You are on page 1of 21

r-s

ne
Site Investigation, Design & Construction

tiv nd
ow
ec rla
of Hydro & Transport Tunnels

e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013

ir w
he - S
Performance Monitoring

ft n
O tio
© a
n nd
M.Sc. Felix Amberg
tio ou
ra F

Amberg Engineering Ltd., Switzerland


st T
llu E
lI C
Al ITA
©
Performance Monitoring
‘Natural’ or at least: ‘Quite Common’ Situation

r-s
 Tunnel construction is behind schedule

ne
 Nobody knows exactly Why?

tiv nd
ow
ec rla
 Some claim ‘the geology’, some claim ‘the contractor’, other the ‘faulty

e
sp e
design’, ‘insufficient management’ etc

re itz
 cost and time overrun are very likely

ir w
he - S
ft n
in addition

O tio
© a
 quality might be poor n nd
 logistics seems inefficient
tio ou

 resources seems to be short or even lacking


ra F
st T
llu E
lI C

What to do in such a situation?


Al ITA

Performance monitoring could help – but what is this?


©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 2
Performance Monitoring
Basics

r-s
Performance Monitoring is part of

ne
tiv nd
ow
ec rla
 the design work

e
sp e
 the contract with the contractor

re itz
ir w
 the execution of the work

he - S
 the costs control

ft n
O tio
and uses various tools, such as © a
n nd
tio ou

 schedules
ra F

 programs
st T
llu E

 works cycle times


lI C
Al ITA

 scenarios
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 3
Performance Monitoring
Design

r-s
Performance monitoring starts in the design phase !

ne
tiv nd
ow
According to the design phase and based on

ec rla
e
 experience

sp e
re itz
 data from similar projects

ir w
he - S
 more or less detailed calculations of work cycles etc

ft n
O tio
the input data for
© a
n nd
 linear performance rates [m/day etc] of the most important works
tio ou

(excavation, support, lining, waterproofing etc)


ra F
st T

 the gross time estimations for other type of work (rigging, installations,
llu E

TBM assembly etc)


lI C
Al ITA

 interdependencies between the different works are evaluated


©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 4
Performance Monitoring
Design

r-s
The results of the performance estimation in the design phase are:

ne
tiv nd
ow
ec rla
 first construction programs (gant charts, time-chainge-programs etc)

e
sp e
 identification of point of conflicts, milestones to meet, delays etc

re itz
ir w
 identification of the ‘critical path(s)’ during further design stages and

he - S
construction

ft n
 inputs for cost estimations

O tio
© a
n nd
However this process must be up-dated in every design phase according
tio ou

to the available input data (devlopment of the project etc).


ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 5
Performance Monitoring
Design – Tools for Performance Monitoring

r-s
PERT (Programm Evaluation and Review Technique)

ne
CPM (Critical Path Method)

tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou

Gantt charts
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 6
Performance Monitoring
Design – Tools for Performance Monitoring

r-s
Time – Chainage - Charts

ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 7
Performance Monitoring
Bidding Documents - Contract

r-s
In the bidding documents the results of the design phases in regard to

ne
performance, time, delays and schedules to be respected are given.

tiv nd
ow
ec rla
e
The Swiss Codes on Underground Construction (sia codes 197 and 198) may

sp e
re itz
serve as a good example of how to handle these issues in the contract (of course

ir w
there are others as well). These codes they stipulate for instance:

he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 8
Performance Monitoring
Bidding Documents - Contract (cont.)

r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
Also some rules are given how to handle time adjustments
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 9
Performance Monitoring
Bidding Documents - Contract (cont.)

r-s
In particular the Swiss codes demand some specific data from the bidder

ne
in regard to working cycles as it is stipulated

tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
With these rules both the contractor and the supervising body have a tool
© a
n nd
to verifiy later on (during constrcution), if the originally planned times for
tio ou
working cycles, the critical path etc still abide or not.
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 10
Performance Monitoring
Bidding Documents - Contract (cont.)

r-s
This Appendix C

ne
looks as follows:

tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 11
Performance Monitoring
Bidding Documents - Contract (cont.)

r-s
In the contract it is possible to include milestones and to allocate a

ne
bonus – malus regulation to it. Some considerations:

tiv nd
ow
ec rla
e
sp e
 where there is a malus, there always should be a bonus. Or: No malus

re itz
without a bonus! It’s a principle of fairness

ir w
he - S
ft n
 Milestones which are relevant for bonus/malus should be evident and

O tio
‘easy’ to justify (succession of work, follow-up works etc)
© a
n nd
tio ou

 Bonus and malus should pricewise be attractive for the contractor –


ra F
st T

always to be checked with financial consequences under ‘normal’


llu E

conditions!
lI C
Al ITA
©

 Keep in mind: Bonus / malus do not necessarily mean the same for
everybody!
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 12
Performance Monitoring
During Construction

r-s
During construction both the contractor and the supervising team

ne
constantly follow the development of the works.

tiv nd
ow
ec rla
e
sp e
In particular:

re itz
ir w
 timely up-date of the development of the work

he - S
 identification of critical points

ft n
 develop scenarios on how to mitigate the risks and implement

O tio
countermeasures
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 13
Performance Monitoring
Complete Construction Schedule of Contractor (Status: End of August 2010)

r-s
ne
tiv nd
ow
Time critical

ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
Major uncertainness in geology over 3‘500 m

© a
n nd Too many dependecies and uncertainties
tio ou
ra F
st T
llu E
lI C
Al ITA

Not enough time for tunnel completition


Detailed planning and detailed construction schedule strongly required
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 14
Performance Monitoring

Mitigation measures

r-s
ne
tiv nd
 Improve the knowledge on the geological conditions (in order to improve the

ow
ec rla
planning)

e
sp e
 Investigation drillings

re itz
ir w
he - S
 Strengthen the TBM to increase excavation rate:
 Special measures for TBM (torque increase etc)

ft n
O tio
© a
n nd
 Detailed projects for Adits 0/2/1 and Adit 1 North including sequence of work
tio ou
ra F

 Technical support for Railway TBM South


st T
llu E
lI C

 Management construction schedule including target-performance comparison


Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 15
Performance Monitoring
Mitigation Measures (cont.)

r-s
ne
tiv nd
 Current Status

ow
ec rla
 TBM has excavated more than 600 m

e
 TBM is currently in a fault zone area

sp e
re itz
 Pipe umbrella and grouting around the TBM are prepared

ir w
he - S
Fault zone interpretation

 Risks

ft n
O tio
 A distance of more than 500 m needs to be excavated with

© a more or less unknown fault zones


n nd
 Each collapse will cost time and resources
tio ou

 No proper stock of spare parts, e.g. tail-shield brushes


ra F

Detail of fault zones for Road Tunnel


st T

 Measures
llu E
lI C

 Construction of a pipe umbrella before reaching a fault zone


Al ITA

 Sufficient overlapping of the umbrella


 Investigation drillings
©

Face stability
 Monitoring and use of TBM parameters

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 16
Performance Monitoring
Construction schedule
According to the contractor‘s

r-s
Tunnel (status xx.yy.zz) time schedule dated of xx.yy.zz

ne
Scenario – planned by site

tiv nd
ow
supervision

ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
08/05/2012
ra F
st T
llu E
lI C
Al ITA
©

17
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Performance Monitoring
Construction schedule
According to the contractor‘s

r-s
Tunnel (status xx.yy.zz) time schedule dated xx.yy.zz

ne
Scenario – planned by Site

tiv nd
ow
Supervision

ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
11/04/2012
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 18
Performance Monitoring
Unsatisfactory Performance

r-s
Countermeasures:

ne
tiv nd
ow
ec rla
 Analyse the circumstances of the situation carefully

e
sp e
 Take all partners, their relevant work contribution etc - simply all

re itz
ir w
aspects into consideration

he - S
 Check the effective work cycle time on site:

ft n
 stay there and observe all steps within (a) work cylce(s)

O tio
© a
 measure the time needed with a stop watch
n nd
 take accurate notes, photographs etc
tio ou
ra F

 Compare the effective work cylce sequence and time with what has
st T

been planned and serves as calculation base for the prices in the bid
llu E
lI C

 Identify shortcomings, reasons for delays etc and eliminate them one
Al ITA

after the other


©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 19
Performance Monitoring
Unsatisfactory Performance (cont.)

r-s
Countermeasures:

ne
tiv nd
ow
ec rla
 If necessary implement drastic measures – like counterattacks etc

e
sp e
 Plan them in-time and carefully (access to site, machinery, material,

re itz
ir w
people, logistics, impact on already on-going work etc)

he - S
 Keep your partners informed and make them contribute their part (like

ft n
up-date of the design, design approvals etc)

O tio
 Try to keep contractually up to date!
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 20
r-s
ne
Site Investigation, Design & Construction

tiv nd
ow
ec rla
of Hydro & Transport Tunnels

e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013

ir w
he - S
ft n
O tio
Disclaimer
© a
n nd
tio ou
A. The speakers are presenting their own personal views and are not
ra F

expressing the view of the Foundation.


st T
llu E
lI C

B. Papers and documents displayed or handed out during the Event are
Al ITA

copyrighted. The participants must observe and comply with all applicable
law regulations concerning the copyright.
©

Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013

You might also like