y Y Y Y Y Y Y Y Y - Y Y Y Y
103 MNO Communications room (tunnel portals) Y Y Y Y Y Y Y Y Y - Y Y Y Y
39 Toilet Y Y Y Y Y Y Y Y Y - Y Y Y Y
40 Fire suppression room Y Y Y Y Y Y Y Y Y - Y Y Y Y
41 Water storage tank - 100m³ Y Y Y Y Y Y Y Y Y Y Y Y Y Y
32 Incoming HV Room (A and B) (Note 1) Y Y Y Y Y Y Y Y Y - Y Y Y Y
33 Transformer room (A and B) Y Y Y Y Y Y Y Y Y - Y Y Y Y
45 Mid-Point Auto Transformer Station (not detailed on Room - - - - - Y - - - - - - - Y
Data sheet – see traction power reports for designs)
60 Refuge area - - - - - - - - Y - - - - Y
61 Lift Electrical Equipment Room - - - - - - - - Y - - - - Y
113 Portal LV room Y Y Y Y Y Y Y Y Y - Y Y Y Y
114 DNO intake room - Two rooms required. Note 2. Y Y Y Y Y Y Y Y Y - Y Y Y Y

62 Interface Substation Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1

Notes

1. The number and arrangement of the incoming rooms at any portal will be dependent on the nature of the incoming supply which may be variable for each tunnel. The MWCC shall liaise with HS2 to understand the power
arrangements at each portal and then propose the number and nature of rooms at each portal based on the location specific circumstances. See HS2-HS2-UT-STD-000-000001 - Requirements for Operational Utility Connections for
further details.

2. See Appendix D for location specific details.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 37 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

21 Appendix B – Room Data Sheet


21.1 Part 1 – General rooms
Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
1 Airway to Upline Direct the Ventilation and 1. Tunnel ventilation EAR, EAP, ECW, None Not controlled. 50 Not directly - None Refer to HS2 None None None 120 No specific
or Downline TID airflow from the intervention. dampers. NWG, NSR, CCP, CLM Expected < 35°C controlled. Technical equipment
tunnel Ventilation 2. Deflector plates ,NGW, NMA, CCG, CAM, during normal Standard on provided
ventilation only. (sometimes). BRS - 25m². Actual area operations and ~150°C Security
system to/from and arrangement during a smoke
the Upline or sensitive to geometry control emergency
Downline and subject to
agreement with HS2.

2 System side Allow tunnel Ventilation and 1. Tunnel ventilation EAR, EAP, ECW,. None Not controlled. 50 Not directly - None Refer to HS2 2 x 110V 16A None None 120 No specific
plenum ventilation intervention. dampers (sometimes). NWG, NSR, CCP, CLM, Expected < 35°C controlled. Technical socket outlet equipment
airflow to merge Ventilation 2. Cast-in frames. NGW, NMA, CCG, CAM,
21.1.1
during normal Standard on provided
or split only. 3. Access hatches BRS - 25m². Actual area operations and ~150°C Security
(sometimes). and arrangement during a smoke
4. Fixed access platforms sensitive to geometry control emergency
(sometimes). and subject to
5. Mobile access platforms agreement with HS2.
(sometimes). Minimum 6m high.
3 Atmosphere Allow tunnel Ventilation and 1. Tunnel ventilation EAR, EAP, ECW, None Not controlled. 50 Not directly - None Refer to HS2 2 x 110V 16A None None 120 No specific
side plenum ventilation intervention. dampers, depending on NWG, NSR, CCP, CLM, Expected < 35°C controlled. Technical socket outlet equipment
airflow to merge Ventilation location. NGW, NMA, CCG, CAM, during normal Standard on provided
or split only. 3. Cast-in frames. BRS - 25m². Actual area operations and ~125°C Security
4. Access hatches. and arrangement during a smoke
5. Powered hoists sensitive to geometry control emergency
(sometimes). and subject to
5. Air terminal agreement with HS2.
(inlet/outlet/louver). Minimum 6m high.
6. Drainage for air
inlet/outlet water ingress.
carry-over
7. Acoustic panels
(sometimes) .
4 Tunnel Contain the Ventilation and 1. Tunnel ventilation fans Min 5m high. Floor area Forced outside Not controlled. 50 Not directly - None Refer to HS2 2 x 110V 16A Cat P2 None 120 Hatch for fan
ventilation fan tunnel intervention. 2. Cast in frames. specific to fan design air for Typically 10 to 20°C controlled. Technical socket outlet removal. Use
room ventilation fans Ventilation 3. Instrument panels. layout and maintenance occupancy. The and ~50 to 60°C Standard on of mobile
and ductwork. only. 4. Sheet metal ductwork approach. great of 0.5 air during a smoke Security lifting
Provides space and accessories. change per control emergency equipment
for removal of 5. Fixed access platforms hour or 20 and trolley to
fans. (sometimes). litre/s. Supply move fan.
6. Sensors and detectors. and exhaust.
7. Access hatches.
8. Jacking or winching
points.
9. Acoustic insulation.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 38 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
5 Tunnel Contain fan Ventilation and 1. Tunnel ventilation 4.5m x 4m x 3.5m high Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
ventilation electrical intervention. Variable Speed Drives. ventilation for not controlled (anti- vertical telephone Technical socket outlet equipment
control room equipment and Ventilation 2. Damper control panel. occupancy (20 condensation heaters panels, required for Standard on 2 x 230V 13A provided.
(shafts only) provide a only. 3. Auto changeover litre/s). Forced in panels). Maximum 200 lux comms to NICC Security socket outlet
location to start switches. ventilation for controlled to 40°C. floor
and stop the fans 4. Ventilation control temperature
and open the panels. control (~ 3900
dampers litre/s). Supply
and exhaust.

6 Tunnel Contain Ventilation and 1. Cast in frames. To be determined by the Forced Not controlled. 200 Not directly Wired None None 1 x 110V 16A Cat P2 None 120 Hatch for fan
ventilation equipment intervention. 2. Sheet metal ductwork MWCC in consultation ventilation for Typically 10 to 20°C controlled. telephone socket outlet removal.
equipment associated with Ventilation and accessories. with the HRS02 occupancy (20 and ~50 to 60°C required for Bridge crane
room(s) the tunnel only. 3. Fixed access platforms Size based on litre/s). Supply during a smoke comms to NICC for vertical
ventilation fans (sometimes). maintenance access and and exhaust control emergency lift through
4. Gantries and support equipment shaft
steelwork. requirements. Nominally
6. Sensors and detectors. 0.6m clear around ducts
7. Access hatches. plus 3m equipment way
8. Tunnel ventilation Min height 4m.
sound attenuators.
9. Tunnel ventilation
dampers, depending on
location.
7 Mechanical Provide a central Ventilation and 1. Air handling units. Varies according to Forced Lower temperature 200 Not directly - None Refer to HS2 2 x 110V 16A Cat P2 None 30 No specific
room(s) location for intervention. 2. Supply and exhaust equipment installed. ventilation for not controlled (anti- controlled. Technical socket outlet equipment
HVAC fans and Fire fighting fans. Min 3m high occupancy (20 condensation heaters Standard on provided
equipment to points. 3. Control panels. litre/s) and in panels). Maximum Security
improve 4. Starters/drives. temperature controlled to 40°C.
maintainability 4. Auto transfer switches. control (~ 170
5. Sensors/detectors. litre/s)
6. Duct heaters.
7. Non-return dampers.
8. Fire dampers.
9. Ductwork and
accessories.
8 Risers (Tunnel Provide a vertical All shafts HV cables, LV cables, Varies according to Natural Not controlled. 50 Not directly - None Refer to HS2 None None None 30 No specific
Comms, Tunnel circulation route comms cables, ductwork, equipment installed. ventilation Anticipate a 10 to controlled. Technical equipment
LV, Shaft LV, for services. pipework, decking. 40°C range. Standard on provided
non-traction HV Security
power, Traction
Power, Wet
Services, HVAC)
9 Services route(s) Provide a All shafts HV cables, LV cables, Varies according to Not directly Not controlled. 50 Not directly - None Refer to HS2 None Cat P2 None 30 No specific
horizontal comms cables, ductwork, equipment installed. ventilated Anticipate a 10 to controlled. Technical equipment
circulation route pipework. 40°C range. Standard on provided
for services. Security
10 Bypass shaft(s) Provide natural Ventilation and 1. Tunnel ventilation 20m² free cross By train piston Not controlled. Nil Not directly - None Refer to HS2 None None None 120 No specific
ventilation to the intervention. dampers. sectional area effect Anticipate a 5 to 35°C controlled. Technical equipment
tunnels. 2. Air-terminal range. Standard on provided
(louvre/inlet/outlet). Security
3. Drainage for air
inlet/outlet water ingress
carry-over.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 39 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
11 Staircase Contain fans and Ventilation and 1. Auto changeover 5m x 2.5m x 3m high Natural Lower temperature 200 Not directly - None Refer to HS2 2 x 110V 16A Cat P2 None 120 No specific
pressurisation starters intervention. switches. ventilation for not controlled (anti- controlled. Technical socket outlet equipment
fan room associated with Fire fighting 2. Starters/drives occupancy and condensation heaters Standard on provided
the staircase points. 3. Control panel. temperature in panels). Maximum Security
pressurisation. Intervention 4. Staircase pressurisation control controlled to 40°C.
May also contain shafts deeper fans.
auto changeover than 9m. 5. Non-return dampers.
switch. 6. Air-terminal.
(louvre/inlet/outlet).
7. Pressure relief dampers
(sometimes).
12 External area for Provide a Ventilation and Air cooled condenser(s) 6m x 2.5m x clear above Outside As outside Nil As per project - None Refer to HS2 None Cat P2 None 30 No specific
split A/C location to reject intervention. Refrigerant pipework criteria for Technical equipment
outdoor units heat Ventilation. external Standard on provided
Fire fighting sensitive Security
points. receptors.

13 Outside area Provide a muster Fire fighting Open air 550m² x clear above Outside As outside 50 As per project Cellular and None Refer to HS2 By designer None None 30 from No specific
point for tunnel points criteria for radio coverage Technical shaft wall. equipment
evacuees to external Standard on 120 mins provided
congregate sensitive Security when part
receptors. of escape
route

16 Sump/ sump Provide a Adelaide Road, Duty and standby pumps 3m x 3m x 4.5m high 15 air changes Not controlled. 200 Not directly - None Refer to HS2 None Cat P2 None 30 No specific
room (tunnel) location to Westgate, Control panel and sensors plus location for control per hour by Anticipate a 5 to 35°C controlled. Technical equipment
collect and pump Greenpark Way, Lifting chains and panels tunnel piston range. Standard on provided
water from the Mandeville equipment effect Security
tunnel and shaft Road, South
Ruislip, Little
Missenden,
Chalfont St
Giles, Chalfont
St Peters and
Bromford
ventilation and
intervention
shafts.
17 Corridor(s) Provide a All shafts 1. Pressurisation release Minimum based on fire Not directly Not controlled. 100 Not directly - None Refer to HS2 1 x 110V 16A Cat P2 and None 30 No specific
circulation route air damper. engineering standards. ventilated Anticipate a 5 to 35°C controlled. Technical socket outlet L4 equipment
for maintenance range. Standard on provided
access and Security
equipment
removal.
18 Vestibule(s) All shafts 1. Opposing doors with Minimum based on fire Not directly Not controlled. 100 Not directly - None Refer to HS2 None Cat P2 None 30 No specific
slow closing mechanism. engineering standards. ventilated Anticipate a 5 to 35°C controlled. Technical equipment
range. Standard on provided
Security

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 40 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
19 Cross passage(s) Provide a Ventilation and 1. 2 x Train radio RRU. Min 1.5m wide x 2m Shunt duct Not controlled. 100 Max 80 dB(A) Operational Integrated Refer to HS2 Provide 750W Cat P2 and None 120 No specific
- General circulation link intervention. 2. 1 x HS2 Comms fibre high passenger access. system with Anticipate a 5 to 40°C radio coverage with fire Technical for HS2 L4 equipment
between running Fire fighting splice facility. Min 3.5m diameter for back up supply range. will be available detection Standard on tunnel provided
tunnel bores points. 3. 1 x Essential power services. Minimum air fan and from train radio Security Comms.
distribution board. length between inner relief air system in the Assume
4. 1 x Non-essential power door faces of 5.5m. tunnel 1,000W for
distribution board. commercial
5. 2 x Door control panel. comms.
6. 1 x HVAC starter and
control panel - combined.
7. 1 x HVAC system.
8. 2 x RF Amplifier for ESR.
9. 1 x Telephone
10. 1 x Ethernet switch and
connection to fibre.
11. 2 x MNO Comms
repeaters
12. 1 x MNO fibre splice
facility.
13. Fire alarm and
detection

20 Maintenance or Provide a vertical Ventilation and - Min 1.2m wide Natural Not controlled. 100 Max 80 dB(A) Radio coverage None Refer to HS2 None Cat P2, Cat None 30 No specific
escape circulation route intervention. ventilation at Anticipate a 5 to 35°C Technical L4 on equipment
staircase(s) for staff and roof (2% of range. Standard on escape provided
contractors floor area) of Security stairs
maintenance.
Pressurised per
BS EN
12101Part 6 for
a Class B system
if escape.
21 Fire fighter's Provide an Ventilation and Air supply grilles for Min 1.2m wide Pressurised per Not controlled. 100 Max 80 dB(A) Provide Assume Refer to HS2 Provide Cat P2 and None 120 No specific
stair intervention intervention. staircase pressurisation. BS EN Anticipate a 5 to 35°C radiating cable CCTV Technical 3,000W for L4 equipment
route for fire Fire fighting Staircase pressurisation 12101Part 6 for range. and connection provided at Standard on boosting of provided
fighters and a points. relief damper (ME-BS-PR). a Class B system for emergency cross Security fire
vertical Intervention. services radio in passage communicati
circulation route stairs and to ons.
for staff and tunnels.
contractors
22 Fire fighter's Provide a Ventilation and 1. Fire hydrant and fire Min 5m², max 20m², min Pressurised per Not controlled. 100 Max 80 dB(A) Provide No CCTV Refer to HS2 None Cat L4 None 120 No specific
lobby - general mustering point intervention. main outlet. 2.5m high BS EN Anticipate a 5 to 35°C radiating cable coverage Technical equipment
for the fire Fire fighting 2. Radiating cable. 12101Part 6 for range. and connection provided; Standard on provided
fighters and a points. a Class B system for emergency may be Security
horizontal Intervention. services radio in subject to
circulation route stairs and to operational
for staff and tunnels. review
contractors
22a Fire fighter's Provide a Ventilation and 1. Traction power status Min 5m², max 20m², min Pressurised per Not controlled. 100 Max 80 dB(A) 1. Provide CCTV Refer to HS2 None Cat L4 None 120 No specific
lobby - Track mustering point intervention. indication panel. 2.5m high BS EN Anticipate a 5 to 35°C radiating cable Technical equipment
level for the fire Fire fighting 2. Tunnel ventilation 12101Part 6 for range. and connection Standard on provided
fighters and a points. system status indication a Class B system for emergency Security
horizontal Intervention. panel. services radio in
circulation route 3. Fire hydrant and fire stairs and to
for staff and main outlet. tunnels.
contractors 2. Telephone
with direct link
to NICC.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 41 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
22b Fire fighter's Provide a Ventilation and 1. Traction power status Min 5m², max 20m², min Pressurised per Not controlled. 100 Max 80 dB(A) 1. Provide CCTV Refer to HS2 None Cat L4 None 120 No specific
lobby - Ground mustering point intervention. indication panel. 2.5m high BS EN Anticipate a 5 to 35°C radiating cable Technical equipment
level for the fire Fire fighting 2. Tunnel ventilation 12101Part 6 for range. and connection Standard on provided
fighters and a points. system status indication a Class B system for emergency Security
horizontal Intervention. panel. services radio in
circulation route 3. Staircase pressurisation stairs and to
for staff and override panel. tunnels.
contractors 4. Breaching inlets for 2. Telephone
tunnels and shafts. with direct link
5. Building plan key box. to NICC.
6. Power supply for ESR
booster units.
7. Pressurisation relief
damper (sometimes).
23 Fire fighter's lift Provide a means Ventilation and Lift Refer to Tunnel Shafts Pressurised per Not controlled. 100 Max 80 dB(A) Radio coverage None Refer to HS2 None Cat P2 and None 120 Lift increased
of vertical intervention. Requirement 1D014- BS EN Anticipate a 5 to 35°C and lift comms Technical L4 to 2,000 kgs
circulation for Fire fighting EDP-AR-DPP-000- 12101Part 6 for range. Standard on SWL for basic
fire fighters and points. 001010. 2.4 x 2.9m a Class B system Security equipment
their equipment Intervention. internal shaft dimension. removal
and provide a
means for
vertical
transportation of
spare parts
24 Fire fighter's Provide a Ventilation and Portable rail trolley 2m x 1m x 2.5m high Not ventilated Not controlled. 50 Not directly - None Refer to HS2 Provide a 220 Cat P2 None 30 No specific
trolley room location to store intervention. Anticipate a 5 to 35°C controlled. Technical V 13A socket equipment
(track level) a rail access Fire fighting range. Standard on outlet for provided
trolley points. Security trickle
Intervention. charger.
26 Lift pit Provide a Ventilation and Sump pump(s) 2m x 2m x 3m Pressurised per Controlled within a 15 200 Not directly - None Refer to HS2 None None None 30 No specific
location for the intervention. Control panel and sensors BS EN to 40°C range. controlled. Technical equipment
lift drainage and Fire fighting Lifting chains and 12101Part 6 for Standard on provided
lower equipment points. equipment a Class B system Security
over run Intervention.
27 Battery room A Contain batteries Ventilation and Batteries 5m x 5m x 3m high each Forced Controlled within a 15 300 Max 80 dB(A) - None Refer to HS2 None Cat P2 Yes 30 Trolley for
or B associated with intervention. Gas detection system room. ventilation for to 25°C range. vertical Technical battery
the essential LV Ventilation. Eye wash facility occupancy and panels, Standard on install/remov
power supply Fire fighting Cooling units gas control (20 200 lux Security al
points. litre/s) floor

LV switch room Locate Ventilation and (1) LV switchboard with 8.8 x 6.1 x 3.5m Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
28 A or B switchgear and intervention. incoming breaker, bus ventilation for not controlled (anti- vertical telephone Technical socket outlet equipment
power factor Ventilation. coupler, TV feeder, DP occupancy (20 condensation heaters panels, required for Standard on provided
correction Fire fighting feeder , cross passage LV litre/s) and in panels). Maximum 200 lux comms to NICC. Security
equipment points. services feeder, MNO temperature controlled to 40°C. floor
associated with comms feeder, UPS A control (~ 610
the tunnel and feeder, stair pressurisation litre/s)
essential shaft feeder, fire fighting lift
equipment. feeder, essential HVAC
Locate feeder, shaft LV services
equipment to room feeder, TPSI room
allow Comms feed, HV intake room feed.
interface for (2) LV essential board
remote control serving tunnel emergency
and monitoring. lighting, tunnel signage,

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 42 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
HS2 communications,
tunnel vent control system
and drives and HV
switchgear controls.
Complete with bypass and
coupling to other essential
board.
(3) Distribution board for
tunnel lighting.
(4) Battery chargers for
essential/secure power
supply.
(5) Auto changeover
switches.
(6) Isolation transformer
for UPS.
(7) Power factor correction
cubicle.
(8) Fire suppression
system and room over
pressure relief damper.
29 Shaft services LV Locate Ventilation and (1) LV switchboard with 5 x 3.5 x 3.5m high Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 None 30 No specific
switch room switchgear and intervention. incoming breaker, feeder ventilation for not controlled (anti- vertical telephone Technical socket outlet equipment
equipment Ventilation. to mechanical room non occupancy (20 condensation heaters panels, required for Standard on 2 x 230V 13A provided
associated with Fire fighting essential HVAC, sump litre/s) and in panels). Maximum 200 lux comms to NICC. Security socket outlet
the shaft MEPH points. pumps, shaft lighting, shaft temperature controlled to 40°C. floor
services small power, FP, security, control (~ 150
hoists. litre/s)
(2) Distribution boards for
shaft lighting and small
power.
(3) FP and security panels.
30 Traction power Locate Ventilation and 4 x gas insulated breakers, 6 x 5 x 5.5m Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 60 No specific
section isolation switchgear and intervention. RTU (Scada box), ventilation for not controlled (anti- vertical communication Technical socket outlet equipment
room equipment Fire fighting marshalling box, 2 x pilot occupancy and condensation heaters panels, to NICC Standard on provided.
required to points except boxes, comms boxes and temperature in panels). Maximum 200 lux Security Double door
sectionalise the OOC north. telephone, key safe, control (300 controlled to 40°C. floor access door
traction power lectern, storage cabinet, litre/s) not less than
system over pressure relief device, 1.6m clear
LV distribution board, fire opening.
suppression equipment.

31 Communication Provide a Ventilation and 1. 'A' circuit BBUs, 5 x 7 x 3.5m high Forced Controlled within a 15 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
s & CCS room location for the intervention. switches and routers and ventilation for to 35°C range. vertical telephone Technical socket outlet equipment
(shafts only), train radio, Ventilation. fibre splice. occupancy (20 panels, required for Standard on 3 x 230V 13A provided
excluding communications 2. 'B' circuit BBUs, switches litre/s). 200 lux comms to NICC. Security socket outlet
commercial and Command and routers and fibre Duty/standby floor
comms Control splice. DX cooling units
Signalling 3. Ethernet patch cubicle.
equipment 4. Room cooling units
required for train 5. LV distribution boards to
control and to provide feeds for tunnel
interface with comms power.
6. Security system cabinet

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 43 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
the tunnel based
systems.
CCS

1. GSM-R
CCS area to be 2. Object Controller.
separated by 3. Axle Counter Evaluator.
cage. 4. RCM Equipment
5. Adhesion/Weather
Monitoring.

32 Incoming HV Locate HV Ventilation and Gas insulated circuit 7 x 5 x 5.5m each room. Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 2 x 110V 16A Cat P2 None 60 Use of
room A or B switchgear intervention. breakers, RTU (Scada box), Two required. ventilation for not controlled (anti- vertical shall not exceed telephone Technical socket outlet mobile lifting
associated with Ventilation. marshalling box, 2 x pilot occupancy and condensation heaters panels, project criteria required for Standard on equipment
the non-traction Fire fighting boxes, comms boxes and temperature in panels). Maximum 200 lux for external comms to NICC. Security and trolley to
power supply to points except telephone, key safe, control controlled to 40°C. floor sensitive move
the shaft Northolt south lectern, storage cabinet, receptors. equipment.
portal. over pressure relief device, Direct access
LV distribution board, to street.
natural ventilation louvre, Double door
cable trough. access door
not less than
2m wide x
2.4m high
opening.
33a Transformer Locate HV Ventilation and Transformer 5 x 5 x 5.5m each room. Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 None Cat P2 None 60 Use of
room A or B transformers intervention. approximately 2.5m long, Two required. ventilation for not controlled (anti- vertical shall not exceed telephone Technical mobile lifting
associated with Ventilation. 1.7m wide, 2.5m high occupancy and condensation heaters panels, project criteria required for Standard on equipment
the non-traction Fire fighting weighing 6000 kgs temperature in panels). Maximum 200 lux for external comms to NICC. Security and trolley to
HV power supply points except mounted on roller wheels. control controlled to 40°C. floor sensitive move
to the shaft Northolt south Natural ventilation louvres receptors. equipment.
portal. Full size door for Direct access
transformer removal. to street.
Floor trench for HV Double door
cabling. access door
not less than
2m wide x
2.4m high
opening.
34 A/T switchgear Locate HV Euston tunnel 4 x breakers, over 5 x 4 x 5.5m Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 2 x 110V 16A Cat P2 None 60 Use of
room switchgear south portal fire pressure relief device. ventilation for not controlled (anti- vertical shall not exceed telephone Technical socket outlet mobile lifting
associated with fighting point; occupancy and condensation heaters panels, project criteria required for Standard on equipment
auto OOC north temperature in panels). Maximum 200 lux for external comms to NICC. Security and trolley to
transformers portal fire control controlled to 40°C. floor sensitive move
fighting point; receptors. equipment.
Chilterns tunnel Direct access
south portal fire to street.
fighting point, Double door
Salusbury Road, access door
South Ruislip, not less than
Chalfont st Giles 2m wide x
and Little 2.4m high
Missenden clear
ventilation and opening.
intervention
shafts.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 44 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
35 A/T transformer Auto- Euston tunnel Transformer (normally 9.5 x 9.5 x clear above Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 None Cat P2 None 60 Mobile crane
room transformers south portal fire one, but two at Euston ventilation for not controlled (anti- vertical shall not exceed telephone Technical used for
fighting point; portal and three at occupancy and condensation heaters panels, project criteria required for Standard on lifting. Direct
OOC north Greenpark Way). temperature in panels). Maximum 200 lux for external comms to NICC. Security access to
portal fire control controlled to 40°C. floor sensitive outside.
fighting point; Allow 25 tonnes weight receptors.
Chilterns tunnel per AT.
south portal fire
fighting point,
Salusbury Road,
South Ruislip,
Chalfont st Giles
and Little
Missenden
ventilation and
intervention
shafts.
36 A/T auxiliary Location for auto Euston tunnel RTU (Scada box), 5 x 4 x 5.5m Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 2 x 110V 16A Cat P2 None 60 Use of
and control transformer south portal fire marshalling box, 2 x pilot ventilation for not controlled (anti- vertical shall not exceed telephone Technical socket outlet mobile lifting
switch room control fighting point; boxes, comms boxes and occupancy and condensation heaters panels, project criteria required for Standard on equipment
(occasionally equipment OOC north telephone, key safe, temperature in panels). Maximum 200 lux for external comms to NICC. Security and trolley to
integrated in portal fire lectern, storage cabinet control controlled to 40°C. floor sensitive move
the A/T fighting point; receptors. equipment.
switchgear Chilterns tunnel Direct access
room). south portal fire to street.
fighting point,
Salusbury Road,
South Ruislip,
Chalfont st Giles
and Little
Missenden
ventilation and
intervention
shafts.
39 Toilet Staff welfare All WC Determined by MWCC Extract Minimum 15°C. 200 Max 80 dB(A) None None None None None None None None
facility

40 Fire suppression Contains fire All Gas suppression bottles, Determined by MWCC Natural Minimum 15°C. 200 Max 80 dB(A) None None None None None None 60 None
room suppression pipework and control preferred
cylinders and panels.
controls
41 Hydrant water
tank

60 Refuge area Hold PRMs until Portal None Minimum 20m2 Via staircase 35 200 Max 80 dB(A) Wired CCTV and Refer to HS2 None Cat P2 and None 120 None
assistance can be intervention pressurisation telephone Video Technical L4
offered during shafts when the required for Communica Standard on
an evacuation. rescue area comms to NICC. tions Security
cannot be
accessed from
the track level

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 45 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Room name Function Shaft type Typical primary equipment Minimum dimensions HVAC System Permissible Mainta NR Outside CCTV Security Small power Fire Fire sup Fire Lifting EQUIP
applicable to (L/W/H) or area m2 Type temperatures (°C) ined Rating/dB(A) comms/ Inside requirements load detection system compart
ID illumin comms/ radio requirements and sensor (mins)
ance coverage and voltages type
(lux)
61 Lift Electrical Contain ATS and All where lifts Auto changeover switch, Determined by MWCC Natural Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
Equipment control panel for are provided lift starter and control preferred but not controlled (anti- vertical telephone Technical socket outlet equipment
Room (LEER) lifts panel may be off condensation heaters panels, required for Standard on provided
general in panels). Maximum 200 lux comms to NICC Security
ventilation controlled to 40°C. floor

21.2 Part 2 – Rooms specific to the portals of short and long tunnels
ID Room name Function Location Primary equipment Minimum dimensions Ventilation Permissible Maintain NR Outside CCTV Security Small power load Fire Fire Fire Lifting
applicable to (L/W/H) system type temperatures (°C) ed Rating/dB(A) comms/ requirements requirements and detection suppressi compart requirements
illuminan Inside voltages and sensor on mentation
ce (lux) comms/ type system (mins)
radio
coverage
103 MNO Provide a Portals Communications 6.m x 4m x 3.5m Forced Controlled within a 300 Max 80 dB(A) - None Refer to HS2 Allow 10 kW to Cat P2 Yes 30 No specific
Communicati location for the equipment racks. Note: ventilation 15 to 35°C range. vertical Technical each room, not equipment
ons room commercial Provisional – further for occupancy panels, Standard on backed. provided
(tunnel comms (MNO) design work required (20 litre/s). 200 lux Security 2 x 230V 13A
portals) and ESN radio when HS2 requirements Duty/standby floor socket outlet
equipment in for commercial comms is DX cooling 2 x 110V 13A
the tunnels known/briefed. units socket outlet

104 HS2 Provide a Portals Communications Two separate rooms with Forced Controlled within a 300 Max 80 dB(A) Wired None Refer to HS2 Allow 3000 W fed Cat P2 Yes 30 No specific
Communicati location for the equipment racks separate access. ventilation 15 to 35°C range. vertical telephone Technical from UPS supply equipment
ons & CCS train radio, Cooling units 7 x 4 x 3.5m high for occupancy panels, required for Standard on 2 x 230V 13A provided
room 1 and 2 communication Note: Provisional - more (20 litre/s). 200 lux comms to Security socket outlet
(tunnel and Command development required. Duty/standby floor NICC. 3 x 110V 16A
portals) Control DX cooling socket outlet
Signalling CCS units
equipment 1. GSM-R .
required for 2. Object Controller
train control 3. Axle Counter Evaluator.
and to interface
with the tunnel
based systems.

CCS area to be
separated by
cage.
105 Tunnel Contain fan Portals Fan soft starters arranged 7m x 7m x 3.5m high Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
ventilation electrical in an MCC ventilation not controlled (anti- vertical telephone Technical socket outlet equipment
control room equipment and Step-up transformer for occupancy condensation panels, required for Standard on 2 x 230V 13A provided.
(portals) provide a Tunnel ventilation control (20 litre/s) heaters in panels). 200 lux comms to Security socket outlet
location to panel and Maximum floor NICC
start, stop and Damper control panel temperature controlled to 40°C.
monitor the jet Damper power panel control
fans Auto changeover switches.
107 Battery room Contain Portals Batteries 2.5m x 4m x 3.5m high Forced Controlled within a 300 Max 80 dB(A) - None Refer to HS2 None Cat P2 Yes 30 Trolley for
(A or B) batteries Gas detection system each room. Two required. ventilation 15 to 25°C range. vertical Technical battery
associated with Eye wash facility for occupancy panels, Standard on install/remova
the essential LV Cooling units and gas 200 lux Security l
power supply control (20 floor
litre/s)

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 46 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

ID Room name Function Location Primary equipment Minimum dimensions Ventilation Permissible Maintain NR Outside CCTV Security Small power load Fire Fire Fire Lifting
applicable to (L/W/H) system type temperatures (°C) ed Rating/dB(A) comms/ requirements requirements and detection suppressi compart requirements
illuminan Inside voltages and sensor on mentation
ce (lux) comms/ type system (mins)
radio
coverage
113 Portal LV Locate Portals (1) LV switchboard with 5 x 3.5 x 3.5m high Forced Lower temperature 300 Max 80 dB(A) Wired None Refer to HS2 2 x 110V 16A Cat P2 Yes 30 No specific
room switchgear and incoming breaker, feeder ventilation not controlled (anti- vertical telephone Technical socket outlet equipment
equipment to mechanical room, sump for occupancy condensation panels, required for Standard on 2 x 230V 13A provided
associated with pumps, portal lighting, (20 litre/s) heaters in panels). 200 lux comms to Security socket outlet
the portal portal small power, FACP, and Maximum floor NICC.
facility MEPH security, hoists. temperature controlled to 40°C.
services (2) Distribution boards for control (~ 150
portal lighting and small litre/s)
power.
(3) FACP and security
panels.

114 DNO intake Locate DNOs Portals Circuit breakers, batteries 4.7 x 3.5 x 4.5m each Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 None Cat P2 None 60 Use of mobile
room - Two HV switchgear and charger for room, but see but see ventilation not controlled (anti- vertical shall not telephone Technical lifting
rooms and switchboard, RTU (Scada Appendix D for location for occupancy condensation panels, exceed project required for Standard on equipment
required transformer box), transformer specific requirements. and heaters in panels). 200 lux criteria for comms to Security and trolley to
room. associated with temperature Maximum floor external NICC. move
the auxiliary control controlled to 40°C. sensitive equipment.
power supply to receptors. Direct access
the shaft to street.

32 Incoming HV Locate HV Portals Gas insulated circuit 7 x 5 x 5.5m each room, Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 2 x 110V 16A Cat P2 None 60 Use of mobile
room A or B switchgear breakers, RTU (Scada box), but see Appendix D for ventilation not controlled (anti- vertical shall not telephone Technical socket outlet lifting
associated with marshalling box, 2 x pilot location specific for occupancy condensation panels, exceed project required for Standard on equipment
the non- boxes, comms boxes and requirements. Two and heaters in panels). 200 lux criteria for comms to Security and trolley to
traction power telephone, key safe, required. temperature Maximum floor external NICC. move
supply to the lectern, storage cabinet, control controlled to 40°C. sensitive equipment.
portal over pressure relief device, receptors. Direct access
LV distribution board, to street.
natural ventilation louvre, Double door
cable trough. access door
not less than
1.6m clear
opening.
33 Transformer Locate HV Portals Transformer 5 x 5 x 5.5m each room, Natural Lower temperature 300 Noise breakout Wired None Refer to HS2 None Cat P2 None 60 Use of mobile
room A or B transformers approximately 2.5m long, but see Appendix D for ventilation not controlled (anti- vertical shall not telephone Technical lifting
associated with 1.7m wide, 2.5m high location specific for occupancy condensation panels, exceed project required for Standard on equipment
the non- weighing 6000 kgs requirements. Two and heaters in panels). 200 lux criteria for comms to Security and trolley to
traction HV mounted on roller wheels. required. temperature Maximum floor external NICC. move
power supply to Natural ventilation louvres control controlled to 40°C. sensitive equipment.
the portal Full size door for receptors. Direct access
transformer removal. to street.
Floor trench for HV
cabling.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 47 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

ID Room name Function Location Primary equipment Minimum dimensions Ventilation Permissible Maintain NR Outside CCTV Security Small power load Fire Fire Fire Lifting
applicable to (L/W/H) system type temperatures (°C) ed Rating/dB(A) comms/ requirements requirements and detection suppressi compart requirements
illuminan Inside voltages and sensor on mentation
ce (lux) comms/ type system (mins)
radio
coverage
62 Interface Metering point Portals and Three switchgear cubicles Specification according to local distribution network operator (DNO) requirements. Nominal 6 x 5 metre building for single circuit. 10 x 5 m with compartmentation for two circuits
Substation and access points per circuit. Rooms to be
demarcation where there are segregated
between connections
Distribution connections to
Network the external
Operator and electricity
HS2, external to distribution
portal building network

22 Appendix C – MWCC and Rail Systems Interface Matrix


22.1 General
22.1.1 Between Revision P01 and P02 of this standard the term Rail Systems Contractor in the table below was replaced with the specific HS2 rail system contract package titles.

22.2 Tunnel ventilation for Euston, Northolt, Chiltern and Bromford tunnels
Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HRS02 RV-TV-IF- Airways, plenums 1. Provide airways, fan rooms and 1. HRS02 shall adopt the fan Comply with detailed requirements 1. Tunnel ventilation 1. Calculations confirming the 1. As built-BIM of the 1. Pressure tests to
001 and fan rooms ventilation ductwork routes to the sizes and room and airway sizes provided provided in Technical Standard - equipment drawn in the BIM ability of the structures to structure to allow the Rail demonstrate maximum
configuration advised by HS2. by the MWCC. Tunnel Ventilation. model based on sizes shown withstand all forces including HRS02 to modify their design, leakage of structure is within
2. If the MWCC wishes to consider changes 2. HRS02 shall provide all sheet on System Design Statements. aerodynamic pressures and if required, due to standard.
to the arrangements these shall be metal ductwork makeup pieces, 2. Identification of ventilation pressures. construction methods and
proposed to HS2. MWCC shall accept the deflector plates, turning vanes, maintenance access and tolerances.
response of HS2 in relation to the proposed fairings. equipment removal routes
changes. 3. HRS02 shall provide access demonstrating viability.
3. Maximise the amount of concrete duct doors to cover openings left in
leaving only short make up pieces to be concrete ducts.
fabricated in sheet steel.

4. Provide access door openings within


concrete ducts.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 48 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HRS02 RV-TV-IF- Duct and 1. Provide primary support points for the 1. The HRS02 shall either adopt Comply with detailed requirements 1. Primary and secondary 1. Information sufficient to - -
002 equipment tunnel ventilation systems and equipment. of modify the secondary support provided in Technical Standard - supports shown in BIM allow HRS02 to understand
supports and 2. Design secondary support steelwork and steelwork design provided by the Tunnel Ventilation. model. the provision and interface.
gantries gantries compatible with the primary MWCC but must accept and work 2. Clear delineation between 2. Maximum load capacity
support points. within the constraints of the primary support provided by and connection method to
primary connection points MWCC and secondary support primary support indicated
provided by the MWCC. proposal. clearly within design.
2. HRS02 provides secondary
support steelwork and gantries.

MWCC HRS02 RV-TV-IF- Openings 1. Provide cast-in frames around each 1. HRS02 shall fabricate mating Comply with detailed requirements 1. Opening size and position 1. Standard details of opening 1. As installed drawing -
003 opening for the connection of tunnel flanges to match the cast-in provided in Technical Standard - indicated. frames. produced prior to HRS02
ventilation ductwork, dampers, access frames. Tunnel Ventilation. 2. Clear indication as to the fabrication of ducts.
opening doors and equipment. 2. HRS02 shall provide secondary frame type for each opening
support mullions for tunnel giving details of flange heights
ventilation dampers. and depths.
3. Corrosion protection plan
to provide evidence of coating
thickness.
MWCC HRS02 RV-TV- Tunnel Ventilation 1. Provide and arrange a tunnel ventilation 1. HRS02 shall be constrained by Comply with detailed requirements 1. Layout of room showing 1. HVAC calculations showing - 1. HVAC system fully
IF-004 Fan Control Room control room with space for ventilation the panel locations provided by provided in Technical Standard - equipment arrangement. the ability of the system to commissioned and working
control panel and damper power supply the MWCC and will be Tunnel Ventilation. cater for the HRS02 heat prior to energisation of HRS02
distribution board. constrained by the equipment emissions. equipment.
sizes provided to the MWCC.
2. HRS02 provides concrete
plinths for floor mounted
equipment.
3. The maximum heat emission
from the HRS022 Equipment shall
be constrained to that advised to
the MWCC.
4. HRS02 shall provide auto-
changeover switch for common
fan.

MWCC HRS02 RV-TV- Fan supports 1. Provide a primary structure beneath the 1. HRS02 shall ensure that the Comply with detailed requirements 1. Indication of fan support 1. Vibration analysis of fan 1. Test to demonstrate -
IF-005 fans capable of resisting transfer of vibration severity and isolation provided in Technical Standard - concept within design. support. resonant frequency of the
objectionable levels of vibration. efficiency of their equipment Tunnel Ventilation. 2. Details of structural structure associated with the
does not exceed that advised to capability of primary support fan support prior to HRS02
the MWCC. to allow HRS02 to connect to design calculations being
the structure. complete.

MWCC HRS02 RV-TV-IF- Fan and damper 1. Provide circuit breakers for the power 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
006 power supplies supply to the tunnel ventilation fans, power demand of their system to provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
dampers, variable speed drive control that advised to the MWCC. Tunnel Ventilation and Technical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS02 design.
boards and ventilation control panel. 2. HRS02 shall provide auto- Standard - Shaft and Portal Building showing provision of 2. Cable and circuit breaker panel wiring diagrams to
2. Provide for a maximum fan motor power changeover switches. Electrical Services. equipment. sizing calculations. allow connection to panels by
of 500 kw per fan for the 200 m3/s fans. 3. Layouts of cable 3. Discrimination study for HRS02.
containment routes between electrical system. 2. Factory and site test results
rooms indicating containment for switchgear.
size and co-ordinated with
other services.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 49 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HRS02 RV-TV-IF- Cable 1. Provide cable containment for the tunnel 1. HRS02 to install, terminate and Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
007 containment ventilation system between the LV rooms test wiring on cable containment provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
and the TVCR, between the TVCR and the TV provided by MWCC. Tunnel Ventilation and Technical rooms indicating containment maximum size and weight containment for HRS02 later installation of HRS02
fan room and between the TVCR and the 2. HRS02 shall be constrained to Standard - Shaft and Portal Building size and co-ordinated with capacity of the cable installation of cables. equipment.
dampers. the cable containment capacity Electrical Services. other services. containment.
provided by the MWCC.

MWCC HRS02 RV-TV- Communications 1. Provide a communications link between 1. HRS02 to connect to installed Comply with detailed requirements 1. Indication of comms point 1. Description of comms - 1. Test results demonstrating
IF-008 & CCS the TVCR and the HS2 Communications communications point and co- provided in Technical Standard - of presence within the room. interface type and method of cable continuity and integrity.
Room. ordinate with HRS04 for Tunnel Ventilation and Technical HRS04 connection.
2. Provide a communications point in the establishment of line wide Standard - Shaft and Portal Building
upper and lower fire fighting lobbies for comms back to NICC. Communications and Building
mimic panels. Management Systems.

MWCC HRS02 RV-TV- Vestibules and 1. Provide vestibules and doors at the - Comply with detailed requirements 1. Doors and vestibules and 1. Technical submittal for 1. Factory test of door to -
IF-09 doors tunnel ventilation plenums cable of provided in Technical Standard - swing directions shown on doors describing ability to demonstrate fatigue
withstanding at least 3000 Pa or the tunnel Tunnel Ventilation. drawings. withstand fatigue forces. resistance and leakage rates
piston pressures when connected to lower prior to installation.
plenums.

MWCC HRS02 RV-TV- Access hatches 1. Provide access hatches to accommodate 1. HRS02 maintenance Comply with detailed requirements 1. Access hatch locations and 1. Calculations as required for 1. Demonstration of -
IF-010 removal of tunnel ventilation equipment. procedures must adopt the provided in Technical Standard - sizes shown and co-ordinated acoustic analysis for noise maximum opening time at
2. Demonstrate within the design that the proposals developed by the Tunnel Ventilation. with the equipment access breakout. factory test.
fans and other equipment can be removed MWCC. and maintenance proposals. 2. Calculation demonstrating 2. Any required factory test
using the access hatches. maximum opening time. for fire and acoustic integrity
3. Drawings showing swing prior to installation.
directions, maximum weight
capacity and clear opening
sizes.
MWCC HRS02 RV-TV-IF- Cranes and 1. Review lifting proposals and identify 1. HRS02 maintenance Comply with detailed requirements 1. Manual handling analysis 1. Maintenance procedures 1. Operating and maintenance -
011 gantries where fixed and where portable lifting procedures must adopt the provided in Technical Standard - indicating time and efficacy of indicating to HRS02 how manuals to allow HRS02to use
equipment may be provided. proposals developed by the Tunnel Ventilation. manual handling versus fixed lifting equipment will be the systems for their
2. Provide fixed lifting equipment where MWCC. cranes. employed. installation and maintenance.
required and where agreed with HS2. 2. HRS02 equipment weights will 2. Statutory load tests prior to
be constrained to those HRS02 works.
identified in this Technical
Standard.
MWCC HRS02 RV-TV- Louvres and 1. Provide spaces for 1. HRS02 provide louvres/screens Comply with detailed requirements 1. Size, location and types of 1. Confirmation airflow - -
IF-012 screens louvres/screens/outlets at the interface and outlets and will be provided in Technical Standard - louvres and screens indicated. resistance of louvres and
with the tunnel ventilation system and the constrained by the size of the Tunnel Ventilation. screens.
outside. outlet provided by the MWCC.

MWCC HRS02 RV-TV-IF- Acoustic 1. Undertake acoustic analysis of noise 1. HRS02 will be constrained to Comply with detailed requirements 1. Description of how the 1. Acoustic analysis indicating - 1. Sample test of noise
013 insulation breakout and transfer from the tunnel the maximum break-out fan provided in Technical Standard - acoustic analysis will be potential for inside and transfer from equipment
ventilation system. sound power levels advised to Tunnel Ventilation. performed at the next design outdoor noise propagation rooms to other spaces prior to
2. Based on the acoustic analysis, provide the MWCC. stage. from tunnel ventilation energisation of tunnel
acoustic insulation for walls and doors to 2. HRS02 to provide additional 2. Preliminary analysis for at equipment rooms. ventilation system. MWCC
prevent objectionable noise breakout from acoustic insulation of equipment least one shaft indicating the 2. Identification of sound may require to use noise
the tunnel ventilation system to other if sound power level exceeded. extent of noise breakout and insulation requirements generator in the absence of
rooms or to outside. the potential mitigation between spaces. functioning TVF.
3. Assume fan noise spectrums advised by measures required. 3. Design calculations
HS2 and a 6mm thick steel fan casing. demonstrating walls and
fixtures will meet the required
sound insulation properties.
4. Details of how wall fixings
can be made into the
insulation without

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 50 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
compromising acoustic
performance.

MWCC HRS02 RV-TV-IF- Staircase and 1. Provide an interface between the 1. HRS02 provides dry contacts in Comply with detailed requirements - 1. Interface recognised and - 1. Functional test of the stair
014 staircase staircase pressurisation and tunnel the tunnel ventilation control provided in Technical Standard - noticed in the system design pressurisation inhibit
pressurisation ventilation system that shuts the system off panel, terminates control cabling Tunnel Ventilation. statement. contacts.
when the tunnel ventilation system is and undertakes final tests.
operational. Note: pressurisation systems at
portals must remain operational.
2. Terminate interface with cables in the
TVCR.
2. MWCC tests the operation of the
contacts.
MWCC HRS02 RV-TV- Mimic panels 1. Provide space at the upper and lower fire 1. HRS02 provides and sets to Comply with detailed requirements 1. Evidence of space in design. - - 1. Functional test of
IF-015 fighting point for mimic panels associated work the panels. provided in Technical Standard - communications system
with the operation of the tunnel ventilation Tunnel Ventilation. functionality.
system. Allow 1.2m high x 0.6m wide x 0.3m
deep.
2. Provide a 230/1/50 6A power supply to
each panel from the essential distribution
board.
3. Provide communications at each panel
back to the TVCR.
MWCC HRS02 RV-TV-IF- Portal Jet fans 1. Provide circuit breakers for the power 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
016 supply to the tunnel ventilation system jet power demand of their system to provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
fans and control panel where portal jet fans that advised to the MWCC. Tunnel Ventilation and Technical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS02 design.
are required . 2. HRS02 shall provide auto- Standard - Shaft and Portal Building showing provision of 2. Discrimination study for panel wiring diagrams to
2. Provide for a maximum fan motor power changeover switches. Electrical Services. equipment. electrical system. allow connection to panels by
of 80 kW for 1960N jet fans and 40 kW for 3 HRS02 shall provide starters, HRS02.
930N jet fans. cabling, and containment within 2. Factory and site test results
tunnels, jet fans and jet fan for switchgear.
support system.

MWCC HRS02 RV-TV- Drainage 1. Provide drainage to plenums, particularly 1. HRS02 shall provide corrosion Comply with detailed requirements 1. Size, location and types of 1. Drainage sizing calculations. - -
IF-017 atmosphere side plenums, to manage water resistance to dampers where provided in Technical Standard - drainage co-ordinated with
carry over from tunnel ventilation louvres required to match the extent of Tunnel Ventilation. the air terminal schedules and
and screens. water carry over that is expected evident in design.
(carry-over is expected in the
bypass dampers only as their
screens will have minimal
weather ingress protection).

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 51 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HRS02 RV-TV-IF- S&C jet fans (Old 1. Provide circuit breakers for the power 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Cable and circuit breaker 1. Details of circuit breaker 1. Adjustments to any breaker
018 Oak Common supply to the tunnel ventilation system jet power demand of their system to provided in Technical Standard - equipment arrangement. sizing calculations. types, curves, settings and settings following finalisation
Tunnel only) fans and control panel required in the S&C that advised to the MWCC. Tunnel Ventilation and Technical 2. Electrical schematic 2. Discrimination study for setting methodology and of HRS02 design.
areas of Old Oak Common station. 2. HRS02 shall provide auto- Standard - Shaft and Portal Building showing provision of electrical system. panel wiring diagrams to
changeover switches. Electrical Services. equipment. 3. Layout of switchgear allow connection to panels by
3. HRS02 shall provide indicating provision of circuit HRS02.
switchgear, jet fans and all breakers for power feeds. 2. Factory and site test results
downstream components from . for switchgear.
the circuit breaker, including
cable containment, fans and
support.
MWCC HRS02 RV-TV-IF- Groundwater 1. Provide circuit breakers for the power 1. Station Contractor shall Comply with detailed requirements 1. Layout of rooms showing 1. Cable and circuit breaker 1. Details of circuit breaker 1. Adjustments to any breaker
019 cooling power supply to the future groundwater cooling constrain the power demand of provided in Technical Standard - equipment arrangement. sizing calculations. types, curves, settings and settings following finalisation
supplies system at Old Oak Common station. their system to that advised to Tunnel Ventilation and Technical 2. Electrical schematic 2. Discrimination study for setting methodology and of HRS02 design.
the MWCC. Standard - Shaft and Portal Building showing provision of electrical system. panel wiring diagrams to
2. Station Contractor provides Electrical Services. equipment. 3. Layout of switchgear allow connection to panels by
switchgear, starters, pumps and indicating provision of circuit HRS02 contractor.
all downstream components breakers for power feeds. 2. Factory and site test results
from the circuit breaker. . for switchgear.

MWCC HRS02 RV-TV-IF- Portal jet fans 1. Provide cable containment for the tunnel 1. HRS02 to install, terminate and Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
020 cable ventilation system between the TVCR and test wiring on cable containment provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
containment 2m into the running tunnel bore or porous provided by MWCC. Tunnel Ventilation and Technical rooms and tunnel indicating maximum size and weight containment for HRS02 later installation of HRS02
portal. 2. HRS02 to provide cable Standard - Shaft and Portal Building containment size and co- capacity of the cable installation of cables. equipment.
2. Cable containment sizes as per Electrical containment within TVCR and Electrical Services. ordinated with other services. containment.
Services standard. within tunnel.
3. HRS02 shall be constrained to
the cable containment capacity
provided by the MWCC.
MWCC HRS02 RV-TV-IF- Victoria Road Box 1. Provide two independent power feeds 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Cable and circuit breaker 1. Details of circuit breaker 1. Adjustments to any breaker
021 Power Supplies from the LV Board A and B within Northolt power demand of their system to provided in Technical Standard - equipment arrangement. sizing calculations. types, curves, settings and settings following finalisation
tunnel South portal fire fighting point to that advised to the MWCC. Tunnel Ventilation and Technical 2. Electrical schematic 2. Discrimination study for setting methodology and of HRS02 design.
serve the tunnel ventilation fan control 2. HRS02 shall provide auto- Standard - Shaft and Portal Building showing provision of electrical system. panel wiring diagrams to
room to serve jet fans/air curtains intended changeover switches. Electrical Services. equipment. 3. Layout of switchgear allow connection to panels by
to prevent heat from entering the tunnel 3. HRS02 shall provide indicating provision of circuit HRS02.
portals. switchgear, jet fans/air curtains breakers for power feeds. 2. Factory and site test results
and all downstream components . for switchgear.
from the circuit breaker,
including cable containment, fans
and support.
MWCC HRS02 RV-TV-IF- Victoria Road Box 1. Provide a fire-protected fibre optic cable 1. HRS02 shall terminate the - 1. Indication of cable route in 1. Detailed design of cable 1. Functional test to -
022 Comms Links with not less than 4 multi-mode cores cables in both rooms and set to designs. route. demonstrate the integrity of
between the HS2 Comms Room at the work the system. the cables.
Northolt tunnel south portal to the TVCR in
the OOC North portal fire fighting point.

MWCC HRS02 RV-TV-IF- Victoria Road Box 1. Provide cable containment between the 1. HRS02 shall constrain the cable Comply with detailed requirements 1. Layout of facility showing - - -
023 Cable LV boards A and B and TVCR. sizes serving the jet fans to those provided in Technical Standard - cable containment route.
Containment 2. Provide a cable route between the TVCR planned for by the MWCC in their Tunnel Ventilation and Technical
and the ventilation jet fans/air curtain fans cable containment. Standard - Shaft and Portal Building
chimneys located at the entrance to the Electrical Services.
OOC tunnel and entrance of the Northolt
tunnel.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 52 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence provided by the MWCC over and above general deliverables. Note, evidence from preceding stage must be
between Discipline number carried forward to next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HRS02 RV-TV-IF- Noise data 1. Provide HRS02 full access to any noise 1. Adopt the MWCC noise - - - - -
024 surveys that are undertaken at any location. information where they deem in
2. Co-ordinate with HRS02 to provide joint appropriate.
approaches to the local authorities with 2. Co-ordinate with MWCC to
respect to noise to the greatest extent provide joint approaches to the
practicable. local authorities with respect to
3. Take the lead role in co-ordinating the noise to the greatest extent
engagement with the local authorities on practicable.
behalf of HRS02.
MWCC HRS02 RV-TV-IF- Interlock with TS 1. Provide an interlock between the building 1. Provide a signal from the TS - - - - -
025 SCADA FACP and the HRS02 TS SCADa to trigger the SCADA to trigger the building
building fire alarm when commanded to by FACP.
the TS SCADA. 2. Terminate the wiring provided
2. Wire a series of cables for a normally by the MWCC to the TS SCADA
closed dry contact and terminate at the within the TVCR.
TVCR. 3. Perform end to end testing of
the interface.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 53 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

22.3 Tunnel ventilation for mechanically ventilated tunnels without shafts


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate Fore construction and Testing and commissioning
manufacture stage gate stage gate
MWCC HRS02 RV-TV- Tunnel Ventilation 1. Provide and arrange a tunnel ventilation 1. HRS02shall be constrained by Comply with detailed requirements 1. Layout of room showing 1. HVAC calculations showing - 1. HVAC system fully
IF-101 Fan Control Room control room with space for ventilation the panel locations provided by provided in Technical Standard - equipment arrangement. the ability of the system to commissioned and working
control panel, damper distribution and the MWCC and will be Tunnel Ventilation. cater for the HRS02 heat prior to energisation of HRS02
control panel, jet fan motor control centres constrained by the equipment emissions. equipment.
and step-up transformers. sizes provided to the MWCC.
2. HRS02 shall provide concrete
plinths for floor mounted
equipment.
3. The maximum heat emission
from the HRS02 equipment shall
be constrained to that advised to
the MWCC.
4. HRS02 shall provide auto-
changeover switch for common
fan.
MWCC HRS02 RV-TV- Communications 1. Provide a communications link between 1. HRS02 to connect to installed Comply with detailed requirements 1. Indication of comms point 1. Description of comms - 1. Test results demonstrating
IF-102 the TVCR and the HS2 Communications communications point and co- provided in Technical Standard - of presence within the room. interface type and method of cable continuity and integrity.
Room. ordinate with HRS04 for Tunnel Ventilation and Technical HRS02 connection.
2. Provide a communications point in the establishment of line wide Standard - Shaft and Portal Building
upper and lower fire fighting lobbies for comms back to NICC. Communications and Building
mimic panels. Management Systems.

MWCC HRS02 RV-TV-IF- Mimic panels 1. Provide space at the point where the fire 1. HRS02 shall provide and sets Comply with detailed Interfacing 1. Evidence of space in design. - - 1. Functional testing of
103 fighters will interface with the tunnel for to work the panels. Requirements provided in Technical Comms link.
mimic panels associated with the operation Standard - Tunnel Ventilation.
of the tunnel ventilation system. Allow 1.2m
high x 0.6m wide x 0.3m deep.
2. Provide a 230/1/50 power supply to each
panel from the essential distribution board.
3. Provide communications at each panel
back to NICC.

MWCC HRS02 RV-TV-IF- Portal jet fans 1. Provide a route for cable containment for 1. HRS02 to size and install all Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
104 cable the tunnel ventilation control room and the cable containment between the provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
containment bore of each tunnel. TVCR and the fans, terminate and Tunnel Ventilation and Technical rooms and tunnel indicating maximum size and weight containment for HRS02 later installation of HRS02
2. Cable containment sizes as per electrical test wiring on cable containment Standard - Shaft and Portal Building containment size and co- capacity of the cable installation of cables. equipment.
standard. provided by MWCC. Electrical Services. ordinated with other services. containment.
2. HRS02 will be constrained to
the cable containment routes
provided by the MWCC.

MWCC HRS02 RV-TV-IF- Portal jet fans 1. Provide circuit breakers for the power 1. HRS02 to constrain the power Comply with detailed requirements 1. Layout of rooms showing 1. Cable and circuit breaker 1. Details of circuit breaker 1. Adjustments to any breaker
105 power supplies supply to the tunnel ventilation system jet demand of their system to that provided in Technical Standard - equipment arrangement. sizing calculations. types, curves, settings and settings following finalisation
fans. advised to the MWCC. Tunnel Ventilation and Technical 2. Electrical schematic 2. Discrimination study for setting methodology and of HRS02 design.
2. HRS02 shall provide auto- Standard - Shaft and Portal Building showing provision of electrical system. panel wiring diagrams to
changeover switches and step-up Electrical Services. equipment. 3. Layout of switchgear allow connection to panels by
transformers. indicating provision of circuit HRS02.
3. HRS02 shall provide breakers for power feeds. 2. Factory and site test results
switchgear, jet fans and all . for switchgear.
downstream components from
the circuit breaker, including
cable containment, fans and
support.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 54 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

22.4 Tunnel E&M Services


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR02 EL-LV-IF- Power supplies to 1. Provide circuit breakers for the power 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
001 tunnel lighting supply to the tunnel lighting system. power demand of their system to provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
2. Provide power for the tunnel lighting that advised to the MWCC. Shaft and Portal Building Electrical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS02 design.
from the UPS backed essential power 2. HRS02 shall provide all cabling Services. showing provision of 2. Cable and circuit breaker panel wiring diagrams to
supply. and sub panels downstream of equipment. sizing calculations. allow connection to panels by
circuit breakers. 3. Discrimination study for HRS02.
electrical system. 2. Factory and site test results
for switchgear.
MWCC HSR02 EL-LV-IF- Power supplies to 1. Provide circuit breakers for the power 1. HRS02, HRS04 and HRS05 shall Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
002 cross passage LV supply to the cross passages. constrain the power demand of provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
services their system to that advised to Shaft and Portal Building Electrical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS02 design.
the MWCC. Services. showing provision of 2. Cable and circuit breaker panel wiring diagrams to
2. HRS02 shall provide all cabling equipment. sizing calculations. allow connection to panels by
and sub panels downstream of 3. Discrimination study for HRS02.
circuit breaker within the shaft electrical system. 2. Factory and site test results
LV services room. for switchgear.
MWCC HSR02 EL-LV-IF- Power supplies to 1. Provide circuit breakers for the power 1. HRS02 shall constrain the Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
003 tunnel signage supply to the tunnel signage. power demand of their system to provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
3 2. Provide power for the tunnel signage
from the UPS backed essential power
that advised to the MWCC.
2. HRS02 shall provide all cabling
Shaft and Portal Building Electrical
Services.
2. Electrical schematic
showing provision of
breakers for power feeds.
2. Cable and circuit breaker
setting methodology and
panel wiring diagrams to
of HRS02 design.

supply. and sub panels downstream of equipment. sizing calculations. allow connection to panels by
3 circuit breaker. 3. Discrimination study for HRS02 contractor.
electrical system. 2. Factory and site test results
for switchgear.
MWCC HSR02 EL-LV-IF- Power supply to 1. Provide a socket outlet at 230/1/50 13A 1. HRS02 shall constrain the - 1. Indication of socket outlet - - -
004 fire fighting rating for the emergency services to power demand of their system to in space.
booster unit connect their radiating cable amplifier. that advised to the MWCC. 2. Electrical schematic
2. Locate the socket outlet at the fire 2. HRS02 to make final showing provision
fighting lobby at ground level. connection and agree socket type
3. Provide the power supply from the with fire and rescue services.
essential (UPS backed) system.

MWCC HSR02 EL-LV-IF- Cable 1. Provide cable containment for the tunnel 1. HRS02 shall install and test Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
005 containment for Rail Systems from within LV Rooms A and B wiring on cable containment provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
tunnel LV services to each tunnel bore and within the tunnel or provided by MWCC. Shaft and Portal Building Electrical rooms indicating containment maximum size and weight containment for HRS02 later installation of HRS02
porous portal for a distance of 2m. 2. HRS02 will be constrained to Services. size and co-ordinated with capacity of the cable installation of cables. equipment.
the cable containment capacity other services. containment.
provided by the MWCC.
3. HRS02 connects to the cable
containment within the tunnel
and provides the final cable
containment within the room.
MWCC HSR02 EL-LV-IF- Space for tunnel 1. Provide space within LV room A and LV 1. HRS02 install distribution Comply with detailed requirements 1. Space for board shown and 1. Layouts of cable - -
006 lighting room B for a tunnel lighting distribution board, connect between the provided in Technical Standard - co-ordinated with other containment routes between
distribution board. main essential distribution board Shaft and Portal Building Electrical services. board and cable containment
boards 2. Provide cable routes between the board and the lighting board and Services. to the tunnel.
and the cable containment that passes from provide all cabling downstream
the tunnel. of the lighting board.
2. HRS02 shall be constrained to
the cable containment capacity
provided by the MWCC.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 55 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR02 EL-LV-IF- Remote control 1. Provide two Cat 5 cables between each 1. HRS02 shall use cables to - - 1. Functional description 1. Wiring diagrams to allow -
007 and monitoring of LV Room A and B and the TVCR to allow the connect the system and make shown in design. HRS02 to connect .
tunnel lighting tunnel lighting to be monitored by the TS final connections between 2. Functional tests of cables.
and signage SCADA. equipment.

MWCC HSR02 EL-LV-IF- Space for tunnel 1. Provide space within LV Room A and LV 1. HRS02 shall install distribution Comply with detailed requirements 1. Space for board shown and 1. Layouts of cable - -
008 signage room B for a tunnel signage distribution board, connect between the provided in Technical Standard - co-ordinated with other containment routes between
distribution board. main essential distribution board Shaft and Portal Building Electrical services. board and cable containment
boards 2. Provide cable routes between the board and the signage board and Services. to the tunnel.
and the cable containment that passes from provide all cabling downstream
the tunnel. of the lighting board.
2. HRS02 shall be constrained to
the cable containment capacity
provided by the MWCC.
MWCC HSR02 EL-LV-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS02 shall be constrained by Comply with detailed requirements 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
009 capacity for duration to serve the tunnel lighting. the UPS and battery capacity provided in Technical Standard - capacity within battery sizing indicating provision of circuit simulated load to prove
tunnel lighting cited. Shaft and Portal Building Electrical calculations. breakers for power feeds. capacity.
Services. 2. Cable and circuit breaker
sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR02 EL-LV-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS02 shall be constrained by Comply with detailed requirements 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
010 capacity for duration to serve the tunnel signage. the UPS and battery capacity provided in Technical Standard - capacity within battery sizing indicating provision of circuit simulated load to prove
tunnel signage cited. Shaft and Portal Building Electrical calculations. breakers for power feeds. capacity.
Services. 2. Cable and circuit breaker
sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR02 EL-LV-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS02 shall be constrained by Comply with detailed requirements 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
011 capacity for fire duration to serve the fire fighters power the UPS and battery capacity provided Technical Standard - Shaft capacity within battery sizing indicating provision of circuit simulated load to prove
fighter power supply. cited. and Portal Building Electrical calculations. breakers for power feeds. capacity.
supply Services. 2. Cable and circuit breaker
sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR02 EL-LV-IF- Power supplies 1. HRS02 shall be constrained by Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
012 for trackside 1. Provide circuit breakers in main switch the circuit breaker sizing provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
electrical boards for trackside electrical equipment specified. Shaft and Portal Building Electrical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS02 design.
equipment 2. HRS02 shall provide sub mains Services. showing provision of 2. Cable and circuit breaker panel wiring diagrams to
(junction lighting, distribution boards and all wiring equipment. sizing calculations. allow connection to panels by
OLE switches, downstream of the circuit 3. Discrimination study for HRS02.
points motors, breaker in the main board. electrical system. 2. Factory and site test results
points heating for switchgear.
and a signalling
REB-equivalent
domestic load)
MWCC HSR02 EL-LV-IF- Space for 1. Provide space in LV room A and LV Room 1. HRS02 shall install distribution Comply with detailed requirements 1. Space for board shown and 1. Layouts of cable - -
013 trackside B for Trackside electrical sub main board. provided in Technical Standard - co-ordinated with other containment routes between
electrical distribution board. 2. HRS02 shall install cable to Tunnel Ventilation and Technical services. board and cable containment
equipment sub main LV board and all Standard - Shaft and Portal Building to the tunnel.
main distribution downstream cabling. Electrical Services.
board
MWCC HSR02 EL-LV-IF- Cable 1. Provide cable containment between LV 1. HRS02 shall be constrained to Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
014 containment for Room A and B and the tunnel/trackway at the cable containment capacity provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
trackside the base of the shaft. provided by the MWCC. Tunnel Ventilation and Technical rooms indicating containment maximum size and weight containment for HRS02 later installation of HRS02
electrical 2. HRS02 installs all downstream Standard - Shaft and Portal Building size and co-ordinated with capacity of the cable installation of cables. equipment.
equipment cabling. Electrical Services. other services. containment.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 56 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR02 EL-LV-IF- Emissions 1. In determining LV cable containment 1. HRS02 to install wiring only in - 1. Develop an EMC mitigation 1. Report describing EMC and - -
015 management layouts carry out emissions studies to cable containment provided by and management strategy. mitigations that have been
investigate and mitigate against the MWCC when outside of their 2. Make allowance for provided.
potential for electromagnetic emissions to own rooms. electromagnetic emissions
negatively affect other services. from the HRS02 plant and
2. In determining LV cable containment installation.
layouts carry out risk analyses in accordance
with the Control of Electromagnetic Fields at
Work regulations and mitigate against risks.
MWCC HSR02 EL-LV-IF- Remote tunnel 1. Provide sump pumps, sump pump control 1. Provide a permanent power - 1. Pump and load schedule. 1. Layout of permanent 1. Control panel/starter wiring 1. Site test results for MWCC’s
016 sumps and pumps panels/starters and a common header supply between the LV Boards A 2. Identification of pump services within cross passage. diagrams. tests of equipment from
discharge header, including earthing and and B at the shaft to the remote feeders on the electrical 2. Layout of cable 2. LV board diagrams. temporary power supply.
bonding of all MWCC installed equipment. sump with A supply and B supply single line diagrams. containment within shaft. 3. Pump selection
2. Accommodate the permanent power in alternate bores and including 3. Pump head sizing calculations.
supply feed for the remote pumps at the all permanent cabling. calculations.
nearest shaft and portal building with an A 2. Provide an auto transfer switch 4. Layout of pipe route from
feed from LV Board A and a B feed from LV in the cross passage and connect tunnel to final sump.
Board B. a single feed to the MWCC
3. Accommodate the A and B power feeds starter/control panel.
within the services risers to the point 3. Provide the permanent
connection to the permanent location pumped discharge main between
within each tunnel bore and provide cable the header in the remote cross
containment from the LV rooms to the passage and the sump at the
tunnel. portal or shaft.
4. Provide temporary power and discharge 4. Account for the permanent
pipework during construction works. cables and pipes when
5. Size pump head based on a 200mm determining the cable
nominal bore ductile iron pipe within the containment and services risers
tunnel. for HRS02.
6. Provide a pipe route from the tunnel to 5. Connect the control and
the sump at the portal or shaft that the monitoring system between the
remote sump is designated to pump into. pump control panel and the
7. Size the sump and portal or shaft to tunnel SCADA system.
accommodate the flow from the remote 6. Test the permanent system
sump. and set the system to work.
8. Test the permanent pumps and control
panel using temporary supplies and provide
the testing procedure to HRS02.
9. Provide information to HRS02 to allow
them to provide the permanent power
supplies and discharge main.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 57 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR02 EL-LV-IF- Remote open 1. Provide sump pumps, sump pump control 1. Provide a permanent power - 1. Pump and load schedule. - 1. Control panel/starter wiring 1. Site test results for MWCC’s
017 route sumps and panels/starters for remote sumps and supply cabling and containment diagrams. tests of equipment from
pumps terminate within an equipment cubicle. between the low voltage 2. Testing procedures. temporary power supply.
2. Provide all temporary and permanent distribution point provided by
pipework associated with the sumps. HRS03 and the pump control
3. Provide earthing and bonding of the panel provided by MWCC.
permanent works installed by the MWCC. 2. Provide earthing and bonding
4. Advise HRS02 and HRS03 of the of the permanent works installed
permanent power supply requirements for by the HRS02.
the pumps. 3. Re-test the system using the
5. Provide all power supplies required for permanent power supply based
temporary operation of the sumps during on the testing procedure issued
construction and permanent supplies if this by the MWCC.
aligns with the HS2 electrical supply
strategy..
6. Test and prove the system using
temporary power supplies prior to
connection of the permanent power supply
by HRS02 and provide the testing procedure
to HRS02.

22.5 Non-traction HV Power


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme Design Stage Gate Detailed Design stage Gate For Construction and Testing, Commissioning,
Manufacture Stage Gate Operation and Maintenance
Stage Gate
MWCC HSR03 EL-HV-IF- HV Incoming 1. Provide an HV incoming switchgear room. 1. HRS03 shall be constrained by See Technical Standard - Shaft and 1. Layout of rooms showing 1. Evidence of co-ordination 1. Details of drilling 1. Fully functioning HVAC
001 Room 2. Undertake preliminary arrangement of the room sizes provided by the Portal Building Electrical Services equipment arrangement. with cable containment points/connection points system prior to HRS03
the room to layout switchgear and control MWCC. for equipment sizes. 2. Proposals of process for routes within the room. where HRS03 may connect to equipment installation.
equipment. 2. HRS03 shall undertake final equipment removal. for their primary switch gear
3. Co-ordinate room layout with cable arrangement of the room layout supports.
troughs and cable containment. and provide all HV equipment
4. Indicate need for podiums within rooms and monitoring.
where bottom entry cabling not practicable. 3. HRS03 shall provide any
5. Provide a level floor (maximum +/-3mm concrete bases or plinths
deviation). required for switchgear.
4. HRS03 shall provide any
podiums, gantries or secondary
support steelwork.
5. HRS03 shall provide all HV
switchgear and control.

MWCC HSR03 EL-HV-IF- Power supply to 1. Provide a 400/3/50 UPS backed essential 1. HRS03 shall be constrained by - 1. Electrical schematic 1. Layouts of room including 1. Details of circuit breaker 1. Adjustments to any breaker
002 HV incoming power supply from a 32A main breaker to the power supply provided by showing provision of power fuse switch location. types, curves, settings and settings following finalisation
switchgear each HV incoming room. the MWCC. supply. 2. Layout of switchgear setting methodology and of HRS03 design.
2. Terminate at a fuse switch within the 2. HRS03 shall provide all LV indicating provision of circuit panel wiring diagrams to
room. electrical power supplies and breakers for power feed. allow connection to panels by
containment downstream of the 3. Cable and circuit breaker HRS03.
fuse switch. sizing calculations. 2. Factory and site test results
4. Discrimination study for for switchgear.
electrical system.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 58 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme Design Stage Gate Detailed Design stage Gate For Construction and Testing, Commissioning,
Manufacture Stage Gate Operation and Maintenance
Stage Gate
MWCC HSR03 EL-HV-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS03 shall be constrained by Comply with detailed requirements 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
003 capacity for HV duration to serve the HV Incoming Room the UPS and battery capacity provided in Technical Standard - capacity within battery sizing indicating provision of circuit simulated load to prove
incoming room cited. Shaft and Portal Building Electrical calculations. breakers for power feeds. capacity.
services 2. Cable and circuit breaker
sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR03 EL-HV-IF- Communications 1. Provide a communications link within 1. HRS03 shall connect to Comply with detailed requirements 1. Indication of comms point 1. Cable route evident in the 1. Location of comms link on 1. Test results demonstrating
004 each incoming HV room for the HV power’s installed communications point provided in Technical Standard - of presence within the room. design. the patch panel. cable continuity and integrity.
SCADA system to connect to the HS2 and co-ordinate with HRS04 for Shaft and Portal Building
Communications Room. establishment of line wide Communications and Building
comms back to NICC. Management Systems.

MWCC HSR03 EL-HV-IF- Incoming power 1. Provide static and dynamic load 1. HRS03shall provide the Comply with detailed requirements 1. Electrical schematics. - 1. Certification that system is 1. Adjustments of calculations
005 supply A and B calculations for each location. transformers and all upstream provided in Technical Standard - 2. Load calculations. safe to energise prior to and breaker settings as HRS03
2. Provide level floor with a deviation of HV works. Shaft and Portal Building Electrical connection of HV loads. design matures.
maximum +/-5mm. 2. HRS03 shall provide and test services
3. Connect to the low voltage side of the HV cable and containment
transformer and provide downstream low between the transformer and HV
voltage electrical systems. switchgear and the transformer
4. Provide an earthing system for the shaft earth.
and transformers to connect to. 3. HRS03 shall set the HV system
5. Certification that downstream system is to work.
safe to energise.
6. Provide LV protection settings/breaker
ratings to allow HRS03 to coordinate with.

MWCC HSR03 EL-HV-IF- Cable 1. Provide cable containment from 1. HRS03 shall install and test Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
006 containment immediately within the HV Incoming Room wiring on cable containment provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
A and within the Upline tunnel bore for a provided by MWCC. Shaft and Portal Building Electrical rooms indicating containment maximum size and weight containment for HRS03 later installation of HRS03
distance of 2m within the tunnel or porous 2. HRS03 shall be constrained to Services. size and co-ordinated with capacity of the cable installation of cables. equipment.
portal. the cable containment capacity other services. containment.
2. Provide cable containment from provided by the MWCC.
immediately within the HV Incoming Room 3. Rail Systems Contractor
B and within the Downline tunnel bore or connects to the cable
porous portal for a distance of 2m. containment within the tunnel.
3. Provide diverse routes where practicable
otherwise provide two-hour fire separation
between routes.
MWCC HSR03 EL-HV-IF- Cable trenches 1. Provide a cable trough beneath the HV 1. HRSO3 shall install and test Comply with detailed requirements 1. Layouts of cable trough 1. Calculations of trough size 1. Demonstration of -
007 incoming HV rooms and the cable wiring in cable containment provided in Technical Standard - routes indicating size and co- clearly indicating maximum accessibility of cable
containment serving the tunnel. provided by MWCC. Shaft and Portal Building Electrical ordinated with other services. size and weight capacity of containment for HRS03 later
2. Provide all necessary drainage and cover 2. HRS03 shall be constrained to Services. the trough. installation of cables.
plates for the cable trough. the cable containment capacity 2. Details of proposed cable
3. Provide diverse routes where practicable provided by the MWCC. brackets and fixing method.
otherwise provide two-hour fire separation 3. HRS03 shall install all cable 3. Details of trough lids and
between routes. support brackets within the drainage methods.
trough.
MWCC HSR03 EL-HV-IF- Emissions 1. In determining HV cable containment 1. HRS03 shall install wiring only Comply with detailed requirements 1. Separation of HV cable 1. Report describing EMC and - -
008 management layouts carry out emissions studies to in cable containment provided by provided in Technical Standard - routes from other services. mitigations that have been
investigate and mitigate against the MWCC when outside of their Shaft and Portal Building LV provided.
potential for electromagnetic emissions to own rooms. Electrical Services.
negatively affect other services.
2. In determining HV cable containment
layouts carry out risk analyses in accordance
with the Control of Electromagnetic Fields at
Work regulations and mitigate against risks.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 59 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme Design Stage Gate Detailed Design stage Gate For Construction and Testing, Commissioning,
Manufacture Stage Gate Operation and Maintenance
Stage Gate
MWCC HSR03 EL-HV-IF- Pressure relief 1. Provide pressure relief from the incoming - - 1. Calculations of vent size - 1. Functional tests of the
009 switchgear rooms to prevent room and evidence of vent on vents.
structural failure in the event of sudden drawings.
release of switchgear insulating gasses.

MWCC HSR03 EL-HV-IF- Heat emissions 1. Provide ventilation to manage the heat HSR03 shall be constrained to the See Technical Standard - Shaft and 1. Calculations of vent - 1. Functional tests of the
010 dissipated from the switchgear in TPSI maximum heat emissions Portal Building HVAC for heat requirements and evidence of ventilation system.
Rooms. allowed for by the MWCC. emissions vent on drawings.

MWCC HSR03 EL-HV-IF- Heat emissions 1. Provide ventilation to manage the heat HSR03 shall be constrained to the See Technical Standard - Shaft and 1. Calculations of vent - 1. Functional tests of the
011 dissipated from the switchgear in Incoming maximum heat emissions Portal Building HVAC for heat requirements and evidence of ventilation system.
HV Rooms. allowed for by the MWCC. emissions vent on drawings.

MWCC HSR03 EL-HV-IF- Acoustics 1. Undertake an acoustic analysis of the 1. HRS03 shall provide Transformer requirements are cited 1.Preliminary calculations of 1. Detailed acoustic 1. Verification that the noise
012 noise breakout from the transformers. transformer noise emission levels within Technical Standard - Shaft noise emission’s and control calculations using transformer emitted in service is within
2. Provide acoustic insulation within the to the MWCC. and Portal Building Electrical measures using typical data which are accepted by criteria.
room and at the louvres to mitigate the 2. HRS03 shall take all practicable Services catalogue data. the local authorities.
noise to a level acceptable to the local measures to minimise noise
authorities. emitted from the transformers.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 60 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

22.6 Communications & CCS


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning and
manufacture stage gate operation stage gate
MWCC HRS04 RC-CW- Power supplies 1. Provide a distribution board within each 1. HRS04 & HRS05 shall constrain Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
IF-001 for MNOs, comms MNO room. the power demand of their provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
& CCS – Portal system to that advised to the Tunnel Ventilation and Technical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS04 & HRS05 designs.
buildings for short MWCC. Standard - Shaft and Portal Building showing provision of 2. Cable and circuit breaker panel wiring diagrams to
tunnels 2. HRS04 & HRS05 shall provide Electrical Services. equipment. sizing calculations. allow connection to panels by
all cabling downstream of the 3. Discrimination study for HRS04.
fuse switch. electrical system. 2. Factory and site test results
for switchgear.
MWCC HRS04 RC-CW- Essential MCCB 1. Provide an essential MCCB panel within 1. HRS04 & HRS05 shall constrain Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
IF-002 panel for HS2 the Communications & CCS Room. the power demand of their provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
Comms & CCS 2. Provide circuit breakers within the MCCB system to that advised to the Tunnel Ventilation and Technical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS04 & HRS05 designs.
panel for the connection of HRS04 loads. MWCC. Standard - Shaft and Portal Building showing provision of 2. Cable and circuit breaker panel wiring diagrams to
2. HRS04 & HRS05 shall provide Electrical Services. equipment. sizing calculations. allow connection to panels by
all cabling downstream of circuit 3. Discrimination study for HRS04 & HRS05.
breakers. electrical system. 2. Factory and site test results
for switchgear.
MWCC HRS04 RC-CW- Power supplies 1. Provide a distribution board fed from a 1. HRS04 & HRS05 shall constrain Comply with detailed requirements 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any breaker
IF-102 for HS2 comms & 32A TPN supply within each of the two HS2 the power demand of their provided in Technical Standard - equipment arrangement. indicating provision of circuit types, curves, settings and settings following finalisation
CCS – Portal portal comms & CCS rooms and fed from system to that advised to the Tunnel Ventilation and Technical 2. Electrical schematic breakers for power feeds. setting methodology and of HRS04 & HRS05 designs.
buildings for short the essential board. MWCC. Standard - Shaft and Portal Building showing provision of 2. Cable and circuit breaker panel wiring diagrams to
tunnels 2. HRS04 & HRS05 shall provide Electrical Services. equipment. sizing calculations. allow connection to panels by
all cabling downstream of the 3. Discrimination study for HRS04 & HRS05.
fuse switch. electrical system. 2. Factory and site test results
for switchgear.
MWCC HRS04 RC-CW- Cable 1. Provide cable containment from 1. HRS04 & HRS05 shall install Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
IF-003 containment for immediately within the Communications & and test wiring on cable provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
tunnel comms CCS and within the Upline and Downline containment provided by MWCC. Tunnel Ventilation and Technical rooms indicating containment maximum size and weight containment for HRS04 & installation of HRS04 & HRS05
(long tunnels) tunnel bores for a distance of 2m. 2. HRS04 & HRS05 shall be Standard - Shaft and Portal Building size and co-ordinated with capacity of the cable HRS05 later installation of Equipment.
constrained to the cable Electrical Services. other services. containment. cables.
containment capacity provided
by the MWCC.
3. HRS04 & HRS05 connects to
the cable containment within the
tunnel.
MWCC HRS04 RC-CW- Cable 1. Provide cable containment from 1. HRS04 & HRS05 shall install Comply with detailed requirements 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
IF-103 containment for immediately within the Communications & and test wiring on cable provided in Technical Standard - containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
tunnel comms CCS Room 1 and 2 to the Upline and containment provided by MWCC. Tunnel Ventilation and Technical rooms indicating containment maximum size and weight containment for HRS04 & installation of HRS04 & HRS05
(short tunnels) Downline tunnel bores for a distance of 2m 2. HRS04 & HRS05 shall be Standard - Shaft and Portal Building size and co-ordinated with capacity of the cable HRS05 later installation of equipment.
inside the porous portals. constrained to the cable Electrical Services. other services. containment. cables.
containment capacity provided
by the MWCC.
3. HRS04 & HRS05 shall connect
to the cable containment within
the tunnel.
MWCC HRS04 RC-CW- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS04 & HRS05 shall be Comply with detailed requirements 1. Evidence of battery - - 1. Discharge test with
IF-004 capacity for HS2 duration to serve the HS2 comms & CCS. constrained by the UPS and provided in Technical Standard - capacity within battery sizing simulated load to prove
comms & CCS battery capacity cited. Tunnel Ventilation and Technical calculations. capacity.
Standard - Shaft and Portal Building
Electrical Services.
MWCC HRS04 RC-CW- Cooling capacity 1. Provide cooling system to offset the heat 1. HRS04 & HRS05 equipment Comply with detailed requirements 1. Evidence of battery - - 1. Discharge test with
IF-005 for HS2 Comms & emissions from the HS2 comms & CCS. shall be constrained to the heat provided in Technical Standard - capacity within battery sizing simulated load to prove
CCS Room emissions from the MWCC Tunnel Ventilation and Technical calculations. capacity.
cooling system. Standard - Shaft and Portal Building
Electrical Services.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 61 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning and
manufacture stage gate operation stage gate
MWCC HRS04 RC-CW- Cooling capacity 1. Provide cooling system to offset the heat 1. HRS04 equipment shall be Comply with detailed requirements 1. Evidence of battery - - 1. Discharge test with
IF-006 for MNO Comms emissions from the HS2 comms. constrained to the heat provided in Technical Standard - capacity within battery sizing simulated load to prove
Room emissions from the MWCC Tunnel Ventilation and Technical calculations. capacity.
cooling system. Standard - Shaft and Portal Building
Electrical Services.

MWCC HRS04 RC-CW- BMS Interface 1. Provide an interface with the BMS system 1. HRS04 shall allocate IP Comply with detailed requirements 1. Evidence of the interface 1. Points lists and design 1. Test reports showing -
IF-007 to allow the NICC to read and write data. addresses in a network co- provided in Technical Standard - equipment in systems values for all monitored providing of variables within
2. Coordinate with the HRS04 to integrate ordination function. Tunnel Ventilation and Technical Architecture Diagrams. equipment. the interface database.
the communications back to NICC. 2. HRS04 shall jointly test the Standard - Shaft and Portal Building 2. Description of proposed 2. Detailed specification and 2. Integrated test report for
data transfer between the Communications and Building interface and data structure. description of the interface end to end testing at NICC.
location and the NICC. Management Systems. and database structure.

MWCC HRS04 RC-CW- Building LAN 1. Provide a Building LAN to facilitate voice 1. HRS04 shall provide routers to Comply with detailed requirements 1. Schematic proposal for 1. Locations of 1. Functional test reports.
IF-008 communications within the shaft. make the LAN active, configure provided in Technical Standard - LAN. communications points in
the LAN and integrate with the Tunnel Ventilation and Technical 2. Description of the design rooms evident on drawings.
HS2 IP WAN. Standard - Shaft and Portal Building basis for the Building LAN.
Communications and Building
Management Systems.
MWCC HRS04 RC-CW- Security LAN 1. Design a security system. 1. HRS04 shall configure the Comply with detailed requirements 1. Schematic proposal of 1. Locations of proposed 1. Functional test reports.
IF-009 2. Provide and install a Security LAN to Security LAN and connect to the provided in Technical Standard - Security system. security equipment shown on
facilitate connection of field devices to the HS2 IP WAN. Tunnel Ventilation and Technical 2. Design statement drawings.
LAN. 2. If instructed to HRS04 shall Standard - Shaft and Portal Building demonstrating compliance 2. Locations and routing of
3. Provide space within the Electrical install, test and commission the Communications and Building with HS2’s Security standard. LAN clearly evident on the
Services Room for security equipment. security systems. Management Systems. design drawings.
4. If instructed, install, test and commission
free-issue security systems.

MWCC HRS05 RC-CW- Radiating cable in 1.Provide spacial allowance with adequate 1. HRS04 shall provide detailed Cable specification to be advised by 1. Evidence of spacial 1.Detailed design 1. Testing and handover
IF-010 shafts coverage for radiating cable. radiated cable specification HRS04 / HS2. allowance and sufficient documentation including documentation.
2.Integrate physical installation within 2. HRS04 shall carry system wide coverage. spatial allowance, coverage
building works including fixings and commissioning. and cable specification.
penetrations
3.Install and local testing of radiating cable

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 62 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

22.7 Traction Power


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR03 RE-OH-IF- TPSI 1. Provide adequate spatial provision for the 1. HRS03 shall be constrained by the Comply with detailed 1. Layout of rooms showing 1. Details of drilling -
001 TPSI at ventilation and intervention shafts room sizes provided by the MWCC. requirements provided in equipment arrangement. points/connection points
and intervention only shafts. 2. HRS03 shall undertake final Shaft and Portal Building 2. Evidence of co-ordination where HRS03 may connect to
2. Undertake preliminary arrangement of arrangement of the room layout and Electrical Services. with cable containment for their primary switch gear
the room to layout switchgear and control provide all HV equipment and routes. supports.
equipment. monitoring. 3. Proposed process for
3. Co-ordinate room layout with cable 3. HRS03 shall provide any concrete equipment removal.
containment. bases or plinths required for
4. Indicate need for podiums within rooms switchgear.
where bottom entry cabling not practicable. 4. HRS03 shall provide any podiums,
gantries or secondary support
steelwork.
5. HRS03 shall provide all HV switchgear
and control.

MWCC HSR03 RE-OH-IF- Power supply to 1. Provide a 400/3/50 UPS backed essential 1. HRS03 shall be constrained by the Comply with detailed 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any
002 TPSI Switchgear power supply from a 32A main breaker to power supply provided by the MWCC. requirements provided in equipment arrangement. indicating provision of circuit types, curves, settings and breaker settings following
each HV incoming room. 2. HRS03 shall provide all LV electrical Technical Standard – Shaft 2. Electrical schematic breakers for power feeds. setting methodology and panel finalisation of HRS03 design.
2. Terminate at a fuse switch within the power supplies and containment and Portal Building Electrical showing provision of 2. Cable and circuit breaker wiring diagrams to allow
room. downstream of the fuse switch. Services equipment. sizing calculations. connection to panels by HRS03.
3. Discrimination study for 2. Factory and site test results
electrical system. for switchgear.
MWCC HSR03 RE-OH-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS03 shall be constrained by the Comply with detailed 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
002a capacity for TPSI duration to serve the TPSI Room UPS and battery capacity cited. requirements provided in capacity within battery sizing indicating provision of circuit simulated load to prove
Switchgear Technical Standard - Shaft calculations. breakers for power feeds. capacity.
and Portal Building Electrical 2. Cable and circuit breaker
services sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR03 RE-OH-IF- Communications 1. Provide a communications point between 1. HRS03 shall connect to installed Comply with detailed 1. Indication of comms point 1. Cable route evident in the 1. Location of comms link on 1. Test results demonstrating
003 the TPSI and the HS2 Communications communications point and co-ordinate requirements provided in of presence within the room. design. the patch panel. cable continuity and
Room and at AT locations between the TPSI with HRS04 for establishment of line Technical Standard - Shaft integrity.
and the AT Auxiliary and control switch wide comms back to NICC. and Portal Building
room and between the AT Auxiliary and Communications and
control switch room and the HS2 Building Management
communications room. Systems.

MWCC HSR03 RE-OH-IF- Cable 1. Provide cable containment from 1. HRS03 shall install and test wiring on Comply with detailed 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
004 containment immediately within the TPSI to both the cable containment provided by MWCC. requirements provided in containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
Upline and Downline tunnel bore for a 2. HRS03 shall be constrained to the Technical Standard - Shaft rooms indicating maximum size and weight containment for HRS03 later installation of HRS03
distance of 2m within the tunnel. cable containment capacity provided by and Portal Building Electrical containment size and co- capacity of the cable installation of cables. equipment.
2. Provide cable containment from the MWCC. Services. ordinated with other containment.
immediately within the TPSI to within the AT 3. HRS03 shall connect to the cable services.
Switchgear room. containment within the tunnel.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 63 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR03 RE-OH-IF- Emissions 1. In determining HV cable containment 1. HRS03 shall install wiring only in Comply with detailed 1. Separation of HV cable 1. Report describing EMC and -
005 management layouts carry out emissions studies to cable containment provided by MWCC requirements provided in routes from other services. mitigations that have been
investigate and mitigate against the when outside of their own rooms. Technical Standard - Shaft provided.
potential for electromagnetic emissions to and Portal Building Electrical
negatively affect other services. Services.
2. In determining HV cable containment
layouts carry out risk analyses in accordance
with the Control of Electromagnetic Fields at
Work regulations and mitigate against risks.
MWCC HSR03 RE-OH-IF- Pressure relief 1. Provide pressure relief from the TPSI and - - - 1. Calculations of vent size and - 1. Functional tests of the
006 from the AT Switchgear room to prevent evidence of vent on drawings. vents.
room structural failure in the event of
sudden release of switchgear insulating
gasses.

MWCC HSR03 RE-OH-IF- Mimic panels 1. Provide space at the upper and lower fire 1. HRS03 shall provide and set to work Comply with detailed -
007 fighting point for mimic panels associated the panels. requirements provided in
with the operation of the traction power Technical Standard - Shaft
system. Allow 1.2m high x 0.6m wide x 0.3m and Portal Building Electrical
deep. Services and Shaft and Portal
2. Provide a 230/1/50 power supply to each Building Communications
panel. and Building Management
3. Provide communications at each panel Systems.
back to the TPSI.

MWCC HSR03 RE-OH-IF- Power supply to 1. Provide for each bore a 230/1/50 UPS 1. HRS03 shall be constrained by the Comply with detailed 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any
008 outside catenary backed essential power supply with a 32A power supply provided by the MWCC. requirements provided in equipment arrangement. indicating provision of circuit types, curves, settings and breaker settings following
switches at main breaker to serve outside catenary. 2. HRS03 shall provide all LV electrical Technical Standard – Shaft 2. Electrical schematic breakers for power feeds. setting methodology and panel finalisation of HRS03 design.
Portals only. 2.Leave as breakers within the UPS board. power supplies and containment and Portal Building Electrical showing provision of 2. Cable and circuit breaker wiring diagrams to allow
downstream of the breaker. Services equipment. sizing calculations. connection to panels by HRS03.
3. Discrimination study for 2. Factory and site test results
electrical system. for switchgear.
MWCC HSR03 RE-OH-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS03 shall be constrained by the Comply with detailed 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
009 capacity for duration to serve the TPSI Room UPS and battery capacity cited. requirements provided in capacity within battery sizing indicating provision of circuit simulated load to prove
outside catenary Technical Standard - Shaft calculations. breakers for power feeds. capacity.
switches and Portal Building Electrical 2. Cable and circuit breaker
services sizing calculations.
3. Discrimination study for
circuits downstream of UPS.
MWCC HSR03 RE-OH-IF- Power supply to 1. Provide a 400/3/50 UPS backed essential 1. HRS03 shall be constrained by the Comply with detailed 1. Layout of rooms showing 1. Layout of switchgear 1. Details of circuit breaker 1. Adjustments to any
010 AT auxiliary and power supply from a 32A main breaker to power supply provided by the MWCC. requirements provided in equipment arrangement. indicating provision of circuit types, curves, settings and breaker settings following
control switch the AT auxiliary and control switch room. 2. HRS03 shall provide all LV electrical Technical Standard – Shaft 2. Electrical schematic breakers for power feeds. setting methodology and panel finalisation of HRS03 design.
room 2. Terminate at a fuse switch within the power supplies and containment and Portal Building Electrical showing provision of 2. Cable and circuit breaker wiring diagrams to allow
room. downstream of the fuse switch. Services equipment. sizing calculations. connection to panels by HRS03.
3. Discrimination study for 2. Factory and site test results
electrical system. for switchgear.
MWCC HSR03 RE-OH-IF- UPS and battery 1. Provide battery capacity for 90 minutes 1. HRS03 shall be constrained by the Comply with detailed 1. Evidence of battery 1. Layout of UPS and batteries - 1. Discharge test with
011 capacity for to AT duration to serve the TPSI Room UPS and battery capacity cited. requirements provided in capacity within battery sizing indicating provision of circuit simulated load to prove
auxiliary and Technical Standard - Shaft calculations. breakers for power feeds. capacity.
control switch and Portal Building Electrical 2. Cable and circuit breaker
room services sizing calculations.
3. Discrimination study for
circuits downstream of UPS.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 64 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR03 RE-OH-IF- Auto 1. Provide AT space as per Room Data 1. HRS03 shall be constrained by the - 1. Layout of rooms showing - 1. Details of drilling -
012 Transformers Sheets. room sizes provided by the MWCC. equipment arrangement. points/connection points
2. Undertake preliminary arrangement of 2. HRS03 shall undertake final 2. Evidence of co-ordination where HRS03 may connect to
the room to layout the transformers. arrangement of the room layout and with cable containment for their primary switch gear
3. Provide a flat and level base capable of provide all HV equipment and routes. supports.
supporting a mass of 25 tonnes per monitoring. 3. Proposed process for
transformer distributed over an area of 3. HRS03 shall provide any concrete equipment removal.
between 1.5 and 2 square metres. bases or plinths required for switchgear
4.Provide a 0.6 x 0.6 x 0.4m deep sump in and connect these to the primary slab.
one corner and connect the sump to the 4. HRS03 shall provide bunding walls,
shaft/site drainage system. Grade the podiums, gantries or secondary support
remainder of the compound to fall towards or access steelwork.
the sump. 5. HRS03 shall provide all HV switchgear
5. Provide any architectural screening and control.
required to fulfil aesthetic requirements 6. HRS03 shall provide and installs oil
related to the shaft appearance. All such interceptor.
screening shall have a free area for 7. HRS03 shall provide any non-
ventilation of not less than 50% and shall be architectural/decorative screening and
open at the top. An easily removable panel mesh.
shall be provided within the screening for
transformer removal, along with a lockable
worker access door.
MWCC HSR03 RE-OH-IF- AT Switch Gear 1. Provide adequate spatial provision for 1. HRS03 shall be constrained by the 1. Layout of rooms showing 1. Layout of rooms showing - 1. Details of drilling -
013 Rooms Autotransformers feeding switchgear at room sizes provided by the MWCC. equipment arrangement. equipment arrangement. points/connection points
ventilation and intervention shafts and 2. HRS03 shall undertake final 2. Evidence of co-ordination 2. Evidence of co-ordination where HRS03 may connect to
intervention only shafts and fire fighting arrangement of the room layout and with cable containment with cable containment for their primary switch gear
points. provide all HV equipment and routes. routes. supports.
2. Undertake preliminary arrangement of monitoring. 3. Proposed process for 3. Proposed process for
the room to layout switchgear and control 3. HRS03 shall provide any concrete equipment removal. equipment removal.
equipment. bases or plinths required for
3. Co-ordinate room layout with cable switchgear.
containment. 4. HRS03 shall provide any podiums,
4. Indicate need for podiums within rooms gantries or secondary support
where bottom entry cabling not practicable. steelwork.
5. HRS03 shall provide all HV switchgear
and control.

MWCC HSR03 RE-OH-IF- AT Auxiliary and 1. Provide adequate spatial provision for 1. HRS03 shall be constrained by the 1. Proposed process for 1. Proposed process for - 1. Details of drilling -
014 Control Room Autotransformers switchgear and control room sizes provided by the MWCC. equipment removal. equipment removal. points/connection points
rooms at shafts and fire fighting points.. 2. HRS03 shall undertake final where HRS03 may connect to
arrangement of the room layout and for their primary switch gear
provide all equipment and monitoring. supports.
3. HRS03 shall provide any concrete
bases or plinths required for
switchgear.

MWCC RE-OH-IF- AT Cable 1. Provide cable containment from the 1. HRS03 shall install and test wiring on Comply with detailed 1. Layouts of cable 1. Calculations of containment 1. Demonstration of 1. Tests demonstrating
015 Containment Autotransformer Switchgear room to the cable containment provided by MWCC. requirements provided in containment routes between sizing clearly indicating accessibility of cable earthing continuity prior to
TPSI. 2. HRS03 shall be constrained to the Technical Standard - Shaft rooms indicating maximum size and weight containment for HRS03 later installation of HRS03
cable containment capacity provided by and Portal Building Electrical containment size and co- capacity of the cable installation of cables. equipment.
the MWCC. Services. ordinated with other containment.
3. HRS03 shall connect to the cable services.
containment within the tunnel.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 65 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction and Testing, commissioning,
manufacture stage gate operation and maintenance
stage gate
MWCC HSR03 RE-OH-IF- AT Cable 1. At Autotransformer sites provide a UTX in 1. HRS03 shall be constrained to the - 1. Layouts of cable - - -
016 Containment the form of 3 no. 150mm diameter ducts cable containment capacity provided by containment routes
between the tunnel wall and Stage 1 slab the MWCC. indicating containment size
passing through maintenance walkway. and co-ordinated with other
Locate the UTX approximately at the centre services.
line of the shaft within tunnel bore.

MWCC HSR03 EL-OH-IF- Acoustics 1. Undertake an acoustic analysis of the 1. HRS03 shall provide transformer Transformer requirements 1.Preliminary calculations of 1. Detailed acoustic 1. Verification that the noise
017 noise breakout from the transformers. noise emission levels to the MWCC. are cited within Technical noise emission’s and control calculations using transformer emitted in service is within
2. Provide acoustic insulation within the 2. HRS03 shall take all practicable Standard - Shaft and Portal measures using typical data which are accepted by the criteria.
room and at the louvres to mitigate the measures to minimise noise emitted Building Electrical Services catalogue data. local authorities.
noise to a level acceptable to the local from the transformers.
authorities.

MWCC HRS02/03 EL-OH-IF- Green Park Way 1. Provide structure and enabling works for 1. Provide fOCS arrangement, cabling To be confirmed with HS2 To be confirmed with HS2 To be confirmed with HS2
018 Express Feeder Green Park Way express feed and neutral and switchgear. Railway Systems Railway Systems Railway Systems
and Neutral section including allowance for OCS
Section arrangement, cabling and switchgear.

22.8 Fire systems


Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction stage gate Testing, commissioning,
operation and maintenance
stage gate
MWCC HSR08 ES-FS-IF- Fire fighting 1. Provide fire fighting points at the tunnel 1. Integrate the tunnel fire Comply with detailed requirements 1. Description of facilities in 1. Evidence of agreement with - -
001 points portals. strategies with the specific provided in Technical Standard - fire strategy. proposals via QDR process.
provisions made at each fire Shaft and Portal Building Fire 2. Evidence of facilities in
fighting point. Engineering. design drawings.

MWCC HSR08 ES-FS-IF- Fire fighter access 1. Provide fire fighter access provisions at 1. Integrate the tunnel fire Comply with detailed requirements 1. Description of facilities in 1. Evidence of agreement with - -
002 at shafts ventilation and intervention shafts and strategies with the specific provided in Technical Standard - fire strategy. proposals via QDR process.
intervention only shafts. provisions made at each fire Shaft and Portal Building Fire 2. Evidence of facilities in
shaft. Engineering. design drawings.

MWCC HSR02 ES-FS-IF- Tunnel fire 1. Provide and test complete tunnel fire 1. Install the hydrant system - 1. Evidence of pipework 1. Details of Rail Systems 1. Test certificates conforming
003 hydrant mains hydrant mains, including breaching inlet within the tunnel connecting to within the design connection points. pipework pressure tests.
points, between the ground level of the fire the MWCC connections. 2. Evidence of co-ordination
fighting point or shafts and the tunnel 2. Provide thrust restraints to of hydrant mains with other
bores. transfer no movement of thrust services.
loads onto the MWCC
connections.
MWCC HSR02 ES-FS-IF- Communications 1. Provide fixed telecoms link to NICC at the 1. Integrate the telecoms with - 1. Evidence within design. - 1. Fixed telephone within 1. Functional tests of comms
004 with NICC ground and track level fire fighting points the NICC control desks for lobbies. links
and within any refuge areas. ventilation and power.
2. The TS SCADA shall interface with the fire 2. Test system end to end.
alarm control panel at the shafts and portal
buildings to provide a signal to activate the
fire alarms at the shafts where the tunnel
ventilation system is active, to indicate that
there is a tunnel emergency.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 66 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Interface Rail Systems Interface Description MWCC Responsibility Rail Systems Responsibility Further design requirements Specific evidence required over and above general deliverables. Note, evidence from preceding stage must be carried forward to
between Discipline number next stage also.
Scheme design stage gate Detailed design stage gate For construction stage gate Testing, commissioning,
operation and maintenance
stage gate
MWCC HSR02, ES-FS-IF- Fire stopping 1. Provide primary sealing of openings to 1. Provide the final fire stopping - - - 1. Evidence of fire stopping
HRS03, 005 within 100mm around any Rail Systems between the MWCC fire stopping to within 100mm of Rail
HRS04, penetrations and openings. within 100mm of the Rail Systems equipment.
depending on Systems equipment and the final 2. Technical descriptions of
the installer Rail Systems installation. fire stopping system adopted
of the to allow Rail Systems to offer
services in a compatible system.
the
penetration.
For multiple
services,
HRS02.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 67 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

23 Appendix D – HV Feeding Arrangement and Room Sizes

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 68 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 69 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 70 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 71 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 72 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 73 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 74 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 75 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

24 Appendix E – Tunnel Pressure Cycles


24.1 General
24.1.1 The interpretation of peak to peak pressure changes for the short tunnels, an in particular
where both tunnel bores are separated by a single door, are affected by time interval over
which the data is analysed.

24.1.2 Table 1 shows the predicted annual number pressure cycles between tunnel bores in a given
pressure range.
Table 1 – Pressure cycles

From/to (kPa) Short Tunnels (long Short Tunnels (short Long (> 5 km) Bored
duration peak to peak) duration peak to peak) Tunnels

3 to 4 - 63,186
4 to 5 - - 27,740
5 to 6 16,951 18,493 33,904
6 to 7 32,361 27,740 61,644
7 to 8 78,591 43,619 10,788
8 to 9 78,591 72,701 16,952
9 to 10 4,623 11,011 0
10 to 11 4,623 0 24,658
11 to 12 24,656 0 4,623
12 to 13 98,624 179,351 4,623
13 to 14 20,033 33,904 20,034
14 to 15 7,705 12,328 4,623
15 to 16 1,541 0 1,541
16 to 17 7,705 12,328 -
17 to 18 3,082 9,246 -
18 to 19 0 -
19 to 20 0 -
20 to 21 1,541 -
21 to 22 1,541 -
22 to 23 1,541 -
23 to 24 1,541 -

24.1.3 The data for the short tunnels in Table 1 has been post processed over two time intervals.
Figure 1 illustrates the time intervals and the impacts on the peak to peak pressure cycles. For
the magenta pressure trace a tunnel to tunnel peak to peak pressure cycle of 17 kPA is
predicted with a positive peak of approximately +11 kPA pressure differential across the door
and a negative peak of -6 kPA pressure differential. The interval between these two peaks is
influenced by the train separation within each tunnel bore. This has been referred to as a
‘short’ duration peak to peak in Table 2.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 76 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

24.1.4 At the next train passage (blue pressure trace) 180 seconds later it is possible that the exact
opposite train passing pattern may occur which would result in a positive peak of 6 kPA and a
negative peak of -11 kPa. Again, the predicted peak to peak pressure cycle is 17 kPa.

24.1.5 When the two 180 second periods are taken together the total pressure change would be from
+11 to -11 giving a peak to peak pressure cycle of 22 kPa. Such cycles are termed ‘long’
duration cycles in Table 1. The Contractor must determine which cycle represents the
appropriate case in undertaking any fatigue calculations.

24.1.6 Table 2 and Table 3 contain a time series of predicted pressure changes over a 4.5 hour period
of randomly-ordered train operations. Minor pressure changes have been removed to provide
a filtered list of pressure changes of significant peak to peak variations.

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 77 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Figure 1 – Example of pressure cycles

Table 2 – Pressure history data points – short tunnels

Point Pressure Point Pressure Point Pressure Point Pressure


(Pa) (Pa) (Pa) (Pa)
1 0 132 -6,049 263 6,049 394 -1,961
2 -6,047 133 1,961 264 -1,760 395 5,451
3 6,049 134 -6,427 265 5,639 396 -5,725
4 -1,961 135 6,353 266 -6,550 397 1,784
5 6,006 136 -6,047 267 6,047 398 -6,047
6 -5,898 137 11,554 268 -6,049 399 6,049
7 6,047 138 -5,629 269 1,961 400 -1,961
8 -6,049 139 2,783 270 -7,532 401 7,343
9 1,961 140 -4,469 271 6,958 402 -7,197
10 -6,054 141 3,336 272 -1,547 403 6,047
11 5,922 142 -2,671 273 3,762 404 -6,049
12 -2,228 143 6,047 274 -6,047 405 1,961
13 6,047 144 -6,049 275 6,049 406 -6,524
14 -6,049 145 1,961 276 -1,961 407 6,464
15 1,961 146 -6,881 277 5,437 408 -6,047
16 -5,809 147 6,809 278 -5,400 409 6,049
17 6,266 148 -6,047 279 2,469 410 -1,961
18 -1,647 149 6,049 280 -6,047 411 6,736
19 6,047 150 -1,961 281 6,049 412 -6,609
20 -10,095 151 5,210 282 -1,961 413 6,047
21 4,559 152 -5,569 283 6,687 414 -6,049

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 78 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Point Pressure Point Pressure Point Pressure Point Pressure


(Pa) (Pa) (Pa) (Pa)
22 -2,075 153 4,816 284 -6,485 415 1,961
23 6,047 154 -8,198 285 6,047 416 -6,517
24 -6,049 155 4,186 286 -6,049 417 6,454
25 532 156 -2,064 287 1,961 418 -6,047
26 -5,665 157 6,047 288 -5,210 419 6,049
27 5,082 158 -6,049 289 5,569 420 -1,961
28 -6,047 159 1,961 290 -1,837 421 6,099
29 6,049 160 -5,778 291 6,014 422 -5,951
30 -1,961 161 5,716 292 -10,194 423 6,047
31 6,646 162 -6,047 293 6,582 424 -6,049
32 -6,590 163 6,049 294 -2,528 425 6,915
33 6,047 164 -1,961 295 4,749 426 -6,047
34 -6,049 165 5,662 296 -3,327 427 6,049
35 1,961 166 -5,641 297 6,047 428 -1,961
36 -5,604 167 6,047 298 -6,049 429 6,881
37 5,537 168 -6,049 299 1,811 430 -6,809
38 -2,274 169 1,961 300 -7,102 431 2,244
39 6,047 170 -4,857 301 6,927 432 -6,047
40 -6,049 171 5,343 302 -6,047 433 6,049
41 1,961 172 -4,816 303 6,049 434 -1,961
42 -6,338 173 8,198 304 -1,811 435 6,507
43 6,384 174 -4,186 305 7,102 436 -6,346
44 -6,047 175 2,064 306 -6,927 437 2,279
45 6,049 176 -6,047 307 1,821 438 -6,047
46 -532 177 6,049 308 -6,047 439 11,213
47 7,616 178 -1,961 309 6,049 440 -6,417
48 -6,144 179 5,679 310 -6,915 441 3,378
49 1,610 180 -6,313 311 6,047 442 -4,662
50 -3,808 181 1,548 312 -6,049 443 3,440
51 2,770 182 -6,047 313 1,961 444 -6,047
52 -2,360 183 6,049 314 -5,613 445 6,049
53 6,047 184 -1,961 315 5,831 446 -1,961
54 -6,049 185 6,517 316 -6,047 447 4,857
55 1,961 186 -6,454 317 6,049 448 -5,343
56 -5,437 187 6,047 318 -1,961 449 1,912
57 5,400 188 -6,049 319 5,528 450 -6,047
58 -2,469 189 532 320 -6,378 451 11,309
59 6,047 190 -8,062 321 1,478 452 -5,303
60 -6,049 191 7,978 322 -6,047 453 3,464
61 1,760 192 -1,892 323 6,049 454 -2,598
62 -5,639 193 3,925 324 -1,961 455 6,047
63 6,550 194 -2,743 325 5,613 456 -6,049
64 -1,315 195 2,276 326 -5,831 457 1,961
65 6,047 196 -6,047 327 6,047 458 -6,236
66 -6,049 197 6,049 328 -6,049 459 6,331

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 79 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Point Pressure Point Pressure Point Pressure Point Pressure


(Pa) (Pa) (Pa) (Pa)
67 1,961 198 -1,961 329 1,961 460 -2,003
68 -5,451 199 5,778 330 -6,297 461 6,047
69 5,725 200 -5,716 331 5,936 462 -6,049
70 -6,047 201 6,047 332 -2,532 463 1,961
71 6,049 202 -6,049 333 6,047 464 -6,646
72 -1,961 203 1,961 334 -6,049 465 6,590
73 5,898 204 -5,898 335 1,961 466 -2,221
74 -6,191 205 6,191 336 -6,949 467 6,047
75 6,047 206 -1,725 337 6,671 468 -6,049
76 -6,049 207 6,047 338 -2,495 469 1,961
77 1,961 208 -11,213 339 6,047 470 -5,528
78 -5,679 209 6,417 340 -6,049 471 6,378
79 6,313 210 -3,378 341 1,961 472 -1,478
80 -1,548 211 4,662 342 -6,006 473 6,047
81 6,047 212 -3,440 343 5,898 474 -11,554
82 -6,049 213 2,764 344 -2,143 475 5,629
83 1,961 214 -6,014 345 6,047 476 -2,783
84 -6,736 215 10,194 346 -6,049 477 4,469
85 6,609 216 -6,582 347 1,961 478 -3,336
86 -6,047 217 2,528 348 -6,687 479 2,671
87 6,049 218 -4,749 349 6,485 480 -6,047
88 -532 219 3,327 350 -6,047 481 10,095
89 8,876 220 -6,047 351 6,049 482 -4,559
90 -7,669 221 6,049 352 -1,961 483 6,047
91 2,088 222 -1,961 353 6,236 484 -6,049
92 -4,076 223 6,524 354 -6,331 485 532
93 2,934 224 -6,464 355 2,003 486 -8,876
94 -2,458 225 6,047 356 -6,047 487 7,669
95 6,047 226 -6,049 357 6,049 488 -2,088
96 -6,049 227 1,961 358 -1,961 489 4,076
97 84 228 -6,507 359 5,809 490 -2,934
98 -6,953 229 6,346 360 -6,266 491 2,458
99 7,405 230 -6,047 361 1,647 492 -6,047
100 -1,791 231 6,049 362 -6,047 493 6,049
101 6,047 232 -84 363 6,049 494 -1,961
102 -6,049 233 6,953 364 -5,012 495 5,604
103 532 234 -7,405 365 1,997 496 -5,537
104 -7,616 235 6,047 366 -6,047 497 6,047
105 6,144 236 -11,309 367 6,049 498 -6,049
106 -1,610 237 5,303 368 -532 499 1,961
107 3,808 238 -3,464 369 8,062 500 -5,662
108 -2,770 239 6,047 370 -7,978 501 5,641
109 2,360 240 -6,049 371 1,892 502 -220
110 -6,047 241 1,961 372 -3,925
111 6,049 242 -7,343 373 2,743

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 80 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Point Pressure Point Pressure Point Pressure Point Pressure


(Pa) (Pa) (Pa) (Pa)
112 -1,961 243 7,197 374 -6,047
113 6,297 244 -6,047 375 6,049
114 -5,936 245 6,049 376 -1,961
115 2,532 246 -1,961 377 6,427
116 -6,047 247 6,376 378 -6,353
117 6,049 248 -6,243 379 6,047
118 -532 249 2,216 380 -6,049
119 5,665 250 -6,047 381 1,961
120 -5,082 251 6,049 382 -6,099
121 2,813 252 -1,961 383 5,951
122 -6,047 253 6,949 384 -6,047
123 6,049 254 -6,671 385 6,049
124 -1,961 255 2,495 386 -1,961
125 6,054 256 -6,047 387 7,532
126 -5,922 257 6,049 388 -6,958
127 6,047 258 -1,961 389 1,547
128 -6,049 259 6,338 390 -3,762
129 5,012 260 -6,384 391 2,667
130 -1,997 261 1,974 392 -6,047
131 6,047 262 -6,047 393 6,049

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 81 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Table 3 - Pressure history data points – long tunnels

Pressure Pressure Pressure Pressure


Point Point Point Point
(Pa) (Pa) (Pa) (Pa)
1 0 166 2,675 332 0 496 0
2 2,452 167 -1,978 333 -3,608 497 -3,608
3 -4,537 168 -1,686 334 6,856 498 7,295
4 2,123 170 0 335 -2,724 499 -2,464
5 -2,191 171 -3,608 336 933 500 1,978
6 471 172 7,067 337 -2,161 501 1,307
8 0 173 -2,289 338 2,075 503 0
9 -3,608 174 1,129 339 1,796 504 -3,608
10 6,821 175 617 341 0 505 6,869
11 -2,726 177 0 342 3,608 506 -2,713
12 965 178 3,608 343 -6,978 507 943
13 -2,125 179 -6,802 344 -328 508 -2,170
14 2,095 180 -339 346 0 509 2,056
15 1,813 182 0 347 -3,608 510 1,579
17 0 183 3,608 348 5,969 512 0
18 3,832 184 -7,295 349 -2,630 513 3,608
19 -839 185 2,464 350 1,065 514 -6,808
20 2,494 186 -1,978 351 628 515 2,718
21 -4,757 187 -1,307 353 0 516 -976
22 2,074 189 0 354 3,026 517 2,136
23 -2,231 190 -3,608 355 -998 518 -2,076
24 706 191 6,796 356 2,461 519 -1,620
26 0 192 -2,733 357 -4,579 521 0
27 3,608 193 2,065 358 2,111 522 -3,608
28 -6,937 194 1,609 359 -2,199 523 6,742
29 2,719 196 0 360 513 524 -2,736
30 -953 197 -3,608 362 0 525 2,093
31 2,207 198 6,757 363 -3,608 526 1,660
32 -2,000 199 -2,712 364 2,484 528 0
33 -1,689 200 2,086 365 -4,534 529 3,608
35 0 201 1,653 366 2,160 530 -2,458
36 -3,608 203 0 367 440 531 4,536
37 6,802 204 -3,625 369 0 532 -2,190
38 339 205 853 370 3,608 533 -392
40 0 206 -2,471 371 -6,969 535 0
41 -3,608 207 4,383 372 -384 536 -3,608
42 6,915 208 -2,099 374 0 537 2,424
43 -2,639 209 2,209 375 -3,826 538 -4,003
44 945 210 -635 376 860 539 2,235
45 -2,206 212 0 377 -2,482 540 155
46 2,089 213 3,608 378 4,578 542 0
47 1,797 214 -6,719 379 -2,099 543 -3,608
49 0 215 2,738 380 2,215 544 6,787
50 3,608 216 -2,101 381 -709 545 -2,738
51 -2,403 217 -1,859 383 0 546 2,067
52 -366 219 0 384 -3,608 547 1,640

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 82 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Pressure Pressure Pressure Pressure


Point Point Point Point
(Pa) (Pa) (Pa) (Pa)
54 0 220 -3,608 385 6,950 549 0
55 3,608 221 6,881 386 -2,193 550 3,608
56 -6,892 222 -2,723 387 956 551 -6,947
57 2,702 223 949 389 0 552 2,622
58 -961 224 -2,179 390 3,608 553 -964
59 2,189 225 2,052 391 -3,606 554 2,201
60 -2,049 226 1,769 392 -352 555 -1,507
61 -1,766 228 0 394 0 557 0
63 0 229 3,608 395 3,608 558 -3,608
64 3,608 230 -6,856 396 -6,757 559 2,436
65 -2,445 231 2,724 397 2,712 560 -4,522
66 4,520 232 -933 398 -2,086 561 2,233
67 -2,204 233 2,161 399 -1,653 562 399
68 -393 234 -2,075 401 0 564 0
70 0 235 -1,796 402 -3,026 565 -3,608
71 3,608 237 0 403 998 566 6,978
72 -6,770 238 -3,608 404 -2,461 567 328
73 2,738 239 6,947 405 4,579 569 0
74 -2,076 240 -2,622 406 -2,111 570 3,608
75 -1,648 241 964 407 2,199 571 -6,821
77 0 242 -2,201 408 -513 572 2,726
78 3,826 243 1,507 410 0 573 -965
79 -860 245 0 411 3,608 574 2,125
80 2,482 246 -3,608 412 -6,915 575 -2,095
81 -4,578 247 6,808 413 2,639 576 -1,813
82 2,099 248 -2,718 414 -945 578 0
83 -2,215 249 976 415 2,206 579 -3,608
84 709 250 -2,136 416 -2,089 580 6,848
86 0 251 2,076 417 -1,797 581 -2,715
87 3,625 252 1,620 419 0 582 949
88 -853 254 0 420 3,608 583 -2,145
89 2,471 255 -3,608 421 -2,424 584 2,089
90 -4,383 256 6,719 422 4,003 585 1,587
91 2,099 257 -2,738 423 -2,235 587 0
92 -2,209 258 2,101 424 -155 588 -3,608
93 635 259 1,859 426 0 589 2,477
95 0 261 0 427 -3,095 590 -4,512
96 -3,608 262 -3,608 428 2,442 591 2,162
97 6,987 263 6,770 429 -4,536 592 424
98 329 264 -2,738 430 2,136 594 0
100 0 265 2,076 431 454 595 3,608
101 3,608 266 1,648 433 0 596 -6,742
102 -6,796 268 0 434 -3,608 597 2,736
103 2,733 269 3,608 435 5,429 598 -2,093
104 -2,065 270 -6,907 436 346 599 -1,660
105 -1,609 271 2,667 438 0 601 0
107 0 272 -951 439 -3,608 602 -3,608

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 83 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Pressure Pressure Pressure Pressure


Point Point Point Point
(Pa) (Pa) (Pa) (Pa)
108 -3,608 273 2,195 440 2,468 603 6,838
109 6,969 274 -2,053 441 -4,534 604 -2,720
110 384 275 -1,769 442 2,176 605 952
112 0 277 0 443 407 606 -2,133
113 -3,608 278 3,608 445 0 607 2,086
114 6,937 279 -6,950 446 -3,608 608 1,804
115 -2,719 280 2,193 447 2,403 610 0
116 953 281 -956 448 366 611 3,608
117 -2,207 283 0 450 0 612 -6,926
118 2,000 284 -2,452 451 3,608 613 2,635
119 1,689 285 4,537 452 -7,682 614 -950
121 0 286 -2,123 453 2,317 615 2,217
122 3,608 287 2,191 454 -1,621 616 -2,164
123 -2,436 288 -471 455 -561 617 -1,908
124 4,522 290 0 457 0 619 0
125 -2,233 291 -3,608 458 3,608 620 -3,608
126 -399 292 2,458 459 -6,987 621 6,728
128 0 293 -4,536 460 -329 622 -2,675
129 3,095 294 2,190 462 0 623 1,978
130 -2,442 295 392 463 -3,608 624 1,686
131 4,536 297 0 464 6,892 626 0
132 -2,136 298 3,608 465 -2,702 627 3,608
133 -454 299 -7,067 466 961 628 -2,484
135 0 300 2,289 467 -2,189 629 4,534
136 3,608 301 -1,129 468 2,049 630 -2,160
137 -2,414 302 -617 469 1,766 631 -440
138 3,416 304 0 471 0 633 0
139 -2,243 305 3,608 472 3,608 634 3,608
140 -375 306 -6,787 473 -6,848 635 -6,881
142 0 307 2,738 474 2,715 636 2,723
143 -3,608 308 -2,067 475 -949 637 -949
144 2,414 309 -1,640 476 2,145 638 2,179
145 -3,416 311 0 477 -2,089 639 -2,052
146 2,243 312 -3,608 478 -1,587 640 -1,769
147 375 313 6,907 480 0 642 0
149 0 314 -2,667 481 -3,608 643 3,608
150 -3,608 315 951 482 2,445 644 -6,869
151 7,682 316 -2,195 483 -4,520 645 2,713
152 -2,317 317 2,053 484 2,204 646 -943
153 1,621 318 1,769 485 393 647 2,170
154 561 320 0 487 0 648 -2,056
156 0 321 -3,608 488 3,608 649 -1,579
157 3,608 322 3,606 489 -6,838 651 0
158 -2,477 323 352 490 2,720 652 -3,608
159 4,512 325 0 491 -952 653 6,926
160 -2,162 326 3,608 492 2,133 654 -2,635
161 -424 327 -2,468 493 -2,086 655 950

Template no.:
HS2-HS2-QY-TEM-000-000008 Page 84 Uncontrolled when printed
Technical Standard - Shaft and Portal Building MWCC and Rail Systems Interfaces
Document no.: HS2-HS2-CV-STD-000-000008
Revision: P03

Pressure Pressure Pressure Pressure


Point Point Point Point
(Pa) (Pa) (Pa) (Pa)
163 0 328 4,534 494 -1,804 656 -2,217
164 3,608 329 -2,176 657 2,164
165 -6,728 330 -407 658 1,908

Template no.: