Professional Documents
Culture Documents
ne
Site Investigation, Design & Construction
tiv nd
ow
ec rla
of Hydro & Transport Tunnels
e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013
ir w
he - S
Performance Monitoring
ft n
O tio
© a
n nd
M.Sc. Felix Amberg
tio ou
ra F
r-s
Tunnel construction is behind schedule
ne
Nobody knows exactly Why?
tiv nd
ow
ec rla
Some claim ‘the geology’, some claim ‘the contractor’, other the ‘faulty
e
sp e
design’, ‘insufficient management’ etc
re itz
cost and time overrun are very likely
ir w
he - S
ft n
in addition
O tio
© a
quality might be poor n nd
logistics seems inefficient
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 2
Performance Monitoring
Basics
r-s
Performance Monitoring is part of
ne
tiv nd
ow
ec rla
the design work
e
sp e
the contract with the contractor
re itz
ir w
the execution of the work
he - S
the costs control
ft n
O tio
and uses various tools, such as © a
n nd
tio ou
schedules
ra F
programs
st T
llu E
scenarios
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 3
Performance Monitoring
Design
r-s
Performance monitoring starts in the design phase !
ne
tiv nd
ow
According to the design phase and based on
ec rla
e
experience
sp e
re itz
data from similar projects
ir w
he - S
more or less detailed calculations of work cycles etc
ft n
O tio
the input data for
© a
n nd
linear performance rates [m/day etc] of the most important works
tio ou
the gross time estimations for other type of work (rigging, installations,
llu E
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 4
Performance Monitoring
Design
r-s
The results of the performance estimation in the design phase are:
ne
tiv nd
ow
ec rla
first construction programs (gant charts, time-chainge-programs etc)
e
sp e
identification of point of conflicts, milestones to meet, delays etc
re itz
ir w
identification of the ‘critical path(s)’ during further design stages and
he - S
construction
ft n
inputs for cost estimations
O tio
© a
n nd
However this process must be up-dated in every design phase according
tio ou
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 5
Performance Monitoring
Design – Tools for Performance Monitoring
r-s
PERT (Programm Evaluation and Review Technique)
ne
CPM (Critical Path Method)
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
Gantt charts
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 6
Performance Monitoring
Design – Tools for Performance Monitoring
r-s
Time – Chainage - Charts
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 7
Performance Monitoring
Bidding Documents - Contract
r-s
In the bidding documents the results of the design phases in regard to
ne
performance, time, delays and schedules to be respected are given.
tiv nd
ow
ec rla
e
The Swiss Codes on Underground Construction (sia codes 197 and 198) may
sp e
re itz
serve as a good example of how to handle these issues in the contract (of course
ir w
there are others as well). These codes they stipulate for instance:
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 8
Performance Monitoring
Bidding Documents - Contract (cont.)
r-s
ne
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
Also some rules are given how to handle time adjustments
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 9
Performance Monitoring
Bidding Documents - Contract (cont.)
r-s
In particular the Swiss codes demand some specific data from the bidder
ne
in regard to working cycles as it is stipulated
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
With these rules both the contractor and the supervising body have a tool
© a
n nd
to verifiy later on (during constrcution), if the originally planned times for
tio ou
working cycles, the critical path etc still abide or not.
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 10
Performance Monitoring
Bidding Documents - Contract (cont.)
r-s
This Appendix C
ne
looks as follows:
tiv nd
ow
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 11
Performance Monitoring
Bidding Documents - Contract (cont.)
r-s
In the contract it is possible to include milestones and to allocate a
ne
bonus – malus regulation to it. Some considerations:
tiv nd
ow
ec rla
e
sp e
where there is a malus, there always should be a bonus. Or: No malus
re itz
without a bonus! It’s a principle of fairness
ir w
he - S
ft n
Milestones which are relevant for bonus/malus should be evident and
O tio
‘easy’ to justify (succession of work, follow-up works etc)
© a
n nd
tio ou
conditions!
lI C
Al ITA
©
Keep in mind: Bonus / malus do not necessarily mean the same for
everybody!
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 12
Performance Monitoring
During Construction
r-s
During construction both the contractor and the supervising team
ne
constantly follow the development of the works.
tiv nd
ow
ec rla
e
sp e
In particular:
re itz
ir w
timely up-date of the development of the work
he - S
identification of critical points
ft n
develop scenarios on how to mitigate the risks and implement
O tio
countermeasures
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 13
Performance Monitoring
Complete Construction Schedule of Contractor (Status: End of August 2010)
r-s
ne
tiv nd
ow
Time critical
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
Major uncertainness in geology over 3‘500 m
© a
n nd Too many dependecies and uncertainties
tio ou
ra F
st T
llu E
lI C
Al ITA
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 14
Performance Monitoring
Mitigation measures
r-s
ne
tiv nd
Improve the knowledge on the geological conditions (in order to improve the
ow
ec rla
planning)
e
sp e
Investigation drillings
re itz
ir w
he - S
Strengthen the TBM to increase excavation rate:
Special measures for TBM (torque increase etc)
ft n
O tio
© a
n nd
Detailed projects for Adits 0/2/1 and Adit 1 North including sequence of work
tio ou
ra F
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 15
Performance Monitoring
Mitigation Measures (cont.)
r-s
ne
tiv nd
Current Status
ow
ec rla
TBM has excavated more than 600 m
e
TBM is currently in a fault zone area
sp e
re itz
Pipe umbrella and grouting around the TBM are prepared
ir w
he - S
Fault zone interpretation
Risks
ft n
O tio
A distance of more than 500 m needs to be excavated with
Measures
llu E
lI C
Face stability
Monitoring and use of TBM parameters
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 16
Performance Monitoring
Construction schedule
According to the contractor‘s
r-s
Tunnel (status xx.yy.zz) time schedule dated of xx.yy.zz
ne
Scenario – planned by site
tiv nd
ow
supervision
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
08/05/2012
ra F
st T
llu E
lI C
Al ITA
©
17
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013
Performance Monitoring
Construction schedule
According to the contractor‘s
r-s
Tunnel (status xx.yy.zz) time schedule dated xx.yy.zz
ne
Scenario – planned by Site
tiv nd
ow
Supervision
ec rla
e
sp e
re itz
ir w
he - S
ft n
O tio
© a
n nd
tio ou
11/04/2012
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 18
Performance Monitoring
Unsatisfactory Performance
r-s
Countermeasures:
ne
tiv nd
ow
ec rla
Analyse the circumstances of the situation carefully
e
sp e
Take all partners, their relevant work contribution etc - simply all
re itz
ir w
aspects into consideration
he - S
Check the effective work cycle time on site:
ft n
stay there and observe all steps within (a) work cylce(s)
O tio
© a
measure the time needed with a stop watch
n nd
take accurate notes, photographs etc
tio ou
ra F
Compare the effective work cylce sequence and time with what has
st T
been planned and serves as calculation base for the prices in the bid
llu E
lI C
Identify shortcomings, reasons for delays etc and eliminate them one
Al ITA
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 19
Performance Monitoring
Unsatisfactory Performance (cont.)
r-s
Countermeasures:
ne
tiv nd
ow
ec rla
If necessary implement drastic measures – like counterattacks etc
e
sp e
Plan them in-time and carefully (access to site, machinery, material,
re itz
ir w
people, logistics, impact on already on-going work etc)
he - S
Keep your partners informed and make them contribute their part (like
ft n
up-date of the design, design approvals etc)
O tio
Try to keep contractually up to date!
© a
n nd
tio ou
ra F
st T
llu E
lI C
Al ITA
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013 20
r-s
ne
Site Investigation, Design & Construction
tiv nd
ow
ec rla
of Hydro & Transport Tunnels
e
sp e
re itz
Kathmandu, Nepal 19 - 20 December 2013
ir w
he - S
ft n
O tio
Disclaimer
© a
n nd
tio ou
A. The speakers are presenting their own personal views and are not
ra F
B. Papers and documents displayed or handed out during the Event are
Al ITA
copyrighted. The participants must observe and comply with all applicable
law regulations concerning the copyright.
©
Site investigation, Design & Construction of Hydro & Transport Tunnels | Kathmandu, Nepal – 19-20 December 2013