17 May 05
FLUOR
Mining & Minerals
This document has been revised as indicated below. Changes after revision 0 are identified by vertical bars at the
right side of the page, with additions being underlined. Please replace all pages of this specification and destroy
the superceded copies. English is the prevailing language of this document.
Project Manager:
Engineering Manager: Brad Matthews 24May05
Area Project Engineer: Brad Matthews 24May05
Lead Discipline Engineer: Patrick Lo 24May05 Gary Christie 24May05
Process Approval:
FLUOR
Mining & Minerals
Table of Contents
1. GENERAL ........................................................................................................................................................ 3
1.1 Summary .......................................................................................................................................................3
1.2 References ....................................................................................................................................................3
1.3 Submittals ......................................................................................................................................................4
2. PRODUCTS...................................................................................................................................................... 4
2.1 General ..........................................................................................................................................................4
2.2 Materials ........................................................................................................................................................4
3. EXECUTION..................................................................................................................................................... 5
3.1 Trench Excavation, Bedding, Backfilling, and Compaction...........................................................................5
3.2 Sewers...........................................................................................................................................................6
3.3 Manholes, Inlets and Catch Basins ...............................................................................................................6
3.4 Inspection and Testing ..................................................................................................................................7
4. ATTACHMENTS .............................................................................................................................................. 8
1. GENERALIDADES ........................................................................................................................................ 10
1.1 Resumen .....................................................................................................................................................10
1.2 Referencias .................................................................................................................................................10
1.3 Remisiones ..................................................................................................................................................11
2. PRODUCTOS................................................................................................................................................. 11
2.1 Generalidades .............................................................................................................................................11
2.2 Materiales ....................................................................................................................................................12
3. EJECUCIÓN................................................................................................................................................... 13
3.1 Excavación, Encamado, Relleno y Compactación de Zanjas.....................................................................13
3.2 Drenajes ......................................................................................................................................................13
3.3 Cajas de Registro, Entradas y Colectores. .................................................................................................14
3.4 Inspección y Prueba ....................................................................................................................................14
4. ANEXOS......................................................................................................................................................... 16
FLUOR
Mining & Minerals
1. GENERAL
1.1 Summary
A. Scope of Specification
This specification prescribes the requirements for the installation of underground storm sewer
systems and culverts with the necessary fittings, manholes, inlets, catch basins, headwalls,
paved ditches and appurtenances as shown on the Drawings and specified herein. This
specification does not apply to above-ground storm drain lines.
B. Related Specifications
1.2 References
A. The publications listed below form part of this specification. Each publication shall be the latest
revision and addendum in effect on the date this specification is issued for construction unless
noted otherwise. Except as modified by the requirements specified herein or the details of the
Drawings, Work included in this specification shall conform to the applicable provisions of these
publications.
FLUOR
Mining & Minerals
10. ASTM D2680 Specifications for Acrylonitrile Butadiene Styrene (ABS) and Polyvinyl
chloride (PVC) Composite Sewer Piping
11. ASTM D3034 Specification for Type PSM Polyvinyl chloride (PVC) Sewer Pipe and
Fittings
12. ASTM D3212 Specifications for Joints for Drain and Sewer Plastic Pipes Using Flexible
Elastomeric Seals
13. ASTM F477 Standard Specification for Elastomeric Seals (Gaskets) for Joining
Plastic Pipe
14. AWWA American Water Works Association
15. AWWA M23 PVC (Polyvinyl Chloride) Pipe Design and Installation
16. AWWA C500 Gate Valves for Water and Sewerage Systems
17. AWWA C901 Polyethylene (PE) Pressure Pipe and Tubing (1/2" - 3")
18. AASHTO American Association of State Highway and Transportation Officials
19. AASHTO M36 Standards for Metallic Coatings for Steel Pipe
20. AASHTO M190 Standards for Non-Metallic Coatings and pavings for corrugated steel
pipes
21. AASHTO M252 Standard specifications for Corrugated Polyethylene Pipe (75mm to
250mm)
22. AASHTO M294 Standard specifications for Corrugated Polyethylene Pipe (300mm to
900mm)
23. ASTM D3350 Standard specifications for Polyethylene Plastic Pipe and Fittings
Material
1.3 Submittals
Manufacturer's certifications shall be submitted to the Construction Manager for pipe, joint materials,
and accessories, showing compliance with this specification prior to installation.
2. PRODUCTS
2.1 General
The prescribed sizes of pipes are nominal inside diameters. Pipes shall be of the size and length
shown on the Drawings. Materials called for on the Drawings shall conform to the specifications
stated below.
2.2 Materials
Pipe and fittings to be in accordance with Specification C-SP-50-001 for line class as indicated
on Drawings.
FLUOR
Mining & Minerals
E. Cast-in-Place Concrete
Cast-in-place concrete for drainage structures including: manholes, inlets, catch basins, collars,
support blocks, headwalls, and paved ditches shall conform to the requirements in Specification
C-CS-15-001.
F. Cement Mortar
Cement mortar used for paving inverts, filling lift holes, joints, patching and anchoring castings
shall consist of one part Portland cement, Type I, ASTM C150, 1/4 part hydrated lime, ASTM
C206, and 21/2 parts clean, sharp, well-graded sand and water free of suspended matter, alkali,
and containing no industrial or domestic waste.
G. Reinforcing Steel
Reinforcing steel shall be in accordance with ASTM A615, Grade 60; and wire fabric shall be in
accordance with ASTM A185.
3. EXECUTION
Unless otherwise specified or indicated on the Drawings, trench excavation, pipe bedding, trench
backfilling and compaction shall be in accordance with Specification C-CS-10-006.
FLUOR
Mining & Minerals
3.2 Sewers
A. Pipe Laying
1. The type, class and size of pipe used shall be as shown on the Drawings. The pipe shall
be laid and maintained to the required line and grade with the necessary fittings, bends,
manholes and other appurtenances placed at the required locations. Installation shall
commence at the lowest point for each segment of the route.
2. The pipe shall be inspected for defects and cracks before being carefully lowered into the
trench, piece by piece. Any defective, damaged or unsound pipe or any pipe that has had
its grade disturbed after laying shall be taken up and replaced. Open ends shall be
protected with a stopper to prevent earth or other materials from entering the pipe during
construction. The interior of the pipe shall be free from dirt, excess water and other foreign
materials as the pipe laying progresses, and left clean at the completion of the installation.
3. Riveted CSP shall be placed with the inside circumferential laps pointing downstream.
Damaged bituminous coating on CSP shall be repaired by applying bituminous material
conforming to AASHTO M190 (TYPE ‘D’).
No pipe shall be laid in water or when trench conditions are unsuitable for such work.
C. Joints
1. Joints shall be constructed as described herein with the intent that they be made
watertight.
2. HDPE pipe joints to be butt fusion joints, to ASTM D2657 unless otherwise specified on
Drawings.
3. CSP shall be joined by standard corrugated connecting bands. Care shall be used to keep
dirt or gravel out from between the pipe and band so that corrugations fit snugly. While
being tightened, the band shall be tapped with a mallet to take up slack and insure a tight
joint.
4. C-HDPE shall be connected using wrap-around band or snap-on couplings.
A. Pipe Openings
Openings Pipe shall be aligned to that of the pipe entering and leaving the manhole. Pipe shall
be properly aligned with connections to manholes, inlets or catch basins as shown on the
Drawings. Where connections are not shown on Drawings, pipe shall terminate flush with the
inside of the structure wall.
B. Cast-in-Place Sections
Cast-in-place sections shall be installed as shown on the Drawings and in accordance with
Specification C-CS-15-011.
FLUOR
Mining & Minerals
Frames and covers shall be set to the proper elevation. The frames shall be installed in
accordance with the Drawings.
D. Concrete Cradles
Concrete cradles shall be constructed as shown on the Drawings and as needed when crossing
over and under other sewer pipe or utility lines.
Manholes and catch basins shall be internally lined with high density polyethylene sheeting or
equivalent approved material as indicated on the Drawings.
A. General
Storm sewer systems and culverts, upon completion or at such time as directed, shall be
cleaned, inspected and tested. The storm sewer or culvert shall have a true grade and line.
Actual elevations shall be within 2 mm of the elevations given on the Drawings.
B. Cleaning
1. Remove foreign material from storm sewers and related appurtenances by flushing with
water or with mechanical equipment. Clear debris flushed from the lines at the nearest
manhole or point of interception. Flushing rates to be sufficient to clean storm sewers of
visible debris or as accepted by the Construction Manager.
2. To ensure all sections of the storm sewer system flow freely each segment is to be
flushed. All flushing is to be performed in the presence of the Construction Manager or his
designate.
C. Exfiltration Test
1. Pipes and joints shall not be completely backfilled until after inspection, testing, and
approval by the Construction Manager.
2. Prior to testing for leakage, the pipe trench shall be backfilled to at least the spring line of
the pipe. If required to prevent pipe movement during testing, additional backfill shall be
added leaving the pipe joints uncovered to permit inspection.
3. Exfiltration Test
a. Fill test section with water in such a manner as to allow displacement of air in line.
Maintain under nominal head for 24 hours to ensure absorption in pipe and
appurtenance walls is complete before test measurements are commenced.
b. Immediately prior to test period add water to pipeline until there is a head of 1 m over
interior crown of pipe measured at highest point of test section or water in manhole is
1 m above static ground water level, whichever is greater, but the maximum head in
any part of the system under test shall not be greater than 7.6 m.
c. Duration of exfiltration test to be two hours.
d. Water loss at end of test period not to exceed maximum allowable exfiltration over
any section of pipe between manholes.
FLUOR
Mining & Minerals
4. There shall be no allowable exfiltration from the test section unless otherwise stated by the
Construction Manager.
5. Repair and retest sewer line as required until test results are within limits specified.
6. Repair visible leaks regardless of test results.
7. Provide measuring devices, meters, water, materials, and labor for making the required
tests.
8. Tests shall be conducted in the presence of the Construction Manager or his designate.
Test data shall be submitted to the Construction Manager for review and approval.
D. Alignment Test
After backfill has been placed and compacted to a depth not less than 300 mm above top of
pipe, a visual inspection shall be made by flashing a light between manholes. Any displacement
or misalignment of invert shall be corrected. This test shall be conducted in the presence of the
Construction Manager or his designate.
4. ATTACHMENTS
Not applicable.
End of Specification
FLUOR
Mining & Minerals
Este documento ha sido revisado como se indica más abajo. Los cambios posteriores a la revisión 0 son
identificados con barras verticales al lado derecho de la página, con los agregados subrayados. Por favor
reemplazar todas las páginas de esta especificación y destruya las copias precedentes.
Gerente de Proyecto:
Gerente de Ingeniería:
Ingeniero de Proyecto del
Área:
Ingeniero Jefe de la
Disciplina:
Aprobación del Proceso:
FLUOR
Mining & Minerals
1. GENERALIDADES
1.1 Resumen
A. Alcance de la Especificación
Esta especificación estipula los requerimientos para la instalación de los sistemas subterráneos
de drenaje de aguas de lluvia y alcantarillado, con los accesorios necesarios, cajas de registro,
entrada, colectores, cabeza de muro, zanjas pavimentadas y aditamentos; tal como se muestra
en los Planos y lo que se especifica aquí. Esta especificación no se aplica a las tuberías de
drenaje de aguas de lluvias que están sobre el terreno.
B. Especificaciones Relacionadas
1.2 Referencias
A. Las publicaciones que se listan a continuación forman parte de esta especificación. Cada
publicación deberá ser de la última revisión y adenda vigente; en la fecha en que ésta
especificación sea publicada para su construcción, a menos que se indique de otra manera. A
excepción de lo modificado por los requerimientos aquí especificados o por los detalles de los
Planos, el Trabajo incluido en esta especificación deberá estar conforme a las provisiones
aplicables de estas publicaciones.
FLUOR
Mining & Minerals
1.3 Remisiones
Las certificaciones del Fabricante para las tuberías, materiales de juntas y accesorios deberán ser
remitidas al Gerente de la Construcción, mostrando la conformidad con esta especificación antes de
su instalación.
2. PRODUCTOS
2.1 Generalidades
Las dimensiones señaladas de las tuberías, son los diámetros nominales internos. Las tuberías
deberán ser del tamaño y longitud mostrados en los Planos. Los materiales solicitados en los Planos
deberán estar en conformidad con las especificaciones establecidas a continuación.
FLUOR
Mining & Minerals
2.2 Materiales
E. Concreto Vaciado-In-Situ
El concreto para estructuras de drenaje vaciado in situ incluyendo: cajas de registro, entrada,
colectores, collares, bloques de apoyo, cabezas de muros, y zanjas pavimentadas; deberán
estar en conformidad con los requerimientos de la Especificación C-CS-15-001.
F. Mortero de Cemento
FLUOR
Mining & Minerals
G. Acero de Refuerzo
El acero de Refuerzo deberá estar de acuerdo con ASTM A615, Grado 60, y la malla de
alambre deberá estar de acuerdo con ASTM A185.
3. EJECUCIÓN
A menos que se especifique o se indique de otra de manera; en los Planos, la excavación de zanjas,
el encamado de las tuberías, el relleno y la compactación de las zanjas, deberán estar de acuerdo
con la Especificación C-CS-10-006.
3.2 Drenajes
Ninguna tubería deberá ser tendida sobre agua o cuando las condiciones de la zanja sean
inadecuadas para tal trabajo.
C. Juntas
1. Las juntas deberán ser construidas tal como están aquí descritas con el propósito de que
sean hechas herméticamente.
2. Las juntas de tuberías HDPE deberán ser juntas por fusión a tope, de acuerdo con ASTM
D2657 a menos que se indique de otra manera en los Planos.
3. Las CSP deberán ser unidas mediante bandas corrugadas de conexión estándar. Se
deberá tener cuidado para mantener la suciedad o la grava fuera del área entre la tubería
y la banda, de modo que las corrugaciones se ajusten apretadamente. Mientras sea
FLUOR
Mining & Minerals
ajustada, la banda será golpeada ligeramente con un martillo de goma para quitar la
soltura y asegurar un empalme apretado.
4. La C-HDPE deberá ser conectada utilizando una banda envolvente o acoplamientos de
fijación rápida a presión.
Las aberturas de las tuberías deberán ser alineadas con aquellas tuberías que ingresan y salen
de la caja de registro. Las tuberías deberán estar correctamente alineadas con las conexiones
de las cajas de registro, entradas o colectores tal como se muestran en los Planos. Donde las
conexiones no sean mostradas en los Planos, la tubería deberá terminar al ras del interior de la
pared de la estructura.
Las secciones vaciadas in situ, deberán ser instaladas tal como son mostradas en los Planos y
de acuerdo con la especificación C-CS-15-011.
C. Marcos y Tapas
Los marcos y tapas deberán ser colocadas con la elevación correcta. Los marcos deberán ser
instalados de acuerdo con los Planos.
D. Soportes de Concreto
Los soportes de concreto deberán ser construidos tal como se muestran en los Planos y como
se requieran cuando se crucen por encima o por debajo de otras líneas de servicio o tuberías
de drenaje.
Las cajas de registro y los colectores deberán estar recubiertos interiormente con un
revestimiento de polietileno de alta densidad o un material equivalente aprobado como se indica
en los Planos.
A. Generalidades
Los sistemas de drenaje para aguas de lluvia y alcantarillados; al momento de ser terminados,
o en el tiempo indicado, deberán ser limpiados, inspeccionados y probados. El drenaje para
aguas de lluvia o alcantarillados deberá tener una línea y nivel correctos. Las elevaciones
reales deberán estar dentro de los 2 mm de las elevaciones dadas en los Planos.
B. Limpieza
1. Retirar el material extraño de los drenajes para aguas de lluvia y de los accesorios
asociados por chorro de agua o con un equipo mecánico. Lavar retirando los desechos
desde las líneas en la caja de registro o punto de intercepción más cercano. La intensidad
de lavado para limpiar desechos visibles de los drenajes para aguas de lluvia, será la
FLUOR
Mining & Minerals
suficiente para limpiar los drenajes para lluvia de los deshechos visibles o como sea
aceptado por el Gerente de la Construcción.
2. Para asegurarse de que todas las secciones del sistema de drenaje para agua de lluvia
fluyan libremente, cada segmento deberá ser lavado. Todo el lavado será ejecutado en
presencia del Gerente de Construcción o alguien designado por él.
C. Prueba de Exfiltraciones
1. Las tuberías y juntas no deberán ser rellenadas por completo hasta después de la
inspección, prueba y aprobación del Gerente de Construcción.
2. Antes de la prueba de fugas, la zanja de la tubería deberá ser rellenada por lo menos
hasta el eje central de la tubería. Si es necesario para evitar el movimiento de la tubería
durante la prueba, se deberá aumentar relleno adicional dejando descubiertas las juntas
de la tubería para permitir la inspección.
3. Prueba de Exfiltración
a. Llenar con agua la sección a prueba, de tal manera que se permita el
desplazamiento del aire en la línea. Mantener bajo presión nominal durante 24
horas, para asegurarse de que la absorción en las paredes de la tubería y anexos
sea completada antes de comenzar las mediciones de prueba.
b. Inmediatamente antes del periodo de prueba, añada agua a la tubería hasta que
haya una presión de 1 m de agua sobre la cúspide del tubo medida en el punto más
alto de la sección de prueba; o, cuando el agua en la caja de registro esté 1 m por
encima del nivel estático del agua del terreno, el que sea mayor, pero la presión
máxima en cualquier parte del sistema bajo esta prueba no deberá ser mayor a
7.6m.
c. La duración de la prueba de exfiltraciones será de dos horas.
d. La pérdida de agua al final del periodo de prueba no excederá la exfiltración máxima
permisible en ninguna sección de la tubería entre las cajas de registro.
4. No deberá haber exfiltración permisible desde la sección de prueba a menos que sea
indicado de otra manera por el Gerente de la Construcción.
5. Reparar y volver a probar la línea de drenaje tal como sea requerido hasta que los
resultados de la prueba estén dentro de los límites especificados.
6. Reparar las fugas visibles sin tomar en cuenta los resultados de la prueba.
7. Proporcionar dispositivos de medición, medidores, agua, materiales y mano de obra para
realizar las pruebas requeridas.
8. Las pruebas deberán ser llevadas a cabo en presencia del Gerente de Construcción o
alguien designado por él. La información de la prueba deberá ser remitida al Gerente de la
Construcción para su revisión y aprobación.
D. Prueba de alineamiento
Después de que el relleno haya sido colocado y compactado hasta una profundidad no menor
de 300 mm por encima de la parte superior de la tubería, se deberá hacer una inspección visual
utilizando una linterna y alumbrando entre las cajas de registro. Cualquier desplazamiento o
FLUOR
Mining & Minerals
desalineamiento de la solera deberá ser corregido. Esta prueba deberá ser realizada en
presencia del Gerente de Construcción o alguien designado por él.
4. ANEXOS
No aplicable.
Fin de la Especificación